Foundation Code Handbook 2017 PDF
Foundation Code Handbook 2017 PDF
to
the Code of Practice
for
Foundations 2017
Structural Division
The Hong Kong Institution of Engineers
An Explanatory Handbook
to
the Code of Practice
for
Foundations 2017
June 2019
Prepared by a Working Committee of
Structural Division
The Hong Kong Institution of Engineers
Published by
Structural Division
The Hong Kong Institution of Engineers
Published by the Structural Division of the Hong Kong Institution of Engineers
Foreword
With an aim to facilitate understanding of the rationale and application of the code of practices
published by the Buildings Department of Hong Kong, the Structural Division of the Hong Kong
Institution of Engineers has published the “Explanatory Handbook to the Code of Practice for
Foundations 2004” for the Foundation Code promulgated in 2004. While the Foundation Code
has been updated and published in 2017, the Structural Division has taken the initiatives to revise
the Handbook accordingly which is now named “An Explanatory Handbook to the Code of
Practice for Foundations 2017”.
The updated handbook adopts similar formats and approaches as the 2004 version. Apart from
adding new materials to explain the new topics, a thorough review of the existing topics has also
been carried out and with updating as necessary.
We trust that the content of this handbook would help practitioners in design and construction of
foundation works for compliance with the current Foundation Code.
With the above, it gives me enormous pleasure to recommend you to read this Handbook. I
would also like to congratulate the Working Committee, chaired by Ir Lam King-kong for their
dedicated efforts and professionalism which make this handbook a great success.
i
An Explanatory Handbook to Code of Practice for Foundations 2017
Acknowledgement
This Explanatory Handbook for the Code of Practice for Foundations 2017 as the revised version
to the previous 2004 version of the Foundation Code aims to echo with the revisions in the Code.
It incorporates the views and comments of experienced researchers and practicing engineers. It
has been compiled by a Working Committee appointed by the Structural Division of the Hong
Kong Institution of Engineers. The Working Committee Members are as follows-
The Chairman of the Working Committee would like to express his deep gratitude to each
Committee Member and those who contributed during the course of the compilation work over
the past years, including the Structural Division Committee Members of the Hong Kong
Institution of Engineers. Without their remarkable contributions and unreserved efforts, this
Explanatory Handbook would not have been successfully finalized and published.
ii
An Explanatory Handbook to Code of Practice for Foundations 2017
Contents
Page
No.
H1 General …………………………………………………………………………...... 1
iii
An Explanatory Handbook to Code of Practice for Foundations 2017
H3 Site Investigation 28
v
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendices
Page
No.
Appendix HA Practical Examples of Inspection of Rock Samples ………………… A-1
Appendix HB A Worked Example on Determination of Ultimate Bearing Capacity
of an Inclined Rectangular Footing …………………………………. B-1
Appendix HC Determination of Settlement and Support Stiffness of Footings on an
Elastic Subgrade …………………………………………………….. C-1
Appendix HD Design of General Flexural Reinforcement in a R.C. Plate Bending
Structure …………………………………………………………….. D-1
Appendix HE A Worked Example on Determination of the Group Reduction
Factor (Geotechnical Capacity) of a Pile Group in Cohesionless
Soil …………………………………………………………………... E-1
Appendix HF Worked Examples for Determination of Ultimate Lateral Shear
Resistances of Piles ………………………………………………… F-1
Appendix HG Checking of Piles against Uplift, Overturning and Buoyancy of a
Hypothetical Pile Group …………………………………………….. G-1
Appendix HH Equivalent Raft Method …………………………………………….. H-1
Appendix HI Buckling of Slender Piles – Embedded, Partially Exposed or Sleeved
in Soil…...…………………………………………………………… I-1
Appendix HJ Principle and Derivation of the Hiley Formula ……………………... J-1
Appendix HK Discussion on Limits of “Final Set” and Criteria for Formulation of
the “Final Set” Table ………………………………………………... K-1
Appendix HL More Details and Examples in Wave Equation, the Case Method and
CAPWAP for Analysis of Pile Capacities …………………………... L-1
Appendix HM Closed Form Solution for the Bearing Capacity Factor Nq in
accordance with Berezantsev ……………………………………….. M-1
Appendix HN Worked Examples for Determination of Ultimate Uplift Resistance
of Piles ………………………………………………………………. N-1
vi
An Explanatory Handbook to Code of Practice for Foundations 2017
Page
No.
References Ref-1
vii
An Explanatory Handbook to Code of Practice for Foundations 2017
List of Tables
Page
No.
Table H5.1 Values of nh for Cohesionless Soils ……………………………….. 61
Table H5.2 Data of Common Precast Prestressed Spun Concrete Pile ……....... 67
Table H5.3 Determination of Geotechnical Capacity of a Small Diameter
Bored Pile …………………………………………………………. 70
Table HG-1 Example of Checking of Piles against Uplift, Overturning and
Buoyancy of a Hypothetical Pile Group ………………………….. G-1
Table HH-1 Summary for Calculation for Worked Example HH-1 …………… H-3
Table HH-2 Calculation for Worked Example HH-2 by the Approach in
Appendix HC ……………………………………………………… H-3
Table HI-1 Restraint Conditions on Lateral Load Analysis on Pile by the
Finite Difference Method …………………………………………. I-3
Table HI-2(a) Table showing Variation of “Equivalent Length Factor” with L/T
ratio and Pile Exposed Length Factor for End-bearing Piles with
Bottom Free ……………………………………………………….. I-4
Table HI-2(b) Table showing Variation of “Equivalent Length Factor” with L/T
ratio and Pile Exposed Length Factor for End-bearing Piles with
Bottom Pinned …………………………………………………….. I-5
Table HI-2(c) Table showing Variation of “Equivalent Length Factor” with L/T
ratio and Pile Exposed Length Factor for End-bearing Piles with
Bottom Fixed ……………………………………………………… I-5
Table HI-2(d) Table showing Variation of “Equivalent Length Factor” with L/T
ratio and Pile Sleeved Length Factor for End-bearing Piles with
Bottom Free ……………………………………………………….. I-6
Table HI-2(e) Table showing Variation of “Equivalent Length Factor” with L/T
ratio and Pile Exposed Length Factor for End-bearing Piles with
Bottom Pinned …………………………………………………….. I-6
Table HI-2(f) Table showing Variation of “Equivalent Length Factor” with L/T
ratio and Pile Exposed Length Factor for End-Bearing Piles with
Bottom Fixed ……………………………………………………… I-7
Table HK-1 Final Set Values per 10 Blows with No Restriction on the S values K-3
Table HK-2 Final Set Values per 10 blows (i) with limits between 25mm and
100mm per 10 Blows; (ii) and (cp+cq)/L ≤ 1.15 where cp+cq is in
mm and L is in m ………………………………………………….. K-3
Table HK-3 Final Set Values per 10 blows (i) with limits between 25mm and
100mm per 10 Blows; (ii) (cp+cq)/L ≤ 1.15 where cp+cq is in mm;
and L is in m; and (iii) S capped at 50mm ………………………… K-4
Table HL-1 Estimation of Ultimate Static Resistance of a Hypothetical Pile by
the Case Method …………………………………………………... L-9
Table HN-1 Computation of Ultimate Uplift Resistance of a Driven Pile
(Effective Stress Method) …………………………………………. N-6
Table HN-2 Computation of Ultimate Uplift Resistance of a Driven Pile (SPTN
Values) ……………………………………….................................. N-7
Table HO-1(a) Coefficient of Translation Soil Poisson’s Ratio µ = 0.3 ………….. O-7
viii
An Explanatory Handbook to Code of Practice for Foundations 2017
Table HO-1(b) Coefficient of Translation Soil Poisson’s Ratio µ = 0.35 ………… O-7
Table HO-1(c) Coefficient of Translation Soil Poisson’s Ratio µ = 0.4 ………….. O-8
Table HO-1(d) Coefficient of Translation Soil Poisson’s Ratio µ = 0.45 ………… O-8
Table HO-1(e) Coefficient of Translation Soil Poisson’s Ratio µ = 0.5 ………….. O-8
Table HO-2(a) Coefficient of Rotation Soil Poisson’s Ratio µ = 0.3 …………….. O-9
Table HO-2(b) Coefficient of Rotation Soil Poisson’s Ratio µ = 0.35 …………… O-9
Table HO-2(c) Coefficient of Rotation Soil Poisson’s Ratio µ = 0.4 …………….. O-9
Table HO-2(d) Coefficient of Rotation Soil Poisson’s Ratio µ = 0.45 …………… O-10
Table HO-2(e) Coefficient of Rotation Soil Poisson’s Ratio µ = 0.5 …………….. O-10
Table HP-1 Restraint Conditions on Lateral Load Analysis on Pile by the
Finite Difference Method …………………………………………. P-1
Table HP-2 Use of Coefficients for Determination of Displacements,
Rotations, Shears and Moments in Piles by the Finite Difference
Method …………………………………………………………...... P-2
Table HP-3(a) Deflection and Moment Coefficients for Pile with Free Head and
Tip Unrestrained from both Lateral Movement and Rotation due to
Horizontal Shear at Cut-off Level ………………………………… P-4
Table HP-3(b) Deflection and Moment Coefficients for Pile with Head Restrained
from Rotation and Tip Unrestrained from both Lateral Movement
and Rotation due to Horizontal Shear at Cut-off Level …………… P-4
Table HP-3(c) Deflection and Moment Coefficients for Pile with Free Head and
Tip Restrained from Lateral Movement but Free to Rotate due to
Horizontal Shear at Cut-off Level ………………………………… P-4
Table HP-3(d) Deflection and Moment Coefficients for Pile with Head Restrained
from Rotation and Tip Restrained from Lateral Movement but
Free to Rotate due to Horizontal Shear at Cut-off Level …………. P-5
Table HP-3(e) Deflection and Moment Coefficients for Pile with Head Pinned
and Tip Restrained from both Lateral Movement and Rotation due
to Horizontal Shear at Cut-off Level ……………………………… P-5
Table HP-3(f) Deflection and Moment Coefficients for Pile with Head Restrained
from Rotation and Tip Restrained from both Lateral Movement
and Rotation due to Horizontal Shear at Cut-off Level ………….. P-5
Table HP-4(a) Rotation Coefficients for Pile Tip Unrestrained from both Lateral
Movement and Rotation due to Moment at Pile Head ……………. P-6
Table HP-4(b) Rotation Coefficients for Pile Tip Restrained from Lateral
Movement but Free to Rotation due to Moment at Pile Head ……. P-6
Table HP-4(c) Rotation Coefficients for Pile Tip Restrained from both Lateral
Movement and Rotation due to Moment at Pile Head ……………. P-6
Table HP-5(a) Shear Coefficients for Pile Tip Unrestrained from both Lateral
Movement and Rotation due to Moment at Pile Head ……………. P-7
Table HP-5(b) Shear Coefficients for Pile Tip Restrained from Lateral Movement
but Free to Rotation due to Moment at Pile Head ………………… P-7
Table HP-5(c) Shear Coefficients for Pile Tip Restrained from both Lateral
Movement and Rotation due to Moment at Pile Head ……………. P-7
Table HP-6 Comparison of Results between Worked Examples HP-1 and HP-2 P-10
Table HQ-1 Lateral Stiffness of the Piled Foundation of Worked Example
HQ-1 ………………………………………………………………. Q-4
ix
An Explanatory Handbook to Code of Practice for Foundations 2017
List of Figures
Page
No.
Figure H1.1 General Configuration of Bell-Out of Bored Pile ………………… 2
Figure H1.2 Typical Final Set Graph …………………………………………… 3
Figure H1.3 Modes of Failure for Ultimate Bearing Capacity …………………. 5
Figure H2.1 Measures to mitigate the Migration of Soil into any Voids that may
be formed underneath the Suspended Structure …………………... 13
Figure H2.2 Worked Example H2.1 for Checking Stability ……………………. 16
Figure H2.3 Typical Socketed H-Pile with Cross Bars as Shear Connectors …... 19
Figure H2.4 Chemical Process of Corrosion …………………………………… 23
Figure H2.5 Splash and Tidal Zone in a Marine Foundation …………………… 24
Figure H2.6 Examples of Cathodic Protection to Piles in Marine Foundations .. 25
Figure H3.1 Vertical Stress Bulb beneath a Square Footing or a Circular
Footing (or Pile) …………………………………………………... 33
Figure H4.1 Ground Pressure Distribution beneath Footing under Different
Assumptions ……………………………………………………… 38
Figure H4.2 Explanation of Ground Bearing Pressure under the Continuum
Theory ……………………………………………………………... 39
Figure H4.3 Demonstration of the Determination of Design Forces on Sections
of Footing …………………………………………………………. 40
Figure H4.4 Plans showing Pad Footings, Strip Footings and Raft Footings ….. 42
Figure H5.1 Illustration of Pile Group Effect on Pile Settlement ………………. 44
Figure H5.2 Load Displacement Path for Set and Temporary Compression of 52
Soil …………………………………………………………………
Figure H5.3 Splicing Details for H-pile (for Lengthening of Pile) …………….. 64
Figure H5.4 Details for Pile Head ……………………………………………… 64
Figure H5.5 Acceptable Details for Pile Toe – Strengthened for Hard Driving 65
on or close to Bedrock ……………………………………………..
Figure H5.6 Details of a 14”×14” Precast Reinforced Concrete Pile …………... 66
Figure H5.7 Details of Pile Shaft of a Precast Prestressed Spun Concrete Pile ... 68
Figure H5.8 Typical Pile Head Details of a Precast Prestressed Spun Concrete
Pile…………………………………………………………………. 68
Figure H5.9 Pile Shoe Details of a Precast Prestressed Spun Concrete Pile …… 68
Figure H5.10 Pile Head Details of a Driven Cast in Place Pile ………………….. 69
Figure H5.11 Details of a Small Diameter CFA Pile …………………………….. 71
Figure H5.12 Details of a Typical Large Diameter Bored Pile …………………... 73
Figure H5.13 Shear Plane for Checking Bond Stress between Steel Bars and
Grout for 4T50 and 5T50 Mini-pile ………………………………. 75
x
An Explanatory Handbook to Code of Practice for Foundations 2017
xi
An Explanatory Handbook to Code of Practice for Foundations 2017
Figure HJ-1 Energy Transfer Process as Assumed by the Hiley Formula ……… J-1
Figure HJ-2 Work Done in Quake and Set as Assumed by the Hiley Formula … J-3
Figure HL-1 Derivation of Wave Speed in Pile …………………………………. L-1
Figure HL-2 Derivation of the Basic Wave Equation ………………………........ L-2
Figure HL-3 Pile Forces and Velocities …………………………………………. L-4
Figure HL-4 Wave Transmission in Pile Shaft ………………………………….. L-5
Figure HL-5 Typical Plot of Measured Forces and Velocities of a Pile by PDA
Test .………………………………………………………………... L-9
Figure HL-6 Smith’s Idealization of Pile ………………………………………... L-10
Figure HL-7 Typical Graphs showing Good Matching between the Measured
Forces and Calculated Forces with Time ………………………….. L-11
Figure HL-8 Wave Forms of P and Z⋅v of a Pile undergoing PDA Test and
Photograph showing the Defected Portion ………………………... L-12
Figure HM-1 Bearing Capacity Factor Nq for Circular Foundations (after Kezdi,
1975) ……………………………………………………………… M-1
Figure HM-2 The Shapes of Failure Modes at the Pile Tips as assumed by (a)
Terzaghi and Berezantsev; (b) Meyerhof; (c) Vesic ………………. M-2
Figure HM-3 Bearing Capacity Factors of Berezantsev and Brinch Hansen (after
Tomlinson 2008) ………………………………………………….. M-2
Figure HM-4 Variation of Nq with φ at Different L/d ratios to Berezantsev …….. M-4
Figure HN-1 Geometrical Shapes due to Overlapping of Soil Columns and Rock
Cones of Two Adjacent Circular Piles ……………………………. N-1
Figure HN-2 Worked Example for Checking Uplift of a Large Diameter Bored N-3
Pile …………………………………………………………………
Figure HN-3 Overlapping of Soil Columns and Rock Cones of 4 Large
Diameter Bored Pile for Worked Example HN-2 …………………. N-4
Figure HN-4 Pile Layout for Worked Example HN-5 ………………………….. N-8
Figure HO-1 Illustration of the Use of (Eqn HO-1) …………………………….. O-1
Figure HO-2 Coordinate System for Calculation of Lateral Displacement of Pile
Cap ………………………………………………………………… O-2
Figure HO-3 Calculation of Horizontal Displacement of a point X on the Front
Face of a Uniformly Distributed Load acting on a Vertical Plane
within a Semi-infinite Homogenous Elastic medium ……………... O-2
Figure HO-4 Lateral Deflection Contour of a Vertical Plane Exerting u.d.l. in a
Semi-infinite Homogenous Elastic Medium ……………………… O-3
Figure HO-5 Front face of a Pile Cap divided into a Number of Equal
Rectangular Elements ……………………………………………... O-4
Figure HP-1 Illustrative Plots of Deflection and Moment Coefficients of Pile
under Lateral Load ………………………………………………… P-3
Figure HP-2 The Winkler’s Spring Model for Piles under Lateral Load …….…. P-9
Figure HP-3 An Example Demonstrating the Differences in Deflection and
Bending Moment of a Pile with Free Head with and without
P-∆ Effect …………………………………………………………. P-11
Figure HP-4 An Example Demonstrating the Differences in Deflection and
Bending Moment of a Pile with Fixed Head with and without
P-∆ Effect ………………………………………………………….. P-12
Figure HQ-1 Piling Layout Plan and Details for Worked Example HQ-1 ……… Q-3
xiii
An Explanatory Handbook to Code of Practice for Foundations 2017
xiv
An Explanatory Handbook to Code of Practice for Foundations 2017
Photo HU3.1 Drilling with the first Temporary Casing ………………………..... U-5
Photo HU3.2 Checking Alignment ………………………..................................... U-5
Photo HU3.3 Drilling Works by ODEX Method ………………………............... U-5
Photo HU3.4 ODEX Drilling Bit ………………………....................................... U-6
Photo HU3.5 Prefabrication of Steel H-pile for Socket Length Portion ……….... U-6
Photo HU3.6 Double Shelter for Noise and Dust Reduction during Piling ……... U-6
Photo HU3.7 Casing Joint Preparation …………………………………………... U-6
Photo HU3.8 Splicing of Temporary Casing …………………………………….. U-6
Photo HU3.9 Splicing of Steel H-pile …………………………………………… U-6
Photo HU3.10 Obtaining Rock Sample after Completion of Drilling Operation … U-6
Photo HU3.11 Preparation Works for Grouting Work ……………………………. U-6
Photo HU3.12 Air-lifting before Grouting Work …………………………………. U-6
Photo HU3.13 Cement Grouting Work for the Socketed H-Pile ………………….. U-7
Photo HU3.14 Extracting Temporary Steel Casing by Vibrating Hammer ……….. U-7
Photo HU3.15 Extracting Temporary Steel Casing by Hydraulic Jack under
Adverse Condition ………………………………………………… U-7
Photo HU3.16 Grouting Testing Work…………………………………………….. U-7
HU.4 Mini-pile
xv
An Explanatory Handbook to Code of Practice for Foundations 2017
Photo HU6.1 Shallow Trench formed and surrounded by Guide Walls and filled
by Bentonite Slurry ……………………………………………….. U-10
Photo HU6.2 Silos on Site for Re-circulation of Bentonite Slurry ……………… U-10
Photo HU6.3 The Hydromill Machine for Trench Excavation …………………. U-10
Photo HU6.4 Cutter at the bottom of The Hydromill Machine …………………. U-11
Photo HU6.5 Excavation by Hydromill within Guide Walls ……………………. U-11
Photo HU6.6 Scrapers used to Clean Trench sides by Removing Excess Filter
Cake ……………………………………………………………….. U-11
Photo HU6.7 Reinforcement Cage Pre-fabricated on Site ………………………. U-11
Photo HU6.8 Lifting Reinforcement Cage ………………………………………. U-11
Photo HU6.9 Lowering Reinforcement Cage into Excavation Trench ………….. U-11
Photo HU6.10 Tremie Concreting for Barrette …………………………………… U-11
Photo HU6.11 Finished Barrette after Concreting / Grouting …………………….. U-11
Photo HU7.1 Open Excavation for Raft Footing Construction ………………….. U-12
Photo HU7.2 Blinding the Bottom Level of the Raft Footing …………………... U-12
Photo HU7.3 Reinforcement Fixing for the Bottom Slab ……………………….. U-12
xvi
An Explanatory Handbook to Code of Practice for Foundations 2017
xvii
An Explanatory Handbook to Code of Practice for Foundations 2017
H1 GENERAL
As similar to the Handbook to Code of Practice for Foundations 2004, this Handbook
explains and elaborates the Code of Practice for Foundations 2017 on a clause by clause
basis, with the clause numbers prefixed by the letter “H” for ease of identification and
distinction. Figures, tables and equations in the Handbook are also prefixed by “H” for
the same purpose.
H1.1 SCOPE
The “Code of Practice for Foundations” is referred to as “the Code” hereafter in this
Handbook.
The Code covers mainly analysis, design, site investigation, construction and testing of
foundations. Relevance to local practice is emphasised.
The Code contains deemed-to-satisfy requirements (satisfying the Hong Kong Building
(Construction) Regulations). However, justifications based on the principles of
mechanics are also permitted, including rational design methods for determination of the
ultimate capacity of subgrades.
Cross references to other technical documents and codes including the current Codes of
Practice for the Structural Use of Concrete and Steel for design are also included. The
Code permits both ultimate limit state and permissible stress methods in the design of
structural elements. However, avoidance of over-stressing a foundation element beyond
its yield strength under the application of the required test load needs also to be
considered in design which constitutes a limiting minimum design strength constraint.
Analysis and design approaches together with a number of worked examples have been
included in this Handbook to illustrate the use of recognized approaches in solving
specific engineering problems. But it must be stressed that these do not represent the
only acceptable approaches. Others based on sound laws of mechanics with justified
design parameters are also acceptable.
H1.2 GLOSSARY
Elaborations / clarifications of some of the terms defined by the Code in this section are
stated as follows :
The allowable load refers to the working load being applied to the foundation and the
subgrade which is usually the “characteristic load” (normally defined as the load with a
5% chance of being exceeded). The allowable bearing pressure is often taken as the
“ultimate bearing capacity” divided by a factor of safety which is checked against the
allowable load in design.
Page 1 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Bell-out
The function of the bell-out of a bored pile is to increase the end-bearing capacity of the
pile due to the enlarged base area so that the structural capacity of the concrete can be
more fully utilized. The general configuration of a bell-out is as shown in Figure H1.1 in
relation to the rockhead and founding levels, with the limitation of the bell-out diameter
to 1.65 times the shaft diameter of the pile (Re clause 5.4.7) which can be taken as that
formed above bedrock as shown in the figure. The limitation of the bell-out size is to
avoid ineffective spreading of the load from the bored pile shaft to the rock bearing
stratum. Furthermore, in addition to the bearing on rock under the use of bell-out, the
Code also allows inclusion of bond / frictional resistance derived from rock for a height
not greater than the lesser of 3m and the rock socket diameter as part of the pile’s load
carrying capacity as provided in clause 5.4.7. However, the socket length can be doubled
(the lesser of 6m and twice the rock socket diameter) if no bell-out is used.
Thickness of
Temporary
Casing Dia. = D3
formed by
Dia. = D2 permanent
formed by the casing and
temporary Soil with sleeving
casing
Dia. = D2
formed by the Thickness of
Rock head level Rock head level
temporary Temporary
casing Casing
500mm for Cat. 1(a) & (b),
300mm for Cat. 1(c), (d) & 2
Overbreak Bell-out
Bell-out
(a) Bored Pile Bell-out without (b) Bored Pile Bell-out with
Permanent Casing Above Permanent Casing above
Page 2 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Final set
The final set (denoted by the symbol s) is defined in the Code as the penetration per blow
of the driving hammer which is the same as that GEO Publication 1/2006. As
distinguished from the elastic displacement of the pile and the soil (usually denoted by Cp
+ Cq), which is recoverable after the strike by the hammer, the set is the permanent
settlement of the pile which is non-recoverable.
The local practice generally is to calculate the final set as the average set value of the last
10 pile driving blows in accordance with the following typical final set graph contained
in Figure H1.2.
Rock Socket
Page 3 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Test driving of a pile is often carried out prior to commencement of the main piling work
and is required even for recognized types of piles, normal installation method and normal
ground geology. Apart from verification of design assumptions, integrity and
constructability can also be verified with respect to the installation method, ground
geology and founding level by the test driving. The term should include installation of
both percussive and non-percussive piles such as driven piles, socketed piles and mini-
piles. Loading test is normally not required.
Test pile
A test pile refers to a completed working pile chosen among others to undergo testing
(usually a loading test) for verification of its load-carrying capacity and/or displacement
characteristics. The success or failure of the test will lead to acceptance, rejection or a
requirement for further tests of the bulk of the remaining working piles represented by the
test pile.
Trial pile
A trial pile is often required for (i) a new pile type; (ii) an unconventional design method,
or verification of a set of design parameters, and/or a new installation method; (iii) a pile
type and/or installation method where there is inadequate local experience; and/or (iv) a
site with complex geology, and/or (v) steel H-piles driven to bedrock with design net
length shorter than 10m and for any other special reasons. Installation and test of the trial
pile is often carried out prior to commencement of the main piling work. Loading test, if
feasible, will normally be required.
The definition in the Code includes both full mobilization of the resistance of the bearing
stratum and substantial deformation. However, the latter is not well defined or quantified.
BS8004:2015 which names by another term “ultimate unit base resistance” has referred
to BSEN1997-1-2004 for defining the term “resistance” as “capacity of a structure to
withstand actions without failure, e.g. resistance of the ground.” Conventionally ultimate
bearing capacity is defined as failure (shear failure according to Craig (2004)) of the
subgrade which involves splitting or tearing away of the subgrade structures generally in
the modes illustrated in Figure H1.3 with reference to a strip footing.
The deformation at ultimate bearing failure is very large and is normally not quantified as
a criterion for defining ultimate bearing capacity. The control of deformation, however,
is taken as a separate criterion for foundation design as in clause 2.1.1 in which a
foundation has to be designed so that it (i) possesses a factor of safety of 2 or 3 over the
ultimate bearing failure; and (ii) has a limiting deformation (quantified) under the
working load condition. It should also be noted that the equation given in clause 2.2.4
based on soil mechanics principle, is only suitable for failure mode (a) in Figure H1.3.
Page 4 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
H1.3 ABBREVIATIONS
GI Ground Investigation
GIU Geotechnical Information Unit of the Civil Engineering Library in the
Civil Engineering and Development Department
HKB(C)R Hong Kong Building (Construction) Regulation
SPT N value Uncorrected Standard Penetration N value before foundation installation
H1.4 SYMBOLS
A number of symbols are listed in this clause of the Code. Nevertheless, the following
should be noted :
(i) L has been defined as the symbol for pile length in mm in this clause. However,
the same symbol has been defined as length of core run in Note (11) under Table
2.1.
Page 5 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
H2.1 GENERAL
The Code describes the basic requirements for foundation design and construction in this
sub-clause. The following are highlighted and discussed:
(ii) The “allowable capacity” of the soil/rock can be determined by the lesser of
(1) the “ultimate capacity” (defined as the least pressure which will cause
shear failure of the soil/rock) divided by an adequate factor of safety
against failure; and
The determination of the factor of safety for the former is based on a number of
factors as stated in the Code. In practice, the factor of safety is in the range of 2
to 3, depending on the uncertainties in the behaviour of the foundation. For
example, the allowable bearing capacity of soil can be obtained from the ultimate
bearing capacity divided by a factor of safety of 3, though it is often the
settlement or differential settlement which is the controlling criterion. Another
example for determination of “allowable capacity” in accordance with the
settlement criterion is that of a common driven pile which is the least load acting
on the pile to cause a pre-determined limiting settlement divided by a factor of
safety of 2;
(iii) The allowable capacity can be increased by 25% when such increase is solely due
to wind which induces load of transient nature.
It should be noted that a foundation should be designed for dead, imposed and wind loads
where imposed load covers live loads, water uplift and earth load. This is to accord with
the Building (Construction) Regulations and the Code of Practice for Dead and Imposed
Load 2011.
Page 6 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
GEOGUIDE 3 is referred to by the Code for the classification of soils and rocks. As
described by the Guide, there are two kinds of rock descriptions to serve specific
purposes. The one for engineering usage of ‘rocks’ and ‘soils’ gives an indication of the
likely engineering properties of the rock. The geological classification of ‘rocks’ and
‘superficial deposits’ enables interpretation of the geological structure of an area and
good correlation between boreholes. In practice, the geological classification does not
include the engineering properties of rock but the engineering properties are often closely
related to the geological characteristics.
Rock material weathering in Hong Kong rarely produces a homogeneous weathered rock
mass where all rock material is weathered to the same degree, or even a simple weathered
profile where the degree of weathering decreases progressively with depth. Complex
variation of weathering throughout the rock mass is often the rule as seen in the Worked
Example HA-1 in Appendix HA which is abstracted from Figure 4 of the GEOGUIDE 3.
The presence of discontinuities and the effects of weathering have a great influence on
engineering behaviour and should be treated with care.
Apart from adopting presumed values for the allowable capacity of soils and rocks, the
Code allows using a rational design method for calculating the ultimate bearing capacity
which, by applying a factor of safety, can be converted to an allowable capacity. A factor
of safety of 3 is normally adopted with respect to geotechnical capacity in view of the
uncertainties involved. An example of the rational design method is that based on the
ultimate bearing capacity equation in the form of qu = cN c + 0.5 BγNγ + qo N q for shallow
strip footings as found in common soil mechanics textbooks. A more detailed form of the
equation taking account of dimensions and load eccentricities at the footing is given in
Vesic (1973) which is also quoted in GEOGUIDE 1 and reproduced in clause 2.2.4 of the
Code. It should be noted that the allowable bearing capacity should be checked against
the loading pressure calculated based on the effective dimensions of the shallow footings
(i.e. Bf’ and Lf’) instead of the maximum bearing pressure derived from the eccentricity
of the loading.
Other factors of safety may be adopted having regard to the nature of the soil or rock, its
variability over the site and the reliability of the design method or whether there is some
form of proof-testing that has been carried out during pile installation. This applies to the
situation when well-established design methods are used. For example, if the Hiley
formula is adopted in driven pile design, where the pile will be subject to some form of
proof-testing by achieving an acceptable final set value, a lower factor of safety of 2 can
commonly be used which is applied to the design working load.
Page 7 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
(1) General
The Code has included in H2.2.2 a set of “Presumed Values” for the allowable
vertical bearing pressures on horizontal ground in its Table 2.1. These values can
be adopted under the conditions stated in paragraphs (1) (a) and (b) of the Code
which refers to the sites where site investigations have been carried out and
normal structures are to be constructed. It should be noted that the use of the
“Presumed Values” does not preclude the requirement for consideration of
settlement of the structure which may need to be assessed separately.
The Code refers to Table 2.1 for presumed values of vertical bearing values of
soil and rock on the basis of the material description. Some points are discussed
as follows :
Page 8 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Note (5) of Table 2.1 requires that the founding stratum should be proved to
a depth of at least 5m into the specified category of rock because a rock
layer of thickness less than 5m is traditionally treated as corestone.
However, in the case of piles with a rock socket, the requirements on pre-
drilling should be followed as stipulated in para. 10 of PNAP APP-18. In
such cases, the drilling should be sunk into the rock mass for at least 5m
below the rock head of the specified grade or the designed length of the rock
socket of the nearest pile, whichever is the deeper.
Table 2.2 of the Code specifies different values of presumed allowable bond or
friction between rock and the concrete of piles for the conditions “under
compression or transient tension” and “under permanent tension.” It should be
understood that transient tension refers to tension in the foundation structure
under transient loads such as wind loads whereas permanent tension results from
persistent dead loads, soil loads and the like. As an example, a load case of
“Dead Load minus Wind Load” resulting in tension should be considered a
transient tension. However, tension resulting from flotation should not be
considered as transient as the duration of the flotation load can be long, possibly
half a day in the case of tidal variation or even longer for severe storm conditions.
The clause allows the use of allowable vertical bearing pressure of 100kPa (if dry)
or 50kPa (if submerged) for the design of minor temporary structures which
should include fencing, hoarding, lamp pole, covered walkway, disabled ramp,
minor single storey buildings – e.g. refuse collection point, pergola.
Examples of insitu testing methods include the “Plate Load Test” and the full scale
loading test.
The clause first lists an equation for determination of allowable vertical bearing pressure
qa for shallow foundations (depth to bottom not greater than 3 m by Note (1)) as follows :
q − qo
qa = u + qo
F
where qu is the ultimate bearing capacity, qo is the effective overburden pressure at the
base of the foundation due to the soil originally exists above the foundation and F is the
Page 9 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
factor of safety not less than 3. The applicability of the formula is irrespective to whether
there will be soil backfill over the top of the foundation after construction.
where qu − qo and qa − qo refer to the effective ultimate bearing capacity and allowable
bearing capacity after reduction of qo which is often known with high certainty. The
ratio of qu − qo to qa − qo is the required factor of safety F .
The clause lists the general equations for determination of qu for shallow foundation
with limitations based on the work of Vesic (1973, 1975) which have been quoted in
GEOGUIDE 1. A worked example is contained in Appendix HB of this Handbook.
Nevertheless, it should be noted that though the use of the bearing capacity equation for
foundations on soil can often achieve values significantly higher than the presumed
values in Table 2.1, two restraints are imposed :
In addition, the Code has provided in Figure 2.4 that the application of the bearing
capacity equation to an irregular shaped shallow footing can be taken as that of a
rectangular one with dimensions as the largest inscribed rectangle in the irregular shape
of the footing. As the bearing capacity increases generally with the plan dimension of the
footing, the approach is generally a conservative one for homogeneous soil or for soil
strata with strength increasing with depth.
(1) General
Page 10 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The Code lists the following formula for estimation of immediate settlement of
foundations on granular based on the elastic theory
qnet B f ' Fo
Se =
Es
The formula is a popular one listed in common text books which can used to
calculate the settlement of a rectangular loaded area with different values of Fo
depending on length breadth ratio of the footing, hard stratum depth to footing
breadth ratio, buried depth to footing breadth ratio and Poisson’s ratio of the soil.
The Code refers the determination of the coefficient Fo to GEO Publication No.
1/2006 (in clause 3.2 of the Publication). Poulos & Davis (1974) and Tomlinson
(2008) contain charts and tables for deriving the Fo under different loading
configurations and loaded area in resting on elastic medium. A series of charts for
quick estimation of mean settlements of rectangular footings covering variations
of the afore-mentioned parameters, together with the basic principles, analytical
approach and worked examples for single and multi-layered soils are included in
Appendix HC for ease of use by the readers.
[A digital copy of the book by Poulos & Davis (1974) is published and with the
permission of the authors and can be downloaded in this link:
http://research.engr.oregonstate.edu/usucger/PandD/PandD.htm]
In fine grained soils, the immediate settlement depends on the rate of the
dissipation of excess pore water pressure caused by the application of the
foundation loads. This is usually termed as primary consolidation settlement.
Soils continue to deform after the primary consolidation settlement and this
process is termed as secondary compression (or creep). Nevertheless, the
followings are highlighted for reference by the readers :
(i) Primary consolidation is the process by which water is expelled from the
fine-grained soil leading to decrease in volume and thus settlement under
long term loading. As the permeability of the soil is low, the
consolidation process will take time, the completion of which may take
years. Primary consolidation can be regarded being completed when the
excess pore water pressure has dissipated to zero;
(ii) Secondary consolidation follows that of the primary consolidation which
is caused by creep – gradual readjustment of the soil particles to a more
stable configuration which leads to further settlement. The time at which
secondary consolidation commences is not well defined. A pragmatic
approach is to assume that the secondary consolidation settlement
commences when 95% of the primary consolidation is reached;
(iii) The soil is described as over-consolidated, normally consolidated or
under-consolidated if it has been under a pre-consolidated stress which is
higher, identical or smaller stress in the past as compared with the present
Page 11 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
stress. The past history of stress affects the consolidation settlement under
applied stress ∆σv;
(iv) The soil parameters including the pre-consolidated stress can be estimated
by the oedometer test.
In the estimation of settlement, the use of soil and rock parameters based on
ground investigation results are crucial. The determining parameter, which is the
Young’s modulus, E of soil can be determined by appropriate laboratory or in-situ
tests such as the plate load test. Nevertheless, the Code suggests the correlation E
= N (in MPa) for granular soils in the absence of more accurate if the design
allowable bearing capacity is not greater than 250kPa. In addition, there are also
recommendations in other references including GEO Publication 1/2006 (2006)
Table 6.10 relating E to SPT N values.
The Code suggests ranges of Poisson’s ratios of soils as related to their SPT N
values. As high Poisson’s ratio implies more significant effects from lateral
strains or stresses, smaller soil settlement in the direction of the applied load and
higher lateral stress / strain are anticipated in the soil with higher Poisson’s ratio.
(1) General
Notwithstanding (1), the Code suggests some reference criteria for settlements
and rotation at base of footing and under-side of pile cap for buildings or
structures not particularly sensitive to movement under conditions listed in the
clause. Nevertheless, as the settlement of upper levels of a building structure due
to dead load can be adjusted throughout the construction sequence, it should be
reasonable to take half of the dead load for estimation of settlement.
Criteria of other recommendations and codes are listed as follows for readers’
reference. These include that by Skempton and MacDonald (1956)
recommending maximum slopes (between any two points within a single
foundation unit or in separate foundation units) to vary from 1 in 500 for steel and
concrete frame infilled structures to 1 in 200 where there is no infill or no danger
of damage to the cladding. Furthermore, Meyerhof (1956) recommended limiting
slopes to 1 in 250 for open frames, 1 in 500 for infilled frames. Burland (1975)
gives a comprehensive summary of the recommendations of these past researches.
In addition, the Eurocode BSEN1997-1:2004 Annex H states that total settlements
up to 50mm are often acceptable for normal structures with isolated foundations
and a maximum relative rotation of 1 in 500 is acceptable for many structures in a
sagging mode and half of that value for a hogging mode. Furthermore, the
Page 12 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The Code requires checking of the structure against ultimate and serviceability
limits if the criteria in (2) cannot be satisfied.
The Code has set a number of design rules in this sub-clause which are generally
applicable to structures built on newly reclaimed land. The rules, being more or less
identical to those listed in PNAP APP-103, aim at minimizing damage to structures and
non-structural components due to settlements and differential settlements.
