CSF Contracts
CSF Contracts
Rene G. Rendon
ABSTRACT
Critical success factors have a direct impact on an organization’s project
management and contract management processes as well as resulting
outcomes. This paper presents the results of survey-based research on
contract management critical success factors, derived from the responses
of approximately 400 contracting officers who represent 7 Department of
Defense (DoD) agencies. The principal contributions of this paper are to
show the similarities in both project management and contract
management critical success factors and the implications for the DoD.
The overall conclusion is that focusing on these critical success factors
can improve the DoD’s management of both projects as well as contracts.
The recommendation is that the DoD should focus on the common
knowledge areas and processes impacting project management and
contract management by addressing the identified critical success factors
in the areas of individual competencies and organizational structures and
processes.
INTRODUCTION
1
The extent and amount of defense procurement spending necessitates
that these contract management processes be well managed (Thai, 2004).
However, this is not necessarily the case. Between 2001 and 2009, the
Government Accountability Office (GAO) has issued 16 reports related
to trends, challenges, and deficiencies in federal government contracting.
Also, between 2002 and 2008, the DoD Inspector General (DoD IG)
issued 142 reports on deficiencies in the DoD acquisition and contract
administration processes. These reports have identified project
management and contract management as some of the critical deficient
areas in DoD contracts. The essence of DoD contract management is the
proper planning, award, and administration of contracts and the oversight
of contractor performance (Rendon & Snider, 2008). The lack of
effective contract administration and contractor oversight increases the
government’s risk of jeopardizing the total value for the dollars spent on
supplies and services. GAO and DoD IG reports have consistently
identified contract administration and contractor oversight as problem
areas in the management of service contracts (GAO, 2005; GAO, 2007;
OIG, 2009). The DoD is at risk of paying higher prices than necessary
for supplies and services. Because of this, the GAO has identified DoD
contract management as a “high-risk” area since 1992 (GAO, 2009,
January). This “high-risk” status reflects the DoD’s challenges in
achieving desired outcomes in terms of meeting procurement cost,
schedule, and performance objectives.
2
applied at various Air Force, Army, and Navy contracting agencies for
the purpose of assessing contract management process capability and
identifying process improvements, as well as obtaining empirical data for
use in characterizing the state of contract management process capability
throughout the DoD (Rendon, 2008; Rendon, 2009b).
3
management critical success factors as identified in the literature with the
contract management critical success factors indentified in our survey-
based research. The principal contributions of this paper are to show the
similarities in both project management and contract management critical
success factors and to discuss the implications for the DoD in terms of
individual and organizational competence. The overall conclusion is that
focusing on these critical success factors can improve the DoD’s
management of both its projects and its contracts.
Theoretical Framework
4
Agency theory is concerned with the conflicting goals between the
principal and agent in obtaining their respective objectives and is focused
on mechanisms related to obtaining information (for example, about the
marketplace, the supply or service, or the contractor), selecting the agent
(to counter the problem of adverse selection), and monitoring the agent’s
performance (to counter the effects of moral hazard). Thus, how
contracts are planned (for example, competitive or sole source),
structured (fixed price or cost reimbursement, with or without incentives),
awarded (based on lowest priced, technically acceptable offer, or the
highest technically rated offer), and administered (centralized or
decentralized, level and type of surveillance, and use of project teams…),
has its basis in agency theory and the principal-agent problem. Agency
theory can also be applied to project management, specifically in the
management of government projects (Moe, 1984). In government
projects, the same principal-agent model exists. The principal, in this
case the project manager, is faced with the problem of ensuring the
agents, in this context the members of the project team, will choose to
pursue the principal’s best interests.
This literature review will first focus on the basics of critical success
factors and then transition to success factors in project management and
contract management.
There has been much written on the identification and value of critical
success factors in business organizations. Daniel (1961) discusses
critical versus non critical elements of a business leading to success.
Rockart (1979) identifies the use of critical success factors in helping
executives define their information needs. He identifies critical success
factors as the “limited number of areas in which results, if they are
satisfactory, will ensure successful competitive performance for the
organization” (1979, p. 85). Rockart also discusses an interview method
for determining a manager’s critical success factors. Bullen and Rockart
(1981) differentiate critical success factors from other organizational
management terms such as “strategy,” “objective,” “goals,” “measures,”
5
and “problems.” They also identify five prime sources of critical success
factors (industry, competitive strategy/industry position, environmental
factors, temporal factors, and managerial position) and a classification
scheme for critical success factors (internal versus external and
monitoring versus building/adapting), as well as a hierarchy of critical
success factors (industry, corporate, sub-organization, and individual)
(Bullen & Rockart, 1981).
