Item # Description Quantity Unit Rate (USD) Total Cost (USD) Mobilization / Demobilization

This document provides a cost estimate for geotechnical investigation works including drilling bore holes, installing piezometers, excavating test pits, and conducting various soil and rock laboratory tests. The total cost is estimated to be USD [amount redacted] based on unit rates for 113 bore holes drilled to various depths totaling 1,505 meters, installation of 15 standpipe piezometers, excavation of 68 test pits, and laboratory testing of soil and rock samples including sieve analysis, direct shear tests, Atterberg limits, consolidation tests, and chemical analysis of soil and water samples.

Uploaded by

Malak Najem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views2 pages

Item # Description Quantity Unit Rate (USD) Total Cost (USD) Mobilization / Demobilization

This document provides a cost estimate for geotechnical investigation works including drilling bore holes, installing piezometers, excavating test pits, and conducting various soil and rock laboratory tests. The total cost is estimated to be USD [amount redacted] based on unit rates for 113 bore holes drilled to various depths totaling 1,505 meters, installation of 15 standpipe piezometers, excavation of 68 test pits, and laboratory testing of soil and rock samples including sieve analysis, direct shear tests, Atterberg limits, consolidation tests, and chemical analysis of soil and water samples.

Uploaded by

Malak Najem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Unit rate Total Cost

Item # Description Quantity


(USD) (USD)
Mobilization / Demobilization
Include access to site for works and
1- L/S
water supply provisions and all other
auxiliary works
Drilling: Bore Holes
Includes moving and setting up drilling rigs,
in-situ testing, sampling, casing if needed and
rock coring, storing, boxing, logging and 113
photographing cores.

Drilling in any material except rock 1430 m


2-
Continuous coring through rock. 75 m

Standpipe piezometers 15

Test pits including excavation, support,


logging, taking samples and photographs 68
Laboratory testing

Soil testing:
- Sieve analysis including moisture content 430
- Direct Shear test including density 110
- Determination of Atterberg limits 430
- Hydrometer test 60
- Unconfined compression on cohesive soils -
(Rate Only) -
- Swell test (Rate Only) -
- Collapse Potential test (Rate Only)
- One dimensional consolidation on cohesive 30
soils, if encountered
-Unconsolidated undrained triaxial on -
3-
cohesive soils if encountered (Rate Only)
- 4-day soaked CBR including Proctor 68
compaction tests
Rock testing:
- Unconfined compression test including bulk
density, Elastic modulus, moisture content. -
(Rate Only)
- Point load index, on rock fragments (Rate -
Only)

Chemical testing in soil samples:


(Water soluble sulfate, chloride, carbonate 40
and PH)
Unit rate Total Cost
Item # Description Quantity
(USD) (USD)
Chemical testing in water samples:
(Water soluble sulfate, chloride, carbonate 15
and PH)
4- Analysis & Reporting 1