To avoid the migration of soil into voids underneath a pile cap formed by ground
consolidation as discussed in item (f) of the sub-clause, Figure H2.1 illustrates an
effective measure for reference which is the construction of a short wall. The figure is
reproduced from the figure in Appendix A of PNAP APP-103 with the additional
illustration of the short wall.
Figure H2.1 – Measures to mitigate the Migration of Soil into any Voids that may be formed
underneath the Suspended Structure
Page 13 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The long-term monitoring and/or maintenance requirements may take the form of a
“performance review” which may be required in Scheduled Areas, sites of complex
geology and for special structures. The usual forms of long-term monitoring include
building settlement and tilt and ground-water table monitoring.
H2.5.1 GENERAL
In addition to the compliance requirement with the Hong Kong Buildings (Construction)
Regulations, reference to relevant requirements from other well-established codes of
practice such as the British Codes and European standards and the general laws of
mechanics can also be made for the structural design of foundations.
Apart from the Building (Construction) Regulations Section 17, the Code of Practice for
Dead and Imposed Loads 2011 published by the Buildings Department should be referred
to for the determination of the design loads. In addition, reference should be made to the
circulars issued by the Fire Services Department giving updated loads for fire engines if
the structure has to be designed to carry fire engines.
It is a popular local trade practice to design separately the foundation and superstructure
of a building. The foundation is designed using a set of assumed loads from the
Page 14 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
For a foundation which has to undergo a “static load” test, the maximum test load can be
2 to 3 times the foundation working load which is generally greater than the partial load
factors used for ultimate strength design. So this can be regarded as another limit state
that has to be taken into account for design.
For the determination of soil loads, active pressure only should be used in checking
stability of the whole structure where adequate soil movement is allowed. Full passive
pressures should only be included when the designer is confident that they will be
mobilized for the duration of loading. It should be noted that the movement to fully
mobilize the passive pressure is usually large unless there is a lock-in movement due to
the construction sequence of the structure. Generally the structural design of members
should be based on at rest soil pressure instead of active soil pressures.
S stabilizing
≥ 1.0 (Eqn H2.1)
fu × S sliding ( flotation ) + 1.5 × S sliding ( others )
Fstabilizing
≥ 1. 0 (Eqn H2.2)
f u × Fuplift ( flotation ) + 1.5 × Fuplift ( others )
M stabilizing
≥ 1 .0 (Eqn H2.3)
1.5 × M overturning ( wind ) + f u × M overturning ( flotation ) + 2.0 × M overturning ( others )
In the above inequalities, the terms S , F and M in the numerators represent stabilizing
lateral forces, vertical forces and moments against the wind, soil, water flotation loads
causing instability respectively. These stabilizing forces and moments are usually
provided by the structure’s own weight and other anchoring forces to the ground, if any.
Page 15 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
For the factor f u , it is 1.5 if the check is based on highest anticipated groundwater table
and becomes 1.1 if the check is based on highest possible groundwater table.
Worked Example H2.1 for the structure shown in Figure H2.2 demonstrates the use of the
above inequalities. In the example, the case of highest anticipated groundwater table is
considered with level as marked on the figure by which lateral hydrostatic load balances
out. It should be noted that the most adverse combination of loads should be used in
determining the factor of safety including (i) wind and soil loads acting in the same
direction; (ii) the live load in the building ignored; (iii) live load acting as surcharge only
on the active soil pressure side; and (iv) highest water table on the active pressure side.
In addition, the stabilizing force due to the soil passive pressure may have to be ignored if
there is probable removal of the soil offering the passive resistance during the life time of
the building.
Worked Example H2.1
(i) Check Sliding Stability
Sliding Force
kN
Wind Load
Passive Soil Resistance = 900kN
kN; Friction at the Base of the Building
Line of action Flotation load kN
m above kN;
Factor of Safety against Sliding is
A Line of action at O.K.
m from A
(ii) Check Uplift Stability
O.K.
Load due to Soil
Active Pressure (iii) Check Overturning Stability (about A)
kN; GWL Overturning moment by wind about A is
Line of action kNm
Soil Passive
m above Resistance Overturning moment by active soil pressure about
A Coefficient of A A is kNm
friction at the kN; Line of Overturning moment by flotation about A is
Lateral loads due m action kNm
to ground water m Stabilizing moment by passive soil pressure about
balance on both Dead Load above A A is kNm
sides.
kN; Stabilizing moment by dead load about A is
Line of action at kNm
m from A Checking against Overturning is
O.K.
It should also be noted that the clause is for checking global stability of the whole
building or structure. It is generally not necessary for buildings with adequate rigidities
or ties at the foundation level to check that every foundation element of the building such
as individual footings or piles can achieve the same factor of safety. However, if each
foundation element can achieve the same factor of safety, stability of the whole structure
can be deemed satisfactory. An example is the checking of all piles. If there is no
tension in any piles, this obviously implies stability of the whole building or structure
against overturning. Checking of pile loads can be carried out according to the following
inequality which is extracted from clause 5.1.6 :
Page 16 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Pmin DL + 0.9 Panchorage ≥ 1.5 Pwind + f u Pfloatation + 2.0 Pothers (Eqn H2.3)
(1) General
Traditionally design of foundations in Hong Kong has been based on the working
stress method for both the checking of ground bearing and the structural design of
individual structural elements. However, in recent years limit state design has
been becoming popular for concrete foundation members, though not yet so
popular for structural steel members. This clause in the Code reflects this practice
by making references to the current Codes of Practice for Structural Use of
Concrete and Steel which are based on limit state design.
Nevertheless, the permissible stress design method is still allowed which can be
conveniently used in design of mini-piles and steel piles because of the
requirement to ensure that the steel bars or sections are not to be stressed beyond
their material yield strength during a load test where the test load is twice that of
the design working load.
(2) Concrete
(i) Limit state design should be adopted generally for structural design of
footings, cast-insitu-piles while leaving the bearing stresses on rock or soil
to be checked against working loads. However, the design of driven
precast concrete pile may still have to follow the permissible stress
method as the Code limits the axial compressive stress on the pile under
working loads to 0.2fcu;
(ii) The Code specifies a 20% reduction in “strength” for concrete where
water is likely to be encountered during concreting or when concrete is
placed underwater or alike. The requirement is more general than the
provision in the Hong Kong Building (Construction) Regulation
(HKB(C)R) which instead limits concrete stresses to 80% of the
appropriate limitation of “design stress”;
Page 17 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
(3) Grout
(4) Steel
(i) Though allowable stresses for structural element design are specified in
the clause, the Code allows both the permissible stress method and the use
of the Code of Practice for the Structural Use of Steel 2011 which
involves ultimate limit state in structural element design. A practitioner
can easily work out that the structural design of steel to the limit state, in
accordance with the Code of Practice for the Structural Use of Steel 2011,
is more economical than the permissible stress method by simply
comparing the design working axial stress (stress due to axial load only) of
steel, of the order of 30% to 50% of the yield stress to that of the limit
state method based on the almost full yield stress, (0.9py to 1.0py) even
with the application of partial load factors ranging from 1.2 to 1.6.
Nevertheless, as there is again the requirement of a loading test with a test
load twice the working load, as for a mini-pile and others, the load
carrying capacity will be capped at values similar to those applying the
permissible stress method;
(ii) The allowable bond stress between steel and grout (minimum
characteristic strength 30MPa at 28 days) for both compression and
tension specified in the Code are 400kPa or 320kPa when grouting under
water. However, local testing work by Chung (2005) and Wang et. al
(2005) showed that the ultimate values for compression are in the range of
300kPa to 600kPa if grouting is done in dry conditions and the grout is
unconfined, giving allowable values of 150kPa to 300kPa upon an
application of a safety factor of 2 which are significantly less than those
specified in the Code. Nevertheless, the ultimate bond strengths are
significantly increased when the grout is placed under confined conditions
(confinement in the steel tube), up to 850 to 1160kPa with their allowable
values (ultimate values divided by 2) in the order of the values specified in
the Code. The phenomenon of higher bond strengths where the grout is
confined occurs because the confinement increases the lateral stresses and
subsequently the bond strengths (largely contributed by friction) which
depends on lateral stress;
(iii) The use of shear connectors can obviously enhance bond stress between
the section and the grout. The Code allows the increase in the allowable
bond stress to 600kPa (or 480kPa when grouting under water) under the
use of shear studs designed in accordance with the Code of Practice for the
Structural Use of Steel 2011. The Code also mentions that steel sections
or other means as substitute for shear studs may also be used. It has been
a practice of the local industry to weld steel cross bars along the flanges of
the steel pile for shear connections as illustrated in Worked Example 2.2
which follows;
Page 18 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
(iv) It is therefore advisable to (a) adopt reduced bond strengths between the
grout and the steel section above the rock socket; and (b) enhance the
bonding in the rock socket by the use of “shear connectors” which can
sustain at least 50% of the bond force. Typical arrangements for the use
of welded cross bars for enhancement of bond within the socket for a
socketed pile are shown in Figure H2.3;
Figure H2.3 – Typical Socketed H-Pile with Cross Bars as Shear Connectors
Page 19 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Allowable bond stress between steel and grout (concreting under water) = 320kPa
without shear studs or other substitutes.
So the total bond force that can be provided by the bare bond between the grout
and the pile is 1.918 × 5 × 320 = 3068.8 kN
As the shear stud is Class 1 material, the partial strength factor γ m1 = 1.0 is used
in accordance with Table 4.1 of the Code of Practice for the Structural Use of
Steel 2011. So the design strength of the shear stud is Pk = 91.22 / γ m1 = 91.22 kN.
Treating the shear stud as if it is in slab under negative moment as per clause
10.3.2.1 of the Code of Practice for the Structural Use of Steel 2011 for
conservative design, its design resistance is Pn = 0.6 Pk = 0.6 × 91.22 = 54.73 kN.
Page 20 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
During loading test when the applied load is twice the working load, the bond
stress should at most be twice the working stress and this load can be safely
resisted as the ultimate bond strength is twice that of the allowable working stress.
H2.6.1 GENERAL
In general, this sub-clause requires that corrosion by the external environment (soil and
underground water) will not weaken the foundation to such an extent that structural
inadequacy results during the life time of the foundation. For example, the loss in
thickness of a steel pile will not render its strength inadequate (by reduction of the cross
sectional area) to resist the imposed load during its life time (say 50 years).
(a) Sulphate attack on concrete, in accordance with Neville (1995), refers to the
chemical reactions in hardened concrete in which (i) tricalcium aluminate (C3A)
hydrate in the concrete reacts with a sulphate salt from outside to form calcium
sulphoaluminate which will result in a volume expansion of 227%; and (ii) base
exchange between calcium hydroxide and the sulphate to form a gypsum with
volume expansion of the solid phase up to 124%. As the expansions are within the
framework of the hydrated cement paste, gradual disintegration of concrete takes
place. However, as remarked in the MTR New Works Design Standards Manual
(2008) (NWDSM), Hong Kong soils contain negligible amounts of naturally
occurring sulphates and therefore sulphate attack in natural soil is generally
insignificant. Nevertheless, if sulphate content is found to be excessive in areas of
reclaimed land, marine environments, leaking water mains and/or service reservoirs,
preventive measures including use of sulphate resisting cement concrete should be
implemented. The sulphate resisting cement has a low content of C3A. Use of PFA
and GGBS as cement replacement, which can alternatively decrease the content of
C3A is also beneficial to sulphate resistance. NWDSM classifies soils with sulphate
content below 0.24% and groundwater with sulphate content below 0.4 gm/litre as
non-aggressive.
Chloride attack is distinct in that its primary action is the corrosion of the steel
reinforcement in the concrete instead of direct corrosion of the concrete. The
chloride first breaks through the protective passivity layer formed by the alkaline
environment of the concrete around the reinforcement, followed by corrosion of the
steel in the presence of water and oxygen. The products of corrosion occupy a
Page 21 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
volume several times larger than the original steel which results in cracking and/or
disintegration of the concrete. Nevertheless, Neville (2003) indicates that such
corrosion will not take place in dry concrete, probably below a relative humidity of
60%, nor in concrete fully immersed in water (where oxygen is very small amount)
except when water can entrain air, for example by wave action. As the chloride
attack usually arises from ingress of chloride ions from outside the concrete and the
primary action is on the steel reinforcement, a dense concrete with adequate cover
to the reinforcement is the best protection against chloride attack. NWDSM
classifies soils with chloride content below 0.05% and groundwater with chloride
content below 200ppm as non-aggressive. Miguel et al. (2010) has developed and
quotes formulae for predicting chloride diffusion rates of concrete in tidal zones.
Aggressive chemicals or agents other than sulphates and chlorides may include
acidic chemicals. Cement in the concrete, being highly alkaline, is not resistant to
attack by strong acids or compounds that may convert to acids. Generally, the
attack occurs by way of decomposition of the products of hydration and the
formation of new compounds which will either be disruptive or soluble.
Consequently, concrete should not be used in locations where this form of attack
may occur, unless with adequate protection such as effective coating. In
accordance with Neville (1995) concrete will be subject to attack by acid in an
acidic environment with a pH value below 6.5. A pH value below 5.5 indicates a
severe environment and below 4.5 a very severe environment (the former is
consistent with NWDSM whilst the latter is consistent with the classification in
Table 4.1 of the Code of Practice for the Structural Use of Concrete 2013).
(b) Alkali Aggregate Reaction (AAR) is a chemical process in which alkalis, mainly
from the cement, combine with certain types of minerals in the aggregate (alkali-
reactive aggregates) in the presence of moisture to produce a gel that can absorb
water and subsequently expand to cause cracking and disruption of concrete. An
effective means of reducing the risk of AAR is to control the alkali content in the
cement, and with appropriate use of cement replacement such as PFA in accordance
with PNAP APP-74. Appendix A of the PNAP has a full description of control of
the AAR, requiring that the “equivalent sodium oxide content” in concrete is not to
exceed 3.0kg/m3.
(c) For foundations constructed on a landfill site where there may be various kinds of
fills with the probable existence of aggressive materials, investigation of the
contents of the materials may have to be taken and appropriate measures
implemented.
(d) Damage by abrasion which refers to damage by abrasive machinery, metal tyred
vehicles or water carrying solids is not common in foundations as they are not
normally exposed to such abrasive actions except for marine foundations subject to
wave attack. However, if abrasive actions do exist, protection which may take the
forms of protective barriers or coatings may have to be provided.
From the above discussion, it can be seen that the composition of concrete, its denseness
and adequacy of cover to reinforcement in concrete foundations are important to
corrosion resistance. The requirements should be more stringent for more severe
environments (which may also require additional measures such as cathodic protection as
Page 22 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
will be discussed in H2.6.4). Rough guides to minimum concrete grades and concrete
covers for reinforced concrete structures in general for various categories of “exposure”
are given in the Code of Practice for the Structural Use of Concrete 2013 and other
standards. In addition, crack widths sometimes need to be estimated against pre-
determined limits to ensure durability.
(a) Sulphate, chloride, aggressive chemicals or other similar agents (including oxygen)
present in the ground will react chemically with steel (with iron as its major
composition) to form other materials which cause corrosion. The corrosion is
chemically a reduction oxidation process in which the iron is “oxidized”. In the
corrosion process, the presence of water is essential and an acidic environment will
accelerate the corrosion process. Figure H2.4 illustrates the chemical process of
corrosion by water and oxygen.
Anode
2e–
Steel
From the figure it can be readily deduced that if (i) the steel is negatively charged,
i.e. the steel becomes a cathode or (ii) electrically connected to a metal of higher
reducing power (e.g. zinc) by which formation of iron cation (Fe2+) is not favoured,
the corrosion process will be inhibited. Anti-corrosion provisions for steel can
therefore be based on these two phenomena.
(b) The alternate wetting and drying by sea waves in the “splash and tidal zones” of
steel piles installed through the sea will accelerate the corrosion rates as illustrated
in Figure H2.5 and therefore special treatment in corrosion protection is required for
the piles. CEDD (2002) recommends that steel piles have to be fully protected
against corrosion (by effective coating and/or cathodic protection described below)
above the seabed throughout their design life;
Page 23 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Atmospheric Atmospheric
Pile zone zone
(c) If the steel pile (with iron as its major composition) is in contact with other metals
of lower “reducing power” such as copper (or alternatively described as having
lower position in the “electrochemical series” in chemistry), oxidation and therefore
corrosion of the steel will be accelerated. It is in fact a common protective measure
to protect steel piles by electrically connecting them to a metal rod of higher
reducing power (such as zinc as illustrated in Figure H2.6(a)) so that corrosion
takes place in that metal instead of the steel pile;
(d) “Stray direct electric current” through the piles are direct electric currents flowing
through the earth from a source not related to the piles affected. When these stray
direct currents accumulate on the steel pile, they can induce “electrolytic corrosion”
of the iron by which iron is lost to the surrounding soil which acts as an electrolyte.
Sources of stray current include existing cathodic protection systems, direct current
power trains or trams, arc-welding equipment, direct current transmission systems,
and electrical grounding systems. Fortunately, in most cases, these corrosion
currents are only measured in thousandths of an ampere and so the effects are
normally not significant. One technique to minimize the corrosion effect involves
insulating or shielding the pile from the stray current source and another involves
draining the collected current by either electrically bonding the pile to the negative
side of the stray current source or installing grounding cell(s). The phenomenon
and techniques are also applicable to underground pipelines.
The rate of corrosion of steel in soil is of the order of about 0.02mm/year in undisturbed
natural soils to 0.05mm/year in non-compacted and aggressive fills (ashes, slag….) as
deduced from BSEN14199:2005 Annex D. The measures protecting against the
corrosion processes mentioned in the above include :
Page 24 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
(iii) Sacrificial steel thickness by which the pile is over-sized so that a certain thickness
of steel is reserved for “sacrifice” by corrosion during the lifetime of the pile;
(iv) Zinc coating, as zinc is a stronger reducing agent than iron and can effect protection
by actions as explained in H2.6.3(c); and
(v) Electro-chemical (cathodic) protection by turning the pile into the cathode of a
corrosion cell.
More stringent protective measures for foundations are naturally required in marine
conditions. The Code has highlighted some of the measures which are adopted in the
“Port Works Design Manual Part 1” by CEDD (2002) for both concrete and steel
foundations. Generally the protective measures mentioned in 2.6.2 and 2.6.3 are
applicable to marine foundations with higher standards. Further discussion is as follows :
(i) The intermittent or periodical wetting and drying due to waves and tides accelerate
penetration of chlorides from the seawater into the reinforced concrete foundation
structure and initiate corrosion of the reinforcement. Therefore, it is important to
use a dense concrete mix with comparatively large concrete cover to protect the
reinforcements. In addition to the specified minimum concrete cover of 75mm, the
Port Works Design Manual also specifies that the cementitious content of the
concrete shall be within 380 – 450 kg/m3, of which the dry mass of condensed silica
fume shall be within 5 – 10% range by mass of the cementitious content;
(ii) Steel tubular piles infilled with concrete may be used where the entire thickness of
the casing is regarded as sacrificial. That is, the infilled concrete core alone can
withstand the imposed load after the casing is entirely eroded in the long term.
Some cathodic protective measures against corrosion are illustrated in Figure H2.6 as
discussed by Goran Camitz (2009).
Electrical Power
Source
Support
Steel Pile Steel Pile Tube
Anode Steel Pile
Cable Electric
Zinc Anode sea Current sea
Anode
(a) Cathodic Protection with “Sacrifice Anode” (b) Cathodic Protection with Electric Current
(zinc anode) for steel piles in a pier Applied to Steel Piles in water. Anodes Rigidly
Mounted in Protection Tubes between Piles
Page 25 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
In relation to expected depths and founding levels of the foundation as required in (1)(c)
of clause 2.7 of the Code, it is a common practice that bedrock contours for foundations
founded on rock and SPT N value contours for driven piles are included in the foundation
plan. The SPT N values for plotting contours are subject to different types of driven piles.
The relevant PNAPs that provide requirements for design in Scheduled Areas include
PNAP APP-24 (PNAP 77) for Scheduled Area No. 3, APP-28 (PNAP 83), APP-30
(PNAP 85) for Scheduled Area No. 1, APP-61 (PNAP 161) for Scheduled Areas Nos. 2
and 4, APP-62 (PNAP 165), for Scheduled Area No. 5 ADM-16 (PNAP 225), APP-131
(PNAP 279) for Scheduled Area No. 3. In addition, drawings showing details and
extents of the MTR Protection Areas can be inspected in the Buildings Department for
Scheduled Area No. 3 or on the website of the MTR given in this link.
[http://www.mtr.com.hk/en/corporate/operations/protection_boundary_map.html]
For Scheduled Area No. 1 (Mid-levels), foundation plans need to be submitted together
with the site formation plans (if any) according to Building (Administration) Regulations
Section 11A. The foundation design should be such that bulk excavation (e.g. for pile
cap construction) should not be lower than the determined bulk excavation limit (DBEL).
Information on the tentative bulk excavation limit (TBEL) can be obtained from the
Buildings Department upon request in writing. The DBEL will be formally issued upon
request when drillhole records for ground investigation and topographic survey covering
the required extent outside the site (specified by the BD at the time of issuing the TBEL)
have been submitted to the satisfaction of the BD.
For Scheduled Areas Nos. 2 and 4 (with marble formation), the current practices of
foundation design are usually based on site characterization using the approach of marble
quality designation (MQD). The Code has outlined detailed requirements in 2.8.2 which
are consistent with GEO Publication 1/2006 and Chan (1994).
A pile redundancy is provided for the uncertainties which the driven piles can be affected
by karst features beneath the pile toe or damaged sustained during driving. The Code
provides guidelines on the adoption of the redundancy factors based on the site
classification taking into account the karst features underneath the site. Preboring may
be used in case the piles have to penetrate overhangs or roofs to install piles at greater
depth. In such circumstances, the pile redundancy can be adjusted accordingly that it
should correspond to the karst feature (and site classification) underneath the installed
piles.
For Scheduled Area No. 3, the MTRCL will impose conditions that may affect the
foundation design. In addition to the requirements specified in PNAP APP-24 (PNAP
77), the following restriction should normally apply:
(i) no foundation work is allowed within 3m from MTR structures;
(ii) no percussive piling works are permitted within 10m from MTR structure.
Page 26 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The relevant PNAP giving detailed information and layout of the Designated Area of the
North Shore Lantau is PNAP APP-134. In accordance with the PNAP, administrative
procedures including site supervision of GI work should also follow the Code of Practice
for Site Supervision 2009. GI work should also be carried out in stages and with an
assessment of whether the building plans should be modified or the buildings relocated
for economy of design when complex geology is encountered and deep foundations are
involved.
Although the designated area is not different from a non-scheduled area in terms of
building control, foundation design should take note of the complex geology of the site
when designing site investigation works and selecting the appropriate foundation option
for the site.
For slope improvement work, it should be noted that the factor of safety has to be
upgraded to the current standard in the checking of the slope.
When designing a foundation in sloping ground, due consideration should be given to the
effect of vertical and/or lateral loads on the stability of the slope. Reference can be made
to GEO Publication 1/2006 for the checking of the bearing capacity for shallow
foundation affected by sloping ground and Geotechnical Manual for Slopes by GEO for
the checking of slope stability. For the design of pile foundations embedded in slopes
which carry lateral load, the slope should be checked for its stability against the imposed
lateral load or, as a common practice, the pile should be “sleeved” to avoid imposing
lateral load onto the slope.
Page 27 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
H3 SITE INVESTIGATION
H3.1 GENERAL
In addition to the various functions of a site investigation report as discussed under this
clause of the Code, the site investigation carried out on site for the proposed foundation
work should also assist the Engineer to:
(i) ascertain suitability of the proposed foundation work for the site;
(ii) choose the most appropriate and/or the most cost effective foundation options for
the building work;
(iii) plan the best method of construction and foresee and mitigate difficulties and
delays that may arise during construction;
(iv) identify the nature of and estimate the volume for waste disposal and surplus
materials arising from the foundation work. The site investigation report should
support any necessary applications to relevant authorities for disposal
arrangement which may require investigation of the impacts on the environment;
(v) identify suitability of the reuse of excavated fills.
Documentary studies are cost and time effective means of compiling available
geotechnical information about the Site which can act as the basis for the planning of
future ground investigations. In fact, the information revealed by the documentary
studies often affects the planning of the permanent work design. The Geotechnical
Information Unit (GIU) of the Civil Engineering Library within the Civil Engineering
and Development Department possesses a collection of such information across the
territory which is most convenient to retrieval and study by practitioners. Reference can
be made to PNAP ADM-7 for details of the documentary studies in the GIU concerning
the acquisition of such information. A digital platform of the GIU is available for
practitioners to examine the ground investigation and laboratory testing reports. It is
accessible in this link (www.ginfo.cedd.gov.hk/dgiu). It is important that the
documentary studies should be carried out before planning the ground investigation prior
to design of foundation work. In addition, the accuracy of the retrieved information
should be verified before use.
The documentary studies should aim at compilation of, but not limited to the followings,
as far as they are available :
Page 28 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
(vi) Design and construction records of current and past site formation works such as
reclamation, construction of slopes, retaining structures and basements (with
highlights on the standards of safety adopted in design);
(vii) Design and construction records of foundation works such as piling;
(viii) Past and/or continuing monitoring records and details of special geotechnical
works, for example, ground anchor, horizontal drain, building settlements, and
slope and retaining wall movements;
(ix) Tunnels and disused tunnels, including design and construction records of linings
and ground support;
(x) Records of past failures including landslides. Flooding and settlement of ground
and structures should also be noted and studied where appropriate.
The site survey comprises a topographical survey, geological survey, survey of existing
structures, survey of any disused tunnel, nullah or stream course, and a survey of
underground services. The following is in addition to items already mentioned and
cautioned in the Code under the same headings :
A topographical survey is important for the planning and design of the construction
work because the topography of the site directly affects the extents of cut and fill
work on site which may have significant effects on construction sequence, cost and
safety. Topography may also dictate access points and types of construction
equipment to be used during construction. For example, on a very steep sloping site,
it may be necessary to form elevated flat platforms using steelwork or extensive
filling work for the construction of large diameter bored piles. If such platform
forming or filling work is costly, the Engineer should carry out feasibility and cost
effectiveness studies by taking into account other feasible foundation options such
as the socketed H-pile or mini-pile involving the use of lighter machinery.
This sub-clause describes the purpose of a geological study and lists the key
requirements for the geological and ground models in respect of foundations.
For the survey of adjacent structures, where required and with permission, sampling
tests on structural members of adjacent structures may be carried out to investigate
and/or confirm their structural integrity in addition to the assessment of paper
records and visual inspection. Agreement from the owners of the adjacent
structures must be sought before carrying out the tests. Where tests are to be
carried out for old building structures, an assessment of the effects of testing must
be made.
For the foundation structures supporting the adjacent structures or buildings, it may
not be enough to limit the survey to their structural integrities only as the adequacy
Page 29 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
In addition, the effects on these adjacent structures of the proposed temporary and
permanent works on site should be carefully studied. These are important items for
inclusion in the foundation plan submissions to the Building Authority.
The survey of underground services aims to locate these services precisely so that
damage to them during construction work, leading to suspension of the intended
services, can be avoided. In addition, the survey can help to minimize risks
originating from underground services such as high voltage power cables, gas pipes
and the associated installations. Extreme care must be taken when surveying and/or
working in close vicinity to these underground services. Before any trial pits,
probes or boreholes are sunk in areas where there may be underground services,
hand-excavated inspection pits should be used to establish the presence or
otherwise of all such services. Hand-operated power tools to facilitate excavation
through hard materials should be used with extreme care in inspection pits.
The conditions of the buried water carrying pipes should be ascertained as far as
possible, as bursting of pressurised pipes and leakage of drains are often reported.
Relevant departments (e.g. Water Supplies Department, Drainage Services
Department and Highways Department) should be approached for obtaining any
records of pipe leakage/burst incidents from their services occurred within the past
12 months.
H3.4.1 GENERAL
Ground investigation is that part of a site investigation carried out in the ground. It
serves to retrieve information about the ground to aid the proposed foundation work in
the following aspects :
(i) estimation of the depths, adequacy and suitability of the bearing strata for the
proposed foundation work;
(ii) estimation of future settlements;
(iii) choice of construction methods and necessary precautionary measures for the
proper execution of the foundation works and the minimization of damage to
Page 30 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Good quality soil samples and continuous rock cores from boreholes should be obtained
for both geological logging and laboratory testing purpose. Laboratory tests should be
carried out to characterize materials and determine relevant design parameters. These
include classification tests to establish the index properties of the ground and strength and
compressibility tests to obtain the foundation design parameters based on soil and rock
mechanics principles. In addition, in-situ testing (e.g. plate load test, standard penetration
test, permeability test) should also be implemented as necessary.
Despite borehole spacing should vary from site to site depending on the complexity of the
site geology and the building plan of the proposed development, it may be worthwhile to
consider having boreholes at 30m centre to centre for general sites to facilitate the detail
design of the proposed foundation works. Additional boreholes shall be sunk in case of
abrupt change in ground condition between boreholes is observed. For the sites underlain
by complex geology or karst marble, it is recommended to refer to GEO Publication No.
1/2006 for guidelines on the strategy in conducting the ground investigation and spacing
of the boreholes.
The current Code of Practice for site supervision in which ground investigation works is
included is the “Code of Practice for Site Supervision 2009” and its corrigenda.
(i) an introduction stating the purpose, timing, nature and extent of the investigation;
(ii) a description of the site including the site location, area covered by the investigation,
the topography and the structure to be constructed on the site;
(iii) a description of the geology of the site (including faulting) and the sources from
which the geology is extracted;
(iv) groundwater and its highest and lowest levels and the period of monitoring;
(v) an account of the field work including the methods of investigation, testing and
equipment used. Difficulties encountered should also be described;
(vi) a summary of the boreholes drilled during the investigation with full reports of the
borehole numbers, locations (with Hong Kong Metric Grid Reference), dates of
Page 31 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
operation, method of forming boreholes, plant equipment used, ground levels and
depths of drilling, descriptions and properties of the soils encountered (except for
wash boring where only the bedrock is extracted for investigation); ground water
levels;
(vii) any interpretation/comment based on data obtained by the engineer. Where
appropriate, the method of analysis, and cross checking of test results should be also
be included.
The Code emphasizes that the number and disposition of boreholes/trial pits should
depend on the size, type, performance requirement of the structure, the general conditions
of the site and the availability of existing information. Chapter 2.4 of GEO Publication
1/2006 provides the general guideline on the extent of ground investigation works.
Below are requirements stated by the Code under clause 7.4.2 for “pre-drilling” for the
following end-bearing pile types, which are applicable generally under all circumstances :
(i) Large Diameter Bored Pile, Barrettes and the like – one pre-drill hole for each pile;
(ii) Mini-pile, Socketed H-pile, H-pile driven to bedrock – pre-drilling be carried out
such that the tip of each pile will not be more than 5m from a pre-drilled hole.
The Code adopts 5m as the required depth for the definition of “bedrock” and therefore
requires drilling into rock for at least 5m for confirmation of bedrock as the end-bearing
stratum for foundation units designed for founding on bedrock. However, for complex
geology, depth of borehole should be increased.
Apart from the requirements on determination of depth for bedrock investigation, the
Code generally requires ground investigation to be carried out to such a depth that stress
increase would cause an insignificant strain or displacement. Taking the stresses beneath
square and circular footings as examples for determination of the depths where
insignificant strains occur, reference can be made to the following “stress bulb” charts as
shown in Figure H3.1 which are arrived at by integration of the Boussinesq Equation (for
determination of stress in a semi-infinite elastic medium due to a point load at the
surface).
Page 32 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
B/2 B/2
45 degrees 45 degrees
Line Line
0.5B 0.5B
1.0B 1.0B
Depth Beneath Footing
2.0B 2.0B
2.5B 2.5B
Circular Footing
Square Footing or Pile
3.0B 3.0B
0B 0.5B 1.0B 1.5B 0B 0.5B 1.0B 1.5B
Figure H3.1 – Vertical Stress Bulb beneath a Square Footing and a Circular Footing (or Pile)
From Figure H3.1, at depths greater than 2.1B (2.1 times the breadth of the footing) for
the square footing and 1.85B (1.85 times the diameter of the footing) for the circular
footing, the vertical stress is only 10% of the contact pressure at the founding stratum.
As such small stresses which imply small strains, further settlements beneath these levels
is likely to be insignificant. So the ground investigation can terminate at these levels.
Nevertheless, if hard stratum, e.g. rock or stiff clay is encountered above these levels
where settlements will be small despite the higher stresses, ground investigation can be
terminated at higher levels. It should also be noted that this “stress bulb” approach is
applicable to both cohesionless and cohesive soils under the assumption that the soil
medium behaves elastically. (The chart for the circular footing can also be used to
estimate stresses beneath a circular bored pile.)
Overlapping of stress bulbs will result if footings are in close proximity. By the elastic
theory, the stress in an overlapping zone at any point is the sum of the stresses by the
individual footings.
H3.4.7 GROUNDWATER
Groundwater level often presents difficulties in the design and construction of foundation
work. In permanent work design, a high groundwater level can give rise to flotation
Page 33 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
problems where the structure is light. Seasonal fluctuations of groundwater level may
induce movements in the permanent structures. During construction when de-watering is
required, care should be taken to avoid subsidence of the ground which may affect
adjacent structures and utilities. Impermeable cut-off or re-charging of ground water may
need to be considered. The groundwater investigation must provide all relevant
information needed for geotechnical design and construction which should include the
followings as appropriate:
(i) depth, thickness, extent and permeability of water-bearing strata in the ground and
joint systems in the rock mass;
(ii) the elevation of the groundwater surface or piezometric surface of aquifers and their
variation over time and actual groundwater levels including possible extreme levels
and their periods of recurrence;
(iii) the pore water pressure distribution; and
(iv) the chemical composition of the groundwater.
Ground investigation works in Scheduled Areas are subject to special control. The
relevant PNAPs for ground investigation in Scheduled Areas are:
(i) ADM-16 (PNAP 225) – Approval and consent is required under the Buildings
Ordinance. However, the concurrent processing option is available.
(ii) APP-28 (PNAP 83) – Requirement for qualified supervision is imposed.
(iii) APP-30 (PNAP 85) – As Scheduled Area No. 1 is located in the region of sloping
ground, a Registered Geotechnical Engineer (RGE) must be appointed under the
Buildings Ordinance.
(iv) APP-61 (PNAP 161) – As the ground conditions in Scheduled Area Nos. 2 and No.
4 are complex, RGE has to be appointed under the Buildings Ordinance.
(v) APP-24 (PNAP 77) – In Scheduled Area No. 3, railway protection areas have been
delineated and shown on relevant plans and a set of building/engineering guidelines
produced to safeguard the safety and stability of the railway structures. As a general
rule, the boundary of the railway protection areas is about 30m outside the outer
surface of the railway structures or the railway fence/wall, or from the nearest rail if
there is no railway fence/wall. Proposal for ground investigation works or
underground drainage works in or for any existing buildings to be carried out within
railway protection areas other than those designated as Schedule Area No. 3 should
be forwarded to the MTRCL for comment prior to commencement of the proposed
works.
(vi) APP-62 (PNAP 165) – In Scheduled Area No. 5, all proposals for new building
works within 100m from the centerline of the gazetted routes of sewage tunnels
shall be subjected to special scrutiny by Government.
For ground investigation works within the Scheduled Areas Nos. 2 and 4, PNAP
APP-61 (PNAP 161) describes the geotechnical control measures in respect of building
works. By virtue of the Buildings Ordinance, ground investigation in these Areas
requires approval and consent of the Building Authority. The AP, RSE and RGE are
required to ensure that ground investigation works are carried out to a high standard and
are properly supervised. The site supervision requirements and the minimum
Page 34 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
qualifications and experience of the supervision personnel and the Competent Person
(Logging) for ground investigation field works are given in the Code of Practice for Site
Supervision 2009. The cores recovered should be examined and properly logged by the
Competent Person (Logging). Pending the substantial completion of the building works,
all cores and samples should be retained on site in good conditions for inspection by the
staff of the Buildings Department and the Geotechnical Engineering Office.
Technical recommendations on the requirements are also provided by the GEO Technical
Guidance Note No. 12 (GEO 2004) and ETWB TC(W) No. 4/2004 (ETWB, 2004).
In addition, for ground investigation within the Designated Area of Northshore Lantau,
GEO Technical Guidance Note No. 12 (GEO 2004) outlines the establishment of the
Designated Area of Northshore Lantau and the relevant technical recommendations.
Related documents are also provided.
The Designated Area is underlain by locally complex geological conditions that require
due attention to be given to the potential problems associated with high-rise buildings
and other structures involving deep foundations. The complex geological conditions
include some, or all, of the following:
(i) An anomalously deep rockhead, locally in excess of 160m below ground level, in
the deeply weathered, mainly instrusive igneous rocks comprising medium-grained
granite and dykes of rhyolites;
(ii) Metasedimentary rocks and their weathering products giving rise to cavities, cavity
fill deposits and residual soil;
(iii) Superficial deposits, typically between 10 and 150m, occupying depressions in the
subcrop surface, most of which lie directly above or adjacent to metasedimentary
rocks and cavity-fill deposits.
The following additional ground conditions are often contributory to the complex
geological conditions and should also be assessed :
In site investigations for developments with deep foundations within the Designated Area,
some guidelines are recommended for identifying the complex geological conditions:
(i) During the initial ground investigation phase, emphasis should be directed to
developing a representative geological and hydrogeological model rather than just
testing.
(ii) Commonly used ground investigation techniques have limitations in identifying
very localized areas of complex geological conditions. Detailed geophysical gravity
surveying has proved to be a useful technique for identifying the locations of
deeply weathered zones and should be considered as a supplement to and a basis
for planning drillholes.
(iii) Reference can be made to the logging guide by Sewell and Kirk (2002).
Page 35 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The Code reminds that ground investigation works within the Designated Area are
subject to special administrative procedures in accordance with the Code of Practice
for Site Supervision 2009 and ground investigations should be carried out in stages.
Page 36 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
H4 SHALLOW FOUNDATIONS
The controlling criteria for the design of shallow footing are often settlement and
differential settlement that would be experienced by the structure, the magnitude of
which are controlled by the serviceability requirements of the structure.
The construction of new footings should avoid conflicts with existing foundations and
underground services, as revealed by the ground investigation. Additional stresses and
movements induced in the adjacent structures, foundations, services and slopes etc.
should also be examined, noting the prescribed values imposed by authorities such as the
MTRC, WSD. The analysis can be carried out by (i) using the simple load spread
assumption (say 2 (vertical) to 1 (horizontal) in soil and 45o in rock); (ii) the continuum
theory by treating the ground as an elastic (or elasto-plastic) medium; or (iii) finite
element method analysis. The latter two approaches have to be carried out by computer
methods.