6
(integrative); 2) monitoring and control (integrative), team selection, and
technical performance; 3) communication, leadership, strategic direction,
and team development; 4) monitoring and control (risk), organizational
support, and stakeholder management (other); 5) organizational
structure; and 6) project definition and stakeholder management (client).
Finally, in a survey of over 150 project management professionals,
Baccarini and Collins (2003) identify fifteen critical factors for project
success. These factors, listed in Table 5, will be discussed later in the
paper.
7
In the next section, I discuss this paper’s research methods and the
research results. A discussion of the research findings compared to the
literature will then be presented.
METHODS
8
baccalaureate degree with at least 24 semester hours of coursework in
accounting, law, business, finance, contracts, purchasing, economics,
industrial management, marketing, quantitative methods, and
organization and management; two years of contracting experience; and
completion of the required contract training courses (DAWIA, 2009).
During 2008 and 2009, the survey website link was emailed to the
contracting officials for the following DoD contracting agencies:
The survey was then forwarded to the eligible contracting personnel for
completion. Reminder emails were sent approximately two weeks into
the survey period. (For TRANSCOM, the surveys were administered via
video-teleconferencing, completed hard-copy, and returned by mail.) The
survey instrument included the appropriate confidentiality and protection
of human subject provisions.
9
support of USTRANSCOM’s mission. The directorate typically
processes approximately 6,000 contract actions, with an annual spend of
approximately $6 billion (USTRANSCOM, 2009).
Navy Command Fleet Industrial Supply Centers (COMFISCS).
COMFISCS is comprised of the following seven individual FISC
commands: FISC-San Diego, FISC-Norfolk, FISC-Puget Sound, FISC-
Pearl Harbor, FISC-Yokosuka, FISC-Sigonella, and FISC-Jacksonville.
COMFISCS is responsible for supplying the Navy fleet with a wide
variety of supplies and services, including appliances, information
technology equipment, office furniture, and ship copiers. Services
procured include ship repair, husbanding functions, laundry, consulting,
and tugboats. In FY 2008, COMFISCS had completed 89,343
contracting actions that obligated a total of $4.2 billion (Bautista & Ward,
2009).
10
responsible for lifecycle management of Army missile, helicopter,
unmanned ground vehicle, and unmanned aerial vehicle weapon systems.
These weapon systems include the Patriot air defense missile system,
Hellfire and Javelin missile system, and Apache, Black Hawk, and
Chinook helicopters. The AMCOM Contracting Center provides
acquisition and contracting support for these weapon systems. In FY2008,
the AMCOM Contracting Center processed approximately 23,600
contract actions and obligated approximately $20.6 billion (AMCOM,
2009).
11
follow, to some extent, the same contract management lifecycle (Rendon
& Snider, 2008).
RESULTS
The survey was deployed to the seven agencies discussed in the previous
section. Table 1 shows, for each organization, the number of eligible
responders from the organization, the number of actual responders, the
response rate, and the number of actual responses. Of the total 821
eligible survey participants, 425 completed the survey, generating a
response rate of approximately 59%. The 425 survey participants
submitted a total of 1,531 responses to the open-ended question on
critical success factors.
Table 1
Table 2
12
DISCUSSION
Workforce (37%)
The Workforce category reflects the largest percentage of survey
responses. Common responses included statements related to having an
adequate number of personnel; proper staffing of vacant positions;
continuous hiring and recruitment of personnel; and a trained,
experienced, and competent workforce.
Also included in this category were responses related to the need for
specific workforce expertise (such as price analyst, quality assurance
personnel, policy specialists, and procurement analyst) and the
establishment of specific organizational entities (such as a contract
administration team, contract closeout team, full-time policy section,
separate small purchase section).
Table 3
13
Table 4
14
Processes (16%)
The Processes category constituted 251 of the 1,531 responses.
Responses included statements related to having documented,
standardized, consistent, efficient, effective, enforced, and streamlined
contracting processes. The most prominent response specifically related
to having standardized processes (39). Also included in this category
were responses related to flexible processes, sufficient time to perform
specific processes such as procurement planning, risk management, and
the integration of processes throughout the organization, and price and
cost analysis processes. This category also includes responses related to
the use of templates, and processes that were measured and continuously
improved through the establishment of lessons learned and best practices.
Processes specifically identified in the responses included procurement
planning (28), contract administration (16), source selection (15),
solicitation (10), contract closeout (4), and solicitation planning (3). In
addition, risk management (2) and project management (2) were also
identified as critical processes. Table 5 provides a sample of survey
responses related to this category.
15
Table 5
16
Relationships (15%)
The survey results provided 237 of the 1,531 responses related to
the Relationships category. Responses within this category included
statements concerning cooperation among acquisition team members and
end-users, coordination and support from program offices, good working
relationships with contractors, trust, and collaboration.
