SCV Load Out Service Requirements Rev.01
SCV Load Out Service Requirements Rev.01
SERVICE REQUIREMENTS
A. GENERAL REQUIREMENT
Cranage/SPMT, loadout frame, support on vessel deck, load out bridge, personnel
gangway, miscellaneous loadout item, etc required for performing loadout shall be under
SUBCONTRACTOR responsibility.
SUBCONTRACTOR to perform below operation in the cargo barge, but not limited to:
Weight 121134 kg
OPTION 1 - LCT
D. SCOPE OF WORK
1. Certified SPMT
2. Certified crane
3. Certified fork lift
4. Certified lashing gear
5. Certified rigging materials (slings, shackles, etc.)
6. Certified lifting equipment
7. Certified welding and NDT equipment
8. Certified testing equipment
9. External ballast system including pump, piping, valve, power generator, etc
10. Gangway for personnel transfer (jetty to barge vice versa)
11. Loadout bridge
12. Mooring system (winch, wire, connections, etc)
13. Certified Gas Test Equipment
E. RESPONSIBILITY MATRIX
CTR SUB
2. Vessel Details X
CTR SUB
4. Transportation arrangement on X
SPMT (including lashing on
SPMT)
11. Supply of Equipment X Equipment shall have valid certificate and certified by
(Equipment (welding machine, relevant authorities. Inspection for equipment shall
craneage, lift riggings etc.)) be performed regularly.
13. Load Out Permit (and other X - Have to appoint registered Stevedoring Company
loading cargo if necessary) to work in Citranusa Kabil Port
- Stevedore Company will take care of permit 1B to
Port Authority and Citranusa Kabil Port
14. Hot Work Permit X - Hot work permit to Harbour Master, arrange by
shipping agent
- Before start hot work there must have a gas free
certificate from a third party
- The shipping agency must inform to the Port if
there will have a hot work and submit a copy of
the hot work permit
- Must have certificate for Personnel's &
Equipment's
- Safety Induction for personnel who will enter
Citranusa Kabil Port
No Work Description Responsibility Remarks
CTR SUB
15. Welding and NDT Operation, X SUBCONTRACTOR shall not start welding and NDT
equipment, and consumables activities prior welding and NDT procedures have
been approved by COMPANY/ CONTRACTOR.
18. QA/QC X
26. Loadout support on barge deck X Including engineering design, fabrication and
installation
31. Pilotage X
G. TENDER REQUIREMENT
H. PRICING
Rates
No. Description Unit
[IDR]
2. Permit : Lump-sum
- Transport/Trucking Permit
- Load Out Permit
- Hot Work Permit
5. Engineering Lump-sum
I. REFERENCE DOCUMENTS
AIPEM
A
S
M
E
U2
CLASS 2
AIPEM
AIPEM