The clause outlines the procedure for design of shallow foundations which mainly
aims at establishment of the allowable bearing pressure together with checking of
settlements. Plate load test will be required under conditions as stated in clause
4.2.2(2). Nevertheless, the analysis of the working bearing pressures beneath the
shallow footing need to be established first.
Page 37 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Plastic stress is
often resulted
Figure H4.1 – Ground Pressure Distribution beneath Footing under Different Assumptions
In comparison, analysis by the Continuum Theory and the Finite Element Method
which will result in high ground pressures at the edges and corners of the footing is
usually more realistic than the Linear Stress Distribution Method and the Winkler
Spring Method as illustrated in Figure H4.2. In fact, for a rigid footing resting on
an elastic semi-infinite subgrade, the pressure at the edge of the footing will be at
infinity using elastic theory. Reference can be made to the work of Borowicka
(1939) for an infinitely long rigid strip and Muki (1961) for a circular rigid disc.
But practically the infinite pressure will not exist. The ground will “yield”, resulting
in “plastic pressures” as illustrated by the dotted lines in Figure H4.1(c).
Page 38 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Original
ground Profile
(a) Under a uniformly distributed load (u.d.l.) exerted by (b) If a footing of certain stiffness carrying u.d.l. is used, the
a flexible footing (zero stiffness), the centre part of settlement will be more “even” than (a). In fact the
the footing will settle to a greater extent than the outer settlement profile will be a horizontal straight line if the
part because of the greater stresses on the ground footing is infinitely rigid. In order to achieve more even
(stress bulb) as created by the greater summation of settlement by which the settlement of the centre portion
influences from the applied load. decreases and the outer portion increases as compared
with (a), the ground pressure has to be re-distributed
such that higher pressure will be at the edges.
Figure H4.2 – Explanation of Ground Bearing Pressure under the Continuum Theory
The “Linear Pressure Distribution” method is a widely used and accepted method
and this method is presumed when the bearing pressures are checked against the
presumed values in Table 2.1 of the Code. Nevertheless, as the Code does not
preclude more accurate methods of analysis, the Winkler Spring Method or the
Continuum Theory are also accepted in the structural design of the footing.
Furthermore, it should be noted that both the “Linear Pressure Distribution” method
and the “Winkler Spring” method cannot achieve settlement compatibility of the
footing structure and the ground. If the designer were to apply the ground reactions
arrived by these two methods to the ground for calculation of settlements by the
continuum theory, e.g. application of the Boussinesq or Mindlin Equations (or their
integrated forms) (Vaziri et al; 1982) or the finite element method, the settlement
profiles of the ground and the footing structure will not match and this is thus a
draw-back of these approaches. Analytical approaches including the work by Lam
et al. (2009), however, have been developed to account for the true subgrade
structure interactions through the use of the “Continuum Theory” which can
achieve compatibility of settlement of the footing and the subgrade.
In addition, as the Winkler Spring Method and the Continuum Theory may result in
very high ground stresses locally, the designer may, with adequate justification
and/or by making conservative assumptions, assume certain limits of ground stress
(elastic limit) beyond which the stress may remain constant (plastic stage).
Reference to other publications for more accurate constitutive laws of rock or soil
can be made.
Page 39 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The Code imposes the requirement of carrying out “plate load test” for shallow
foundations (founded on soil) described in clause 8.2 when any one of the 3
conditions listed in clause 4.2.2 (2) is satisfied which includes (a) use of presumed
values for qa greater than 300kPa unless qa − qo less than 50kPa; (b) use of the
bearing capacity equation in clause 2.2.4; (c) use of Young's modulus greater than
the 1 × SPT N values in MPa in settlement determination. The plate load test
serves to correlate the settlement of a test plate (300mm to 400mm plan
dimension) under the test loads to that of the actual shallow foundation for
determination of the Young’s Modulus of soil and back-calculation of foundation
settlement.
The structural design of shallow reinforced concrete footing should be in accordance with
the latest version of the Code of Practice for the Structural Use of Concrete 2013.
Generally the structural design of footings should be carried out to resist the “internal
forces” determined by structural analysis. In the conventional structural design of
footings, the internal forces acting on a cross section are often determined by balancing
the applied loads and reactions as demonstrated by Figure H4.3. The analysis and design
are effectively based on a “one-dimensional beam model”.
Shear
X Torsion Bending
X Section X
However, as can be seen readily, the application of the method is quite limited, because (i)
the simulation of a plate structure as a beam structure may not be realistic and; (ii) there
is difficulty in determining the “effective width” of the cross section beyond which local
effects cannot be well captured.
Page 40 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
In contrast to the conventional method, the structural analysis of footings in the local
industry is now frequently based on the “2-dimensional plate bending model” using finite
element analysis. In this approach, the footing is idealized as a 2-dimensional plate
bending structure. “Stresses” which comprise the bending moments, twisting moments
and shear forces per unit plan width of the footing are the analytical results of the
structural design process. The origin and nature of the twisting moment which are not so
familiar to some designers are discussed in Appendix HD. Approaches have been
developed to arrive at a complete flexural design allowing for the bending moments and
twisting moments. The simplest and most popular approach is that based on the Wood-
Armer Equations by Wood (1968). The equations have been adopted in the New Zealand
Code NSZ 3101 Commentary (2006) and are reproduced in Appendix HD with
illustrative worked examples.
Out-of-plane shear stresses (shear forces per unit width) are also obtained for the
checking of out-of-plane shear. Under pre-determined global axes in X and Y directions
in the mathematical model, shear stresses are denoted along the X and Y directions as Vx
and Vy . It can be easily proved (Lam and Law (2009)) that the maximum shear stress for
design is Vmax = Vx + Vy and the failure plane on a plan view is at an angle of
2 2
tan −1 (Vy Vx ) to the X axis. Design against out-of-plane shears should be carried out for
this value of Vmax (in shear force per unit plan width) accordingly.
In addition to the direct approach based on “stress” determined by the Finite Element
Method, an approach based on “node force” has been employed in a popular software
which is being widely used locally. However, there are shortcomings to the approach
which have been discussed by Lam and Law (2009). In short, the “node force” used in
the approach is a hypothetical parameter which does not exist in the structure and the
design based on this approach fails to take into account some important structural
behaviours. A more reasonable approach is to take the average stresses over a design
width for the reinforcement design in reinforced concrete, and such an approach is
usually a more economical in design which is available in some computer software.
The Code also notes that the stability of shallow foundations should comply with clause
2.5.4.
Page 41 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The Code distinguishes three types of footing foundation, namely the “pad footing”,
“strip footing” and “raft footing” in this Section. By common understanding of the
profession, the distinction between the three types of footing is roughly based on their
plan sizes or plan length to width ratios as roughly shown by Figure H4.4, though no
strict limits of plan sizes and length to width ratios have been imposed.
Figure H4.4 – Plans showing Pad Footings, Strip Footings and Raft Footings
Footings in close proximity will likely adversely affect each other in settlement and stress
superimposition which may need to be accounted for. Nevertheless, it may be a rule of
thumb that the effects of a different footing at a higher level can be ignored if the footing
is outside the “2 (vertical) in 1 (horizontal)” (in soil) and 45o (in rock) stress spread from
the higher footing, as illustrated in Figure H3.1. Alternatively, simple superimposition of
the stresses due to different footings can be carried by the continuum theory under the
elastic theory.
A pad footing is one which is relatively small in plan size and usually supports a single
column. Pad footing foundations are usually used to support structures with isolated
columns where the bearing pressures are within allowable limits of the subgrade.
However, the use of isolated pad footings may result in significant differential
settlements between the footings due to different stress levels on the subgrade and/or the
varying bearing capacities and stiffnesses of the subgrade in different locations. In
addition to the differential settlements that will be incurred to the superstructure as
cautioned by the Code, the overlapping of “stress bulbs” in the subgrade together with
consideration of the cross influences between settlements should also be considered for
pad footings in close proximity.
The Code has imposed in clause 2.3.2(2) limit of differential settlement to 1:500 for
shallow foundations generally for buildings or structures not particularly sensitive to
movement. This limit between adjacent footings supporting a structure is also generally
Page 42 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
A strip footing is one which is narrow in the transverse direction normally supporting
walls. Ties by beams in the direction perpendicular to the length of the strip footing may
sometimes be required to enhance stability or to cater for construction errors and the
beams should be designed for at least certain eccentric moments.
Depending on the ratio of the structural width of the strip footing to the structural depth
and length, the structural behaviour of a strip footing may resemble that of a beam
structure rather than a plate structure. Analysis and design as a beam structure may
therefore be more appropriate.
A raft footing is relatively large in plan size and usually supports a number of columns
and walls. The use of a raft footing is common for structures (i) with closely spaced
vertical members; (ii) with a comparatively large loading or if resting on weak subgrade
requiring a large bearing area; and (iii) varying intensities of imposed loads across the
raft or resting on varying subgrade where differential settlements can be significant. A
raft structure enables differential settlements to be more effectively minimized.
Nevertheless, the Code has cautioned that raft footings should be designed with adequate
strengths to withstand the differential settlements.
In addition, “two way bending” structural behaviour is often more pronounced in raft
footings. Therefore design assuming plate bending behaviour would be more appropriate
than that according to the beam theory as discussed in H4.3.
Traditionally, it is believed that a stiff structure can achieve an even stress distribution on
the subgrade. Although a stiff foundation structure can more effectively spread the loads
from the interior columns or walls over large areas, very high local pressures can still
result along the edges of the foundation as discussed in H4.2. Nevertheless, “local
overstress” of the subgrade (which may turn the subgrade from the elastic stage to the
plastic stage) can be tolerated and the concept average bearing pressure should be
followed in foundation design.
Page 43 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
H5 PILE FOUNDATIONS
H5.1 GENERAL
In addition to the general requirements for a pile foundation as discussed by the Code, it
should be noted that “settlement” and “structural capacity” are the usual controlling
design criteria for piles, with settlement often proving to be the dominant criterion.
The Building Authority maintains a list of recognized types of pile foundations for ease
of control. The common types of pile such as the driven steel H-pile, prebored H-pile,
large diameter bored pile, barrette and mini-pile, for example are included. There are
provisions in this Section for the inclusion of new types of pile into the list comprising
the submission of technical data, past performance and demonstration of performance
which likely include loading tests.
The performance of a single pile will be different if load carrying piles are installed in
close proximity because of the overlapping of stresses created by the piles in the subgrade.
The effect is commonly known as the “Group Effect” and is generally an adverse effect
which may reduce the load carrying capacity of any single pile and increase settlement as
illustrated in Figure H5.1.
Settlement Profile
Piles
But there are cases when the effect can become beneficial, e.g. when the subgrade is
densified by closely spaced driven piles increasing the load carrying capacity.
Obviously the group effect is more pronounced for friction piles than for end-bearing
piles founded on competent stratum. The Code does not require consideration of group
Page 44 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
effects for end bearing piles (including piles driven to firm soil of SPT N value ≥ 200)
and piles founded on rock of Category 1(c) or better.
The Code has adopted a simple approach whereby a group reduction factor of 0.85 can be
applied for piles under prescribed conditions. The factor is applied to the pile capacity of
individual piles (for friction piles spaced at less than 3 times the pile perimeter), not the
settlement. Theoretically, there are two group reduction factors, one relates to settlement
and the other to geotechnical capacity. It is well accepted that a pile group has a larger
average settlement than a single pile with the same average load. However, for piles
installed in sand the group capacity is usually higher than that arrived by summation of
the capacities of all the individual piles. An illustrative example is enclosed in Appendix
HE in which a pile group with its piles, pile cap and the soil mass among the piles is
idealized as an integrated structure behaving as a sunken footing founded at the average
founding level of the piles. By determining the ultimate bearing capacity of the
“idealized footing” and with the application of a factor of safety of 3, the allowable total
bearing of the pile group can be determined and compared against the summation of the
capacities of all the individual piles. A pile group factor exceeding unity can be obtained
in this way. As the Code does allow use of factors other than 0.85 (including unity) when
justified by recognized engineering principles, the method can be adopted to justify for
the use of a pile group factor exceeding 0.85.
Despite this easy-to-use provision in the Code, there are also other theoretical approaches
to allow for the interactions between piles and the subgrade and/or the pile cap structure.
Relevant works include that of Randolph (1977) and Poulos & Davis (1980). Both
Randolph and Poulos & Davis’ work take into account the superposition of stresses
and/or settlements of the adjacent piles in determining pile settlements so that the
settlement of any pile is actually the summation of the actions of its own and others. The
work of Randolph was based on the shear deformation of soil whilst Poulos & Davis
(1980) used the integrated forms of Mindlin’s Equation to calculate pile settlements.
Randolph developed a software PIGLET (1980), (2004) for analyzing piles (vertical and
raking) under rigid caps with employment of his theory. Cheng (2013) extended the
approach to cover flexible pile cap cases while keeping Randolph’s theory in assessing
pile-soil interactions in the software PLATE. However, these approaches are based on
elastic deformation of soil only. More sophisticated geotechnical-structural finite
element computer programs have incorporated more advanced soil models including
plastic stress-strain behaviour of soils.
Page 45 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The Code specifies minimum pile spacing for various types of pile so as to (i) minimize
the group effects of overstressing the subgrade and/or creating excessive settlement; and
(ii) allow for positional and verticality tolerances in pile construction. However, the
requirement (i) may be waived for piles founding on competent strata. For example, for a
mini-pile or socketed pile where the bearing capacity is derived from rock, the minimum
pile spacing requirement could be based on consideration of construction tolerances only.
With full justifications based on recognized engineering principles or tests, proposals for
other minimum pile spacing values may be accepted.
The Code specifies that for driven piles and small diameter piles, adequate horizontal
restraints in at least 2 directions shall be provided for individual piles or pile caps.
However, the restraint should only be necessary for potentially “unstable” pile groups, for
example a pile group comprising only one or two piles where restraint is effected by
tying at the pile cap levels to other pile groups or foundations. A pile group with a large
numbers of driven piles or small diameter piles is stable and tying to other foundations is
not necessary.
The passive resistance of the ground has to be determined by recognized soil mechanics
principles. Ultimate lateral resistances to movements of the pile cap and the pile group in
soil and rock depend on the passive resistance of the soil and the ultimate lateral bearing
capacity of the rock. Reference can be made to clause 5.3.4 and Appendix HF for
determination of the ultimate lateral resistance to movement of a pile while that of the
pile cap is generally governed by the passive resistance of the soil.
The clause is concerned with checking the stability of the piled foundation against uplift,
overturning and buoyancy by achieving the required factors of safety as stated in clause
2.5.4 for the whole structure. In addition, if all piles of the structure satisfy the following
two equations, then stability of the whole structure is deemed to have satisfied.
(a) Dmin + 0.9 Ru − 2.0 I a − 1.5U a (or 1.1U p ) − 1.5Wk ≥ 0 (ultimate load condition);
Page 46 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
where the symbols are defined by the Code. It can readily be seen that generally equation
(a) controls the pile design unless Ru has a very high value comparatively and Ru > 2 Ra .
A demonstration is enclosed in Appendix HG for a hypothetical pile group in which the
loads on each pile for various load cases are analyzed.
The clause allows stability check to be carried out “globally” as in Worked Example
H2.2 by which the entire structure is treated as an integral unit with the assumption that
the structure possesses adequate stiffness and the structural members have adequate
strengths to effect global behaviour. Generally, if the structural analysis is carried out for
the “integral structure” used for global analysis for stability (with the same load factors
for stability check) and the structural design is carried out accordingly, the stiffness and
strengths of the members are deemed to satisfy the stability requirements. However, it
should be noted that some individual piles may not possess adequate factors of safety
against uplift if equation (a) above is not satisfied while global stability is found
satisfactory to clause 2.5.4. So, instead, equation (b) above should be checked to ensure
all piles do not fail uplift under working load, or otherwise non-linear analysis has to be
carried out, by which the piles reaching their maximum values will stay at these values
and excess being taken up by others.
The equivalent raft method as mentioned by the Code for determination of pile group
settlement is a conventional method which applies to pile groups of closely spaced piles.
The closely spaced piles with the soil held by the piles can effectively perform as a
sunken raft footing. The settlements are then estimated as if the pile group is a sunken
footing at the levels equal to two thirds of the pile group in case the piles are end-bearing
on soil or at the hard rock stratum if founded on hard rock stratum. The method is fully
described by Tomlinson (2008) which also specifies the spread of the foundation loads.
Detailed discussions of the method together with a worked example are enclosed in
Appendix HH. Nevertheless, it should be noted that there are quite a number of methods
complying with recognized engineering principles for the estimation of pile group
settlements, apart from the equivalent raft method.
Negative skin friction (NSF) on a pile originates from the downward drag action due to
the settlement of soil that surrounds the pile. The relative movement between the
installed piles and the surrounding soils is usually caused by the consolidation settlement
of fine-grained soils that take a long time to complete after the pile installation. It is
common that the effect of NSF should be considered on sites in newly reclaimed land
where consolidation settlement of fine-grained soil strata is still on-going after the
completion of the structure. In addition, as the soil strata above the consolidating stratum
will also settle, the determination of NSF should include effects due to the consolidating
stratum and all soil strata above it.
Page 47 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
In considering provision of a double skin permanent liner infilled with inert flexible
material to reduce NSF, such a pile may be free-standing for certain height and is not
embedded in the soil. The ‘buckling’ problem may lead to reduction of the load carrying
capacity of the pile.
(i) NSF depends on the relative displacement between the piles and the surrounding
soils. If there is subsequent settlement of the pile against the surrounding soil, the
NSF will be reduced or even eliminated;
(ii) NSF will develop with time as the soil consolidates. When it exists, NSF acts
together with the dead load and permanent imposed load (a term used in clause
2.3.3.3 of the Code of Practice for the Structural Use of Concrete 2013) on the pile.
Therefore the pile must be structurally designed to resist dead + permanent imposed
load + NSF. However, a transitory imposed load creating a transitory pile
settlement will help reduce NSF and therefore needs not be taken into account in
design unless it is greater than twice the NSF which, apart from entirely nullifying
the NSF, adds a load greater than the NSF itself, thus constituting a critical design
load, leading to a design load of dead + permanent imposed + transitory imposed
load.
The Code outlines two approaches for the determination of NSF in clauses 5.2.2 and
5.2.3.
the pile shaft in which β is the coefficient directly converting the effective vertical stress
σ ' to the friction τ s and p is the perimeter of the pile. Analytically it may be
considered that β = K s tan δ where K s and tan δ are respectively coefficients for
converting the effective vertical stress in the soil to horizontal stress and for converting
horizontal stress to a friction (Bowles 1996). The use of this β coefficient constitutes
the “Beta approach”. The β values can be back analyzed from pile loading tests to
derive the positive skin friction force which assumes the relationship τ s = K sσ ' tan δ as
described in more details in 5.3.2 (1)(b). It should be noted that the method of pile
construction would influence the horizontal stress. The derivation of K s may be
correlated to the at-rest lateral coefficient of the soil, K o . GEO Publication 1/2006 gives
some guidance on the use of K s for displacement and replacement piles. Table 6.3 of
the Publication summarizes the range of β values interpreted from pile loading tests
conducted in saprolites in Hong Kong. From the table it can be seen that the β values
can vary a lot for different installation method and types of piles. The clause in the Code
recommends the use of a typical value of 0.25 in saprolites, sand or marine deposit in
Page 48 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
design, in the absence of more accurate assessment. However, economy of the pile
design in term of NSF consideration may be achieved by deriving the β values using
recognized engineering principles and/or verified by tests.
The length of the pile, for determination of NSF is taken conservatively to the depth of
the consolidation stratum, though strictly speaking NSF ends at the “neutral point” which
is at a higher level. However, the determination of the neutral point is generally difficult.
The group effect should also be considered in the determination of negative skin friction.
In the alternative approach, NSF does not need to be considered when checking the
ground bearing capacity (geotechnical capacity) of the pile, but the NSF does need to be
fully considered in the checking of the structural capacity. This is based on the
consideration of the limit state that where the ground supporting the pile has reached the
ultimate condition, the pile under this limit state would be settled leading to a reversal of
relative movement between the pile and the surrounding soils. Therefore all NSF in the
pile is eliminated and needs not be considered in the following equation / condition :
Assuming the allowable ground-bearing capacity of the pile has a safety factor of not less
than 2 and the load factors for ultimate loads are not greater than 2, the above equation /
condition may be simplified to :
In addition, the Code requires that checking of the settlement behaviour of the pile under
total loads including NSF should be satisfactory.
The Code allows the test load for a pile designed by the alternative approach be 2Pc +
NSF instead of the normal requirement of twice of the total allowable load which should
be 2(Pc + NSF) where Pc is the allowable bearing load for the pile and NSF is determined
in accordance with clause 5.2.2. This is because (i) the NSF so determined is an ultimate
load as discussed above which should be divided by 2 for conversion to allowable load;
(ii) the excessive settlement of the pile during a loading test can effectively eliminate the
NSF.
More detailed discussion on NSF can be found in Fellenius (1989) and other references.
Page 49 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
specified. Furthermore, the Code reminds that the buckling capacity of piles should be
checked to allow for embedment in soft strata. Slender piles with considerable lengths
which are sleeved or exposed should also be checked for buckling. A discussion of the
buckling phenomenon in piles based on Law (2013) together with design tables is given
in Appendix HI.
The ultimate bearing capacity of a driven pile can be determined from (a) dynamic
formula; (b) a static formula; and (c) a loading test.
The Code has listed the Hiley formula as a dynamic formula and values / ranges of
parameters for the production of final set tables. The Handbook, as in addition to
the Hiley Formula, also includes discussions on various popular techniques
including wave equations, PDA, Case Equation, CAPWAP in the determination of
pile load capacity and pile integrity.
The Hiley Formula listed in the clause which is also the commonest dynamic
formula used locally is reproduced as follows
Page 50 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The formula assumes “rigid body collision” between the hammer and the pile
in setting up the momentum transfer equation (Re (Eqn HJ-2) in Appendix HJ)
as part of the derivation of the Hiley Formula. This assumes that every part of
the pile is affected and moves with the same velocity after impact. This is
obviously not valid as the pile is compressible and the error is significant for a
long pile in which the pile and the hammer may separate (momentum transfer
completed) before the impact “wave” can travel to the tip of the pile. As such,
only a certain length of the pile (termed the “affected length”) is affected
Wh + e 2 (W p + Wr )
Wh + (W p + Wr )
during impact. The factor representing the percentage of
The formula assumes elasto-plastic behaviour of the soil and that the load on
the soil increases slowly from zero to the maximum at Pu where the soil
reaches its elastic limit at cq , beyond which the soil continues to slip (deform)
at the constant load Pu until S which is the permanent toe movement of the
Pile or the “Final Set” measured in pile driving. The energy transfer assumed
by the Hiley Formula is represented by the area below the load displacement
line in Figure H5.2(a). But in fact, the problem is not a static one as, in
addition to the static force, a “damping” force in the soil is also mobilized
when the pile moves relatively to the soil at a certain speed so that the actual
“load path” diagram should be represented by Figure H5.2(b). As this soil
damping force consumes some energy which dissipates to the soil around
when pile driving has finished, the pile will exhibit static behaviour only, and
the load carrying capacity of the soil is overestimated by the formula.
Page 51 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
cq s
cq s
Pu
Force Force
Pu
O O
Displacement Displacement
(a) Idealized Load Path by Hiley Formula (b) Actual Load Path
Figure H5.2 – Load Displacement Path for Set and Temporary Compression of Soil
Two major sources of error are identified in relation to the foregoing discussion but
there are means to minimize them:
Page 52 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
XWh h
Emax = XWh h = Pu s + 0.5 Pu (c p + cq ) ⇒ Pu =
s + 0.5(c p + cq )
(Eqn H5.2)
with X allowing for the effects of hammer efficiency and energy loss due to
impact. But these factors are related to the characteristics of the hammers and
the site geology and therefore need to be established on site through energy
measurements and back-calculations. The factors would have different values
even on the same site for different hammers, different pile lengths, soil
geology etc.
Summing up, it is generally accepted that Hiley’s Formula under-estimates the pile
capacity (determined by static loading test as required by the Code) or requires
more than adequately stringent “Set” to achieve the required pile capacity,
especially for long piles. Past practice is to limit the final “Set” values to certain
ranges including “not less than 25mm per 10 blows unless rock has been reached”,
resulting in very narrow range for the Set values available. In recent years there is a
modification that “Set” between more than 50mm but not greater than 100mm per
10 blows can also be accepted though capped at 50mm per 10 blows in the
calculation of Pu . In addition, the calculated final “Set” should be discarded if the
( )
corresponding c p + cq L > 1.15 where c p , cq are in mm and L in m for the
purpose of limiting the driving stress in the pile. The practice is formally
incorporated in the clause. A discussion of the evolution and demonstration of the
use of these limits are given in Appendix HK.
The basic wave equation for pile driving follows a partial differential equation. The
equation is a one dimensional (geometrically) solution describing the displacement
of any point of the pile at co-ordinate x and at time t which reads :
∂ 2u 2 ∂ u
2
= c + S ( x, t ) (Eqn H5.3)
∂t 2 ∂x 2
Page 53 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
where
u is the displacement of a point in the pile from its original position;
x is the co-ordinate of a point on the pile, often taken as distance from the
pile top;
t is time;
c is the wave speed in the pile which is equal to E ρ where E and ρ are
the Young’s Modulus and the density of the material making up the pile
respectively; and
S ( x, t ) is the term representing the soil resistance force at x and t comprising both
the static and dynamic components
Derivation of the differential equation can be found in Appendix HL and text books
including Poulos & Davis (1980) and Bowles (1996). By solving the equation the
displacement at any point of the pile and at any time can be obtained provided that
S ( x, t ) and other boundary conditions of the differential equation such as initial
displacements, velocities etc. are known. However, it is often the other way round
in that by measuring the displacements (sets) and velocities etc. and making
assumptions on parameters such as the form of distribution of resistance, soil spring
values, quake (elastic limit of the soil), damping constants of soil etc., the soil
resistance which represents the load capacity of the pile is calculated instead. Smith
(1962) suggested an approach to solve the equation in which the pile is idealized
into a series of masses connected by elastic springs and “dashpots” as illustrated in
Figure HL-6 in Appendix HL. Each of the masses meets soil resistances, both static
(dependent on displacement of soil) and dynamic (dependent on the velocity of the
mass when the pile is struck by the hammer) components. A pile capacity versus
final set values can be obtained. The analysis is tedious and the iterative
computation usually requires a computer programme to derive the solution.
Use of the Pile Driving Analyzer (PDA) is a technique by which the pile dynamic
behaviours during driving including pile forces and accelerations are measured by
such electronic devices as transducers and accelerometers installed at the top of the
pile. By applying wave theory analysis to these measured quantities, the load
carrying capacity, soil parameters, energy transfer, pile driving stresses and
integrity of the pile can be estimated. Among these methods, the Case method and
CAPWAP are relatively common and are described in details in Appendix HL.
(i) Maximum energy delivered to the pile by the ram (EMX). As discussed, this
energy can be used to calibrate the hammer efficiency and the impact factor
used in the Hiley Formula. The quantity can be found for a single hammer
blow and an averaged value over 10 blows can also be calculated;
(ii) Maximum impact force (FMX) which is usually the first maximum force as
shown in Figure HL-7 in Appendix HL. This force can be used to calculate
the static capacity of the pile by the Case Method commonly used in the
industry as described below and in Appendix HL;
(iii) Forces and velocities (particle velocities) at the top of the pile are normally
Page 54 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
taken at 1024 (210) “time measurement points” (or multiples). (The use of the
1024 time measurement points is for facilitation of the working of “Fast
Fourier Transform”.) Thus if the total time taken for measurement is 102.4ms
(millisecond), the readings are taken at 0.1ms intervals;
The following quantities can then be calculated based on the measured quantities:
(i) The maximum compressive stress (CSX), which is simply the measured
maximum force in the pile divided by the cross sectional area of the pile;
(ii) The ultimate static capacity of the pile (RMX) which can be calculated by the
Case Method under various assumed J c values (soil damping constants) as
demonstrated in HL.3.2 in Appendix HL;
(iii) The pile integrity factor (BTA) which is arrived at by examination of the wave
forms. More detailed discussion is given in Appendix HL;
(iv) The compressive stress at the bottom of the pile (CSB);
(v) Total skin friction (SFT).
The Case Method (Rausche et al., 1985) is a closed-form solution based on the
assumptions of a uniform pile cross-section, linear elastic pile behaviour; and others
as stated in Appendix HL Section HL.3. For a pile with impedance Z p = EA c
where E , A and c are the Young’s Modulus of the pile material, cross sectional
area of the pile and wave propagation velocity of the stress-wave in the pile
respectively, the ultimate static capacity is approximately given by
R=
(1 − J c ) (F + Z v ) + (1 + J c ) (F − Z v ) (Eqn H5.4)
1 p 1 2 p 2
2 2
where R is the ultimate static capacity of the pile;
F1 is the pile head force measured at time tc1 ;
F2 is the pile head force measured at time tc 2 ;
v1 is the pile head velocity measured at time tc1 ;
v2 is the pile head velocity measured at time tc 2 ;
tc1 is the time when the pile head force F1 is recorded;
tc 2 = tc1 + 2 L c ;
L is the length of pile measured from pile head instruments to pile toe;
c is the propagation of velocity of stress-wave in pile and can be
calculated by c = E ρ where E and ρ are the Young’s Modulus
and density of the piling material respectively;
Jc is the “Lumped Case damping factor” which defines the dynamic
component of the pile at the pile toe. Its value depends on the type
of soil at the pile toe and the dimensions of the pile.
Page 55 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
is given in Appendix HL. It should be noted that Case method is more accurate
when the end bearing resistance is the dominating component, as the damping
factor is lumped at the pile toe only.
With this technique, the velocities and forces are first measured by the PDA method
at the top of the pile during the strike by the hammer. The pile head forces (or pile
head velocities) are then input into the Wave Equation as ‘input excitation’ to carry
out analysis under a set of initially assumed soil parameters including quake,
damping constant, ultimate friction distribution along pile shaft etc. Normally, the
back-calculated pile head velocities (or pile head forces) would be different from
the measured ones. The soil parameters are then adjusted and the Wave Equation
reanalyzed until a reasonably good matching between the calculated and measured
values is obtained. Then, there is a good reason to assume that the correct soil
parameters have been ascertained and the ultimate static capacity of the pile can be
calculated. However, it should be noted that the answers may not be unique, i.e.
different sets of soil parameters can all result in good matching with the measured
quantities.
(i) The hammer input excitation is measured by electronic devices. The energy
at the top of the pile can also be estimated. It thus eliminates the use of the
assumed values of hammer efficiency and the elastic compression cc ;
(ii) In the Wave Equation Analysis, the only measurable quantity to be checked
against the calculated pile load capacity is the “set”. However, the CAPWAP
enables pile load capacity to be arrived at by achieving a match between the
calculated and measured pile head velocities and forces. Thus CAPWAP
should be able to give more accurate answers.
Page 56 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
As CAPWAP can give a fairly accurate pile load capacity, the CAPWAP capacity
can be used to calibrate the parameters, including the hammer efficiency Eh and the
coefficient of restitution e used in the Hiley Formula by back-substitution. The
calibrated formula can then be used to determine the final set table. The calibrated
parameters may not carry any physical meanings by which they were derived. They
may be considered simply as coefficients to fit into the Hiley Formula which may
only be used in the particular site and hammer with certain fall heights.
The static formula for determination of the geotechnical load capacity of pile is
based on soil mechanics principles from which shaft friction and end-bearing of the
pile in the soil are determined and the sum gives the total capacity of the pile.
Generally the unit shaft friction and end-bearing are determined by the following
expressions which is based on soil mechanics theory.
Page 57 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
based on limited field data. Accurate assessments are often difficult, but the
assessments tend to be on the conservative side.
As for the end bearing capacity in accordance with (Eqn H5.6), the component
σ ' N q is often the pre-dominant one. There are different theoretical approaches for
the determination of N q by Berezantsev, Vesic, Hansen etc. However, according to
Poulos (1980), Vesic (1967) had pointed out that Berezantsev et al. (1961) appeared
to fit the available test data best. GEO Publication 1/2006 has included the design
chart in Poulos (1980) based on Berezantsev’s work. Nevertheless, a more precise
chart showing relations with pile length to diameter ratio is found in Tomlinson
(2008) which is extracted in Appendix HM together with some discussions on
Berezantsev’s approach and the mathematical expressions.
In addition, loading test on instrumented pile can be carried out to determine the
soil parameters. Strain gauges are installed along their shafts so that the strains and
consequently stresses along the pile shaft can be measured and finally skin frictions
and the end-bearing of the pile can be determined. The measured values can then
be applied to other piles in the same site for pre-determination of their bearing
capacities.
Compliance criteria for a pile loading test are often in terms of limitation of
settlements and/or residual settlements. The test is often specified for verification
of pile loading capacity. The testing procedures involved for common types of
piles are clearly stipulated in the Code.
Determination of the bearing capacity of piles socketed into rock by the Code is
comparatively straightforward when compared with driven piles as the capacity is
usually based on the geometry of the pile and the allowable bearing pressures
and/or bond strengths of different categories of rock. The Code explicitly allows
the combined use of end-bearing and shaft resistance in the determination of the
total bearing capacity of large diameter bored piles in accordance with clause 5.4.7
of the Code. However, for all other piles, the combined use of end-bearing and
shaft resistance is restricted unless it can be justified that settlements under working
load conditions are acceptable and adequate to mobilize the required shaft
resistance and end bearing simultaneously. The is because mobilization of the
required shaft friction and end-bearing may require movements of the subgrade of
different orders which might not be compatible along the pile shaft and the pile base,
taking into account the shortening of the pile under the applied load. In addition,
the minimum socket length in rock specified in Note (3) under Table 2.1 of the
Code could be ignored in pile bearing calculation for large diameter bored piles and
other piles socketed in rock.
(1) General
Page 58 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The clause defines allowable and ultimate anchorage resistance (Ra and Ru) of a pile
against uplift as respectively the allowable and ultimate uplift resistance of pile
shaft plus “effective self-weight” of the pile. The anchorage resistance refers to the
frictional resistance of soil on the pile shaft with methods of determination
stipulated in sub-clause (3). Nevertheless, the Code further states that anchorage
resistance is limited by the effect weight of soil mass/cone weight the pile
mobilized as a check against “pull out failure” of the pile with the weight of rock
cone and soil column effectively carried by it. It should, however, be noted that the
Code lists the limitation by a mathematical inequality for Ru only as
While there is no similar inequality listed for Ra, similar check for Ra is therefore
not necessary. In fact, it should be very adequate to take the effective weight as an
upper limit in checking for stability as the load factors for the de-stabilizing forces
are all taken into account in cl. 5.1.6.
The clause reminds that friction and bond resistance of the pile shaft with rock
should be based on simple figures in Table 2.2 of the Code and also that the
ultimate bond stress is related to the allowable value by a factor of safety of 2.
Detailed criteria are laid down in the clause for determination of the extent of the
rock / soil cone / column the pile can mobilize as weight against uplift. The criteria
are based on conservative consideration with the maximum half angle of the
inverted rock cone limited to 30o which is for heavily jointed or shattered rock. In
addition, the weight of the soil mass is also limited to that directly over the rock
cone while neglecting friction between the outer face of the soil column and the
surrounding soil as shown in Figure 5.1(a) of the Code which also illustrates that
soil weight beyond boundary to be ignored. In addition, as a conservative approach,
the bell-out (if any) is considered not effective by the Code in mobilizing the cone
and cylinder shaped mass of soil and rock above the base of the pile. As the
determination of the volume of rock and soil is complicated in case the soil columns
and rock cones of adjacent piles overlap as shown in Figure 5.1(b), some useful
algebraic expressions are given in Appendix HN, together with worked examples.
Although the worked examples are for large diameter bored piles, the same
approach can be applied to rock socketed piles.
Unlike friction piles in sub-clauses (3)(a)(ii) and (iii) which require uplift resistance
due to permanent tension to be half of that of transient tension, the uplift resistance
for piles with rock socket determined in this sub-clause applies equally to transient
and permanent tension.
This clause is for determination of uplift resistance of piles from shaft friction only
in granular soil. Three methods are outlined for driven steel H-piles. The first
method is based on a nominal uniform allowable shaft friction of 10kPa, with the
Page 59 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
ultimate value doubled. The second method is based on effective stress theory
which correlates the shaft friction to the horizontal stress acting normally to the
circumference of the pile which in turn depends on the effective vertical stress. The
third method is based on empirical correlation of shaft friction to SPT N values of
soil. For the second and third method, limiting values are imposed unless verified
by trial piles and the values determined are for transient tension with that due to
permanent tension being halved. So for the application of the equations in clause
5.1.6 which contain single value for Ru and Ra , they may have to be modified as
follows
I a + U a − Dmin Wk
(b) + ≤1
Ra − permanent Ra − transient
In fact, the two relations listed above are equivalent to adoption of the original
formulae in the Code with the transient wind loads to be checked against the
transient resistance, i.e. Ru − transient and Ra − transient .
The Code has not specified specific design requirements for other pile types. It
would be acceptable so long recognized engineering principles are complied with.
Assessment of the effective weight of the soil cone/soil column for pile groups in
granular soil also involves complicated geometry. A worked example
demonstrating compliance with the design requirements is included in Appendix
HN.
Horizontal restraint can be provided by the piles or the pile cap alone or the combined
action of both. Estimation of the restraint of a pile cap can be based on the elastic
continuum theory where the pile cap is embedded in a semi-infinite elastic medium.
Mindlin’s Equations or their integrated forms (Vaziri et al. 1982) can be used to
determine restraints on pile cap. More in-depth discussions based on Law & Cheng
(2014) are given in Appendix HO in which tabulated values are given for determination
of the lateral restraint by a more rigorous approach taking compatibility of the pile cap
and the soil movement into account. Nevertheless, caution should be taken in design if
there is probable removal of the embedding soil to the pile cap.
The Code requires checking of the load carrying capacity of the pile and capacity of the
lateral soil resistance, as an addition to deflection when considering group effects.
Lateral deflection of pile is discussed first in this section.
As for the pile cap case above, the lateral deflection of a pile can also be based on the
elastic continuum method (summarized by Poulos & Davis 1980) or the finite element
method. Randolph (1981) has fitted the results of finite element analysis into algebraic
expressions and proposed formulae which are reproduced in GEO Publication 1/2006.