Table 6
17
Table 7
18
Resources (9%)
The Resources category consisted of 134 of the 1,531 responses. The
responses in this category included a wide variety of various resources
needed in the contracting process such as automated contract writing
systems, contract tracking tools, and other information technology
resources. Also included in this category were facilities, equipment,
supplies, technical support, and logistical support, as well as adequate
travel funds. Table 8 provides a sample of survey responses related to
this category.
Table 8
19
Leadership (9%)
The Leadership category accounted for 132 of the 1,531 responses.
These responses were all related to the need for strong, empowered
leadership and management support, quick decision-making, clear lines
of authority, and people-oriented management. This category also
included responses related to recognition of and support of contracting
officers, and managerial ability and experience. Table 9 provides a
sample of survey responses related to this category.
Table 9
20
Policies (4%)
The Policies category made up 66 of the 1,531 responses. This category
included responses such as updated, clear, concise, uniform guidance,
directions, and regulations. This category also included proper
dissemination of headquarters policies and the enforcement and concise
interpretation of policies. Also included in this category were responses
related to reducing unnecessary reviews and approvals (such as peer
reviews) and having realistic milestones and goals. Table 10 provides a
sample of survey responses related to this category.
Table 10
21
Requirements (3%)
Respondents provided 48 of the 1,531 responses within the Requirements
category. The Requirements category consisted of statements related to
complete, timely procurement request packages; complete, clear, defined
and timely procurement requirements; proper technical reviews; and
well-written statements of work (SOW), performance work statements
(PWS), and justification and approvals (J&A). Also included in this
category were responses related to complete and accurate budgets, stable
funding, and adequate procurement funding. Table 11 provides a sample
of survey responses related to this category.
Table 11
22
Comparison with Literature Review Findings
Table 12
23
Estimates, Adequate Project Control, Risk Management, Project
Planning).
Although the Policies category was not identified by Crawford, per se, it
could be implied in the Strategic Direction factor. The Policies category
was identified by Frame (Defined Procedures), and could also be implied
by Frame’s Organizational Vision and Institutionalization of Project
Management, as well as by Baccarini and Collins’ finding of Top
Management Support.
24
government contracting problems 1) problems relating to letting
contracts, 2) communication issues, 3) contractor internal management
issues, 4) government contract management issues, and 5) environment
or external issues are similar to the identified contract management
critical success factors identified in this research. This also holds true for
Rendon’s five organizational contract management process best practice
categories: 1) process strength, 2) successful results, 3) management
support, 4) process integration, and 5) process measurement. The final
section of this paper will present conclusions and recommendations
based on my research findings.
This research has shown that the contract management critical success
factor categories identified in the survey results are similar to critical
success factor categories for project management identified in the
literature. These research findings of similar success factors for both
project management and contract management can provide valuable
recommendations for improving organizational success in managing
projects and contracts.
25
These research findings suggest that the DoD should focus on the
common knowledge areas and processes impacting project management
and contract management by addressing the critical success factors of
Workforce, Processes, Relationships, Resources, Leadership, and Polices.
The DoD should consider combining some of the training and education
provided to project managers and contracting officers, as well as
consider integrating organizational structures and processes for
managing both projects and contracts. Because of the direct relationship
critical success factors have on an organization’s processes and resulting
outcomes, the DoD should address the critical success factor categories
identified in this research in improving its management of projects and
contracts.
26
ACKNOWLEDGEMENTS
The author gratefully acknowledges the support of recent graduates of
the Naval Postgraduate School Contract Management degree program
who contributed to this research: LCDR Romeo O. Bautista, US Navy;
Capt. Christopher J. Anglin, US Air Force; Major Jason D. Good, US
Army; LCDR Carl R. Ward, US Navy; Kevin P. Puma, Department of
the Army; Beth A. Sherr, Department of the Army; Ralph M. Neely,
Department of Defense; and Dina T. Jeffers, Department of the Army.
27
REFERENCES
28
Cohen, S., & Eimicke, W. (2008). The Responsible Contract Manager:
Protecting the Public Interest in an Outsourced World. Washington, DC:
Georgetown University Press.
29
Government Accountability Office (GAO). (2005, March). Contract
Management: Opportunities to Improve Surveillance on Department of
Defense Service Contracts (GAO-05-274). Washington, DC: Author.
30
Morris, P. W., & Hough, G. H. (1987). The Anatomy of Major Projects.
New York: John Wiley & Sons
31
Rendon, R. G. (2009a). “Contract Changes Management.” In G. A.
Garrett (Ed.), Contract Administration: Tools, Techniques and Best
Practices (pp. 69-87). Riverwoods, IL: CCH.
Schultz, R. L., Slevin, D. P., & Pinto, J. K. (1987). “Strategy and Tactics
in a Process Model of Project Implementation.” Interfaces, 17 (3): 34-46.
32