Page 60 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
From (Eqn HP-1) in Appendix HP, it follows that the final restraint exerted by the soil on
the pile is independent on the width (or diameter) of the pile which appears not very
reasonable. Poulos & Davis (1980) actually proposed that kh in (Eqn HP-1) (the
coefficient of horizontal subgrade reaction of the soil defined as the pressure required to
move the soil by unit length) should be proportional to ( z B ) where n is slightly greater
n
than 1 for sandy soil and n = 0 for clayey soil. Since n is close to unity, kh can be
approximately taken as independent of pile diameter. In addition, Siu (1992)
alternatively proposed to modify kh by applying the factor (B B0 ) where B is the
0.25
According to GEO Publication 1/2006, the nh values quoted in Table 5.1 of the Code are
valid for stresses up to half of the ultimate bearing capacity of the soil with allowance
made for long term movement.
Page 61 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
To account for the group effect, reductions on the nh value as functions of pile spacing
in the direction of loading have been proposed in the Canadian Foundation Engineering
Manual (1978) which is reproduced in Table 5.2 of the Code. Nevertheless, if
interpolation of values is assumed, the relation can be fitted to a linear equation as
Reduction Factor = Ratio of pile spacing to pile diameter × 0.15 – 0.2 (Eqn H5.10)
Both the Canadian Foundation Engineering Manual and the Code have no clear
indication on the reduction factor when the ratio of pile spacing to pile diameter is less
than 3 but the pile spacing still satisfies the minimum requirements in cl. 5.1.3 of the
Code. Nevertheless, it should be reasonable to adopt a value as extrapolation from the
values of Table 5.2 which is the simple application of (Eqn H5.10).
In Appendix HP, the analysis of a pile under lateral load is illustrated with results in
deflections and internal forces of the pile. For structural design, partial load factors
should be applied as appropriate.
For checking the lateral load capacity of a pile which is governed either by the ultimate
soil strength or the structural strength of the pile, approaches by Broms (1964a &1964b)
and Poulos & Davis (1980) may be followed respectively for floating piles and socketed
piles. The ultimate loads so arrived at should be divided by a factor of safety of 3 for
checking against the characteristic lateral load. Illustrations of the checking of the
ultimate lateral resistance of a floating pile assuming pinned and fixed connections to the
pile cap is demonstrated in Appendix HF with numerical worked examples.
As a control to excessive pile deflection, the Code requires P-∆ effects to be addressed
when estimated pile deflection exceeds 25mm by elastic analysis. Both deflections and
internal forces in the pile will be increased when P-∆ effect is included in design
consideration. Some detailed discussion is outlined in Appendix HP, with reference to
Appendix HI.
The Code further warrants that piles and pile caps should not be used together to resist
lateral forces unless a distribution of forces between piles and pile caps can be
demonstrated. The distribution can be calculated assuming compatibility of displacement
of the piles and pile cap with the pre-determined lateral stiffness of the piles and the pile
cap. A recommended approach with a numerical example is given in Appendix HQ.
Analysis can also be carried out by computer with appropriate lateral stiffness inputs of
the piles and pile cap.
The clause outlines particular requirements for some specific types of pile commonly
used in Hong Kong. The following serves to highlight the characteristics of each type of
pile and elaborates the requirements further with illustrations by figures and practical
examples.
The points in common relating to the design of all types of piles under this clause are
listed as follows :
Page 62 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
(i) The load carrying capacities of the piles can be increased by 25% due to wind load
under the permissible stress method as per clause 2.5.5(1) of the Code;
(ii) Pile group reduction factors should be applied where appropriate in accordance with
clause 5.1.2 of the Code;
Allowable working loading capacity (axial load) of the pile is limited by clause
2.5.5(4) of the Code as follows :
where f y is the yield strength of the steel and Ap is the cross sectional area of the
pile. The lower factor of 0.3 for a pile installed by driving is to reduce the bearing
capacity of the driven pile so as to minimize the use of the heavy hammer and high
drop height to avoid high stresses during pile driving.
The minimum steel yield stresses should be determined from the “design strength”
of steelwork in accordance with Table 3.2 of the Code of Practice for the Structural
Use of Steel 2011 or BSEN10025. The yield stresses depend on the grades and
thicknesses of the steel pile sections. A thicker section has a smaller yield strength
because of the greater locked-in stresses created during the cooling of the hot-rolled
section.
Nevertheless, the Code also allows the use of limit state design in the structural
design of piles in accordance with the Code of Practice for Structural Use of Steel
2011. So the designer may use limit state design for pile sections under axial load
and bending, while limiting axial load to comply with (Eqn H5.11) and (Eqn 5.12).
The geotechnical capacity of the driven pile can also be ascertained by a dynamic
formula. For driven steel H pile or small diameter tubular piles, the pile would
generally be founded on soil of a specified SPT N values, e.g. not lower than 200.
However, driven piles founded on soil of SPT N values < 200 are also acceptable if
their capacities can be justified by other rational means.
(ii) The clause also requires “splicing”, “pile head” and “pile tip” details to be included
in the foundation plan. Typical details are illustrated in Figures H5.3 to H5.5. In
addition, the clause lists the requirements for weld testing in relation to the control
of workmanship including certification of welder tests, welding procedure
specification and the welding procedure test. Sample rates of not less than 10% of
the total number of welded joints by non-destructive testing are also specified for
destructive testing.
Page 63 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Page 64 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Figure H5.5 – Acceptable Details for Pile Toe – Strengthened for Hard Driving on or close to Bedrock
As the pile is installed after pre-boring, its design axial load capacity is given by (Eqn
H5.12) in accordance with clause 2.5.5(4) of the Code. Reference to Table 3.4 of the
Code of Practice for the Structural Use of Steel 2011 or BSEN10025 for the design
strength of steel should also be made.
The following Worked Example H5.1 illustrates the determination of the required bond
lengths between (i) the steel section and the grout; and (ii) the grout and the rock.
Design of Load Carrying Capacity of the Pile (excluding casing and grout)
(i) Due to structural strength of the Steel Section :
P = 0.5 × 430 × 28400 × 10−3 = 6106 kN
(ii) To withstand the maximum load capacity of 6106kN, the minimum socket grouted
length in rock should be 6106 (0.55π × 700 ) = 5.048 m;
(iii) Again to withstand the same maximum load, the minimum bond length between the
grout and the steel section is 6106 (1.918 × 480 ) = 6.632 m which should be
measured within the rock socket where effective confinement to the grout can be
provided by rock for achievement of the 480kPa bond strength.
So, to maximize the load carrying capacity of the pile as per its structural provisions and
taking the required bond length into account, the minimum bond length required in
Category 1(c) rock (as derived in the foregoing) is 6.632m.
Page 65 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Shorter bond lengths can be used if the pile is not designed for its maximum load
carrying capacity.
Details of the splicing of piles and the pile head for socketed steel H-piles are similar to
those for Steel H-piles/Steel Tubular Piles as discussed in H5.4.1, Figures H5.3 to H5.5.
Typical elevation of the socketed portion of a socketed pile is shown in Figure H2.3.
The Code requires rock sockets of sufficient strengths (and depths) to resist the ultimate
shears and moments acting at the pile tip. The ultimate lateral strength of the rock can be
assumed to be one third of the vertical allowable bearing pressure provided that there are
no unfavourable joint sets or a steeply inclined rock surface in accordance with clause
2.2.2(3) of the Code. Reference can be made to Figures 51 to 53 of GEOGUIDE 1 for
determination of the required depths of the socket.
The precast reinforced concrete pile is a large displacement pile driven into the ground
where the geotechnical capacity is usually determined by a dynamic formula. Due to the
relatively low load carrying capacity of the pile (governed by its small structural size and
materials) and its limited penetration power through underground obstructions, the pile is
usually used to support low or medium rise buildings on ground without significant
amount of boulders or corestones. In addition, the pile should not be subjected to hard
driving which can easily lead to damage of the pile head and pile toe.
Currently the pile is not commonly used in the local industry. A typical pile of square 14
inch (355.6mm) and concrete mix grade 20 (allowable concrete stress = 5MPa) possesses
a maximum structural load carrying capacity of the order of 355.62 × 5 × 10-3 = 632 kN.
The capacity may be further limited by the geotechnical capacity as determined by its
final set value in accordance with a dynamic formula. A typical detail of the 14 inch
square pile is shown in Figure H5.6.
4-3/4”φ
1” 12” 1”
Page 66 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The precast prestressed spun concrete pile is manufactured using high grade concrete
(cube strength up to 78MPa) with prestressed tendons embedded in the pile. Spinning of
the pile shaft is involved during manufacture of the pile. The prestressing force in the
tendons serves to resist the transient tensions which may be induced during pile driving,
though it takes up some of the compressive load carrying capacity of the pile.
Like precast reinforced concrete piles, the pile is a large displacement pile and both share
similar construction problems such as a low resistance to hard driving to penetrate
underground obstructions. Reports of structural damage were not uncommon when the
piles were hard driven to decomposed rock strata of high SPT N values with significant
boulder contents. (as often pre-determined in design). The advantage of this type of pile
is that they are normally terminated at soil strata with SPT N values greater than 120,
which would usually be founded at a shallower depth when compared with small
diameter displacement piles, such as driven steel H pile. However, the driving sequence
has to be planned carefully to minimize the difficulty in driving the piles in over-
densified soil due to driving of the already installed piles and pile rising, e.g. pile driving
in the outward directions. Re-driving of pile (after suffering from pile rising) may also be
needed. So the pile has to be constructed with great care.
The load carrying capacities of the common types of precast prestressed concrete piles
are listed in Table H5.3. It should be noted that the maximum compressive load capacity
of the pile is obtained by multiplying the cross sectional area of the pile by one quarter of
the cube strength of concrete after deduction of the strength taken up by the pre-stressing
tendons. A sample calculation is done for the second item in Table H5.2 as
0.25 × (78.48 − 5.33) × 125664 × 10−3 = 2298 ≈ 2300 kN
where the concrete cube strength and the ultimate stress induced in the concrete by the
prestressing tendons are 78.48MPa and 5.33MPa respectively.
Outside Inside Wall Cross Effective Allowable Tensile Strength of Allowable Allowable
Diameter Diameter Thickness Sectional Prestress Bearing Pile (kN) Shearing Cracking
(D) (mm) (T) Area (MPa) Capacity Strength Bending
Allowable Ultimate
(mm) (mm) (cm2) of Pile (kN) Moment
(kN) (kNm)
400 206 97 923 5.10 1,690 471 969 227 73.55
500 300 100 1257 5.33 2,300 669 1347 304 137.29
500 250 125 1473 5.03 2,700 741 1536 361 147.10
600 390 105 1633 4.95 3,000 809 1690 382 215.75
600 340 130 1920 5.24 3,500 1005 2041 466 245.17
Precast prestressed spun concrete piles should not be designed to resist bending and/or
tension. Also, a follower is not recommended for use with this piling system.
Figure H5.7 to Figure H5.9 show typical details of this type of Pile. For driving the pile
into stiff soil, there are two common types of pile shoes, one being conical type, the other
being cross type. The cross type pile shoe with cross stiffeners is shown in Figure H5.9.
Page 67 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Figure H5.7 – Details of Pile Shaft of a Precast Prestressed Spun Concrete Pile
Figure H5.8 – Typical Pile Head Details of a Precast Prestressed Spun Concrete Pile
Figure H5.9 – Pile Shoe Details for a Precast Prestressed Spun Concrete Pile
The pile is constructed by driving a steel tube capped at the bottom into the ground until a
satisfactory “set” has been achieved in accordance with a dynamic formula or for a length
Page 68 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
determined by a static formula for the load carrying capacity which is usually pre-
determined by the structural provisions. Concrete is then poured into the tube with
reinforcing steel and the steel tube extracted (with the bottom cap detached) before the
concrete hardens.
The Code limits the size of the pile to 750mm. Popular sizes used in the 1980s were
610mm diameter and 635mm diameter with grade 25 concrete (permissible stress =
6.25MPa). The capacities are therefore
0.25 × 6102 π × 6.25 × 10−3 = 1827 kN and 0.25 × 6352 π × 6.25 × 10−3 = 1979 kN.
As vibrations may adversely affect the integrity of newly poured concrete, the Code does
not allow driving of new piles which are less than 5 diameters away within 24 hours.
(1) General
The Code defines a small diameter bored pile as a bored pile with diameter not
exceeding 750mm which may be formed by boring a casing into the ground and
subsequently filling the hole with concrete or grout. As the pile derives its bearing
largely from skin friction, pressure grouting or pressurized concrete are favoured.
Basically, the total allowable bearing capacity of the pile is derived from skin
friction and end-bearing which are often related to the SPT N values.
Trial piles are generally necessary for this type of pile as the bearing capacities and
the integrity of the pile are affected by so many uncertainties related to the site
geology and construction method. Even with adequate trial piles to justify the
Page 69 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
friction factor μ (used to correlate unit skin friction to SPT N values), the factor is
recommended to be capped at 0.7 generally.
The CFA pile is a small diameter bored pile formed by augering into the ground and
then subsequently filling the hole with cement sand grout (by pumping) and a
reinforcement cage. Under pressurized grouting, a higher friction factor μ can be
allowed for this type of small diameter bored pile. The Code allows the factor to be
1.0 which can be increased to 1.6 with trial pile tests. A sample design calculation
of a CFA pile with pressurized cement sand grout is presented below as Worked
Example H5.2. The design data for the pile and calculations are as follows :
The geotechnical capacity of the pile is determined in accordance with the empirical
relations that shaft friction is 1.6 N av ( µ = 1.6 ) kN/m2 and end-bearing is 5 N b
kN/m2 in accordance with the Code with N av capped at 40. The SPT N values of
the soil embedding the pile are listed in Table H5.3 by which the total shaft friction
and end-bearing are calculated as 1709.60kN.
Page 70 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
As the geotechnical capacity of the pile which is 1709kN is greater than the
structural capacity, the structural capacity of 1460kN dictates.
The Code also stresses the monitoring of the grout factor, because of the relatively
high uncertainty of the behaviour of the pile, together with precautionary measures.
Details of a small diameter CFA pile are shown in Figure H5.11. It should be noted that
the reinforcement cage is normally not required to extend for the full length of the pile as
long as structural adequacy of the pile can be demonstrated.
Pile
Cap
Cut-off level
75
A A
Section A-A
N.T.S.
In Hong Kong, the geotechnical capacity of the large diameter bored pile usually derives
from end-bearing with or without inclusion of shaft bond/friction with the rock along its
pile shaft. As the concrete grades currently used are usually high, up to grade 45, giving
a permissible compressive stress of the order of 11.25MPa which is well in excess of the
rock bearing pressure of the order of 3 to 10MPa, bell-outs for enlargement of the end-
bearing areas have been extensively used so that the geotechnical capacity can match the
structural capacity in the pile shaft. Configuration of the large diameter bored pile with
bell-out and the use of the shaft friction is demonstrated in Figure H1.1.
The design principles of large diameter bored pile are summarized as follows :
Page 71 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
(i) The loading capacity of a large diameter bored pile usually derives from the end
bearing capacity on rock with or without shaft friction between rock and concrete;
(ii) If there is a reduction of the cross sectional area in a rock socket, checking of the
structural section for the reduced area is required with or without compensating
reinforcement as necessary;
(iii) The presumed values for allowable vertical bearing pressure and shaft resistance are
given in Table 2.1 and Table 2.2 of the Code respectively;
(iv) The maximum bell-out size of large diameter bored pile shall not exceed 1.65 times
the shaft diameter and the gradient should not exceed 30o from vertical;
(v) It should be noted that the nominal socket length of 0.5m or 0.3m as specified in
note (3) under Table 2.1 are extra provisions over the limitation on design socket
length and should not be counted in the calculation of shaft bond/friction. Normally,
the nominal socket length can be well provided by the bell-out, if any;
(vi) Socket length for bond or frictional resistance of the pile for enhancing bearing
capacity of the pile should be limited to the lesser of 1 time the rock diameter and
3m if bell-out is used and the limitation can be relaxed to the lesser of 2 times the
rock diameter and 6m if bell-out is not used.
(vii) The design load capacity of a pile shaft is also governed by the structural section
design of the pile, bearing in mind that a reduction of 20% of concrete or grout
strength should be adopted if concreting or grouting under water;
(viii) In steep bedrock profile, two adjacent large diameter bored piles shall be founded at
levels differing by not more than the clear distance between them unless stability of
the rock can be checked by recognized engineering principle. As the internal
friction angle of bedrock is often taken as 40o, it is suggested that an elevation less
than 40o can be taken as not being a steep bedrock profile, in which case the
requirement can be exempted. In addition, the checking of overstresses as part of
rock slope stability check can be based on the continuum theory by which reference
can be made to Figure H3.1. For example, a 2m diameter pile with a bearing stress
of 4500kN/m2, at a clear distance of 2m from and a level 2m above another pile will
create a maximum additional stress of 0.08 × 4500 = 360 kN/m2 at the perimeter of
the other pile (0.12 is estimated from Figure H3.1). It can also be seen from Figure
H3.1 that additional stress on a pile due to another pile at a higher level will be less
than 5% of the bearing stress of the higher pile if their clear distance is more than
one diameter apart as marked up by the 45 degrees lines.
A sample design of the load carrying capacity of a large diameter bored pile under
Worked Example H5.3 is demonstrated as follows :
Page 72 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The total geotechnical capacity of the pile without bell-out but with socket length of 6m
is 35343 + 39584 = 79427 kN
The total geotechnical capacity of the pile with bell-out but with 3m socket length is
96221 + 19792 = 116013 kN
So the use of bell-out (though with less allowable shaft friction) is more efficient in
enhancing geotechnical capacity of the pile.
Typical details of a large diameter bored pile are shown in Figure H5.12.
90o
750
30o
Page 73 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
H5.4.8 MINI-PILES
The structural capacity of a mini-pile is comparatively low due to its relatively small size.
However, as the machinery required for the construction is small and construction is fast,
the pile is suitable for construction of buildings in sites where access is difficult. Though
the overall load carrying capacity of a mini-pile foundation is not small if the piles are
installed to minimum pile spacing (the smaller of 750mm and twice the outer diameter
according to clause 5.1.3 of the Code), they may not be suitable for high-rise building as
the pile cannot resist lateral load unless “raked”. Where mini-piles are to be adopted for
high-rise building, some raking mini-piles are required to resist the lateral loads acting on
the building structure.
The Code includes detailed descriptions of the design principles and construction
considerations for this type of pile under this clause. The design principles of a mini-pile
are briefly summarized as follows :
(i) With f y = 500 MPa, the load carrying capacity of a normal 4T50 mini-pile is only
4 × 252 π × 0.475 × 500 / 1000 = 1865 kN and that with 5T50 is 2332kN accordingly
which are both less than the limit of 2350kN imposed by the Code;
(ii) The presumed allowable bond or friction between rock and concrete is given in
Table 2.2 of the Code;
(iii) The perimeter of the shear plane for checking bond stress between the steel bars and
grout are shown and determined in Figure H5.13 according to the clause 5.4.8(2)(e)
of the Code :
Page 74 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
70
o
36
20 35
72o
Figure H5.13 – Shear Plane for Checking Bond Stress between Steel Bars and Grout
for 4T50 and 5T50 Mini-pile
(iv) The allowable bond strength between steel bars and grout is limited to 0.8MPa
which is small as compared with the ultimate bond strength as stated in clause 8.4.4
of the Code of Practice for Structural Use of Concrete 2013. Taking the 4T50 mini-
pile where the perimeter is 437mm, the bond length required to achieve the design
capacity of 1865kN is 1865/(0.437×800) = 5.33m which is the minimum length of a
4T50 mini-pile to develop the full capacity;
(v) The allowable buckling capacity of the mini-pile may be checked with
consideration of lateral restraints from the grout, permanent steel casing and the
surrounding soil. A worked example is enclosed in Appendix HI;
(vi) Only raking mini-pile can be used to resist lateral load in view of the small bending
strengths of the pile. Figure H5.14 shows a structural configuration involving a
raking pile that can achieve equilibrium in resisting the applied lateral load and
result in no bending moments on the piles.
Resultant Applied
Lateral Load
The raking pile and the vertical
Pile Reactions pile should be so arranged that
the lines of actions (axial loads)
of the piles and the resultant
applied lateral load are
concurrent so as to achieve
rotational equilibrium.
Page 75 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
A sample design of the load carrying capacity of a mini-pile under Worked Example
H5.4 in accordance with Figure H5.15 is demonstrated as follows :
Design of Load Carrying Capacity of the Pile (excluding casing and grout)
(i) Due to structural strength of the reinforcing bars
P = 4 × 0.25 × 502 × π × 0.475 × 500 = 1865 kN
(ii) To withstand the maximum load capacity of 1865kN, the minimum socket grouted
length should be 1865 (π × 0.235 × 700 ) = 3.61 m.
So, to maximize the load carrying capacity of the pile as per its structural provisions and
taking the required bond length with grout into account, the minimum bond length
required in Category 1(c) rock (as derived in the foregoing) is 5.33m > 3.61m.
In view of the relatively small slenderness of the mini-pile, the Code reminds checking
the allowable buckling capacity. Reference may be made to Appendix HI.
Page 76 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
TYPE 1
MIN. 300mm CLEAR
SPACING BETWEEN MECHANICAL
COUPLERS COUPLER
TYPE 1 MECHANICAL
COUPLER MIN.
200mm CLEAR
SPACING BETWEEN
COUPLERS
235mm φ
DRILLED HOLE
H5.4.9 BARRETTES
Barrettes or barrette piles are constructed by machine excavation under a slurry filled
trench down to the founding level. A reinforcement cage (and other structural elements
as necessary, such as stanchions) is then inserted, followed by concreting of the
excavated trench by tremie method. Barrettes are usually of rectangular plan section.
Page 77 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
More detailed descriptions of this type of foundation are as follows. The descriptions
also apply to diaphragm walls, which are essentially a succession of contiguous barrettes
and as such can also be used as foundations resisting vertical loads.
While excavating the trench under bentonite slurry, the water from the slurry
tends to filter out into the surrounding soil, driven by the necessary pressure
head difference between the slurry and the outside groundwater. In this
process, the bentonite clay particles are retained at the soil interface and form
what is called a “cake”, plugging the soil pores and rendering the interface
impermeable. The cake is generally a few millimetres thick and the
performance depends essentially on the permeability of the surrounding soil
(water from slurry has to flow out), and the permeability of the bentonite cake
itself which in turn depends on the mud quality.
The friction capacity of barrettes in soil may also be enhanced using shaft
grouting, which consists of grouting the interface between the concrete and
the soil, so as to compact the soil and increase the lateral stress acting on the
barrette. The foundations of the International Commerce Centre in Hong
Kong are a major example of such design.
However, it should be noted that instrumented trial piles are often required
before construction of the working piles in order to verify the design
assumptions, particularly on the mobilised pile shaft.
Page 78 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Where there is a socket, rock socket friction also contributes to the load
carrying capacity, in addition to the end-bearing capacity. Rock socket
friction shall follow the requirements of Table 2.2 of the Code in relation to
“Presumed Allowable Bond or Friction between Rock and Concrete for Piles”.
Minimum nominal friction : When full scale load tests are carried out, it is
sometimes attempted to eliminate friction over the top section of the barrettes
in order to concentrate the load in the soil stratum to be tested (e.g. CDG).
This is usually done by means of creating an artificial interface using
“Volclay” panels or similar arrangement. Monitoring results always show that
even with such an artificial interface, the mobilized ultimate friction is always
in the order of 25 to 30 kPa. Therefore it is concluded that an allowable
nominal friction of 10 kPa can be adopted.
The slurry used for excavation may be based on bentonite, polymers or compatible
combinations thereof.
Rigid reinforced concrete guide walls are usually provided to maintain alignment
and verticality of the excavation as well as for supporting the weight of the
structural elements (e.g. reinforcement cage, stanchions) hanging in the trench prior
to pouring the concrete.
As for bored piles, the type of concrete used for barrettes and diaphragm walls shall
have suitable workability characteristics. Suitable concrete characteristics are
provided in BSEN 1538:2010+A1:2015 “Execution of special geotechnical works :
Diaphragm Walls”.
Page 79 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Page 80 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Caisson
Cap
blinding
Cut off level
75
Caisson 100
Ring nominal
cover to
blinders
Diameter Diameter
of of
Caisson Caisson
binders
600 min.
Key in
rock
Bedrock
A steel H-pile driven to bedrock is used in locations where the bedrock is shallow and the
soil above bedrock does not have sufficient strength to take the set so that the pile is
driven to bedrock for founding. The pile is described as being “driven to refusal” with
set value less than 10mm per 10 blows. The bedrock to be founded on should not be
inferior to category 1(d) in accordance with Table 2.1 of the Code.
The Code also requires special considerations when the bedrock is steeper than 25o from
the horizontal to avoid “slipping” of the pile at the bedrock under hard driving. In
addition, even if the slope of the bedrock is less than 25o to the horizontal, the Code
cautions that drop heights of the hammer should be reduced when driving is close to the
bedrock so as to secure better anchorage of the pile into the bedrock.
The details of the pile are similar to those of steel H-piles discussed in 5.4.1. The Code
has cautioned users to check against (i) buckling, construction tolerances and stability
due to the relatively thin layer of embedment soil; (ii) the necessity of a strengthened pile
base (hard driving when reaching bedrock where the superimposition of the upward and
downward stress waves can magnify the stress on the pile toe as discussed in Appendix
Page 81 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
HL); and (iii) additional testing requirements including driving a sufficient number of
trial piles to demonstrate “buildability” of the pile prior to installation of the working
piles.
When piles are short, the Code reminds the users of stability problem. Design of a “fixed
head” is recommended especially when the embedding soil is weak. For piles shorter
than 10m, trial piles may be required.
The Code also requires the peak driving stress at final set be not less than 75% of the
yield stress of the pile when undergoing dynamic load test. The dynamic test may be
limited to piles of lengths shorter than 30 m. There is also room for decrease of the peak
driving stress to 65% of the yield stress of the pile which should be able to ensure
adequacy in the test.
Steel H shear piles are effective in enhancing lateral shear capacity of a pile foundation as
each provides full lateral shear capacity of a pile with no structural capacity exhausted by
axial load. As they are not required to be installed to strong bearing strata and to undergo
final set or loading test, the construction time of them are relatively short.
To maximize lateral shear capacity, the pile heads of the steel H shear piles have to be
fixed to the pile cap with adequate lengths of anchorage into the pile cap. As the piles
will protrude above the lowest layer of reinforcing bars of the pile cap, some construction
difficulties will be imposed.
Except for statically determinate cases, the Code requires the analysis of pile load
distribution through pile cap be generally carried out by flexible cap analysis
incorporating stiffnesses of the pile cap and the piles. In addition, it also stresses on the
interaction effects between the piles. While it is easy to incorporate stiffness of a pile cap
in the mathematical model, the axial stiffness of a pile is often difficult as strictly
speaking the soil restraint along the pile shaft and the settlement of the pile tip in soil
which directly affect the axial stiffness are difficult to determine. The interactions
between the piles through the soil medium are even more difficult to determine. Methods
by Poulos & Davis (1970) and Randolph (1980) involving complicated mathematical
expressions, tables or charts for limited cases may be employed but they are not
popularly used in the trade practice at present.
The Code reiterates that mini-piles possess limited bending stiffness and only raking
mini-piles should be designed to resist lateral load in analysis. So unless raking piles are
used, lateral restraints can only be provided by pile cap.
Reinforcement and detailing of pile caps are similar to raft footings as discussed in H4.3
and Appendix HD. Nevertheless, detailing is more complicated in case steel H-piles
protrude into the pile cap for fixity against rotation which may interfere with the bottom
steel bars. As it is not advisable to use wide spacing of steel bars which may result in
excessive cracking affecting durability, the Code requires additional reinforcing bars
Page 82 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
when the spacing of the continuous steel bars is increased to 400mm to cope with the
commonly used steel pile such as 305×305×223 piles having lateral dimensions in the
order of 330mm. Figure H5.18 demonstrates the arrangement.
X ≤ 250 X
≤ 250
X-X
additional
bar bent and
welded to
the flange of
the H-pile
Y
Y-Y
Figure H5.18 – Additional Bars to Trim Wide Spacing of Main Bars to Avoid Conflict with
H-piles in Pile Cap as per clause 5.5 of the Code
Page 83 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Similarly, the horizontal resistance of the ground can also be mobilized from bond or side
resistance at the side walls and the base, together with the passive resistance of soil.
Worked Example H2.1 under H2.5.4 demonstrates mobilization of the horizontal
resistance of the ground so that the basement or hollow box structures can achieve
acceptable factors of safety against sliding and overturning.
The Code cautions that when more than one component (e.g. base friction plus side
friction) is utilized as ground resistance for the basement or hollow box structure, it has to
be demonstrated that they can be mobilized simultaneously. Compatibility of movements
should be demonstrated.
The Code also requires that unacceptable disturbance (movement and stress) to the
ground or adjacent structures and services should not be caused by the foundation
structure. Assessment of such disturbance has to be carried out in the design stage, when
additional stresses and movements induced should be estimated and where required,
measures implemented to keep the disturbances within tolerable limits. Some of the
tolerable limits are pre-determined by authorities such as the MTRC, WSD and some are
statutory ones. Sometimes monitoring during and/or after construction has to be carried
out to ensure that the limits are not exceeded. Assessment of the disturbance in the
design stage involves determination of additional stress and movements induced on other
structures through the soil medium. For simple configurations, the assessment can be
based on charts and/or formulae provided by publications including Poulos & Davis
(1973) which are in accordance with the continuum theory. More sophisticated analysis
can be carried out by numerical modeling based on either the finite element or continuum
method. Nevertheless, a worked example using the continuum theory based on Mindlin’s
Equations to estimate the stresses induced on a nearby structure due to a newly
constructed structure founded on hollow box foundation is given in Appendix HR.
There is a requirement in the Code that the concrete used should not be inferior to grade
C35 and be sufficiently water-tight. This is to avoid the trapping of water inside the box
Page 84 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
structure which may upset the pre-determined load balance in design stage. If water-
tightness cannot be fully guaranteed, a water pumping system (automatic if required)
should be installed.
Stability against buoyancy is important, especially when the dead weight of the structure
is less than the water upthrust at the permanent finished stage or during construction.
Reference to H2.5.4 and Worked Example H2.1 of this Handbook can be made for the
checking of stability against buoyancy. Use of ground anchors may be required to
withstand the buoyancy uplift. More details are discussed in H6.4. However, it should
be noted that permanent prestressed anchors designed to resist permanent upthrust may
not be acceptable to the Buildings Department. This is because the use of permanent
prestressed ground anchors in a project would impose a long-term monitoring
commitment on the maintenance parties which usually involves appreciable recurrent
cost and, should deficiencies be revealed, remedial works may be difficult and expensive.
Past experience shows that compliance with such commitment by owners is not
practically viable.
The Code remarks that the design of the permanent structure should take into account the
stresses that may have developed during the various stages of the construction sequence.
An example is the design of the base slab of a basement which has to cater for different
distributions of soil and water upthrust at different stages of construction and where the
load distribution at the final stage is not the most critical at all locations.
Care has to be taken if there are services or structures (such as tunnels) that have to be
connected to a basement structure and the basement is resting on soil where the increase
in settlement as construction proceeds is significant. This is because these services or
structures connected to other foundations may be subject to different settlements at their
other ends, thus creating differential settlements that may be intolerable. Flexible
connections may have to be used. Another practice is to defer the connection work to
until completion of the superstructure so that the settlement of the basement structure is
almost completed (at least due to dead load). Figure H6.1 illustrates the phenomenon.
differential
settlement
(i) Service connected to the (ii) Settlement of the Basement Service connected to the
Basement when superstructure continues when superstructure basement upon completion of
construction not yet commenced. construction proceeds, thus superstructure so that
creates differential settlement differential settlement will be
to the linking services. minimized.
(a) Construction sequence by which services connected to (b) Construction sequence by which services
basement prior to construction of superstructure. connection after completion of superstructure.
Page 85 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The obvious advantage in constructing a diaphragm wall is that temporary works such as
sheetpiling can be eliminated as the permanent wall structure can also act as a soil
retaining structure during excavation. As the wall structure is very strong compared with
steel sheetpiling, shoring work can be minimized and is more suitable in case of deep
excavation. In some cases, diaphragm walls are used for the “top down construction
method” of basement by which diaphragm walls are first formed, followed by excavation
from the ground level downwards and successive construction of the floor slab structures.
It is relatively speedy for constructing the basement and superstructure simultaneously
provided that good site planning is implemented.
The diaphragm wall, being an impermeable structure, can serve the water cut-off
purpose during excavation work by lengthening the water flow path as shown in
Figure H6.2.
In Figure H6.2, the flow lines indicate the direction of the flow of water and the
equipotential lines are contours along which the “total head” (elevation head plus
static pore water pressure) is constant. The deeper the key-in of the impermeable
wall, the longer is the flow path and therefore the smaller the rate of water flow into
Page 86 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
the excavation. Analysis for a 2-dimensional flow field can be based on the
fundamental equations listed in Appendix HS. Approximate determination of the
hydrostatic pressures on the wall and water seepage rates can be carried out by the
“flow net” analysis described in most of the text books in soil mechanics.
Nevertheless, analytical solutions of the basic equations are available for some
simple configurations and their uses are demonstrated as worked examples in
Appendix HS. For more complicated cases, use of the computer analysis software
will be necessary.
3. Bending moments, shear forces and deflections due to lateral loads for the
proposed construction sequence
The bending moments, shear forces and deflections due to lateral loads for the
proposed construction sequence are the results of excavation analysis. The
structural strengths of the wall structure should be able to resist the forces induced
in them, together with tolerable deflections. The deflections induced in the
surrounding ground and structures should also be studied if found significant.
The proposed construction sequence should also be taken into account if found to
have significant effects on stresses (locked-in stresses) in the structures and
deflections. The phenomenon of “locked-in” stress in a diaphragm wall under “top
down construction” sequence is illustrated in Figure H6.3 as a simplified case with
only two layers of strutting. In the analysis, apart from the possible changing of soil
load profiles as highlighted in the figure, compatibility of displacements of the soil
profiles, the wall and the strutting may also need to be ensured. The same
phenomenon can in fact apply to other similar excavations such as those supported
by sheetpile walls in which successive strutting supports are installed as excavation
proceeds downwards from ground level. Commercial software are available to
analyze multi-layer strut excavations with full account taken of the construction
sequence.
Page 87 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Stage (1) : Basement wall Stage (2) : Front part Stage (3) : Top Floor constructed, but the
excavated for certain depth, deflection and forces in the wall remains as
constructed.
wall deflected by δ1 with δ1, F1 & M1. F1 & M1 are “locked” in the
forces F1 and M1 induced. wall. Top strut is free of load at this stage.
δ3 δ1
δ2
Model 1 +
Model 2
Stage (4) : Further excavation and lower floor The analysis of the wall for forces and displacements to simulate the construction
constructed. Deflection of the wall increases sequence can be conveniently carried out by performing analysis according to the
to δ2. Top strut load is due to δ2 – δ1 (δ1 final configuration as Model 1 (with prop by the upper floor) to obtain the
creates no load on strut) with new forces F2 deflections and forces δ3, F3 & M3 + the deflection and forces of Model 2 which is
& M2. The lower floor constructed does not the wall structure under the prescribed deflected shapes at Stage (2) with deflections
affect δ2, F2 & M2 at this stage. and forces δ1, F1 & M1.
To maintain stability in the slurry trench excavation, the bentonite slurry should be
maintained at a certain depth above the groundwater level outside the trench
excavation such that the slurry pressures exceed the pressure exerted by the soil and
ground water with a certain factor of safety. Reference can be made to Hajinal I. et
Page 88 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Where ground anchors are needed to resist the buoyancy force acting on the structure,
they are normally formed in rock whereby steel tendon/bars are grouted in drilled holes in
the rock. The uplift resistance of the ground anchor depends on (i) strength of the anchor
bars; (ii) bond strength of the grout with the steel bars; (iii) bond strength of the grout
with rock; and (iv) weight of the rock mass and the overlying soil that will be mobilized
by the anchor. Demonstration of item (iv) is shown in Figure H5.3. The effects of
adjacent anchors should also be considered with due regard to the overlapping of
mobilized rock and soil masses. An illustration is shown in Figure H6.4.
Ground Level
Figure H6.4 – Illustration of Mobilization of Soil Mass against Uplift for Foundation
Elements in Close Proximity
Page 89 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
Reference can be made to Table 2.2 of the Code for the bond strength of grout with rock.
The cement grout should comply with the requirements of GEOSPEC 1 of CEDD (1989)
by which the grout should consist of OPC and water only. Sand and PFA should not be
used in general. As for the bond strength of steel bars with grout, reference can be made
to reliable test data.
For pre-stressed anchors, design and construction shall comply with GEOSPEC 1 of
CEDD (1989). Monitoring should also be carried out as necessary.
Page 90 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
H7.1 GENERAL
In addition to the requirements as stipulated in the Code under this sub-clause, a review
of actual site conditions should be conducted to ascertain the adequacy of the design and
suitability of the construction method prior to execution of the foundation construction
work.
The list of Registered Specialist Contractors (Foundation Work) can be found in the web-
site of the Buildings Department.
Adequate resources from the AP, RSE, RGE and RSC Streams must also be ensured so
that the quality supervision for foundation works can be carried out.
Whilst the Code concentrates on the testing of materials in this sub-clause, discussion in
relation to construction practice and safety is also outlined.
(i) Whilst the HKB(C)R (2012) requires the standard size of test cubes to be
150mm, an alternative standard size of 100mm is also allowed in the Code of
Practice for the Structural Use of Concrete 2013. The use of the smaller size
test cubes serves to reduce the crushing loads exerted by the testing machines
which might otherwise be too high to test concrete of grade exceeding 60.
The alternative size is to meet the increasing demand for the use of high
strength concrete which has been gaining popularity in recent years;
(ii) PFA and GGBS should preferably be used in large volume concrete pour for
pile caps and raft footings so as to reduce the heat of hydration. In case of
very massive structures, say over 3m thickness, additional precautionary
Page 91 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
measures including the use of icy water in the concrete mix, planned
sequential concrete pours, temperature monitoring etc. should be considered;
(iii) Corrosion protection of the concrete is a concern in adverse sub-soil
conditions. More detailed discussion can be found in H2.6.
(2) Reinforcement
In addition to the testing of the material, tests of welds are also important. Testing
methods and frequencies are also illustrated in the Code of Practice for the
Structural Use of Steel 2011.
In the driving of steel piles, it is an established practice to limit the driving stress to
80 – 90% of the yield stress of the steel pile in order to avoid damage due to “hard
driving”. Measurements of the driving stresses are often made by PDA tests.
H7.1.4 EXCAVATION
Excavations, especially deep excavations, often bring safety concerns. The Building
Authority requires prior submission and approval of an “Excavation and Lateral Support
Plan” (ELS Plan) if the extent and depth of the excavation exceed that stipulated in the
PNAP APP-57. For excavations of minor extent, submissions and acknowledgements of
“shoring and excavation procedure details” may be sufficient as required by the Building
Authority.
As far as excavation is concerned, the following may also act as guidelines for the design
and execution of the excavation :
(i) Adequate data in relation to soil strengths and ground water levels should be
acquired and analyzed;
(ii) Determination of the type of excavation (open cut excavation or shored
excavation) and construction method should be based on factors including (1)
Page 92 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
depth of excavation; (2) strength of the soil; (3) ground water level; (4)
environmental consideration (e.g. noise and dust); and (5) anticipated effects on
the adjacent structures or utilities;
(iii) In the case of an open cut excavation, the gradients of the slopes should be
designed with adequate factors of safety and if necessary, the surface may have to
be protected by such measures as covering by tarpaulin sheets or chunam to
prevent surface infiltration if considered necessary. Surface drainage channels
should also be provided in order to properly direct the surface run-off to a safe
discharge point;
(iv) In case of a shored excavation, stability and strength of the shoring should be
checked against the soil loads appropriately determined. Effects of the
construction sequence should be catered for as appropriate;
(v) Monitoring (generally against soil movement, water draw-down, vibration) should
be considered as necessary with pre-determined warning and stop-work threshold
limits. Generally the three “triggering levels” – alert, alarm and action levels as
stipulated in PNAP APP18 can be adopted in monitoring. In addition, authorities
including MTRC and WSD have imposed well known threshold limits to induced
stresses, movements and vibrations on their structures and installations due to
nearby construction;
(vi) Effects of water draw-down on adjacent structures and utilities should be assessed
as it may create excessive settlements. Re-charging may be necessary to restore
ground water to acceptable levels during construction;
(vii) The necessity of grouting may be considered for stabilization of the soil and
enhancement of water cut-off;
(viii) Danger due to the upheaving of soil at the bottom of the excavation needs to be
assessed;
(ix) According to the Construction Sites (Safety) Regulations, excavations deeper than
1.2m need to be shored. The shoring work is especially important in areas of high
ground water.
Photographs showing open and shored excavations are in Figures H7.1(a) and (b).
Page 93 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The following serve to supplement the assessment as required in the Code. They are
suggested measures and should be implemented as necessary to suit actual site conditions.
Alternative measure can always be suggested instead :
(a) In the preparation of the detailed report as required under this sub-clause, the
engineer should determine the scope and details of the investigation in accordance
with his professional judgement which may include (i) review of existing records,
(ii) visual inspections, (iii) determination of tests (non-destructive or destructive)
that need to be carried out for assessment;
(b) Where sensitive structures and services are in close proximity, the estimation of the
effects including “stresses”, “movements”, “vibrations” on them as a result of the
proposed foundation should be carried out as appropriate;
(c) Where required, examples of preventive measures proposals may include (i)
“sleeving” of newly constructed piles or walls along certain portions of their lengths
so as to avoid loads to be exerted by these portions onto the soil which may
otherwise create instability; (ii) strutting of excavations to prevent excessive lateral
movements of existing foundations; (iii) re-charging of surrounding sub-soil by
water to minimize settlements due to water draw-down; and (iv) careful control of
the construction procedures to avoid over-break and ground loss during pre-boring
process. These are illustrated in Figure H7.2. In addition, the monitoring scheme
and contingency plans should also be included where necessary.
External
lateral load Strutting to prevent
acting on lateral movement of
foundation foundation
Sleeving, to
ensure no Transmission Water
lateral load of lateral load recharging
transmission beneath safe if necessary
angle line Casing and
Existing
Pre-determined drill bit should
foundation
Safe Angle not advance
Water independently
Pile on slope “sleeved” for length above safe angle Pumping to avoid
line so that lateral load is not transmitted to the slope Well overbreak
above the line which will otherwise create instability. during boring
Having completed the detailed report on the structural conditions of all surrounding
buildings, land, structures and existing services that are likely to be affected by the
proposed foundation works, as well as the estimation of the effect due to the works (such
as vibration, ground loss or ground water drawdown), the most appropriate foundation
Page 94 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
type and construction sequence should be selected, together with proposals for preventive
measures, a monitoring scheme and contingency plans as appropriate.
Depending on the assessed effect of foundation works, and also the importance of the
surrounding buildings, land, structures and existing services, precautionary measures in
the form of shoring, underpinning should be included in the foundation proposal as
appropriate.
Founding Details
Page 95 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The Code gives a comprehensive description of the monitoring plan including the three
“Triggering A” levels (“Alert”, “Alarm” and “Action” Levels as stipulated in AP/RSE
Practice Notes APP-18) under this sub-clause.
Photographs for the various instruments and their installations for monitoring purpose are
shown in Figures H7.4(a) to H7.4(e).
Page 96 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
H7.2.5 DEWATERING
Dewatering using electric submersible pumps to drawdown the groundwater table is very
common in keeping the excavation dry for foundation works such as the construction of a
raft foundation. Recharging to maintain within design limits the groundwater level
outside the excavation may be considered when necessary. The groundwater table during
construction is to be properly checked by monitoring stations. Figure H7.5 schematically
shows water draw-down by pumping and a photograph of submersible pumps.
Excavation
GWL
drawdown
Submersible pumps
H7.2.6 VIBRATION
The Code also cautions that resonance may occur if the frequency of a continuous
vibration coincides with the natural frequency of a building structure. However, the
vibration is generally a band of ground excitation of many frequencies and the substantial
responses of a building may be due to a few of its lowest natural frequencies and careful
study has to be carried out to identify the adverse effects. Fortunately, dynamic analysis
by computer method is common today. However, care should be taken in assessing
stiffness of the building as the non-structural components which are often ignored in
structural analysis can contribute substantially to the stiffness and hence lower the natural
frequencies.
The formula for estimation of vres is extracted BS5228-2:2009 Table E.1 for percussive
piling which is in turn quoted from Hiller and Crabb (2000). The formula takes a similar
form to that of Attewell and Farmer (1973). The latter uses horizontal distance from the
pile axis as the variable instead of the slope distance used by the former.
Page 97 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
H7.2.8 BLASTING
Regulatory control on the safety and security on the use of explosives in Hong Kong is
under the control of the Commissioner of Mines (Director of Civil Engineering and
Development).
When an explosive is detonated, shock waves and vibration are generated. Vibration is
measured in terms of peak particle velocity (ppv) in units of mm/sec. A report is
generally required for assessing vibrations that would be incurred to the surrounding
structures and facilities to ensure that they are within tolerable limits.
In addition to the records and reports materials as stipulated in the Code, the following
should also be included :
(i) Rockhead contours should be mapped with information obtained from the initial SI
report, pre-boring and post construction drilling records;
(ii) Rockhead contours (for end bearing piles on rock) or contours for soil having SPT
N value ≥ 200 for driven steel piles normally, though SPT N value < 200 is
sometimes acceptable for other large displacement piles, such as tubular pile,
precast prestressed concrete piles, etc.;
(iii) Sonic Tests on large diameter bored piles;
(iv) Ultrasonic echo sounder tests on large diameter bored piles;
(v) Material tests reports including concrete core tests, grout cube tests.
Page 98 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
If considered necessary, the trial pile may be “instrumented” by which strains, and
settlements can be measured for the subsequent derivation of soil resistances along the
pile shaft.
In accordance with the Code, test driving is required for driven piles. The current
practice also includes test installations for pre-bored piles such as mini-piles and socketed
H-piles.
Test boring is important for sites where the construction activities may induce excessive
settlements and vibrations which are detrimental to nearby structures or utilities.
In addition to item (c) of the test boring proposal requiring the minimum rate of
advancement of the drill bit be stated, the maximum rate should also be stated for
monitoring.
H7.4.3 PRE-DRILLING
Reference to clause 2.1 of the Code should be made for the definition of “bedrock” in the
determination of depth of pre-drilling in rock.
For barrettes which are long on plan (in excess of 5m), it may be worthwhile to consider
sinking more than one pre-drilling hole for confirmation of bedrock levels.
Further investigation may be required if there are substantial differences between the pre-
drilling and the post construction proof drilling records. Good quality drilling is required
to avoid possible damage to the soundness of the interface. Triple barrel drilling and
drilling fluid such as foam, supermud or polymers can be used.
The tests may include Pile Driving Analyzer Tests (PDA), CAPWAP etc.
Page 99 of 114
An Explanatory Handbook to Code of Practice for Foundations 2017
The Code tabulates construction tolerances for foundation elements generally in this
clause.
The justification mentioned in Note (2) can comprise re-analysis and / or re-design of the
structure with the as-constructed dimensions / layouts.
Common ground treatment methods include (i) grouting; (ii) dynamic compaction; (iii)
vibroflotation; and (iv) stone column construction. While grouting can easily be
understood, dynamic compaction is a soil densification process achieved by dropping
heavy weights of concrete and steel hammers from heights of 10m to 30m onto a grid
pattern. Vibroflotation involves the use of a vibrating probe that can penetrate granular
soil to depths of over 30m. The vibrations of the probe cause the grain structure to
collapse thereby densifying the soil surrounding the probe. Stone columns are columns
of gravel constructed in the ground to improve the bearing pressures. The stone columns
can be constructed by the vibroflotation method or by driving steel casings and
subsequently filled with gravels which are tamped with a drop hammer as the steel casing
is gradually withdrawn.
(1) Noise
Sources of noise may include but are not limited to the following:
Generally noise levels below 75dB(A) are acceptable. In case of percussive piling
work where the construction noise levels are very high, limitations to certain period
of time for the piling work will generally be imposed.
Measures for reducing noise may involve the use of a noise barrier (Figure H7.6(a)),
noise muffler (Figure H7.6(b)) or the use of Quality Powered Mechanical
Equipment (QPME) which produce less noise during foundation work.
Figure H7.6(a) – Noise Figure H7.6(b) – Noise Muffler Enclosing Hydraulic Hammer
Barrier during Percussive Piling Work
Sources of smoke and fumes are usually generated from sources including :
(i) Combustion of fuel for operating powered mechanical equipment (PME) such
as air compressors, generators or construction plant and;
(ii) Excavation of dusty materials.
Routine maintenance and servicing of the diesel engines of mechanical plant is vital
in preventing emission of excessive black smoke and fumes. Figure H7.7 shows the
use of an exhaust purifier for a diesel power pack plant, which can help to improve
the quality of exhaust gas significantly.
Figure H7.8 shows the spraying of water to suppress dust generated by foundation
excavation.
Figure H7.7 – Exhaust Purifier for Diesel Figure H7.8 – Spraying of Water for Dust
Power Pack of Reverse Circulation Drill Suppression
(i) A discharge License for disposal of waste water issued by EPD must be
obtained prior to discharging waste water into urban drains. Discharged water
must be passed through an efficient desilting system (e.g. using a series of
desilting tanks) prior to discharging and the discharged water must comply
with all the requirements stipulated in the Discharge License.
(ii) Registration with EPD as a chemical waste producer must be completed and
all collection of chemical waste must be handled by chemical waste collectors
registered with EPD.
(4) Vibration
Reference may be made to H7.2.5 for its limitation and means of estimating
vibrations due to foundation construction.
For foundation works in the Scheduled Areas defined by the Fifth Schedule of Buildings
Ordinance, there may be special requirements imposed by the Building Authority.
Consequently, sufficient time must be allowed in the planning and designing foundations,
as well as in the execution of foundation works in the Scheduled Areas.
H8.1 GENERAL
The plate load test as described in the Code aims at determination of allowable bearing
capacity and estimation of Young’s modulus of soil through measurement of the
settlement of a square or circular “plate” under pre-determined loading.
The derivation of the formulae listed in the Code for determination of allowable bearing
capacity and Young’s modulus by plate load tests are as follows :
(1) Square Plate : By the formulae listed in Table 2.3 of the Code,
ζ γs = 1 − 0.4 × 1 = 0.6
So the ultimate bearing capacity is qult = ζ γs × 0.5 BγNγ = 0.3BγNγ ;
Thus qallowable = qult ÷ 3 = 0.1BγNγ ⇒ Wt = 0.1γB 3 Nγ
(2) Circular Plate : Approximation is made by finding a square of same area of
the circle. The side of the square is π 4 B .
So Wt = 0.1γ ( π 4B ) BN
2
γ = 0.025πγB 3 Nγ .
By Poulos (1974), the formulae for calculating settlement S of a square rigid plate
and a circular rigid plate with a uniform pressure p , dimension B on soil of
Young’s modulus Es , Poisson’s ratio v and as a semi-infinite medium are
respectively
S=
(
p × B 1 − v2) π
and S = (1 − v 2 )
p × 0 .5 B
1.13Es 2 Es
Wt
with Wt as the applied load at which S is measured so that p = and
B2
Wt
p= for the square plate and the circular plate respectively and re-
0.25πB 2
arranging the above equations:
Es =
(
Wt 1 − v 2 ) W 1 − v2
for square plate; and Es = t
( ) for circular plate as listed in
1.13SB SB
the Code.
The Es so determined will be used to verify the design values used in the settlement
calculations done in the design stage.
However, there is a criticism that only the top soil (less than half a metre) can be
mobilized in the plate load test due to the small plan dimensions of the testing plate
whilst the actual footing with much larger plan dimensions can mobilize soil at depths of
1 to 1.5 times the plan dimensions of the footing. The settlement measured can therefore
be significantly over-estimated.
Li (2007) discussed the problems of using plate load test as a verification test for proving
the bearing capacity of the founding soil. According to the recognized engineering
principle, the bearing capacity depends on the dimensions of the shallow footing. The
common size of the testing plate ranges between 300mm and 600mm, which is much
smaller when compared with the actual dimension of the footing. Failure in the plate
load test does not necessarily indicate that the shallow footing will experience a general
shearing failure at the same bearing pressure. In many cases, settlement is usually the
controlling factor in determining the allowable bearing capacity. In fact, the plate load
test is best to determine the soil stiffness, Es , for confirming the estimated settlement
(GEO, 2006). Where there is evidence that weaker soils exist beneath the test level or the
soil strength is not increasing with depth, it may be necessary to carry out a series of plate
load tests at different levels.
The Standard Penetration Test (SPT) is often carried out during ground investigation to
assess the ground conditions and to infer the anticipated founding levels for foundations.
The procedures for SPT are described in GEOGUIDE 2.
The SPT N values measured give an indication of compactness of the soils. Empirical
correlations are available in the literature to relate soil properties, such as soil stiffness
and strength parameters, to SPT N values (GEO, 1993; GCO, 1990). It should be
cautioned that such correlations may be subject to a high degree of variability and care
must be taken in using such correlations, particularly for clayey soils.
Test loads used for proof tests of piles are either applied by means of a jack which
obtains its reaction from (i) kentledge heavier than the required test load or (ii) tension
piles or suitable anchors. For (i), to prevent the applied load from being eccentrically
applied to the pile, the centre of gravity of the kentledge should lie on the axis of the test
pile. For (ii), the anchor or anchor piles should be at adequate distance from the test pile
so as to minimize effects on settlement of the test pile due to loads in the anchor or
anchor piles.
A test pile may be laterally restrained in the loading test if it is also laterally restrained
(by the pile cap or tie beams) under the permanent condition. The restraint may be
important if the pile is laterally free for a certain height such that buckling or inclination
will significantly reduce its bearing capacity.
Procedure and failure criteria for pile load test are discussed in this clause.
(a) The reason for excluding group effect from determination of test loads is obvious,
as normally only single test piles are loaded during the loading test. The Code also
states that the test load should be applied at the cut-off level. Nevertheless, if the
application of the test load is at a higher level, the allowable maximum settlement
as arrived at by (e) (i) below should be modified by the use of a longer value of pile
length;
(b) The test load on a test pile is generally twice its working load (2W). However, if
the working load is very high so that the imposition of kentledge up to 2W is not
practical, the test load may be reduced to below 2W, subject to acceptance by the
Buildings Department. Moreover, the maximum allowable settlement for loading
test in (e)(i) should be adjusted if the test load is not 2W. If the test load is xW
where x < 2, the first term of the formula in (e)(i) for determination of the maximum
allowable settlement should accordingly become xW . In addition, the terms
AE
D
+ 4 that follow may also require adjustment;
120
(c) The requirement that the load at each incremental stage be held for 10 minutes or
longer until the rate of settlement is less than 0.05mm in 10 minutes is to ensure the
settlement of the pile is practically completed at the applied load;
(d) The measuring devices should be calibrated before use. Normally, 4 dial gauges
arranged at corners of a square above the pile head are installed to measure the
settlement of the pile as shown in Figure H8.1. Average values of the measured
settlements should be taken as the settlement of the pile. Care should be taken
when there are significant differences in values of the 4 readings which reveal that
the pile may have been eccentrically loaded;
Hydraulic Jack
Reference Beam
Pile with
Instrumentation
(e) Failure criteria for load test of piles with a least lateral dimension not exceeding
750mm are stipulated in this sub-clause. Load tests for piles exceeding a least
dimension of 750mm will probably require test loads of such magnitude that it is
impractical to carry out the test. For piles with a diameter or least lateral dimension
not exceeding 750mm, the test is deemed to be unsatisfactory if any of the
following conditions apply:
(i) The criterion for maximum settlement at the pile head is stipulated in this sub-
2WL D
clause by the formula + + 4 mm in which the symbols are defined in
AE 120
the Code.
This failure criterion is similar to the Davisson (1972) criterion which is one
of the most widely used methods in the world. Originally, the Davisson (1972)
criterion was intended for quick load test and the settlement due to long term
creep is excluded. Nevertheless, it has been developed for end-bearing piles
by considering the deformation required to cause yielding of soil at pile toes.
This deformation is known as “soil quake” as denoted by Qt . Based on the
loading test results, dynamic measurements and wave equation analysis, Qt is
determined to be 0.10 inch in most soils for a normal pile dimension of 1 foot
but increases linearly with pile size. So, when converted to the unit in mm,
D
this term becomes (probably) where D is normally taken as the least
120
dimension of the pile in mm. In a pile load test, ultimate load is presumed to
have reached when the pile head settlement ∆ h is 0.15 inch (= 4 mm) plus Qt
and the sum is below the “elastic deflection index line”. This index line can
be calculated by assuming the pile as a fixed-base free-standing column which
2WL
is at the applied load normally equal to twice the design working load.
AE
So, by adding these three terms together, the equation listed in the Code is
arrived at;
(ii) By the Code requirement, the loading test is deemed unsatisfactory if the
“residual settlement” exceeds the greater of
The criterion D/120 + 4mm was used only originally, intending to limit the
degrees of “yield” or “plastic settlement” that has occurred during pile load
testing. 25% of the maximum pile head settlement has been added in recent
years to make allowance for the locked in stresses. The requirement is not
common in other parts of the world. Past experience indicates that this
criterion is more difficult to fulfil than the maximum settlement criterion
discussed in (i). As a result, piles often have to be driven to deeper levels in
order to fulfil this additional requirement. This may cause problems in pile
termination and even pile damage when the piles are long;
(f) The Code states that grout can be taken into consideration in the calculation of axial
stiffness of mini-piles and socketed H-piles while the casing can be included in the
determination of axial compression / extension of the pile in the loading test;
(g) Normally confirmatory tests on large diameter bored piles (diameter > 750mm),
barrette piles and hand-dug caissons are performed by concrete coring instead of
that by imposition of loads.
A typical load settlement proof test curve due to the imposition of load on a local socketed
H-pile is shown in Figure H8.2.
5.0
10.0
Pile Head Settlement (mm)
15.0 Cycle 1
20.0 Cycle 2
25.0
30.0
35.0
40.0
45.0
50.0
55.0
60.0
Two types of proof core-drilling; namely interface coring and full length coring, are
commonly used in large diameter bored piles, barrettes and the like.
Interface coring should be taken through the reservation tube for each of the large
diameter bored piles, barrettes and the like to a distance of at least 1m above and below
the rock/pile interface. The main purpose is to confirm good contact between the
concrete and rock. It can also serve to check the length of pile, quality of the concrete
near the pile base and give some indication of the soundness of the founding rock.
Common types of defects at the concrete/rock interface are the presence of sediments,
soil inclusions, unbounded aggregates and rock fragments debris. Remedial treatment
may be necessary subjected to the review by AP/RSE/RGE (see clause 12 of PNAP APP-
18). Typical remedial treatments for bored piles commonly accepted by BD include
water jetting and subsequent pressure grouting for sediments and/or segregation at the
pile/rock interface not exceeding (i) 50mm for pile lengths less than 30m; and (ii) 100mm
for pile length longer than 30m. Verification cores after grouting are normally not
necessary. However, sediments and/or segregation in excess of the foregoing will require
further investigation of the extent of the defects and the effects on the pile performance.
If the defect is localized and the effect on the overall pile performance is not significant,
cleaning by high pressure water jetting and pressure grouting shall be used to rectify the
defects. However, verification cores are normally required to prove the effectiveness of
the treatment. Prescribed methods for remedial treatments of barrettes and the like have
not been developed, but reference can be made to those for bored piles.
Local imperfections such as weak seams, more weathered and/or shattered rocks are
sometimes present at the bearing stratum below the interface. However, it is sometimes
The concrete core taken should not show any sign of honeycombing or segregation of the
individual constituent materials. Defects, if identified, should be investigated as to their
extent and their effects on pile performance. Destructive compression tests can be carried
out to ascertain the concrete strength if required. The compressive strengths of the
concrete core can be corrected to equivalent cube strengths which can thus act as a
checking or compliance criterion of the permanent concrete work of the pile. If the
defect is localized and does not affect overall pile performance, high pressure water
jetting and pressure grouting shall be used to rectify the defects, with verification cores to
prove the effectiveness of the treatment.
Concrete cores are sometimes included by some practitioners in the calculation of the
TCR. On this basis, they argue that the presence of defects at the concrete/rock interface
up to 150mm is acceptable due to the achievement of 85% TCR. This is contrary to the
Ordinance which requires sound, adequate interface in good contact, and not some
irregular materials at the toe due to workmanship. In Hong Kong, rock weathering rarely
produces a homogeneous weathered rock mass where all rock material is weathered to
the same degree, or even a simple weathered profile where the degree of weathering
decreases progressively with depth. The presence of these discontinuities and the effects
of weathering have a great influence on engineering behaviour. According to
GEOGUIDE 3, TCR is one of the parameters in classifying the engineering properties of
a rock mass. Inclusion of a concrete core in the calculation of the TCR is therefore
irrational because concrete is an artificial material. Furthermore, this will make TCR
become arbitrary as it can vary depending on the start and the end of the drilling in the
interface coring. Notwithstanding this, the TCR of founding rock is reported in the
drilling log of the interface coring. Caution is required on the interpretation of the
capacity of the founding rock since the rock core run is less than 1.0m.
Full coring should be taken throughout the full length of large diameter bored piles,
barrettes and the like selected by the BD to a distance of at least half a diameter of the
pile base or 600mm whichever is larger into the rock upon which the pile is founded.
The main purpose is to confirm the adequacy of the interface between the concrete and
rock, quality of the concrete and soundness of the rock for founding. Defects revealed
should be treated in similar fashion to those given for the interface coring.
The test should be carried out by a HOKLAS accredited laboratory as per clause 8.1 of
the Code. In addition to the provisions in the Code, the followings are discussed :
(i) Introduction
As discussed in the Code, sonic logging is one of the most commonly used
types of non-destructive test to examine the integrity and homogeneity of cast-in-
place concrete piles, diaphragm walls and barrettes. However, it should be noted
that only the existence of, but not the nature of, defects can be identified with this
test. Figure H8.3 illustrates the execution of the test.
Concrete Transducer
Pile (emitter)
Transducer Transducer Wave
(emitter) (receiver) Direction Transducer
Wave
Direction (receiver)
Steel
Access
Tubes
(water
filled) Paths of the sonic pulse detecting
if there is anomaly in concrete Plan Single Tube
Twin Tube
Figure H8.3 – Twin Tube and Single Tube Set-up of Sonic Logging Test
(ii) Equipment
The equipment for sonic logging generally consists of one ultrasonic pulse emission
probe, one (or multiple) reception probe(s), a depth encoder and a main unit which
is used to record the information collected in the test and for subsequent analysis.
In order to perform this test, the access tubes are fixed in the desired position before
concreting. Although both plastic and metal access tubes can be used, metal access
tubes are preferred because of the smaller risk of debonding (i.e. separation between
the tube and the concrete). Users should follow manufacturer’s instruction in
choosing the minimum diameter of the access tuber. Sometimes, the access tube
can also be used for interface coring to investigate the condition at the bottom of the
pile and the interface between the concrete and founding rock/soil. As such, the
diameter of the access tube should be large enough to suit the coring process. If the
diameter of the tube is double or more than double of the diameter of the probe, a
centralizer should be attached to the probe so as to minimize any possible snagging
on irregularities in the access tube.
Although the single tube method is adequate for performing sonic logging, the
cross-hole method is preferable as long as the pile (or the concrete element to be
tested) is large enough to accommodate two or more access tubes.
During the test, the emitting probe and receiving probe are lowered into the access
tube(s) at the same speed as shown in Figure H8.3. Time of propagation (also
called first arrival time, FAT) and the attenuation of energy of an ultrasound pulse
transmitted from the emitting probe to the receiving probe will be recorded by the
equipment. If the concrete is homogeneous, the FAT and attenuation of energy is
generally stable. If the time and/or attenuation of energy at certain location is
excessively varied, a defect is suspected at that location. The defect can be a soil
inclusion, cracks or segregation in concrete.
(1) One emitting probe and one receiving probe are lowered down to the bottom
of the water-filled parallel tubes;
(2) The equipment is triggered and the emitting and receiving probes are pulled
up simultaneously;
(3) When the probes are being pulled up, the emitting probe emits sonic signals
and the main unit of the equipment will also recorded the relevant parameters
of the signal (i.e. arriving time of the signal, energy, corresponding depth etc.)
through the receiving probe and the depth encoder;
(4) The test result will then be presented graphically. The graph will show the
arrival time and energy of signals along the pile.
According to the principle of the test, an excessively long arrival time or severe
attenuation of the signal received is an indication of defect. If an anomaly is found
at certain levels in one profile, the signals at the corresponding levels of other
profiles should be carefully compared. The overall assessment should be made
based on the study and comparison of all profiles, taking into account of other
factors such as concreting sequence, possibility of air gap around the tube, etc.
Because of the limitations of this kind of test, sometimes further investigation such
as coring may be required to confirm the existence of a defect. Figure H8.4 shows
an “anomaly” to the sonic signal of a pile 14m below ground. Coring of the pile
confirmed that there are cracks in the concrete at that location.
Level
with
anomaly
The sonic echo test is also known as the “Pile Integrity Test” (PIT) or “low strain
dynamic test”. The name “low strain dynamic” stems from the fact that the strain
produced by the hand-held hammer is low. The test is quick and cost effective. Its
working principles and limitations are described in the Code. The test should be carried
out by a HOKLAS accredited laboratory as per clause 8.1 of the Code.
The test has not been commonly carried out in Hong Kong in recent years.
The commonest dynamic load tests comprise the Pile Driving Analyzer (PDA) and the
CAPWAP which have been described in detail in H5.3.2 and Appendix HL.
The Code requires effects due to pile interaction be made if any reaction piles are closer
than the lesser of 3 pile diameter and 2m to the test pile, as in consistency with GEO
Publication 1/2006. The interaction may be accounted for by the elastic theory such as
Poulos & Davis (1980) or Randolph (1977). They both involve calculation of settlement
of soil due to a pile embedded in soil under vertical loads. The method by Randolph is
simpler and has been quoted by GEO Publication 1/2006 for pile under compression.
While a reaction pile in close proximity to a test pile undergoing tension loading test is
under compression, it will then be creating settlement on the test pile which reduces its
up-rise during loading. Randolph’s equations are shown in Appendix HV.
A photograph showing a tension test arrangement (for a raking pile) is shown in Figure
H8.5.
Load Cell
Hydraulic
Supporting Jack
Frame
Reaction
Pile
Test Pile
Figure H8.5 – Photograph showing Arrangement of a Tension Pile Test (Raking Pile)
In addition to the provisions / requirements in the Code, the following are added :
(1) Apart from reaction piles, the ground may be used for reaction purposes to provide
the tension load on the pile if it is adequately strong such as sound rock as
illustrated in Figure H8.6. Nevertheless, the ground beams or bearers should be
spaced at an ample distance from the test pile as otherwise the lateral pressure on
the pile induced by the load on the ground will increase the skin friction of the pile;
(2) Effects due to close proximity of the reaction pile should be considered;
(3) If the tension loads on the pile are intermittent or cyclic in nature, it may be more
desirable to adopt repetitive loading sequence on the test pile. Reference can be
made to Tomlinson (1994).
In addition to the provisions / requirements in the Code, the following are added :
Lateral load tests on piles may be used to verify soil parameters suitable for a particular
analysis or design method. An example is the horizontal subgrade reactions (Terzaghi
1955) based on the Winkler spring theory in which the pile is mathematically modeled as
a flexible beam and the soil restraints modeled as lateral springs (Winkler springs). The
measured deflection profile can then be used to back-calculate the horizontal subgrade
reaction values and these values can be used to predict deflection profiles for other piles
together with the forces induced. Reference can be made to H5.3.4.
The descriptions and precautionary measures provided in the Code are comprehensive.
An example of the “trace results” of the excavation profile of a large diameter bored pile,
including its bell-out is included in Figure H8.7.
Trace of
Pile Shaft
Trace of Pile
Bell-out of
Large
Diameter
Bored Pile
Note : Refer to Geoguide 3 (GCO, 1988) for classification of rock decomposition Grade I to VI
Figure HA-1 – Representation of a Corestone–bearing Rock Mass (Malone, 1990)
As described by GEO Publication 1/2006 (2006), the thickness and nature of weathering profiles
varying markedly depends on the rock type, topographical location and geological history.
Taking an example quoted from GEOGUIDE 3, the corestone-bearing profiles as shown in
Figure HA-1 are primarily developed in medium and coarse grained granites and coarse ash tuffs.
The incidence of corestones generally increases with depth in a weathering profile, although
abrupt lateral variations are also common. The depth and extent of weathering can vary
considerably with changes in rock type and discontinuity spacings. Thus, the inherent spatial
variability of the soil masses formed from the weathering of rocks insitu and the undulating
weathering front are important considerations in the design and construction of foundations.
A-1
Appendix HB
X b = 1.5 m
ω = 20 o
P = 8000 kN
Df = 3m
H = 1000 kN Soil of φ = 35 o ;
c = 10 kPa
α f = 10 o γ s = 20 kN/m3
q = γ s D f = 60 kPa
0.5 B f = 3 m
0.5 B f = 3 m
Section
0.5 L f = 4 m
e L = 0.3 m Point of Load
Application
0.5 L f = 4 m
e B = 0.4 m
Plan Shape
B-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HB
It can be seen that the ultimate bearing capacity by (Eqn B-2) is made up of three components
with failures along the assumed failure surface : (i) the first one of which is given by cohesion of
the soil; (ii) the second one is due to friction effected by weight of the soil mass; and (iii) the last
one is due to friction effected by the adjacent surcharge.
For general use where a footing of finite dimensions which may be tilted and / or adjacent to
slope, (Eqn HB-1) is derived based on (Eqn HB-2) with the ζ s as coefficients to account effects
for (1) length width ratio of the footing; (2) inclination of resultant loads to the footing; (3) tiling
of the footing; and (4) sloping of ground.
For the footing shown in Figure HB-2, the following factors are computed prior to arrival of the
final ultimate bearing capacity.
Shape Factors
B N
ζ cs = 1 + f q = 1.541
L f Nc
B-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HB
Bf
ζ γs = 1 − 0.4 = 0.7
Lf
Bφ
ζ qs = 1 + tan φ = 1.525
Lφ
Inclination Factors
mi = (2 + B fe / L fe )/ (1 + B fe / L fe ) = 1.587
mi
H
ζ qi = 1 −
= 0.821
P + B fe L fe c cot f
1 − ζ qi
ζ ci = ζ qi − = 0.815
N c tan φ
mi +1
H
ζ γi = 1 −
= 0.725
P + B fe L fe c cot f
Tilt Factors
ζ γt = (1 − a φ tan φ )2 = 0.771
ζ qt = ζ γt = 0.771
1 − ζ qt
ζ ct = ζ qt − = 0.763
N c tan φ
So the ultimate bearing capacity when the footing is at the edge of the slope is
qu = cN cζ csζ ciζ ctζ cg + 0.5 B feg s N g ζ gsζ giζ gtζ gg + qN qζ qsζ qiζ qtζ qg
= 271.399 + 394.974 + 779.554 = 1445.926 kPa < 3000kPa
It can be seen that the surcharge adjacent to the footing gives the greatest contribution in this
example.
The ultimate bearing capacity of the same footing without tilting, sloping ground and resists
vertical load only is re-calculated. The ultimate bearing pressure increases to qu = 5340.727 kPa,
(though the Code limits the value to 3000kPa as per Clause 2.2.4). So it can be seen that these
factors have significant effects on reduction of ultimate bearing pressure.
When the footing is at ground level which can be assumed for the footing to be located at
4 B fe = 20.8 m from the edge of the slope, the ground sloping factors are all unity, the ultimate
capacity becomes
qu = cN cζ csζ ciζ ct + 0.5 B feg s N g ζ gsζ giζ gt + qN qζ qsζ qiζ qt
B-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HB
By Figure 2.3(c) of the Code, the ultimate bearing capacity of the footing which is at 1.5m from
the edge of the slope can be interpolated between the ultimate values at edge = 1445.926kPa and
that at 4 B fe = 20.8 m which is 3345.902kPa. The linearly interpolated value is 1582.943kPa as
demonstrated in Figure HB-3.
3345.902kPa
Bearing
Capacity
1582.943kPa
1445.926kPa
Distance of Footing from Edge of Slope (m)
1.5m
4 B fe = 20.8 m
With the overburden pressure q0 = γ s D f = 20 × 3 = 60 kPa and by the equation listed in 2.2.4 of
the Code, the allowable bearing capacity can be calculated as follows :
qu − q 0 1582.943 − 60
qa = + q0 = + 60 = 567.648 kPa.
F 3
B-4
Appendix HC
To estimate the settlement and support stiffness of footings, the basic equation for
computation of the corner of a rectangular flexible footing of dimension B'L' on
the surface of an elastic layer can be used which is computed by the Theory of
Elasticity (Timoshenko and Goodier (1951)) quoted as follows :
1 v2 1 2v
H q0 B' I1 I2 I F (Eqn HC-1)
Es 1 v
Y i i
IF i 1
(Eqn HC-2)
1 2 Y1
where 1 3 4v ; 2 5 12v 8v 2 ; 3 4v1 2v ;
4 1 4v 8v 2 ’ 5 41 2v 2
R 2D' ;
R1 L'2 R 2 ; R2 B'2 R 2 ;
R3 L'2 B'2 R 2 ; R4 L'2 B'2
R B' R4 L' R4 L' B'
3 3 3
Y1 L' ln 4 B ' ln ;
L' B' 3L ' B '
C-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
1
0.95
0.9
0.85
Depth Factor IF
0.8
0.75
Figure HC-1(a)
0.7
– Variation of
0.65 Depth Factor
0.6 with L/B Ratios
0.55 for Soil of
0.5 Poisson’s Ratio
0.45 = 0.3
0.1 1 10
1
0.95
0.9
0.85
Depth Factor IF
0.8
0.75 Figure HC-1(b)
0.7 – Variation of
0.65 Depth Factor
0.6 with L/B Ratios
0.55 for Soil of
0.5 Poisson’s Ratio
0.45 = 0.35
0.1 1 10
C-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
1
0.95
0.9
0.85
Depth Factor IF
0.8
0.75 Figure HC-1(c)
0.7 – Variation of
0.65 Depth Factor
0.6 with L/B Ratios
0.55
for Soil of
0.5
Poisson’s Ratio
0.45
= 0.4
0.1 1 10
1
0.95
0.9
0.85
Depth Factor IF
0.8
0.75 Figure HC-1(d)
0.7 – Variation of
0.65 Depth Factor
0.6 with L/B Ratios
0.55 for Soil of
0.5 Poisson’s Ratio
0.45 = 0.45
0.1 1 10
1
0.95
0.9
0.85
Depth Factor IF
0.8
0.75 Figure HC-1(e)
0.7 – Variation of
0.65 Depth Factor
0.6 with L/B Ratios
0.55 for Soil of
0.5 Poisson’s ratio
0.45 = 0.5
0.1 1 10
C-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
Ground Level
Figure HC-2 – Illustration of Symbols used in the Equations for Estimating Corner
Settlements of Rectangular Footing
Settlements at any point beneath the footing can be determined in accordance with the
principle illustrated in Figure HC-3.
A B
Settlement of X is the sum of settlements of the
X corners due to u.d.l. on areas A, B, C and D, each
of which is determined by (Eqn HC-1)
C D
It is obvious that settlements at the centre of the footing are greater than those at the
corners and the edges if the applied load is a uniformly distributed load.
C-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
Maximum
Settlement is at
the centre which
is 27.85mm.
Minimum
Settlement is at
the Corner
which is
12.08mm.
Average
Settlement is
22.90mm
( X Y S)
Figure HC-4 – Settlement Contours for a Rectangular Footing exerting Uniformly
Distributed Load on an Elastic Subgrade
However, this phenomenon can only be true if the footing is flexible enough to
deform with the same settlement contours as the subgrade. If the footing is
possessing some stiffness by which the settlements will be less extreme (i.e. the
differences in settlements between the centre and the corners and edges are smaller),
there will be a redistribution of pressures on the subgrade such that the centre portion
will experience smaller pressures than those at the corners and the edges.
Charts are drafted for general use in estimating average settlement of rectangular
footings under uniformly distributed loads with founding levels on ground. In the
exercise, a rectangular footing with its lesser plan dimension equal to unity and the
greater plan dimension equal to M ( 1.0 ) is used. In each of the footing,
settlements of 441 nos. of nodes spaced at equal intervals in the two directions
(including the corner nodes and edge nodes) parallel to the length and breadth of the
footing are analyzed in accordance with the approach as described in the foregoing
1 2v
sections.
The coefficient I 1 v 2 I1 I 2 b' (by Eqn HC-1) is
1 v
calculated for each node which is in general the sum of the contributions of the 4
rectangles adjoining to the node (see Figure HC-3) and b' is the lesser plan
dimension of the adjoining rectangle. Weighted averaging of the I values for the
441 nodes is carried out for the whole footing and the coefficients are plotted against
ratio of soil stratum thickness to footing width (the N values in (Eqn HC-1)) in
Figures HC-5(a) to HC-5(e) for various values of length breadth ratios (the M values
in (Eqn HC-1)) of the footing and Poisson’s ratios of soil. According to (Eqn HC-1),
q
multiplying the coefficients in Figures HC-5(a) to HC-5(e) by 0 B ' will give the
Es
average settlement of the footing. If the footing is a sunken one as shown in Figure
HC-2, the settlement should be further multiplied by the factor I F as calculated by
(Eqn HC-2) or estimated from Figure HC-1.
C-5
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
M=10
2
1.9 H
M=7
1.8
1.7
Hard Stratum
1.6
1.5
1.4
1.3
1.2
1.1
1
0.9
0.8
0.7
0.6 M=1 M=1.2 M=1.5 M=2 M=2.5 M=3 M=4 M=5
0.5
0.4
0.3
0.2
0.1
0
0.1 1 10 100 1000
H/B'
Figure HC-5(a) – Coefficients for Determination of Average Settlement of Rectangular Footing Resting on
Top of an Elastic Half-space of Finite Depth to Hard Stratum, Soil of Poisson’s ratio = 0.3
M=10
1.9
1.8 H
M=7
1.7
1.6 Hard Stratum
1.5
1.4
1.3
1.2
1.1
1
0.9
0.8
0.7
0.6 M=1 M=1.2 M=1.5 M=2 M=2.5 M=3 M=4 M=5
0.5
0.4
0.3
0.2
0.1
0
0.1 1 10 100 1000
H/B'
Figure HC-5(b) – Coefficients for Determination of Average Settlement of Rectangular Footing Resting on
Top of an Elastic Half-space of Finite Depth to Hard Stratum, Soil of Poisson’s ratio = 0.35
C-6
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
1.9 M=10
1.8
H
1.7 M=7
1.6
1.5 Hard Stratum
1.4
1.3
1.2
1.1
1
0.9
0.8
0.7
0.6
M=1 M=1.2 M=1.5 M=2 M=2.5 M=3 M=4 M=5
0.5
0.4
0.3
0.2
0.1
0
0.1 1 10 100 1000
H/B'
Figure HC-5(c) – Coefficients for Determination of Average Settlement of Rectangular Footing Resting on
Top of an Elastic Half-space of Finite Depth to Hard Stratum, Soil of Poisson’s ratio = 0.4
2 M=15
1.9
B’
Average Settlement Coefficients
1.8 M=10
1.7
H
1.6 M=7
1.5
Hard Stratum
1.4
1.3
1.2
1.1
1
0.9
0.8
0.7
0.6
0.5
0.4 M=1 M=1.2 M=1.5 M=2 M=2.5 M=3 M=4 M=5
0.3
0.2
0.1
0
0.1 1 10 100 1000
H/B'
Figure HC-5(d) – Coefficients for Determination of Average Settlement of Rectangular Footing Resting on
Top of an Elastic Half-space of Finite Depth to Hard Stratum, Soil of Poisson’s ratio = 0.45
C-7
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
M=10
1.6
1.5 H
M=7
1.4
1.3 Hard Stratum
1.2
1.1
1
0.9
0.8
0.7
0.6
0.5 M=1 M=1.2 M=1.5 M=2 M=2.5 M=3 M=4 M=5
0.4
0.3
0.2
0.1
0
0.1 1 10 100 1000
H/B'
Figure HC-5(e) – Coefficients for Determination of Average Settlement of Rectangular Footing Resting on
Top of an Elastic Half-space of Finite Depth to Hard Stratum, Soil of Poisson’s ratio = 0.5
Figure HC-5(e) matches very well with that similarly produced by the National
Research Council of Canada which has been reproduced by Azizi F. (2000) pp200 for
v 0.5 .
For footing buried below the ground surface at certain depths, the settlement can be
simply multiplied by the coefficients calculated by (Eqn HC-2) or read from Figure
HC-1.
The approach discussed in the previous sections can be extended to estimation of the
settlements of footings of non-rectangular plan shapes on a subgrade, so far as the
plan shape of the footing can be divided into a number of rectangles, each carrying
uniformly distributed loads. The estimation will involve estimating the settlement of
C-8
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
points outside rectangles by the process which can be explained in Figure HC-6. By
averaging an adequate number of point settlements, the average settlement of the
non-rectangular plan shaped footing can be estimated.
B
P
A A uniformly distributed load (u.d.l.) is exerting on Rectangle
ABCD. The settlement it will create in X is calculated by adding
(i) Corner displacement due to u.d.l. on rectangle APXS; and
S R X (ii) Corner displacement due to u.d.l. on rectangle SXQD
Subtracting
(iii) Corner displacement due to u.d.l. on rectangle BPXR; and
(iv) Corner displacement due to u.d.l. on rectangle RXQC
D
Q
C
S R X
A uniformly distributed load (u.d.l.) is exerting on Rectangle
ABCD. The settlement it will create in X is calculated by adding
P (i) Corner displacement due to u.d.l. on rectangle SXQD
A
B Subtracting
(ii) Corner displacement due to u.d.l. on rectangle SXPA; and
(iii) Corner displacement due to u.d.l. on rectangle RXQC
Adding
(iv) Corner displacement due to u.d.l. on rectangle RXPB (which
has been subtracted twice in (ii) and (iii))
D
C Q
Figure HC-6 – Estimation of Settlement outside Rectangle Plan Footing carrying u.d.l.
D
C E Settlement of X due to u.d.l. on the cruciform
shaped footing ABCDEFGHJNKLMNO is the
sum of the corner displacement of the adjoining
A B F rectangles LPXK, KXQJ, PCDX, XDEQ, together
G
with rectangles ABMN and FGHI. Settlement due
O P Q
X to u.d.l on the adjoining rectangles ABMN and
FGHI can be estimated in accordance with Figure
N
M I H HC-3 and that due to ABMN and FGHI which are
outside X has to be estimated in accordance with
Figure HC-6.
L J
K
C-9
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
E1 , v1 E1 , v1 E2 , v2
h1 h1 h1
E2 , v2
= + h1+h2 –
h2 E2 , v2
(a) Settlement of footing on (b) Settlement due to soil of (c) Settlement due to soil of the (d) Settlement due to soil of
a 2-layer soil strata. the first layer of depth h1 second layer of depth h1+h2 the second layer of depth h1
The settlement of the footing on the 2 layer subgrade will be the settlement calculated in (b) plus that in (c)
minus that in (d).
m
m m
kPa
m kPa
m
Hard Stratum
C-10
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
L' 12 h 8
M 1.5 ; N 1.0 , v 0.4
B' 8 B' 8
Average settlement coefficient is 0.43 from Figure HC-5(c), so average
settlement is
q B' 100 8
I 0 0.43 0.0344 m =34.4mm
E 10000
C-11
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HC
So the total average settlement is 0.86 34.4 6.8 1.8 36.98 mm.
C-12
Appendix HD
Rigorous analysis of a plate bending structure generally reveals a “twisting moment” at points of
the structure, as in addition to bending moments in any mutually two perpendicular directions.
However, design to resist a twisting moment is not as straightforward as it is for the bending
moments. The existence and nature of the twisting moment are demonstrated in the rest of this
appendix.
Figure HD-1 shows a small right-angled triangular element cut from a plate bending structure
with its short sides parallel to the pre-determined x and y axes. The triangular element generally
sustains bending moments (per unit width) M x and M y about the x and y axes as shown.
The vectors representing the moments are also shown.
For the triangular element to be in equilibrium, the direction (vector direction) of the bending
moment M b about the hypotenuse, in general, does not align with that of the vector sum of
M x and M y . So M b alone cannot achieve equilibrium for the triangular element and
another moment M t whose direction being perpendicular to the hypotenuse must exist to
perform the function. However, this M t (the direction of which is shown in Figure HD-1
taken from Lam and Law (2009)) is actually “twisting” the section, creating “complementary
shear stress” (in contrast to pure flexural tensile and compressive stresses) which are in-plane
shear flows on the structure as shown on the right half of the Figure.
Plate Structure
Mt exists so
as achieve
equilibrium
for the
triangular
element.
Mt
My
Mb
y y
x
Mx
x Complementary shear stress pattern
created by the twisting moment
As the hypotenuse can be in any orientation, it follows that a twisting moment exists, in general
at any orientations, including the global X and Y directions. So at any point in a plate bending
D-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HD
structure, there exists a set of moments comprising two bending moments at mutually
perpendicular directions and a twisting moment as summarized in Figure HD-2. In Figure
HD-2, M x , M y and M xy (the twisting moment) form a complete set of “moments” at a point
with respect to the orientation .
Mxy
Mx My
Mxy
Mx
Y
Mxy My
y x
Mxy
X
It should be noted that the three moments change magnitudes as varies. At the orientation
where M xy 0 , the moments M x , M y become the “principal moments” and the orientation
becomes the “principal directions”. The phenomenon is entirely analogous to the in-plane
stress problem such that the variation of moments with orientation can be represented on a
“Mohr Circle” as shown in Figure HD-3. In Figure HD-3, the moments M x , M y and M xy
at a point in the structure exist at an orientation to one principal direction and when 0 ,
the bending moments at the point will become M 1 and M 2 (principal moments) and the
twisting moment is zero.
The moments Mx, My and Mxy are at
an orientation to the principal
directions at which the bending
moments are the principal moments
Mxy and the twisting moment is zero.
M2 M1 M2
M1 My
My Mxy
Mx
Mxy
Mx
y
M1 M2
x
Figure HD-3 – Bending and Twisting Moment as Represented by the Mohr Circle
D-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HD
Theoretically it is sufficient to design the structure to resist the principal moments in the
principal directions. However, in practice it is impossible to do so for reinforced concrete slabs
as the principal directions change from point to point and from load case to load case. So if it is
the intention that the reinforcing bars are in pre-determined directions where the twisting
moments are in general not zero, it is necessary to cater for the twisting moments. The Wood
Armer Equations by Wood (1968) for the reinforced concrete design of plate structures are to
* *
work out the “design moments” M x and M y in selected directions so that they incorporate
effects due to M x , M y and M xy . The underlying principle of the Wood-Armer Equations is
* *
that structural design based on M x and M y can resist bending moments in any directions
while leaving the twisting moments to be resisted by the concrete. This is known as the
“Normal Yield Criterion” which can be mathematically expressed as follows :
The left hand side of the above inequality represents the flexural strengths of the plate structure
in the direction upon the provision of flexural strengths of M x and M y in the x and y
* *
directions as derived by the Johansen’s Criterion (1962) whilst the right side represents the
‘normal moment’ which is the bending moment in the direction .
The Wood Armer Equations from Wood (1968) are reproduced as follows, with the convention
that sagging moments are positive and hogging moment are negative:
If, in these changed formulae, the wrong algebraic sign results for M x or M y , then no such
reinforcement is required. If both M x and M y are negative, no bottom reinforcement is
required.
If, in these changed formulae, the wrong algebraic sign results for M x or M y , then no such
D-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HD
The following 2 examples demonstrate the use of the Wood-Armer Equations and their
fulfillment of the “normal yield criterion”.
* *
A plot of the strengths provided by M x and M y (sagging only) as determined by the left side
of (Eqn HD-1) and the normal bending moments based on M x 7 ; M y 23 ; M xy 9 as
determined by the right hand side of (Eqn HD-1) have been done for orientations from 0o to 360o
and presented in Figure HD-4. It can be seen that the moment capacity curve (only sagging)
envelops the normal bending moment for all orientations.
Normal Bending Moment, Twisting Moment, Design Moment by Wood
Armer Equation in Worked Example HD-1 : M x = 7, M y = 23, M xy = 9
Bending Moment Moment Capacity by Wood Armer +ve Moment Capacity by Wood Armer -ve
30
25
Moment (kNm/m)
20
15
10
0
0 30 60 90 120 150 180 210 240 270 300 330 360
Figure HD-4 – Plots of Normal Moments and Strengths by Wood Armer Equation for
Worked Example HD-1
D-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HD
* *
Plots of the strengths provided by M x and M y (for both sagging and hogging) as determined
by the left hand side of (Eqn HD-1) and the normal moments worked out by M x 7 ;
M y 23 ; M xy 9 as determined by the right hand side of (Eqn HD-1) for orientations from
0o to 360o are presented in Figure HD-5. It can be seen that the moment capacity curves
(sagging and hogging) envelop the normal bending moment for all orientations.
Normal Bending M oment M oment Capacity by Wood Armer +ve M oment Capacity by Wood Armer -ve
15
10
5
Moment (kNm/m)
0
-5 0 30 60 90 120 150 180 210 240 270 300 330 360
-10
-15
-20
-25
-30
-35
Figure HD-5 – Plots of Normal Moments and Strengths by Wood Armer Equation for
Worked Example HD-2
D-5
Appendix HE
Consider a pile group of 30 nos. S450 305305223kg/m driven piles capped by a pile cap and
arranged as shown in Figure HE-1. The pile group with the soil mass embedded among the
piles is “idealized” as a sunken footing at the average pile tip level which is 24m below ground.
1.5m
1.5m
1.5m 7.8m
X 1.5m X
1.5m
Plan of the
Foundation
6.3m
1.5m GWL
Soil Parameters :
(i) average angle of shear resistance = 36o;
(ii) cohesion, c = 10kN/m2;
(iii) soil density above GWL ’ = 20kN/m3
(iv) submerged soil density ’ = 20 – 10 = 10kN/m3
21m
Section X-X
Figure HE-1 – Worked Example HE-1 for Pile Group Reduction Factor
E-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HE
The ultimate bearing capacity of the “idealized footing” is determined by the equation
qu cN c cs 0.5 B f s N s qN q qs (Eqn HE-1)
where c is the cohesion of the soil, B f is the effective width of the idealized footing, s is
the effective density of the soil, q is the surcharge on the area adjacent to the footing, the N
factors are the bearing capacity factors and the factors are those same factors which relate to
the plan length to breadth ratio of the “idealized footing”. The equations for determination of
the factors can be found in clause 2.2.4 of the Code and GEOGUIDE 1 (2000) Figure A1.
Soil Parameters
360 ; c 10 kN/m2; ' 20 kN/m3 above GWL; ' 20 10 10 kN/m3 below GWL
Shape Factors
B N Bf Bf
cs 1 f q 1.603 ; s 1 0.4 0.677 ; qs 1 tan 1.587
L f Nc Lf Lf
The allowable load of the pile group based on the “idealized footing” is
qallowable B f L f 245700 kN.
Comparing with the load carrying capacity calculated as the summation of the individual load
carrying capacity of each pile, which is at most 30 3663.6 109908 kN, the ratio is
245700
2.24 1.0
109908
So the pile group reduction factor can remain as unity which is governed by the “structural
capacity” of the pile group.
E-2
Appendix HF
= 16.550423h 2 + 239.26155h
As zero shear exists in this level, the lateral soil
15m shear balances the applied shear S
S = 16.55042h 2 + 239.2615h (a)
Listing the moment equation as follows and
limiting it to 300kNm
h2 h h
S × h − 736.19 × + 101.849h × × × 0.325
2 2 3
= 300 (b)
Solving equations (a) and (b) (involving solution
(ii) Revised Check by Allowing the Pile to have Reversed Moments of cubic equation), h = 1.485 m and
along the Pile Shaft and Limiting to Flexural Strength of the S = 16.55042h 2 + 239.2615h = 391.84 kN
Pile, i.e. the Pile becomes a “Long Pile” So the ultimate shear capacity required is
391.84kN
Figure HF-1 – Worked Example HF-1 for Determination of Ultimate Lateral Shear
Resistances of Piles Pinned at Pile Cap
F-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HF
The pile in Worked Example HF-1 is now rigidly connected to the pile cap and its ultimate shear
resistance of the pile due to soil is to be re-worked.
Figure HF-2 – Worked Example HF-2 for Determination of Ultimate Lateral Shear
Resistances of Piles Rigidly Connected at Pile Cap
F-2
Appendix HG
The pile group comprises 26 nos. of 305×305×223 Grade S450J0 H-piles. No piles have
adverse live load (i.e. uplift due to live load). The Ru values are derived from cohesion (c = 20
kPa as the ultimate value being twice the allowable value of 10kPa) on the pile shaft.
Critical Load
Wind Axial Load Uplift Checking
Combination
Pile Dmin TL Dmin
Wind X Wind Y Wmax TL TL Upthrust Ra Ru Dmin–Wmax Dmin–1.5Wmax Dmin+0.9Ru–
No. (DL+LL) –Wmax
+Wmax Ua +U+Ra +Ua 1.5(Ua+Wmax)
(kN) (kN) +Ua
(kN) (kN) (kN) (kN) (kN) (kN) (kN) (kN) (kN) (kN) (kN)
(kN)
P1 1566 2211 -483 -987 987 2211 3198 -70 509 633 1227 1142 16 1085
P2 1450 2030 -83 -1033 1033 2030 3063 -69 348 633 1227 981 -169 901
P3 1438 2007 338 -1148 1148 2007 3155 -66 224 633 1227 857 -350 721
P4 1581 2217 982 -1407 1407 2217 3624 -58 116 633 1227 749 -588 488
P5 1671 2366 -808 -870 870 2366 3236 -70 731 633 1227 1364 296 1365
P6 1732 2458 -1154 -743 1154 2458 3612 -68 510 633 1227 1143 -67 1003
P7 1462 2036 986 -1131 1131 2036 3167 -58 273 633 1227 906 -293 783
P8 1641 2308 -1238 -513 1238 2308 3546 -68 335 633 1227 968 -284 786
P9 1389 1923 1029 -863 1029 1923 2952 -57 303 633 1227 936 -212 864
P10 1584 2207 -1365 -211 1365 2207 3572 -65 154 633 1227 787 -529 543
P11 1370 1890 1144 -455 1144 1890 3034 -53 173 633 1227 806 -399 679
P12 1429 1968 342 -62 342 1968 2310 -58 1029 633 1227 1662 858 1933
P13 1513 2096 -1469 143 1469 2096 3565 -60 -16 633 1227 617 -751 324
P14 1501 2068 -65 213 213 2068 2281 -58 1230 633 1227 1863 1124 2199
P15 1412 1951 1312 113 1312 1951 3263 -46 54 633 1227 687 -602 479
P16 1454 2008 878 399 878 2008 2886 -47 529 633 1227 1162 90 1171
P17 1473 2036 -1547 465 1547 2036 3583 -55 -129 633 1227 504 -903 174
P18 1518 2096 422 656 656 2096 2752 -49 813 633 1227 1446 485 1565
P19 1483 2054 1465 654 1465 2054 3519 -40 -22 633 1227 611 -755 330
P20 1530 2111 -1240 710 1240 2111 3351 -53 237 633 1227 870 -383 695
P21 1592 2199 -40 884 884 2199 3083 -50 658 633 1227 1291 216 1295
P22 1536 2127 985 934 985 2127 3112 -42 509 633 1227 1142 17 1100
P23 1451 2002 -1600 821 1600 2002 3602 -50 -199 633 1227 434 -999 80
P24 1596 2204 -893 995 995 2204 3199 -50 551 633 1227 1184 54 1133
P25 1603 2219 488 1177 1177 2219 3396 -43 383 633 1227 1016 -206 877
P26 1579 2194 1616 1258 1616 2194 3810 -35 -72 633 1227 561 -880 207
Table HG-1 – Example of Checking of Piles against Uplift, Overturning and Buoyancy of a
Hypothetical Pile Group
Notes :
(i) As the values in the last column are all greater than zero, cl. 5.1.6 of the Code is fulfilled;
(ii) The load factor for uplift U can be 1.1 instead of 1.5 if the ground water level is taken as
the ground level in the determination of U;
(iii) A further check on the ultimate resistance Ru involving effective weight of soil mass/rock
cone in accordance with cl. 5.3.3(b) should be required if the pile is in tension.
G-1
Appendix HH
Figure HH-1 – Extract from Tomlinson (2008) Demonstrating the Principles of the
Equivalent Raft Method
Worked Example HH-1 illustrated by Figure HH-2 is used to demonstrate the equivalent
raft method. In addition to the data given in the figure, the followings are added :
H-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HH
1.5m
Plan Length of the Pile
1.5m Group in the Direction
perpendicular to the
Piles 1 Paper is 40 m
(374 Nos.)
20m 4
Founding Level of
Equivalent Raft
Layer 1 30o
E = 100000kPa 10m 12m
v = 0.4
Hard Stratum
Similarly, the plan dimensions at base levels of Layer 2 and Layer 3 are
B3 = 40 + 22 tan 300 × 2 = 65.403 m and L3 = 50 + 22 tan 300 × 2 = 75.403 m;
B4 = 40 + 30 tan 300 × 2 = 74.641 m and L3 = 50 + 30 tan 300 × 2 = 84.641 m.
The average plan width and length of Layer 1 are (40 + 53.856 ) 2 = 46.928 m and
(50 + 63.856) 2 = 56.928 m giving a plan area of 46.928 × 56.928 = 2671.52 m2.
Under the applied load of 100000 kN, treating the soil layer as an elastic material of
height 12m with the load evenly exerted on the top of the layer, the settlement of Layer 1
is
PL 100000 × 12
= = 0.00449 .
AE 2671.52 × 100000
Settlement of other layers are similarly worked out worked out and summarized in Table
HH-1.
H-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HH
Table HH-2 – Calculation for Worked Example HH-2 by the Approach in Appendix HC
(the I and I F coefficients are read from Figures HC-1 and HC-5 of Appendix HC).
M = 50 / 40 = 1.25 . In the last column, the settlement is calculated by (q0 B ' Es )I × I F .
The items with * are subtractive items.
The settlement determined is 4.594 mm which is significantly less than that by Tomlinson
of 6.10 mm. This may be due to the assumption of 30o load spread in soil being too
conservative by Tomlinson’s approach. Another factor to account for the difference is
due to the lack of consideration of the Poisson’s effect of the soil which also helps reduce
settlement.
Nevertheless, the above only caters for the settlement of the soil, additional settlement
should also be allowed for the elastic shortening of the piles. Conservative estimation can
be made through the elastic shortening (AE/L) approach which assumes the greatest
shortening by ignoring skin friction along the pile shaft. As the cross sectional area of
each of the pile is 0.0284m2, conservatively ignoring the skin friction on the piles and
assuming each pile have each share of the load from the pile cap, the elastic shortening of
the piles are estimated as
PL 100000 × 30
= = 0.00138 m = 1.38mm
AE 374 × 0.0284 × 205 × 106
H-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HH
This elastic shortening of the pile may be added to the settlement due to the compression
of the soil.
H-4
Appendix HI
The finite difference model for the analysis of (Eqn HI-1) is shown in Figure HI-2.
Applied load P
Applied load P
Node –2
Node –1
Node 1
Node 2
z
Node 3
Node 0 to N are
real nodes while
v Pile length Node –1, –2, N+1,
L divided N+2 are fictitious
into N Node i
ones added for
segments, finite difference
each of analysis
equal
length of
L
δ=
N
Node N–1
Node N
Node N+1
Node N+2
Node N+3
Figure HI-1 – Illustration of the Buckling Figure HI-2 – The Finite Difference Model
Phenomenon of Pile in Elastic Soil for the Simulation of a Pile
I-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HI
It is obvious that
z
K h = B × k h = B × nh= nh z (Eqn HI-4)
B
So (Eqn HI-1) can be written as
d 4v d 2v
E p I p 4 + P 2 + nh zv = 0 (Eqn HI-5)
dz dz
Analytical solution for (Eqn HI-5) is difficult, taking into account the many different
boundary conditions including end support conditions of piles, portions of pile length
being sleeved or exposed. Nevertheless, they can be solved by a numerical method such
as the finite difference method for the model shown in Figure HI-2.
By the Finite Difference Method, the pile of length L is divided into N segments of
equal length (each of segment length L N with N + 1 no. of “real nodes” and 4
“fictitious” nodes as shown in Figure HI-2. (Eqn HI-5) for the ith node (z coordinate
= iL N ) can be written as
v − 4vi +1 + 6vi − 4vi −1 + vi −2 vi +1 − 2vi + vi +1 i
E p I p i+2 + P + nh Lvi = 0
(L / N )4
(L / N )
2
N
EpI p N 2 nh L5 i
⇒ (vi−1 − 2vi + vi+1 ) = − v − 4v + 6 + v − 4v + vi+2 (Eqn HI-6)
PL2
i −2 i −1 E p I p N 5
i i +1
EpI p N 2 L 5 i
⇒ (vi −1 − 2vi + vi +1 ) = − vi − 2 − 4vi −1 + 6 + vi − 4 vi +1 + vi + 2 (Eqn HI-7)
PL2 T N
5
Accuracy of the solution increases with increasing value of N. N + 1 equations can be
formulated by (Eqn HI-7) for the N + 1 “real nodes” in the pile. However, to form
equations at Nodes 1, 2, N and N + 1 , 4 additional fictitious nodes have to be added
I-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HI
which are numbered -2, -1, N + 2 , N + 3 as shown in Figure HI-2. Thus 4 more
equations are required which have to be derived from restraints at pile top and pile tip for
solution of the problem. They are summarized in Table HI-1.
Table HI-1 – Restraint Conditions on Lateral Load Analysis on Pile by the Finite Difference Method
With the boundary conditions at the pile ends added, (Eqn HI-7) can be written in a
E I
matrix form [A][v ] = − p 2p N 2 [B ][v ] where [ A] and [B ] can be readily formulated
PL
and the expression can be written as
E I E I
[B]−1[A][v] = − p 2p N 2 [v] ⇒ [C ][v] = − p 2p N 2 [v] (Eqn HI-8)
PL PL
where [C ] = [B ] [A]
−1
EpI p
(Eqn HI-8) is an eigen-value problem. The eigen-values λ = − 2
N 2 can be solved
PL
2
EpI p N
and P=− (Eqn HI-9)
λL2
(Eqn HI-9) gives the buckling loads and the eigen-vectors giving the relative values of v
are the buckling mode shapes. Theoretically, there will be N + 1 valid modes or
buckling loads. The smallest load will be the fundamental buckling load or Euler load.
To find an equivalent length RLeq L as if the pile is a simple strut pinned at both ends and
p 2EpI p EpI p N 2
free from restraints along its pile shaft, we may list P = =−
(R L)
, which
Leq
2
λL2
gives the equivalent length ratio as
RLeq = π − λ N (Eqn HI-10)
By the above, Tables HI-2(a) to HI-2(f) which were extracted from Law (2013) with
extension to L T = 40 showing the equivalent length ratios against the L T ratios for
I-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HI
end bearing piles are presented (where P is constant along the pile shaft) with different
exposed length and sleeved length factors. Intermediate values can be interpolated.
The exposed and sleeved length factors are the ratios of the lengths of the top part of the
pile exposed above ground and sleeved below ground respectively as shown in Figure
HI-3 (extracted from Law (2013)) to the total length of the pile. (Eqn HI-8) can easily
be modified to account for the effects of these length factors. In addition, it can also be
noted that the equivalent length ratios are almost independent of the pile tip support
conditions at high L T ratios, indicating that the pile tip support conditions become
unimportant when the pile is long or the soil resistance is high.
Soil top level
Rex×L Rsle×L
Soil top level
Kh increases
Kh increases L linearly from L
linearly from 0 at soil top
0 at soil top level
level
Rex is the exposed length ratio Rsle is the sleeved length ratio
Top Pinned / Bottom Free Top fixed / Bottom Free Top Free / Bottom Free
L/T
Exposed Length Factor (Rex) Exposed Length Factor (Rex) Exposed Length Factor (Rex)
Ratio
0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4
0 – – – – – 2.000 2.000 2.000 2.000 2.000 – – – – –
1 6.293 6.757 7.341 8.098 9.118 1.942 1.949 1.955 1.962 1.969 18.854 23.227 29.459 38.474 52.362
2 1.234 1.291 1.370 1.482 1.645 1.225 1.266 1.313 1.369 1.436 3.362 4.154 5.255 6.852 9.307
3 0.869 0.896 0.925 0.956 0.984 0.787 0.804 0.823 0.846 0.873 1.330 1.637 2.046 2.626 3.509
4 0.606 0.642 0.690 0.752 0.824 0.588 0.610 0.636 0.666 0.701 0.922 1.107 1.318 1.586 1.980
5 0.439 0.454 0.480 0.542 0.632 0.438 0.454 0.476 0.507 0.554 0.737 0.924 1.116 1.314 1.541
6 0.349 0.367 0.400 0.449 0.513 0.346 0.358 0.372 0.389 0.420 0.612 0.800 0.995 1.191 1.390
7 0.283 0.304 0.353 0.411 0.473 0.283 0.293 0.305 0.324 0.351 0.525 0.713 0.908 1.106 1.304
8 0.240 0.271 0.322 0.382 0.447 0.239 0.246 0.255 0.281 0.326 0.459 0.648 0.843 1.041 1.241
9 0.210 0.246 0.299 0.361 0.426 0.205 0.211 0.224 0.262 0.308 0.408 0.597 0.794 0.992 1.191
10 0.189 0.226 0.281 0.344 0.410 0.179 0.184 0.208 0.249 0.295 0.368 0.557 0.754 0.952 1.152
12 0.157 0.197 0.255 0.320 0.387 0.142 0.151 0.186 0.230 0.278 0.307 0.497 0.694 0.893 1.093
14 0.135 0.176 0.237 0.303 0.371 0.117 0.134 0.172 0.218 0.266 0.263 0.454 0.652 0.851 1.051
16 0.118 0.161 0.223 0.291 0.359 0.099 0.121 0.162 0.208 0.257 0.230 0.422 0.621 0.820 1.020
18 0.105 0.150 0.213 0.281 0.350 0.088 0.111 0.154 0.201 0.250 0.205 0.398 0.596 0.796 0.996
20 0.095 0.141 0.205 0.274 0.343 0.079 0.104 0.148 0.196 0.245 0.185 0.378 0.577 0.776 0.976
22 0.086 0.133 0.199 0.268 0.337 0.072 0.098 0.143 0.192 0.241 0.168 0.362 0.561 0.760 0.960
24 0.079 0.128 0.194 0.263 0.332 0.066 0.093 0.139 0.188 0.238 0.154 0.348 0.547 0.747 0.947
26 0.073 0.123 0.188 0.259 0.326 0.061 0.090 0.136 0.185 0.235 0.142 0.337 0.536 0.736 0.936
28 0.068 0.119 0.186 0.255 0.325 0.056 0.086 0.133 0.183 0.232 0.132 0.327 0.527 0.727 0.926
30 0.063 0.115 0.183 0.252 0.322 0.053 0.084 0.131 0.180 0.230 0.124 0.319 0.518 0.718 0.918
32 0.059 0.112 0.18 0.249 0.319 0.049 0.081 0.129 0.178 0.228 0.116 0.312 0.511 0.711 0.911
34 0.056 0.11 0.178 0.247 0.317 0.047 0.079 0.127 0.177 0.227 0.110 0.305 0.505 0.705 0.905
36 0.053 0.107 0.176 0.245 0.315 0.044 0.077 0.126 0.175 0.225 0.104 0.300 0.499 0.699 0.899
38 0.050 0.105 0.174 0.243 0.313 0.042 0.076 0.124 0.174 0.224 0.098 0.295 0.494 0.694 0.894
40 0.047 0.103 0.172 0.242 0.311 0.040 0.075 0.123 0.173 0.223 0.094 0.290 0.490 0.690 0.890
Table HI-2(a) – Table showing Variation of “Equivalent Length Factor” with L/T ratio and
Pile Exposed Length Factor for End-bearing Piles with Bottom Free
I-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HI
Top Pinned / Bottom Pinned Top fixed / Bottom Pinned Top Free / Bottom Pinned
L/T
Exposed Length Factor (Rex) Exposed Length Factor (Rex) Exposed Length Factor (Rex)
Ratio
0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4
0 1.000 1.000 1.000 1.000 1.000 0.699 0.699 0.699 0.699 0.699 – – – – –
1 0.997 0.998 0.998 0.999 0.999 0.698 0.699 0.699 0.699 0.699 10.906 13.461 17.030 22.236 30.256
2 0.927 0.940 0.954 0.967 0.979 0.674 0.678 0.682 0.686 0.690 2.076 2.529 3.156 4.066 5.468
3 0.671 0.711 0.759 0.813 0.869 0.557 0.575 0.595 0.617 0.640 1.187 1.360 1.570 1.857 2.307
4 0.461 0.490 0.533 0.595 0.674 0.388 0.406 0.434 0.473 0.521 0.922 1.102 1.280 1.459 1.663
5 0.381 0.411 0.450 0.498 0.554 0.323 0.337 0.353 0.372 0.402 0.735 0.922 1.116 1.306 1.489
6 0.314 0.348 0.394 0.449 0.507 0.261 0.280 0.308 0.337 0.371 0.612 0.799 0.994 1.191 1.387
7 0.270 0.303 0.352 0.410 0.473 0.226 0.242 0.267 0.303 0.345 0.525 0.713 0.907 1.105 1.304
8 0.236 0.271 0.322 0.382 0.446 0.197 0.214 0.242 0.279 0.323 0.459 0.648 0.843 1.041 1.240
9 0.210 0.246 0.299 0.360 0.426 0.175 0.193 0.223 0.262 0.307 0.408 0.597 0.794 0.992 1.191
10 0.189 0.226 0.281 0.344 0.410 0.158 0.176 0.208 0.249 0.295 0.368 0.557 0.754 0.952 1.152
12 0.157 0.197 0.255 0.320 0.387 0.131 0.151 0.186 0.230 0.278 0.307 0.497 0.694 0.893 1.093
14 0.135 0.176 0.237 0.303 0.371 0.113 0.134 0.172 0.218 0.266 0.263 0.454 0.652 0.851 1.051
16 0.118 0.161 0.223 0.291 0.359 0.099 0.121 0.162 0.208 0.257 0.230 0.422 0.621 0.820 1.020
18 0.105 0.150 0.213 0.281 0.350 0.088 0.111 0.154 0.201 0.250 0.205 0.398 0.596 0.796 0.996
20 0.095 0.141 0.205 0.274 0.343 0.079 0.104 0.148 0.196 0.245 0.185 0.378 0.577 0.776 0.976
22 0.086 0.133 0.199 0.268 0.337 0.072 0.098 0.143 0.192 0.241 0.168 0.362 0.561 0.760 0.960
24 0.079 0.128 0.194 0.263 0.332 0.066 0.093 0.139 0.188 0.238 0.154 0.348 0.547 0.747 0.947
26 0.073 0.123 0.190 0.259 0.328 0.061 0.090 0.136 0.185 0.235 0.142 0.337 0.536 0.736 0.931
28 0.068 0.119 0.186 0.255 0.325 0.056 0.086 0.133 0.183 0.232 0.132 0.327 0.527 0.727 0.926
30 0.063 0.115 0.183 0.252 0.322 0.053 0.084 0.131 0.180 0.230 0.124 0.319 0.518 0.718 0.918
32 0.059 0.112 0.180 0.249 0.319 0.049 0.081 0.129 0.178 0.228 0.116 0.312 0.511 0.711 0.911
34 0.056 0.110 0.178 0.247 0.317 0.047 0.076 0.127 0.177 0.227 0.110 0.305 0.505 0.705 0.905
36 0.053 0.107 0.176 0.245 0.315 0.044 0.077 0.126 0.175 0.225 0.104 0.300 0.499 0.699 0.899
38 0.050 0.105 0.174 0.243 0.313 0.042 0.076 0.124 0.174 0.224 0.098 0.295 0.494 0.694 0.894
40 0.047 0.103 0.172 0.242 0.311 0.040 0.075 0.123 0.173 0.223 0.094 0.290 0.490 0.690 0.890
Table HI-2(b) – Table showing Variation of “Equivalent Length Factor” with L/T
ratio and Pile Exposed Length Factor for End-bearing Piles with Bottom Pinned
Top Pinned / Bottom Fixed Top fixed / Bottom Fixed Top Free / Bottom Fixed
L/T
Exposed Length Factor (Rex) Exposed Length Factor (Rex) Exposed Length Factor (Rex)
Ratio
0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4
0 0.699 0.699 0.699 0.699 0.699 0.500 0.500 0.500 0.500 0.500 2.000 2.000 2.000 2.000 2.000
1 0.699 0.699 0.699 0.699 0.699 0.500 0.500 0.500 0.500 0.500 1.897 1.993 1.996 1.998 1.999
2 0.681 0.685 0.689 0.693 0.696 0.493 0.494 0.496 0.497 0.498 1.694 1.809 1.893 1.948 1.978
3 0.593 0.614 0.636 0.658 0.676 0.451 0.460 0.469 0.478 0.487 1.176 1.360 1.550 1.725 1.862
4 0.458 0.490 0.530 0.576 0.623 0.364 0.381 0.402 0.427 0.453 0.908 1.084 1.266 1.456 1.652
5 0.374 0.404 0.445 0.496 0.554 0.304 0.318 0.337 0.365 0.402 0.734 0.919 1.107 1.293 1.483
6 0.314 0.347 0.392 0.445 0.504 0.260 0.277 0.300 0.329 0.365 0.612 0.799 0.993 1.187 1.377
7 0.270 0.303 0.352 0.409 0.471 0.224 0.241 0.267 0.302 0.341 0.525 0.713 0.907 1.105 1.301
8 0.236 0.271 0.322 0.382 0.446 0.197 0.214 0.242 0.279 0.322 0.459 0.648 0.843 1.041 1.240
9 0.210 0.246 0.299 0.360 0.426 0.175 0.193 0.223 0.262 0.307 0.408 0.597 0.794 0.992 1.191
10 0.189 0.226 0.281 0.344 0.410 0.158 0.176 0.208 0.249 0.295 0.368 0.557 0.754 0.952 1.152
12 0.157 0.197 0.255 0.320 0.387 0.131 0.151 0.186 0.230 0.278 0.307 0.497 0.694 0.893 1.093
14 0.135 0.176 0.237 0.303 0.371 0.113 0.134 0.172 0.218 0.266 0.263 0.454 0.652 0.851 1.051
16 0.118 0.161 0.223 0.291 0.359 0.099 0.121 0.162 0.208 0.257 0.230 0.422 0.621 0.820 1.020
18 0.105 0.150 0.213 0.281 0.350 0.088 0.111 0.154 0.201 0.250 0.205 0.398 0.596 0.796 0.996
20 0.095 0.141 0.205 0.274 0.343 0.079 0.104 0.148 0.196 0.245 0.185 0.378 0.577 0.776 0.976
22 0.086 0.133 0.199 0.268 0.337 0.072 0.098 0.143 0.192 0.241 0.168 0.362 0.561 0.760 0.960
24 0.079 0.128 0.194 0.263 0.328 0.066 0.093 0.139 0.188 0.238 0.154 0.348 0.547 0.747 0.947
26 0.073 0.121 0.190 0.259 0.326 0.061 0.090 0.136 0.185 0.233 0.142 0.337 0.531 0.736 0.931
28 0.068 0.119 0.186 0.255 0.325 0.056 0.086 0.133 0.183 0.232 0.132 0.327 0.527 0.727 0.926
30 0.063 0.115 0.183 0.252 0.322 0.053 0.084 0.131 0.180 0.230 0.124 0.319 0.518 0.718 0.918
32 0.059 0.112 0.18 0.249 0.319 0.049 0.081 0.129 0.178 0.228 0.116 0.312 0.511 0.711 0.911
34 0.056 0.110 0.178 0.247 0.317 0.047 0.079 0.127 0.177 0.227 0.11 0.305 0.505 0.705 0.905
36 0.053 0.107 0.176 0.245 0.315 0.044 0.077 0.126 0.175 0.225 0.104 0.300 0.499 0.699 0.899
38 0.050 0.105 0.174 0.243 0.313 0.042 0.076 0.124 0.174 0.224 0.098 0.295 0.494 0.694 0.894
40 0.047 0.103 0.172 0.242 0.311 0.040 0.075 0.123 0.173 0.223 0.094 0.290 0.490 0.690 0.890
Table HI-2(c) – Table showing Variation of “Equivalent Length Factor” with L/T ratio and
Pile Exposed Length Factor for End-bearing Piles with Bottom Fixed
I-5
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HI
Top Pinned / Bottom Free Top fixed / Bottom Free Top Free / Bottom Free
L/T Sleeved Length Factor (Rsle) Sleeved Length Factor (Rsle) Sleeved Length Factor (Rsle)
Ratio
0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4
0 – – – – – 2.000 2.000 2.000 2.000 2.000 – – – – –
1 6.293 6.293 6.298 6.320 6.378 1.942 1.942 1.942 1.942 1.942 18.854 19.566 21.397 24.443 29.183
2 1.234 1.234 1.234 1.234 1.236 1.225 1.225 1.225 1.226 1.226 3.362 3.493 3.829 4.380 5.229
3 0.869 0.869 0.871 0.879 0.895 0.787 0.787 0.787 0.788 0.791 1.330 1.395 1.547 1.775 2.101
4 0.606 0.607 0.609 0.618 0.645 0.588 0.588 0.588 0.590 0.596 0.922 0.982 1.102 1.254 1.438
5 0.439 0.439 0.440 0.441 0.446 0.438 0.438 0.438 0.438 0.439 0.737 0.808 0.940 1.098 1.269
6 0.349 0.349 0.353 0.377 0.426 0.346 0.346 0.346 0.347 0.350 0.612 0.692 0.834 1.000 1.177
7 0.283 0.283 0.295 0.341 0.398 0.283 0.283 0.283 0.284 0.294 0.525 0.612 0.762 0.933 1.113
8 0.240 0.241 0.268 0.319 0.379 0.239 0.239 0.239 0.239 0.273 0.459 0.553 0.709 0.884 1.067
9 0.210 0.215 0.249 0.303 0.365 0.205 0.205 0.205 0.220 0.263 0.408 0.508 0.669 0.847 1.033
10 0.189 0.196 0.234 0.291 0.354 0.179 0.179 0.179 0.211 0.255 0.368 0.473 0.638 0.819 1.006
12 0.157 0.167 0.214 0.274 0.339 0.142 0.142 0.156 0.198 0.243 0.307 0.421 0.593 0.777 0.967
14 0.135 0.149 0.200 0.263 0.329 0.117 0.117 0.145 0.189 0.236 0.263 0.385 0.561 0.748 0.940
16 0.118 0.135 0.191 0.256 0.322 0.099 0.103 0.138 0.183 0.231 0.230 0.359 0.539 0.728 0.920
18 0.105 0.126 0.184 0.250 0.317 0.088 0.094 0.133 0.179 0.227 0.205 0.339 0.522 0.712 0.906
20 0.095 0.119 0.179 0.245 0.313 0.079 0.088 0.129 0.176 0.224 0.185 0.324 0.508 0.700 0.894
22 0.086 0.113 0.175 0.242 0.310 0.072 0.083 0.126 0.173 0.222 0.168 0.312 0.498 0.690 0.885
24 0.079 0.109 0.172 0.239 0.307 0.066 0.079 0.123 0.171 0.220 0.154 0.302 0.489 0.682 0.878
26 0.073 0.105 0.169 0.237 0.305 0.061 0.076 0.121 0.169 0.218 0.142 0.293 0.482 0.673 0.872
28 0.068 0.102 0.167 0.235 0.303 0.056 0.074 0.120 0.168 0.217 0.132 0.286 0.476 0.670 0.866
30 0.063 0.100 0.165 0.233 0.302 0.053 0.072 0.118 0.167 0.216 0.124 0.280 0.471 0.666 0.862
32 0.059 0.098 0.163 0.232 0.300 0.049 0.071 0.117 0.166 0.215 0.116 0.275 0.466 0.662 0.858
34 0.056 0.096 0.162 0.230 0.299 0.047 0.069 0.116 0.165 0.214 0.110 0.271 0.463 0.658 0.855
36 0.053 0.094 0.161 0.229 0.298 0.044 0.068 0.115 0.164 0.213 0.104 0.267 0.459 0.655 0.853
38 0.050 0.093 0.160 0.228 0.297 0.042 0.067 0.115 0.163 0.213 0.098 0.263 0.456 0.653 0.85
40 0.047 0.092 0.159 0.228 0.297 0.040 0.066 0.114 0.163 0.212 0.094 0.260 0.454 0.650 0.848
Table HI-2(d) – Table showing Variation of “Equivalent Length Factor” with L/T ratio
and Pile Sleeved Length Factor for End-bearing Piles with Bottom Free
Top Pinned / Bottom Pinned Top fixed / Bottom Pinned Top Free / Bottom Pinned
L/T
Sleeved Length Factor (Rsle) Sleeved Length Factor (Rsle) Sleeved Length Factor (Rsle)
Ratio
0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4
0 1.000 1.000 1.000 1.000 1.000 0.699 0.699 0.699 0.699 0.699 – – – – –
1 0.997 0.997 0.998 0.998 0.998 0.698 0.698 0.698 0.698 0.698 10.906 11.232 12.108 13.604 15.965
2 0.927 0.927 0.928 0.932 0.939 0.674 0.674 0.674 0.674 0.676 2.076 2.142 2.313 2.592 3.017
3 0.671 0.671 0.674 0.686 0.714 0.557 0.557 0.557 0.558 0.564 1.187 1.232 1.329 1.459 1.623
4 0.461 0.461 0.468 0.488 0.523 0.388 0.388 0.388 0.388 0.389 0.922 0.982 1.099 1.240 1.391
5 0.381 0.382 0.392 0.421 0.465 0.323 0.323 0.324 0.331 0.350 0.735 0.806 0.939 1.098 1.268
6 0.314 0.316 0.333 0.372 0.425 0.261 0.262 0.264 0.280 0.312 0.612 0.691 0.834 0.999 1.176
7 0.270 0.273 0.295 0.340 0.397 0.226 0.226 0.231 0.252 0.288 0.525 0.612 0.762 0.933 1.113
8 0.236 0.240 0.268 0.319 0.378 0.197 0.197 0.205 0.234 0.273 0.459 0.553 0.709 0.884 1.067
9 0.210 0.215 0.249 0.303 0.365 0.175 0.176 0.187 0.220 0.263 0.408 0.508 0.669 0.847 1.033
10 0.189 0.196 0.234 0.291 0.354 0.158 0.158 0.174 0.211 0.255 0.368 0.473 0.638 0.819 1.006
12 0.157 0.167 0.214 0.274 0.339 0.131 0.133 0.156 0.198 0.243 0.307 0.421 0.593 0.777 0.967
14 0.135 0.149 0.200 0.263 0.329 0.113 0.116 0.145 0.189 0.236 0.263 0.385 0.561 0.748 0.940
16 0.118 0.135 0.191 0.256 0.322 0.099 0.103 0.138 0.183 0.231 0.230 0.359 0.539 0.728 0.920
18 0.105 0.126 0.184 0.250 0.317 0.088 0.094 0.133 0.179 0.227 0.205 0.339 0.522 0.712 0.906
20 0.095 0.119 0.179 0.245 0.313 0.079 0.088 0.129 0.176 0.224 0.185 0.324 0.508 0.700 0.894
22 0.086 0.113 0.175 0.242 0.310 0.072 0.083 0.126 0.173 0.222 0.168 0.312 0.498 0.690 0.885
24 0.079 0.109 0.172 0.239 0.307 0.066 0.079 0.123 0.171 0.220 0.154 0.302 0.489 0.682 0.878
26 0.073 0.105 0.168 0.237 0.305 0.061 0.076 0.121 0.169 0.218 0.142 0.293 0.482 0.676 0.872
28 0.068 0.102 0.167 0.235 0.303 0.056 0.074 0.12 0.168 0.217 0.132 0.286 0.476 0.67 0.866
30 0.063 0.100 0.165 0.233 0.302 0.053 0.072 0.118 0.167 0.216 0.124 0.280 0.471 0.666 0.862
32 0.059 0.098 0.163 0.232 0.300 0.049 0.071 0.117 0.166 0.215 0.116 0.275 0.466 0.662 0.858
34 0.056 0.096 0.162 0.230 0.299 0.047 0.069 0.116 0.165 0.214 0.110 0.271 0.463 0.658 0.855
36 0.053 0.094 0.161 0.229 0.298 0.044 0.068 0.115 0.164 0.213 0.104 0.267 0.459 0.655 0.853
38 0.050 0.093 0.160 0.228 0.297 0.042 0.067 0.115 0.163 0.213 0.098 0.263 0.456 0.653 0.850
40 0.047 0.092 0.159 0.228 0.297 0.040 0.066 0.114 0.163 0.212 0.094 0.260 0.454 0.650 0.848
Table HI-2(e) – Table showing Variation of “Equivalent Length Factor” with L/T ratio and
Pile Exposed Length Factor for End-bearing Piles with Bottom Pinned
I-6
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HI
Top Pinned / Bottom Fixed Top fixed / Bottom Fixed Top Free / Bottom Fixed
L/T
Sleeved Length Factor (Rsle) Sleeved Length Factor (Rsle) Sleeved Length Factor (Rsle)
Ratio
0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4 0 0.1 0.2 0.3 0.4
0 0.699 0.699 0.699 0.699 0.699 0.500 0.500 0.500 0.500 0.500 2.000 2.000 2.000 2.000 2.000
1 0.699 0.699 0.699 0.699 0.699 0.500 0.500 0.500 0.500 0.500 1.897 1.988 1.991 1.994 1.997
2 0.681 0.681 0.682 0.684 0.687 0.493 0.493 0.493 0.493 0.494 1.694 1.721 1.778 1.844 1.905
3 0.593 0.593 0.596 0.606 0.625 0.451 0.451 0.451 0.453 0.459 1.176 1.224 1.326 1.459 1.608
4 0.458 0.459 0.466 0.487 0.523 0.364 0.364 0.364 0.369 0.384 0.908 0.966 1.082 1.222 1.378
5 0.374 0.375 0.387 0.416 0.460 0.304 0.304 0.306 0.315 0.337 0.734 0.805 0.936 1.092 1.258
6 0.314 0.316 0.333 0.372 0.424 0.260 0.260 0.263 0.279 0.310 0.612 0.691 0.834 0.999 1.175
7 0.270 0.272 0.295 0.340 0.397 0.224 0.224 0.229 0.252 0.288 0.525 0.612 0.762 0.933 1.113
8 0.236 0.240 0.268 0.319 0.378 0.197 0.197 0.205 0.233 0.273 0.459 0.553 0.709 0.884 1.067
9 0.210 0.215 0.249 0.303 0.365 0.175 0.176 0.187 0.220 0.263 0.408 0.508 0.669 0.847 1.033
10 0.189 0.196 0.234 0.291 0.354 0.158 0.158 0.174 0.211 0.255 0.368 0.473 0.638 0.819 1.006
12 0.157 0.167 0.214 0.274 0.339 0.131 0.133 0.156 0.198 0.243 0.307 0.421 0.593 0.777 0.967
14 0.135 0.149 0.200 0.263 0.329 0.113 0.116 0.145 0.189 0.236 0.263 0.385 0.561 0.748 0.940
16 0.118 0.135 0.191 0.256 0.322 0.099 0.103 0.138 0.183 0.231 0.230 0.359 0.539 0.728 0.920
18 0.105 0.126 0.184 0.250 0.317 0.088 0.094 0.133 0.179 0.227 0.205 0.339 0.522 0.712 0.906
20 0.095 0.119 0.179 0.245 0.313 0.079 0.088 0.129 0.176 0.224 0.185 0.324 0.508 0.700 0.894
22 0.086 0.113 0.175 0.242 0.310 0.072 0.083 0.126 0.173 0.222 0.168 0.312 0.498 0.690 0.885
24 0.079 0.109 0.172 0.239 0.307 0.066 0.079 0.123 0.171 0.220 0.154 0.302 0.489 0.682 0.878
26 0.073 0.105 0.169 0.237 0.305 0.061 0.076 0.121 0.169 0.218 0.142 0.293 0.482 0.676 0.872
28 0.068 0.102 0.167 0.235 0.303 0.056 0.074 0.120 0.168 0.217 0.132 0.286 0.476 0.670 0.866
30 0.063 0.100 0.165 0.233 0.302 0.053 0.072 0.118 0.167 0.216 0.124 0.280 0.471 0.666 0.862
32 0.059 0.098 0.163 0.232 0.300 0.049 0.071 0.117 0.166 0.215 0.116 0.275 0.466 0.662 0.858
34 0.056 0.096 0.162 0.230 0.299 0.047 0.069 0.116 0.165 0.214 0.110 0.271 0.463 0.658 0.855
36 0.053 0.094 0.161 0.229 0.298 0.044 0.068 0.115 0.164 0.213 0.104 0.267 0.459 0.655 0.853
38 0.050 0.093 0.160 0.228 0.297 0.042 0.067 0.115 0.163 0.213 0.098 0.263 0.456 0.653 0.850
40 0.047 0.092 0.159 0.228 0.297 0.040 0.066 0.114 0.163 0.212 0.094 0.260 0.454 0.650 0.848
Table HI-2(f) – Table showing Variation of “Equivalent Length Factor” with L/T ratio and
Pile Exposed Length Factor for End-Bearing Piles with Bottom Fixed
Law (2013) points out that the analytical results of “buckling” reveals only that a strut
can take up the shape of any of the analyzed buckling modes, with any magnitude i.e. the
“discrete buckling” loads. It is not the case, as discussed in some references and text
books such as Coates et al (1980) that the Euler load is a threshold load above which the
strut becomes unstable.
Nevertheless, a strut normally fails due to its own “initial imperfection” at loads well
below the Euler load. By initial imperfection we refer to the initial “bowing” of the
strut causing eccentric bending in the strut under applied pure axial load. The axial load
will create further “bowing”, which may cause the strut to fail subsequently. It has,
however, been proved that the Euler load is the absolute maximum, at which the
imperfection (bowing) will increase to infinity, i.e. the strut will fail certainly.
It should also be noted that provisions in the steel and concrete codes (BS5950 and
BS8110) for reduction of load capacity of a strut due to its length are actually not to cater
for the theoretical “buckling phenomenon”. The provisions are to account for the extra
bending caused by the initial imperfections assumed which lead to reduction of strut load
capacity. The analysis for the Euler load, however, is useful in determining the effective
length of the pile and the “buckling mode shape” which is the most critical initial
imperfection shape leading to subsequent failure. Law (2013) has analyzed and
provided design charts. Upon determination of the equivalent buckling length, it would
I-7
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HI
be acceptable, based on the approach outlined in HI.4, to determine the reduced load
carrying capacity. Nevertheless, Law (2013) has, by assuming a sinusoidal deflected
initial imperfection profile for the pile, developed an approach for determination of the
moment due to the axial load and the imperfection for the pile under lateral restraint.
The moment can then be taken into design.
Consider a 4-T50 mini-pile with cross section as shown in Figure HI-4 driven into soil of
nh = 1300 kN/m3 of total length 30m and the top 3m exposed. Its head is pinned at the
underside of the pile cap and its other end socketed into rock which is considered as
fixed.
263/273 CHS
π 2734 π 2634
Icasing = − = 37808149 mm4
64 64
π 50 4 π 50 2
IT50 = 4 + × 35 2 = 10848312 mm4
64 4
20
35 4
Itotal = 48656461mm
E p I p = 205 × 10 6 × 48656361 × 10 −12 = 9974.57 kNm2
For nh = 1300 kN/m3
T = 5 E p I p / nh = 1.503 m
T50 bars
structural capacity of the pile of 0.475 × 500 × 7854 ×10 −3 = 1865 kN. It can be seen that
this theoretical “Euler” load is very high.
However, as discussed in HI.3, the codified design against “buckling” is not performed
by checking against this Euler load. Instead, the codes including BS5950, the Code of
Practice for Structural Use of Steel 2011 determine the reduced load carrying capacity of
the strut based on its “initial imperfections”. The 2 steel codes are based on
back-calculation from the experimental failure loads of struts of various types of sections
and grades to determine the initial imperfections and provide formulae and tables for
determination of the reduced strengths. To calculate the reduced strengths, we may
assume the mini-pile to adopt the CHS section as no study has been carried out on the
mini-pile section to determine initial imperfections. So according to Table 8.7 of the
Code of Practice for Structural Use of Steel 2011, curve a) should be followed. The
next step is to find the radius of gyration r of the section and subsequently the λ
value which is Leq r .
I-8
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HI
By Table 8.8 (a) of the Steel Code and assuming S460 (nearest to the grade of the T50
bars), the design strength of steel drops from 460N/mm2 to 331N/mm2, i.e. drops to 72%
of its original value. So the load carrying capacity of the pile is 1689 × 0.72 = 1216 kN.
However, if the pile is completely embedded, by Table HI-2(c), the equivalent length
factor is 0.095 and the equivalent length is Leq = 0.095 × 30 = 2.85 m. With
λ = 2850 / 63.51 = 44.87 and by Table 8.8 (a) of the Steel Code, the design strength of
steel drops from 460N/mm2 to 415.26N/mm2, i.e. drops to 90.3% of its original value. So
the load carrying capacity of the pile is 1689 × 0.903 = 1525 kN.
The buckling phenomenon can also be solved by the stiffness method through the use of
the “geometric matrix”. The stiffness matrix and the geometric matrix of a strut of
length L and flexural stiffness EI are
12 EI 6 EI − 12 EI 6 EI
L3 L L3 L2
6 EI 36 3L − 36 3L
4 EI − 6 EI 2 EI
2
L and [k ] = − 1 3L 4 L − 3L − L
2
[ke ] = − 12L EI
2
L L2
− 6 EI 12 EI − 6 EI G
30 L − 36 − 3L 36 − 3L
L3 L2 L3 2
6 EI
L
3L − L2 − 3L 4 L2
2 EI − 6 EI 4 EI
L2 L L2 L
(Eqn HI-11)
It can be proven that the stiffness of the strut under an axial P becomes
If P is so chosen that when the matrix [K e ] + P[K G ] diminishes implying zero stiffness
of the pile, the buckling of the pile takes place and P becomes the buckling load, with
[v] as the lateral displacement matrix. So we may list
I-9
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HI
Again (Eqn HI-14) is an eigen-value problem for the matrix [K e ] [K G ] and the
−1
−1
eigen-values λ = by which the buckling load can be determined as
P
−1
P= (Eqn HI-15)
λ
And the eigen vectors [v ] analyzed represent the buckling modes (shapes).
Both the finite difference approach and the stiffness method described above can be used
directly to calculate lateral displacements with inclusion of P-∆ effects. Further details
are discussed in Appendix HP.
I-10
Appendix HJ
The Hiley Formula, like most of the pile dynamic formulae is based on an energy
approach by which the energy injected from the driving hammer into the pile is set equal
to the work done by the pile on the soil in the form of “set” (advancement of the pile into
the soil) and temporary compression of the soil (quake) and the pile itself. The ultimate
resistance on the pile is then solved by the principle of conservation of energy. The
energy transfer process is demonstrated in Figure HJ-1.
Hammer Weight Wh
Loss in potential energy of
hammer = Wh h . After some
energy loss due to guard and
rail etc., energy before Hammer Drop
impact is EhWh h Height h
EhWh h
h (
W + e2 W + W
p r ) with further
temporary compression of
the Pile and the Soil along
Wh + W p + Wr
the Pile shaft is
deduction of 0.5 Pu cc due to loss in ( )
0.5 Pu c p + c q
compressing the cushion.
Total Ultimate
Resistance of the Pile
from the Pile Shaft
and the Base is Pu
Legend :
J-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HJ
Referring to Figure HJ-1, consider the drop hammer of weight Wh dropping from height
h and impact on the pile of weight W p and the weight of the helmet Wr . The loss of
potential energy of the hammer is Wh h . After some loss due to hammer efficiency, the
energy of the hammer just before impact is EhWh h , which is converted to the kinetic
W 2
energy of the hammer h U h where Uh is the velocity of the hammer before impact.
2g
By equating the two energies,
U h = Eh 2 gh (Eqn HJ-1)
Let Vh and V P be the velocities of the hammer and the pile (and helmet) after impact,
then during impact, by the Law of Conservation of Momentum (the contribution of the
soil is ignored)
Wh W (W + Wr )V ⇒ W U = W V + (W + W )V
U h = h Vh + p (Eqn HJ-2)
p h h h h p r p
g g g
Assuming the rigid body impact condition and applying Newton’s Law of Restitution, we
V p − Vh
have = −e ⇒ Vh = V p − eU h (Eqn HJ-3)
0 −Uh
WhU h = Wh (V p − eU h ) + (W p + Wr )V p ⇒ V p =
(1 + e )Wh
Wh + (W p + Wr )
Uh (Eqn HJ-4)
The kinetic energy of the pile and the cushion after impact is
(W p+ Wr ) 2
V p (Eqn HJ-5)
2g
Combining (Eqn HJ-5) with (Eqn HJ-1) and (Eqn HJ-4), the kinetic energy of the pile
with the cushion after impact is
(W p+ Wr ) (1 + e )Wh
2
( )
1 + 2e + e 2 Wh (W p + Wr )
Eh 2 gh = EhWh h
(Wh + Wp + Wr )2
(Eqn HJ-6)
2g Wh + W p + Wr
Wh 2
The kinetic energy of the hammer after impact is Vh
2g
J-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HJ
Adding the energies of the pile with cushion in (Eqn HJ-6) and that of the hammer in
(Eqn HJ-7), the total energy T .E. is
T .E. = EhWh h
( )
1 + 2e + e 2 Wh (W p + Wr ) Wh − e(W p + Wr )
2
+ EhWh h
(Wh + Wp + Wr )
2
Wh + W p + Wr
W + e (W p + Wr )
2
This total energy is eventually transferred to the pile and is dissipated through work done
against soil resistances and elastic compression of the pile and cushion.
Assuming the soil is exhibiting elasto-plastic behaviour with elastic limit cq (the
quake) beyond which the soil resistance is constant at Pu and for a distance s which is
the set, the work done on the soil is
0.5 Pu cq + Pu s (Eqn HJ-9)
Pu
The area beneath the force /
displacement curve
Force represents the work done on
soil by a force varying from 0
to Pu, assuming static
problem.
Displacement
cq s
Figure HJ-2 – Work done in Quake and Set as Assumed by the Hiley Formula
Similarly, again assuming static behaviour, the work done on the elastic compression of the
pile and the cushion is
J-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HJ
where c p and cc are respectively the temporary compressions of the pile and the cushion.
So, equating the energy after impact to the work done on temporary compression of the pile
/ the soil and total “Set” of the Pile,
Wh + e 2 (W p + Wr )
EhWh h = 0.5 Pu cq + Pu s + 0.5 Pu c p + 0.5 Pu cc = 0.5 Pu (cc + c p + cq ) + Pu s
Wh + W p + Wr
EhWh h Wh + e 2 (W p + Wr )
⇒ Pu =
s + 0.5(cc + c p + cq ) Wh + W p + Wr
(Eqn HJ-11)
It should be noted that c p + cq and s can be measured during the final set of the pile.
cc is small comparatively. It is often assumed to be constant, ranging from 4 to 6 mm. The
value is either assumed or can be measured by video camera.
J-4
Appendix HK
Discussion of Limits of “Final Set” and Criteria for Formulation of the “Final Set”
Table
Other than piles driven to refusal achieving sets less than 10mm per 10 blows, the format
of a final set table depends on the pile driving formula. The final set table relates the
allowable maximum final set value S of a driven pile for a given design ultimate capacity
to the elastic displacement of the pile head or other measurable quantities. The elastic
displacement of the pile head is often regarded as the sum of the elastic compression of
the piles cp and the elastic settlement of the ground cq when the pile is being driven. For
the Hiley formula commonly used in Hong Kong, the actual final set s is related to cp+cq
and the pile length L. A driven pile is considered to have achieved a sufficient ultimate
pile capacity if s is smaller than S.
The ultimate pile capacity that can be developed by pile driving depends on the energy
imparted to the pile. The same pile driving energy can be attained by using a lighter
hammer with a larger drop height or a heavy hammer with a smaller drop height. Each
combination of hammer weight and drop height produces a different final set table.
A higher drop height will tend to induce higher driving stress and thus a higher risk of
damaging the pile. From a theoretical point of view, it is preferable to use a heavy
hammer with a smaller drop height to limit the driving stress.
It is common to impose criteria limiting the applicable range of s. In Hong Kong, the
most commonly used criteria in the past were that the combination of hammer weight and
drop height should be such that s will not be higher than 50mm per 10 blows or less than
25mm per 10 blows. It was believed that the first criterion of requiring s to be more
than 25mm per 10 blows was originated from the Civil Engineering Code of Practice 4
(ICE, 1954). There was a good reason for setting this limit. In the 1950s and 1960s,
precast concrete piles were perhaps the most common type of driven piles. Imposing a
lower limit is equivalent to discouraging the contractor from using a light hammer with a
large drop height. This indirectly controls the driving stress and hence the potential for
damaging precast concrete piles.
The setting of this lower bound limit of 25mm per 10 blows was later abandoned in the
British standards CP2004 and BS8004 (BSI, 1972, 1986), but replaced by the second
criterion of setting an upper limit of S not greater than 50mm per 10 blows. The reason
for imposing such an upper limit is not explained in the British Standards nor discussed
in the literature. From a theoretical point of view, this criterion is not reasonable.
Imposing an upper limit will deter contractors from using a heavy hammer which is
beneficial in reducing driving stresses.
If both of the above two criteria are imposed, the applicable range of S becomes very
narrow. A driven pile which has attained a very small actual set value s will not be
acceptable if the combination of measured cp+cq value and actual pile length is outside
K-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HK
the applicable range of S. The criteria for limiting the applicable range are developed so
as to minimize the potential of pile damage. A driven pile with a small actual set value s
that can achieve a higher pile capacity and has no apparent damage occurring during pile
driving could be deemed not acceptable under such criteria. The contractors have to
select a suitable combination of hammer weight and drop height that can meet the
applicable range of S. They are often compelled to use drop hammers to perform final
setting of piles even though the piles have been pitched by hydraulic hammers. With a
drop hammer, the drop height can be varied much more easily than is the case with a
hydraulic hammer to increase the chance of finding a suitable final set table that can
fulfill the criteria.
In determining the criteria for formulating the Final Set Table, that the pile driving stress
can now be measured directly by a Pile Driving Analyzer (PDA) is a consideration.
According to recent studies by Lam (2007) and Li & Lam (2007) based on a large
database of PDA test results, the driving stress is found to have no correlation with S.
Fung et al (2004), Lam (2007) and Li & Lam (2007) further observed that the ratio of
(cp+cq)/L is a simple and useful indicator of pile driving stress. Lam (2007) and Li &
Lam (2007) proposed that by limiting the ratio of (cp+cq)/L to 1.15 where cp+cq is in
millimetre and L is in metre, the driving stress in steel H-piles can generally be controlled
to less than 80% of the yield stress of steel piles at which the risk of damage to the pile is
considered to be acceptably small. Based on these findings, the following criteria were
formulated for the final set table which are acceptable to the Buildings Department and
finally incorporated into the Code.
(i) The upper bound limit of S is relaxed to 100mm per 10 blows, but with the
allowable value capped at 50mm. That is, if a calculated value of S between 50
and 100 is obtained, a value of 50 will still be used in the final set table;
(ii) (cp+cq)/L is limited to not greater than 1.15 where cp+cq is in millimetre and L is in
metre.
The following Worked Example HK-1, of a final set table is developed using the above
criteria based on the Hiley formula. It can be observed that the applicable range of S has
become much wider, making it easier for compliance.
Data
Weight of Hammer : 16T
Type of Pile : 305×305×223 kg/m S450J0 Steel H-pile
Design Working Capacity 3053kN
Factor of Safety : 2
Design Ultimate Capacity R = 6106kN
Weight of Hammer : W = 156.96kN
Drop Height of Hammer: H = 1.5m
Maximum Driving Energy: E = 235.44kJ
Average Hammer Efficiency: = 0.7
Pile Helmet Compression: cc = 5mm
Coefficient of Restitution: e = 0.32
Weight of Pile Helmet: Wr = 30kN
K-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HK
First of all, if no restriction on the S values at all, the set table is as shown in Table HK-1.
Pile
Length Temporary Compression cp+cq
(m) 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
15 146 141 136 131 126 121 116 111 106 101 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 21
16 144 139 134 129 124 119 114 109 104 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 24 19
17 142 137 132 127 122 117 112 107 102 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 22 17
18 141 136 131 126 121 116 111 106 101 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 21 16
19 139 134 129 124 119 114 109 104 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 24 19 14
20 137 132 127 122 117 112 107 102 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 22 17 12
21 136 131 126 121 116 111 106 101 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 21 16 11
22 134 129 124 119 114 109 104 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 24 19 14 9
23 133 128 123 118 113 108 103 98 93 88 83 78 73 68 63 58 53 48 43 38 33 28 23 18 13 8
24 131 126 121 116 111 106 101 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 21 16 11 6
25 130 125 120 115 110 105 100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5
26 129 124 119 114 109 104 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 24 19 14 9 4
27 127 122 117 112 107 102 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 22 17 12 7 2
28 126 121 116 111 106 101 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 21 16 11 6 1
29 124 119 114 109 104 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 24 19 14 9 4 -1
30 123 118 113 108 103 98 93 88 83 78 73 68 63 58 53 48 43 38 33 28 23 18 13 8 3 -2
31 122 117 112 107 102 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 22 17 12 7 2 -3
32 121 116 111 106 101 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 21 16 11 6 1 -4
33 119 114 109 104 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 24 19 14 9 4 -1 -6
34 118 113 108 103 98 93 88 83 78 73 68 63 58 53 48 43 38 33 28 23 18 13 8 3 -2 -7
35 117 112 107 102 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 22 17 12 7 2 -3 -8
36 116 111 106 101 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 21 16 11 6 1 -4 -9
37 115 110 105 100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0 -5 -10
38 113 108 103 98 93 88 83 78 73 68 63 58 53 48 43 38 33 28 23 18 13 8 3 -2 -7 -12
39 112 107 102 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 22 17 12 7 2 -3 -8 -13
40 111 106 101 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 21 16 11 6 1 -4 -9 -14
41 110 105 100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0 -5 -10 -15
42 109 104 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 24 19 14 9 4 -1 -6 -11 -16
43 108 103 98 93 88 83 78 73 68 63 58 53 48 43 38 33 28 23 18 13 8 3 -2 -7 -12 -17
44 107 102 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 22 17 12 7 2 -3 -8 -13 -18
Table HK-1 – Final Set Values per 10 blows with No Restriction on the S values
If adopting the requirements that the applicable range of allowable set S = 25 to 100mm;
and (cp+cq)/L 1.15 where cp+cq is in mm and L is in metre. Table HK-1 is reduced to
Table HK-2.
Pile
Length Temporary Compression cp+cq
(m) 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
15 - - - - - - - - - - 96 91 - - - - - - - - - - - - - -
16 - - - - - - - - - 99 94 89 84 - - - - - - - - - - - - -
17 - - - - - - - - - 97 92 87 82 77 - - - - - - - - - - - -
18 - - - - - - - - - 96 91 86 81 76 71 - - - - - - - - - - -
19 - - - - - - - - 99 94 89 84 79 74 69 64 - - - - - - - - - -
20 - - - - - - - - 97 92 87 82 77 72 67 62 57 - - - - - - - - -
21 - - - - - - - - 96 91 86 81 76 71 66 61 56 51 46 - - - - - - -
22 - - - - - - - 99 94 89 84 79 74 69 64 59 54 49 44 39 - - - - - -
23 - - - - - - - 98 93 88 83 78 73 68 63 58 53 48 43 38 33 - - - - -
24 - - - - - - - 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 - - - -
25 - - - - - - 100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 - - - - -
26 - - - - - - 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 - - - - -
27 - - - - - - 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 - - - - -
28 - - - - - - 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 - - - - -
29 - - - - - 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 - - - - - -
30 - - - - - 98 93 88 83 78 73 68 63 58 53 48 43 38 33 28 - - - - - -
31 - - - - - 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 - - - - - -
32 - - - - - 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 - - - - - -
33 - - - - 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 - - - - - - -
34 - - - - 98 93 88 83 78 73 68 63 58 53 48 43 38 33 28 - - - - - - -
35 - - - - 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 - - - - - - -
36 - - - - 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 - - - - - - -
37 - - - 100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 - - - - - - - -
38 - - - 98 93 88 83 78 73 68 63 58 53 48 43 38 33 28 - - - - - - - -
39 - - - 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 - - - - - - - -
40 - - - 96 91 86 81 76 71 66 61 56 51 46 41 36 31 26 - - - - - - - -
41 - - - 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 - - - - - - - -
42 - - 99 94 89 84 79 74 69 64 59 54 49 44 39 34 29 - - - - - - - - -
43 - - 98 93 88 83 78 73 68 63 58 53 48 43 38 33 28 - - - - - - - - -
44 - - 97 92 87 82 77 72 67 62 57 52 47 42 37 32 27 - - - - - - - - -
Table HK-2 – Final Set Values per 10 blows (i) with limits between 25mm and 100mm per 10
blows; (ii) and (cp+cq)/L 1.15 where cp+cq is in mm and L is in m
K-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HK
Finally, to be conservative, the values of S in excess of 50mm are capped at 50mm so that
the final set table of Table HK-2 is modified as follows as Table HK-3:
Pile
Length Temporary Compression cp+cq
(m) 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
15 - - - - - - - - - - 50 50 - - - - - - - - - - - - - -
16 - - - - - - - - - 50 50 50 50 - - - - - - - - - - - - -
Zone C1
17 - - - - - - - - - 50 50 50 50 50 - - - - - - - - - - - -
18 - - - - - - - - - 50 50 50 50 50 50 - - - - - - - - - - -
Zone C2
19 - - - - - - - - 50 50 50 50 50 50 50 50 - - - - - - - - - -
20 - - - - - - - - 50 50 50 50 50 50 50 50 50 - - - - - - - - -
21 - - - - - - - - 50 50 50 50 50 50 50 50 50 50 46 - - - - - - -
22 - - - - - - - 50 50 50 50 50 50 50 50 50 50 49 44 39 - - - - - -
23 - - - - - - - 50 50 50 50 50 50 50 50 50 50 48 43 38 33 - - - - -
24 - - - - - - - 50 50 50 50 50 50 50 50 50 50 46 41 36 31 26 - - - -
Zone A
25 - - - - - - 50 50 50 50 50 50 50 50 50 50 50 45 40 35 30 - - - - -
26 - - - - - - 50 50 50 50 50 50 50 50 50 50 49 44 39 34 29 - - - - -
27 - - - - - - 50 50 50 50 50 50 50 50 50 50 47 42 37 32 27 - - - - -
28 - - - - - - 50 50 50 50 50 50 50 50 50 50 46 41 36 31 26 - - - - -
29 - - - - - 50 50 50 50 50 50 50 50 50 50 49 44 39 34 29 - - - - - -
30 - - - - - 50 50 50 50 50 50 50 50 50 50 48 43 38 33 28 - - - - - -
31 - - - - - 50 50 50 50 50 50 50 50 50 50 47 42 37 32 27 - - -Zone- B - -
32 - - - - - 50 50 50 50 50 50 50 50 50 50 46 41 36 31 26 - - - - - -
Zone E
33 - - - - 50 50 50 50 50 50 50 50 50 50 49 44 39 34 29 - - - - - - -
34 - - - - 50 50 50 50 50 50 50 50 50 50 48 43 38 33 28 - - - - - - -
35 - - - - 50 50 50 50 50 50 50 50 50 50 47 42 37 32 27 - - - - - - -
36 - - - - 50 50 50 50 50 50 50 50 50 50 46 41 36 31 26 - - - - - - -
37 - - - 50 50 50 50 50 50 50 50 50 50 50 45 40Zone
35D 30 - - - - - - - -
38 - - - 50 50 50 50 50 50 50 50 50 50 48 43 38 33 28 - - - - - - - -
39 - - - 50 50 50 50 50 50 50 50 50 50 47 42 37 32 27 - - - - - - - -
40 - - - 50 50 50 50 50 50 50 50 50 50 46 41 36 31 26 - - - - - - - -
41 - - - 50 50 50 50 50 50 50 50 50 50 45 40 35 30 25 - - - - - - - -
42 - - 50 50 50 50 50 50 50 50 50 50 49 44 39 34 29 - - - - - - - - -
43 - - 50 50 50 50 50 50 50 50 50 50 48 43 38 33 28 - - - - - - - - -
44 - - 50 50 50 50 50 50 50 50 50 50 47 42 37 32 27 - - - - - - - - -
Table HK-3 – Final Set Values per 10 blows (i) with limits between 25mm and 100mm per 10
blows; (ii) (cp+cq)/L 1.15 where cp+cq is in mm; and L is in m; and (iii) S capped at 50mm
By Table HK-3, only Zones D and E are applicable zones. The controlling criteria in
Zones A to E are described as follows :
To conclude, comparing with the previous practice, an additional large area of Zone D is
added where the calculated value of S is relaxed to 100mm but capped at 50mm but a Zone
C2 is excluded due to the imposition of the restraint (cp+cq)/L 1.15 to avoid overstressing
the pile.
K-4
Appendix HL
Capacities
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
More Details and Examples in Wave Equation, the Case Method and CAPWAP for
Analysis of Pile Capacities
The speed of wave in a pile is an important parameter in the determination of pile load
capacity by making use of the Wave Equation on the Case Method and CAPWAP
analysis. This parameter can be derived as in follows:
The speed of force wave is therefore about 4000 to 5100m/sec in concrete and steel
respectively. The wave speed should not be confused with the actual particle velocity
which is comparatively very small, of the order of a few metres per second.
L-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
The pile driving force will be a boundary condition of (Eqn HL-4) and if S ( x, t ) is
known (even if it is related to the particle movement and velocity of the pile), the particle
movement of the pile including the “Set” can be determined. Nevertheless, the equation
is often used to back-calculate the pile shaft and end-bearing resistance with known
values of measurable quantities such as forces, particle movements, velocities and set.
The Case Method is based on the basic wave equation (Eqn HL-4). The basic
assumptions are as follows :
(i) The pile is uniform in section and construction material, i.e. the impedance
Z = AE / c is constant;
(ii) The stress wave experiences no energy loss in its transmission through the pile shaft
and there are no distortions of signals;
(iii) The resistance to the dynamic component of the force is at the pile toe only whilst
that of the pile shaft is ignored;
(iv) The resistance to the dynamic component is proportional to the particle velocity;
The following contains derivation of the formulae used in the Method with reference to
王杰賢(2001). If the reader is not interested, he may go directly to HL.3.2 where the
symbols used in the formula are fully defined and the application is demonstrated.
(Eqn HL-4) describes the particle displacement of the pile at any position x and time t ,
L-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
u ( x, t ) = h( x − ct ) + f ( x + ct ) (Eqn HL-5)
where h and f are arbitrary functions determined by the initial boundary conditions.
Physically h and f may respectively be regarded as the downward and upward waves
travelling in opposite directions but with the same speed c as derived in (Eqn HL-1).
h and f cannot be measured directly, but the sum of these two waves which is the
actual wave in the pile can be measured by the strain gauges and accelerometers in such
tests as PDA tests. The shapes of the two waves remain unchanged in their course of
transmission. However, at any level of the pile the side resistance R will de-generate
into two resistance waves (both of magnitude 0.5 R ), one of which is an upward
compressive wave and the other is a downward tension wave. The resistance wave
serves to increase the resistance and decrease the velocity of the pile at its top. As the
total resistance of the pile is the sum of the static and dynamic resistance generated by the
striking hammer, the Case Method is to determine the static resistance which is the true
resistance of the pile in the course of its service life by wave analysis with a number of
assumptions. The following sets out the detailed derivation of the formula to be used.
For the downward particle velocity (the actual moving velocity of the section)
∂h( x − ct ) ∂h( x − ct ) ∂x ∂h( x − ct )
vd = = ⋅ = ⋅ (− c )
∂t ∂x ∂t ∂x
− ∂h(x − ct ) vd
As strain ε d = =
∂x c
v AE
the downward force Fd = AEε d = AE d = vd = Zvd , (Eqn HL-6)
c c
by putting Z = AE / c , called the impedance as a mechanical property of the pile.
Similarly, it can be deduced that the upward force is Fu = − Zvu (Eqn HL-7)
where vu is the upward particle velocity.
So generally, it can be described that the velocity and force at any section of the pile shaft
are made up of the upward and downward components as illustrated in Figure HL-3(a).
That is:
v = vu + vd (Eqn HL-8)
F = Fu + Fd (Eqn HL-9)
L-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
Fd =
1
(FM + ZvM ) (Eqn HL-12)
2
Fu = (FM − ZvM )
1
(Eqn HL-13)
2
At the pile base, if it is free without any base resistance as illustrated in Figure HL-3(b),
F = 0 i.e. Fu = − Fd (Eqn HL-14)
vu = vd ; v = vu + vd = 2vd (Eqn HL-15)
At the pile base, if it is restrained from movement as illustrated in Figure HL-3(c)
v = 0 i.e. vu + vd = 0 ⇒ vu = −vd (Eqn HL-16)
Fu = Fd ; F = Fu + Fd = 2 Fd (Eqn HL-17)
(Eqn HL-17) is important as it shows by theory that the pile tip penetration force is at
most twice the pile axial force during driving. Without this dynamic effect, driving of
pile will require a much higher driving force which may damage the pile.
F1d F1u
Upward
Fu wave v1d v1u
vu 0.5Ri
Ri
0.5Ri
Fd
v2d v2u
Fd Fu Fd Fu
vd Downward vu+vd = 0
wave Fu+Fd = 0 F2d F2u
HL-3(a) Speed and Force HL-3(b) Free Pile HL-3(c) Restrained Pile HL-3(d) Action by Shaft
at any section of a Pile Base Base Friction
The actual pile base condition will be between “free” and “restrained”, depending on the
stiffness of the pile base subgrade. Reference is now made to Figure HL-3(d) for the
analysis of side friction. Above and below the section i , the forces and velocities can
be formulated as:
Above the section: F1 = F1u + F1d ; v1 = v1u + v1d ; F1 = − Zv1 (Eqn HL-18)
Below the section : F2 = F2u + F2 d ; v2 = v2u + v2 d ; F2 = Zv2 (Eqn HL-19)
L-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
Consider Figure HL-4, illustrating the transmission of waves in the pile shaft with
particular reference to a section at xi below ground. The pile is of length L below
ground, and its head at height H above ground, cross sectional area A , Young’s
Modulus E and density ρ (the last two are for determination of wave speed c by (Eqn
HL-1)). A sensor is installed at ground level.
2L/c
2(H+xi)/c
sensor Time
H
F(t)
xi 0.5Ri
0.5Ri
0.5Ri
L
F(t)
0.5Ri
When the compressive wave is transmitted to the pile tip which is assumed to be free
after time L / c , a reflective wave (tension wave by which Fu = − Fd = − F and
vu = vd = v ) is generated and reaches the sensor after time 2 L / c . The wave then
subsequently reaches the top level of the pile at which it is reflected back to the sensor at
2(L + H ) / c . So the velocity and force detected by the sensor at time t is due to the
wave reaching the sensor at time t and all the previous waves ( n numbers) reaching
the sensor after reflections at top level and tip of the pile as listed in (Eqn HL-22) and
L-5
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
(Eqn HL-23),
1 2L 2L 2H 4L 2H 4L 4H
vMF (t ) = F (t ) + F t − + Ft − − + Ft − − + Ft − − + .....
Z c c c c c c c
n
2 jL 2 jH n 2 jL 2 jH
=
1
F (t ) + ∑ F t − − ( j − 1 ) + ∑ F t − c − c (Eqn HL-22)
Z j =1 c c j =1
2 jL 2 jH
( j − 1) + ∑ F t − 2 jL − 2 jH
n n
FMF (t ) = F (t ) − ∑ F t − − (Eqn HL-23)
j =1 c c j =1 c c
As for the side friction R at xi as indicated in Figure HL-4, similar to the generated
upward waves, we can put down
1 1 n 2 x 2 jL 2 jH 1 n 2 xi 2 jL 2 jH
v MRu (t ) = − ∑ Ri t − i − − + − ∑ Ri t − − − ( j − 1)
Z 2 j =0 c c c 2 i =0 c c c
(Eqn HL-24)
1 2 x 2 jL 2 jH 2 x 2 jL 2 jH
( j − 1)
n n
FMRu (t ) = ∑ Ri t − i − − − ∑ Ri t − i − −
2 j =0 c c c i =0 c c c
(Eqn HL-25)
If there are N segments each giving friction forces R1 , R2 …… RN , then
− 1 N n 2 xi 2 jL 2 jH N n 2 xi 2 jL 2 jH
v MRu (t ) = ∑∑ Ri t − − − + ∑∑ R t − − − ( j − 1)
c i =1 j =0
i
2Z i =1 j =0 c c c c c
(Eqn HL-26)
1 N n
2 x 2 jL 2 jH N n
2 xi 2 jL 2 jH
FMRu (t ) = ∑∑ Ri t − i − − − ∑∑ R t − − − ( j − 1)
c i =1 j =0
i
2 i =1 j =0 c c c c c
(Eqn HL-27)
Similarly for the downward waves,
− 1 N n 2 xi 2 jL 2 jH
( j − 1) + ∑∑ Ri t − 2 xi − 2 jL − 2 jH
N n
vMRd (t ) = ∑∑ Ri t − − −
2 Z i =1 j =0 c c c i =1 j =0 c c c
(Eqn HL-28)
2 x 2 jL 2 jH
( j − 1) − ∑∑ Ri t − 2 xi − 2 jL − 2 jH
N n N n
FMRd (t ) = ∑∑ Ri t − i −
1
−
2 i=1 j =0 c c c i=1 j =0 c c c
(Eqn HL-29)
The signal v M and FM as detected by the sensor is the sum of the above.
vM = v MF + vMRu + vMRd (Eqn HL-30)
FM = FMF + FMRu + FMRd (Eqn HL-31)
Energy loss in the form of radiating damping to the surrounding has been ignored in the
above derivation. So error can be more significant if the testing time is long involving
many time steps.
L-6
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
(Eqn HL-33) represents the basic equation for the Case Method. However, RT
comprises both the static and dynamic components, i.e.
RT = Rstatic + Rdynamic ⇒ Rstatic = RT − Rdynamic . (Eqn HL-34)
Rstatic is to be found, which is the capacity of the pile during its service life.
Assuming Rdynamic originated from the pile tip and that Rdynamic is directly proportional
to the velocity where the constant of proportionality is a “damping coefficient” J p . That
is
Rdynamic (t ) = J p vtoe (t ) (Eqn HL-35)
When the wave generated by the blow at top reaches the pile tip, we can write
1 N
Ftoe = FM (t ) − ∑ Ri (t ) = FM (t ) − RT (t )
1
(Eqn HL-36)
2 i=1 2
2 1
vtoe = 2vd = 2 toe = FM (t ) − RT (t ) = [2 FM (t ) − RT (t )]
F 1
(Eqn HL-37)
Z Z 2 Z
Rstatic (t1 ) =
(1 − J c ) [F (t ) + Zv (t )] + (1 + J c ) F t + 2 L − Zv t + 2 L (Eqn HL-38)
M 1 M 1 M 1 M 1
2 2 c c
L-7
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
The Case Formula for the ultimate static resistance of the Pile is as follows :
Rstatic (t1 ) =
(1 − J c ) [F (t ) + Zv (t )] + (1 + J c ) F t + 2 L − Zv t + 2 L (Eqn HL-38)
M 1 M 1
2 c
M 1 M 1
2 c
By (Eqn HL-38), the ultimate static resistance of the pile at time t1 can be estimated if
the Pile Driving Analyzer (PDA) can produce readings of forces and velocities at time
2L
which are FM (t1 ) , vM (t1 ) ; FM t1 +
2L
t1 (any chosen time) and t1 + ,
c c
2L
vM t1 + and with the assumed values of J c . In the equation, the following
c
symbols are re-iterated :
A worked example to demonstrate the use of the formula using a hypothetical pile is as
follows :
Data :
L-8
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
The following graph in Figure HL-5 shows the plot of the measured forces and velocities
at the top level of a pile (length 46.8m) by a typical PDA test during a particular blow by
a hammer. The first peaks of force and velocity indicate the peak values upon the
arrival of the wave at the top without reflection and the later wave forms are results of
superimposition of the upward and downward waves comprising reflected waves. The
second peak in the force wave after time 18.40msec is likely due to superimposition of
the reflected wave generated at the pile tip.
Figure HL-5 – Typical Plot of Measured Forces and Velocities of a Pile by PDA Test
The recorded values are tabulated in the following table and the ultimate static resistances
of the pile for J c varying from 0.4 to 0.9 are calculated in accordance with (Eqn HL-38).
In the table, tc1 = t1 + 2 L / c = t1 + 18.4 msec.
(t1 ) (msec) (kN) (m/sec) (kN) (m/sec) J c = 0.4 J c = 0.5 J c = 0.6 J c = 0.7 J c = 0.8 J c = 0.9
0 7750 6.66 6400 0.53 8682.07 8199.82 7717.56 7235.30 6753.05 6270.79
3.68 3200 2.45 6350 -0.43 6600.23 6641.21 6682.19 6723.16 6764.14 6805.12
7.36 4185 2.88 4923 -1.52 6925.93 6884.38 6842.83 6801.28 6759.73 6718.18
11.04 4050 1.6 3125 -2.17 5708.75 5695.38 5682.01 5668.64 5655.27 5641.90
14.72 6875 0.87 3125 -2.60 6650.85 6563.15 6475.44 6387.74 6300.03 6212.33
18.40 6400 0.53 1750 -2.92 5686.60 5591.97 5497.34 5402.70 5308.07 5213.44
Maximum Resistance 8682.07 8199.82 7717.56 7235.30 6764.14 6805.12
Table HL-1 – Estimation of Ultimate Static Resistance of a Hypothetical Pile by the Case Method
The appropriate value of J c is dependent on the type of soil at the pile toe. GEO
Publication 1/2006 quotes values ranging from 0.05 for clean sand to 1.1 for clay in its
Table 9.2. For an appropriate chosen value of J c , the ultimate static resistance of the
L-9
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
pile should be the maximum value identified for choices of t1 as listed in the last row of
Table HL-1.
Figure HL-6 shows schematically the “Smith Model” for dynamic analysis of a pile. In
the model the pile is idealized into a series of “lumped masses” connected by elastic
springs. In the wave equation analysis, the set and the ultimate static resistance of the
pile can be calculated under the assumed values of various parameters during driving.
Hammer impact
W1 velocity Vh
Hammer
W3
W4
W5
Ksq(1+J×vn) as generally
the quake q will be
exceeded.
W11
W12
Pile end-bearing
L-10
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
In the CAPWAP analysis, the matching of forces and velocities with time between the
measured values and those calculated values by the wave equation (transformed into a
numerical approach developed by Smith (1960)) under various sets of assumed parameters
can be done for a pre-determined hammer blow. Good matching can justify the validity of
the assumed parameters and thus the ultimate static resistance of the pile can be calculated.
The following Figure HL-7 shows good matching between the measured force and the
calculated force and measured velocity with computed velocity using the wave equation (in
numerical form) for an actual blow on a pile.
Figure HL-7 – Typical Graphs showing Good Matching between the Measured Forces and
Calculated Forces with Time
Another function of the PDA test is the assessment of pile shaft integrity through the
examination of anomalies in the wave forms. Figure HL-8 displays the wave forms of a
force wave (the P wave) and a Z ⋅ v wave (impedance as defined by (Eqn HL-6) times
wave velocity which is a force generated by the wave where the particle velocity is v )
obtained in a PDA test of a steel H-pile. The crossing of the P curve and Z ⋅ v
curves indicates an anomaly and the integrity number is estimated to be 0.8. The depth
of the anomaly below ground can also be located which is the arithmetic product of the
wave speed and the time between the start of the test and the time when the reflected
wave has reached the sensor at the top. The wave speed is a constant for a material
which is 5060 m/sec in steel.
L-11
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HL
The pile is finally extracted from the ground and it is noticed that it is bent as shown in
the photograph also in Figure HL-8, the location of which agrees with the assessment
described above.
.
Figure HL-8 – Wave Forms of P and Z ⋅ v of a Pile undergoing PDA Test and Photograph
showing the Defected Portion
L-12
Appendix HM
Closed Form Solution for the Bearing Capacity Factor Nq in accordance with Berezantsev
HM.1 General Review of Bearing Capacity Factors for End Bearing Piles
As a well known phenomenon, a pile can develop very substantial end bearing capacity
in soil at depth due to the high surcharge by the weight of the surrounding soil. As a
common design approach by most of the researchers, the ultimate bearing capacity of pile
in cohesionless soil is related to the effective overburden pressure at the pile base and the
pile base area as
M-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HM
Figure HM-2 – The Shapes of Failure Modes at the Pile Tips as assumed by (a)
Terzaghi and Berezantsev; (b) Meyerhof; (c) Vesic
M-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HM
As the original derivation of the formulae for determination of N q were usually lengthy
and complicated, use of these charts was comparatively convenient before the era of
computers. However, it should be even more convenient and accurate to use computer to
calculate the N q values based on the original formulae nowadays. Law & Li (2017)
has outlined the analytical procedure for determination of N q by Berezantsev (1961)
which is reproduced as follows. The analysis is easy to perform on spreadsheets.
Law & Li (2017) has referred to 鄭大同 (1979) which was based on Berezantsev et al
(1961) to derive the following procedures for the determination of N q a function of
and L d ratio. The detailed derivations of the equations are omitted.
tan
(i) Determine the l a ratio as l a 2e 4 2 2
sin (Eqn HM-2)
4 2
where a 0.5d
M-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HM
cot 1.2 0.26 cot e1.5 tan 1
(Eqn HM-9)
1 1 sin tan
(ix) Determine Bk
3 1 sin
e
1.5 M e tan (Eqn HM-10)
1 1 L
(x) Finally, N q Ak Bk T (Eqn HM-11)
L / d 2 d
Using the above, Figure HM-4 as follows is constructed which agrees very well with
Tomlinson (2008).
M-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HM
4 2
l d 0.5l a 2.282
k1 l d 0.5 2.782
2 tan tan 2.690
4 2
2
2 L
tan k1 cot
1
2
4 2 d 4 2 k1
ED tan k1
1
L
4 2 1 L
tan 1 2 2 d
L
k1 4 2d d
0.514
k 2 0.25 ED 2k1 tan
T 1 0.733
k1 0.25
2
tan
sin 2e 2 2 2 cos
4 2 2 2.171
M
2 2 tan 2
cos e sin
2 4 2
2 tan tan 0.729
4 2
cos0.5 e( 0.5 0.5 ) tan 0.5
M 1 1 e1.5 tan
1 cos cos0.5
1 sin 1.5 tan 3
Ak 0.77 cot 4 2 e 82.454
3 4 2
cot 1.2 0.26 cot e1.5 tan 1
1 1 sin tan
Bk
3 1 sin
e
1.5 M e tan 75.319
1 1 L
Nq Ak BkT 59.313
L / d 2 d
M-5
Appendix HN
Due to overlapping of the soil columns and rock cones for piles against uplift as
illustrated by Figures 5.1 and 5.2 of the Code, the shaded portions of the soil column and
rock cone on the top right portion of Figure HN-1 should be deducted from calculation of
effective weight for a pile against uplift. Mathematical expressions for the
determination of the geometric volumes of the overlapped portions are presented in the
first part of this appendix.
R Ro R
r θ
D
Plan area of Soil Column
above Rock
Overlapped area between 2 adjacent
r d Overlapped
circular piles (above rock head
Portion of
stratum) y Rock Cone
dcotα
R − y tαn α
d − y tαn α
α
Elevation of r
Rock Cone
Horizontal Section at y
below Junction
between Soil Column
and Rock Cone
Figure HN-1 – Geometrical Shapes due to Overlapping of Soil Columns and Rock Cones of
Two Adjacent Circular Piles
Consider a circular pile with R as its radius of the soil column as shown in Figure 5.1
of the Code. If its soil column overlaps with another pile of radius of soil column Ro
with centre to centre distance D as shown in the top left portion of Figure HN-1, the
distance r can be determined through the application of the cosine rule as
N-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HN
R 2 + D 2 − Ro
2
r = R cosθ = (Eqn HN-1)
2D
Referring to the top right portion of Figure HN-1, the area of shaded portion is
R2 − r 2
As = R (2θ ) − r R − r = R sin
1 2 2 2 2 −1 − r R2 − r 2 (Eqn HN-2)
2 R
Vs = As L (Eqn HN-3)
Below the rock head level, the overlapped portion will be that beyond a vertical plane at
r from the centre a height of d cot α as illustrated in Figure HN-2, with α limited to
30o by the Code. Consider an “elementary slice” at depth y beneath rock head
stratum, the radius of the elementary slice is R − y tαn α and the width beyond
“touching line” with the adjacent circular pile is d − y tαn α as illustrated in Figure
HN-2. So the area of the overlapped portion by (Eqn HN-2) for one pile is
(R − y tan a )2 − r 2
A( y ) = [R − y tan a ] sin
−1
−r (R − y tan a )2 − r 2
2
R − y tan a
The volume of the elementary slice will be A( y )dy . Integrating over the height of
overlapping of d cot α , the volume of the overlapping portion of the rock cone is
d cot α
Vr = ∫ A( y )dy
0
cot α 3 r R2 − r 2
Vr = r ln + R 3 sin −1 − 2 Rr R 2 − r 2 (Eqn HN-4)
3 R− R −r
2 2
R
d cot α
Vr ≈ As (Eqn HN-5)
3
where As is taken from (Eqn HN-2).
N-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HN
The above geometric expressions can be used to evaluate the volume of soil columns and
rock cones as required by clause 5.3.3 of the Code.
HN.2 Worked Example HN-1 – Ultimate Uplift Resistance of a Single Large Diameter
Bored Pile by Weight of Rock Cone and Soil Column
GRL
GWL
Pile Loading
D.L. = 30000kN
Dmin = 26000kN
LL = 12000kN
Wind W = 12000kN
Uplift, U = 14500kN
V1
d1 = 35m
Density of Soil taken as 19kN/m3
r1
Density of Rock taken as 22 kN/m3
Density of concrete taken as 24.5kN/m3
Soil
Density of water taken as 9.8kN/m3
Check for Allowable Bond Resistance to Table 2.2 of the Code (under permanent tension
condition)
Allowable Bond Resistance from Rock Rbond = 2.5 × π × 4.5 × 350 = 12370.02kN
N-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HN
Check for Ultimate Anchorage and Allowable Anchorage to Cl. 5.1.6 of the Code
Dmin + 0.9Ru – 2.0Ia – 1.5Ua – 1.5W = 26000 + 0.9 × 17197 – 2 × 0 – 1.5 × 14500 – 1.5 ×
12000 = 1727 kN > 0
HN.3 Worked Example HN-2 – Ultimate Uplift Resistance of Group of Large Diameter
Bored Piles by Effective Weight of Soil Column and Rock Cone
Consider a group of 4 large diameter bored piles, each of same geometry as in Worked
Example HN-2 with centre to centre 6.0m as shown in Figure HN-3.
6m
6m
Figure HN-3 – Overlapping of Soil Columns and Rock Cones of 4 Large Diameter Bored
Piles for Worked Example HN-2
Consider one single pile, the volumes of the overlapped portion of the soil column and
rock cone of a pile are to be worked out.
By (Eqn HN-1), the distance r is calculated as (the radius of the soil column is
r1 = R = 3.848 m as per calculation in Worked Example HN-1)
R 2 + D 2 − Ro 3.8482 + 62 − 3.8482
2
r= = = 3m
2D 2×6
(the symbols being defined in Figure HN-1. It can readily be seen that r = 0.5 D if
R = Ro )
By (Eqn HN-2), the area of the overlapped portion in the soil column is
N-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HN
R2 − r 2
As = R 2 sin −1 − r R 2 − r 2 = 2.791 m2;
R
As there are 2 overlaps, the total volume of soil to be deducted is 97.685 × 2 = 195.37 m3
and the weight of the soil column is
cot α 3 r R2 − r 2
Vr = r ln + R 3 sin −1 − 2 Rr R 2 − r 2 = 1.6 m3;
3 R− R −r
2 2
R
Or by (Eqn HN-5),
d cot α
Vr ≈ As = 1.366 m3
3
A driven H-pile (305×305×223 kg/m) 46m long encounters soil of N-values as shown in
Table HN-1. Adopting the Effective Stress Method τ s = βs v ' capped at 120kPa in
accordance with clause 5.3.3(3)(ii) of the Code, Without trial pile, β = 0.2 , the ultimate
skin friction against uplift under transient tension worked out is worked out by Table
HN-1.
N-5
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HN
Table HN-1 – Computation of Ultimate Uplift Resistance of a Driven Pile (Effective Stress
Method)
As the perimeter of the pile is 1.326m (the enclosing rectangle for the pile section), the
total ultimate tension capacity against uplift for transient load on the pile is Ru-transient =
1943.04kN/m × 1.326m = 2576kN.
The ultimate tension capacity against uplift for permanent load is Ru-permanent = 2576/2 =
1288kN.
Taking a factor of safety = 3, the allowable uplift resistance of the pile is Ra-transient =
2576/3 = 859kN for transient load and Ra-permanent = 1288/3 = 429kN for permanent load.
Check for Ultimate Anchorage and Allowable Anchorage to Cl. 5.1.6 of the Code
N-6
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HN
A driven H-pile (305×305×223 kg/m) 46m long encounters soil of N-values as shown in
Table HN-2. Without trial pile, the empirical correlation with SPT N-values as the
ultimate value τ s = 0.75 N is adopted in accordance with clause 5.3.3(3)(iii) of the Code
with τ s capped at 60kPa (or SPT N capped at 80), the ultimate skin friction against
uplift under transient tension is worked out by Table HN-2.
As the perimeter of the pile is 1.326m, the total ultimate tension capacity against uplift
for transient load on the pile is Ru-transient = 1849.5kN/m × 1.326m = 2452.44kN.
The ultimate tension capacity against uplift for permanent load is Ru-permanent = 2452.44/2
= 1226.22kN.
Taking a factor of safety = 3, the allowable uplift resistance of the pile is Ra-transient =
2452.44/3 = 817.48kN for transient load and Ra-permanent = 1226.22/3 = 407.74kN for
permanent load.
N-7
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HN
Check for Ultimate Anchorage and Allowable Anchorage to Cl. 5.1.6 of the Code
HN.6 Worked Example HN-5 – Effective weight of the Soil Columns and Cones of a
Group of Floating Piles
The effective weight of the soil columns and cones of a pile group comprising 9 driven
H-piles (305×305×223 kg/m) against uplift is as shown in Figure HN-4. The piles are
4m centre to centre apart. With the B and D dimension of the H-pile as B = 325.7mm and
D = 337.9mm, the plan dimensions of the overlapping rectangles and circles are as shown
in Figure HN-4.
Lot boundary
6.163m 4m 4m
6m 4.163m 4.163m 6m
4.169m
SPT N ≥ 30
8m
6m Level Y
4.169m
24m
6m
4
(2-0.163)
1
2m ×4=7.348m
2m
4.169m
4.169m
Level Y
N-8
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HN
Ignoring the lot boundary first, the plan area of the soil column at ground level is
π × 62
8.326 × 8.338 + 2 × 8.326 × 6 + 2 × 8.338 × 6 + 4 × = 382.488 m2
4
The soil volume beneath Level X can be regarded as comprising a square cylinder, 4
prisms and 4 quadrant circular cones at the corners as shown in Level Y in Figure HN-4.
So the volume is
1 1 1 1
8.326 × 8.338 × 24 + 2 × × 6 × 8.326 × 24 + 2 × × 6 × 8.338 × 24 + 4 × × × π × 62 × 24
2 2 4 3
= 1666.133 + 1198.944 + 1200.672 + 904.779
= 4970.528 m3
However, there are 4 “pyramids” of plan area (4 − 0.326 )(4 − 0.338) = 13.454 m2 and
height 7.348m among the pile tip that need to be deducted. The volume of these 4
“pyramids” is
1
4 × × 13.454 × 7.348 = 131.813 m3
3
If the lot boundary is considered, volume beyond the lot boundary is to be determined for
deduction. The plan area of the portion is (with the use of (Eqn HN-2)
62 − 42
8.338 × 2 + 62 sin −1 − 4 62 − 42 = 29.066 m2, giving a volume of
6
29.066 × 10 = 290.66 m3 above Level X.
For the portion below Level X comprising a prism and a cut cone with volume that can
be calculated by (Eqn HN-4), the volume is
1 4 4 3 62 − 42
× 8.338 × 2 × 8 + 4 3 ln + 6 sin −1 − 2 × 6 × 4 62 − 42
3
2 6− 6 −4 6
2 2
= 104.842 m3.
So volume of soil beyond lot boundary to be deducted is 290.66 + 104.842 = 395.502 m3.
Net soil volume after deduction of the portion beyond lot boundary is
8663.587 − 395.502 = 8268.085 m3.
If the buoyant unit weight of soil is 19 − 9.8 = 9.2 kN/m3, the total soil weight for
balancing uplift is 8268.085 × 9.2 = 76066.392 kN.
N-9
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HN
Shared among the 9 identical piles, the effective weight available for each pile against
uplift is 76066.392 / 9 = 8541.82 kN.
As the effective weight available for each pile is greater than the structural capacity of the
pile, the bond friction of soil on pile shaft is the controlling factor in this case.
N-10
Appendix HO
(i) Mindlin’s Equations and their integrated forms (Vaziri et al 1982) which are
applicable to calculations of displacements inside a semi-infinite homogeneous
elastic medium due to loads applied in the medium are adopted for estimating
pile cap lateral displacement due to lateral loads. The use of Mindlin’s
Equations are considered to give conservative estimations as long as parameters
of the upper layer of soil embedding the pile cap only are used in the estimation,
as the deeper and generally harder soil beneath will tend to reduce the soil
movement;
(ii) Basically the original form of Mindlin’s Equation which calculates horizontal
displacement x at any point in a horizontal direction in a semi-infinite
homogeneous elastic medium due to a horizontal point load Q acting in the
same direction and in the same medium is used. By considering the vertical
face of the pile cap as exerting a serious of point loads on soil idealized as an
elastic medium, and as we are only interested in the displacement of the soil
immediately at the wall face, we can simplify Mindlin’s Equation as follows :
where G and are the shear modulus and Poisson’s ratio of the soil and the
other dimensional symbols are explained in Figure HO-1.
Ground Level
c
c R2 Pile Cap
Vertical Face
Point of z
Q Pile Cap
Application Point with Vertical
of Load Q horizontal Face
R1 displacement
x as created
by Q as per
(Eqn HO-1)
Wall Front Elevation Side Elevation
Using the coordinate system as shown in Figure HO-2, the lateral deflection at
O-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HO
any point u, v due to load from the rectangular pile cap face can be expressed
as summation of effects due to all points x, y on the face as
c1 dy (x,y)
dx
(u,v)
b/2 b/2
Figure HO-2 – Coordinate System for Calculation of Lateral Displacement of Pile Cap
(Eqn HO-2) can be used to calculate the lateral deflections due to a rectangular patch
of lateral load of any load intensity as long as the elastic limits of the soil medium are
not exceeded. If the load is a uniformly distributed load, q in (Eqn HO-2) is a
constant. Poulos and Davis (1980) have quoted the closed form solutions by
Douglas and Davis (1964) for the upper and lower corners of a rectangular patch of a
uniformly distributed load. The deflection of any point X within the rectangular
patch can therefore be determined by the summation of effects due to the 4 rectangles
as demonstrated in Figure HO-3 which is extracted from Law & Cheng (2014).
Horizontal Displacement of X is
A B
X xL ( A) xL ( B ) xU (C ) xU ( D )
X where xL( A) is the displacement at the lower
C D corner of rectangle A due to u.d.l. acting on A etc.
O-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HO
Yet the algebraic expressions for the solutions are very lengthy. So instead Law &
Cheng (2014) have evaluated the double integral in (Eqn HO-2) directly by numerical
methods with the aid of modern computers which is simpler in formulation.
However, a pile cap exerting a horizontal load on the soil medium normally has a
very large in-plane stiffness such that its front face cannot deform as discussed in
HO.2 and HO.3. Effectively the plane section containing the front face of the pile
cap should remain plane after soil movement named by Law & Cheng as “rigid face”.
In order to satisfy Mindlin’s Equations, it follows that the horizontal pressures on the
front face of the pile cap should vary such that the horizontal movements of the soil
remain intact with the cap in a vertical plane.
The proposed approach is based on numerical analysis. The vertical face of the pile
cap confronting the soil is divided into a number of equal rectangular elements each
of width b' and depth d ' , centre at y i , z i and each having a uniform pressure
pi to be determined as shown in Figure HO-5 extracted from Law & Cheng (2014).
The displacement at the centre of the element i will be the summation of effects
from loads of itself and all other elements.
O-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HO
c2 y
b’
c1 ( xi , yi ) d’
Figure HO-5 – Front face of a Pile Cap divided into a Number of Equal Rectangular
Elements
The reduced form of the Mindlin’s Equation as listed in (Eqn HO-1) in Figure HO-1 for
a point load will be used to calculate the contribution to the displacement of element i
due to an element j by considering the element j to be exerting a point load of
magnitude p j b'd ' .
3 4 1 2 zi z j 41 1 2
p j b' d '
ij (Eqn HO-3)
16G 1 R1 R2 R2
3
R2 zi z j
where zi 0.5c1 c2 yi ; z j 0.5c1 c2 y j
R1 x x y y
i j
2
i j
2
; R2 x x c c
i j
2
1 2 yi y j
2
However, direct application of (Eqn HO-4) to calculate effect on element i due to the
load on itself cannot be carried out as R1 will be zero. So the integrated forms of the
equations (Eqn HO-2) and (Eqn HO-3) in Figure HO-2 have to be used with the
average displacement approach as discussed in para. HO.2 with the approximation that
the pressure is uniform within the small area represented by the joint. By this
approach, the displacements at the four corners and the centre of the element i are
calculated by the integrated forms of the equation and the weighted mean value is then
taken as ii due to a unit load applied to the element. The coefficient f ii is
ii
obtained from f ii
pi
So the total deflection at the centre of an element i is
i f ii pi f ij p j
i j
O-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HO
f ii pi f ij p j i 0 (Eqn HO-6)
i j
However, i follows a linear deflection. Let the deflection at the centre of the front
face of the cap be 0 , then the deflection of the centre of element i is 0 my i
where m is a constant. So (Eqn HO-6) can be re-written as
f ii pi f ij p j 0 myi 0 (Eqn HO-7)
i j
N equations will be formulated if the pile cap front face is divided into N elements.
For summation of the total force, under the application of the total external force P
P
pib' d ' P pi b' d ' (Eqn HO-8)
For summation of the total moment about the centre under the action of the external
moment (torsional about a vertical axis through the centre of the pile cap face)
M
pib' d ' yi M pi yi b' d ' (Eqn HO-9)
From (Eqn HO-7) to (Eqn HO-9), there will be N 2 equations solving N 2
unknowns which comprise the N nos. of pi , the centre deflection 0 and the
constant m . With determination of 0 and m , the deflection profile of the whole
pile cap vertical face can be determined. Re-arranging (Eqn HO-7) to (Eqn HO-9) in
matrix form, (Eqn HO-10) is formulated as follows :
y1 y2 y3 . . . y N 1 yN 0 0 p1 M
1 1 1 . . . 1 1 0
0 p2 P
f1,1 f1, 2 f1,3 . . . f1, N 1 f1, N 1 y1 p3 0
f 2,1 f 2, 2 f 2,3 . . . f 2, N 1 f 2, N 1 y2 . 1 0
. . . . . . . . . . . b' d ' 0
. . . . . . . . . . pN 0
. . . . . . . . . . 0 0
f N ,1 f N ,2 f N ,3 . . . f N , N 1 f N ,N 1 y N m 0
(Eqn HO-10)
The approach as described in HO.4 is applied to the solution of the pile cap face as
described in Worked Example HO-1. For comparison purpose, the applied load on
the face is first set to 50 8 2 800 kN which is the same as the applied load on the
“flexible face”.
The deflection becomes a unique value of 16.72mm which is smaller than the average
value of 18.19mm arrived in Worked Example HO-1.
However, very high pressures at the corners and edges result and the pressures
increase with an increasing number of “meshes” (division of the face in a number of
O-5
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HO
grids). Law & Cheng (2014) points out that the pressures should be at infinity
which is a common phenomenon in the application of continuum theory. However,
in actual practice, the soil would “yield” at certain stress levels and therefore another
parameter, which is the yield stress of soil, should be introduced into the calculation.
As an acceptable approach, the passive resistance of the soil which is dependent on
the vertical effective stresses in the soil can be used to determine the yield stress.
The next consideration is on the on-plan rotation of the cap. For a “rigid face”, to
resist a pure torsional moment, the pressures on different halves of the face (the two
halves being formed by a vertical line through the centre of the face) are in opposite
directions. While soil cannot sustain tensile stresses, the opposite pressures have to
be derived from compression on the far end of the cap. As it is unlikely that there
are interactions between the pressures at the opposite faces of the cap as they are far
apart through a solid cap structure, the f i , j coefficients in (Eqn HO-10) should be
set to zero if point i and point j belong to different faces. By this modification,
applying a torsional moment of M 1200 kNm to the face, the rotation is
m 0.002297 rad. This is obtained by setting M 1200 in (Eqn HO-10) and
P 0 in addition to modification of the f coefficients. Again peak stresses occur
at the edges of the face. Law & Cheng (2014) however conclude that the elastic
analysis as described above is the most conservative approach.
In order to eliminate the use of yield stresses of the soil so as to simplify the problem,
Law & Cheng (2014) discuss that conservative results for the cap movements
comprising translation and rotation can be achieved by (i) adopting the average
deflection due to a uniformly distributed pressure on a vertical face as the cap moves
laterally; (ii) adopting the rigid face approach for the determination of rotation despite
the occurrence of the high stresses along the edges and the corners. Based on this
approach and the assumptions, Law & Cheng (2014) prepared tables containing
coefficients for determination of translational and on-plan rotational stiffnesses of a
pile cap which are reproduced in Tables HO-1(a) to (e) and HO-2(a) to (e). By the
term “translational stiffness” of a pile cap, we refer to the horizontal shear acting on a
pile cap required to produce unit translation and similarly for the rotational stiffness,
it is the on-plan moment required to produce unit rotation. In these tables, the
notations for determination of the depth and dimensions of the pile cap face by Poulos
2c 2c
& Davis (1980) are used by which K1 1 and K 2 2 where c1 , c2 are
b b
defined in Figure HO-2 and b is the width of the cap. In Tables HO-1(a) to (e), the
coefficients obtained should be multiplied by bG to arrive at the estimated
translation stiffness while those for Tables HO-2(a) to (e) be multiplied by b3G to
obtain the rotational stiffness.
2 3.5 2 1.5
As a check, for Worked Example HO-1, K1 0.875 , K 2 0.375 ,
8 8
the coefficient for translation as interpolated in Figure HO-1(b) is 2.960. When this
O-6
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HO
E 5000
coefficient is multiplied by bG , where G 1851.85 kN/m2,
21 2 1 0.35
the translation stiffness is 2.960 8 1851.85 43851.85 kN/m. Upon application
of the horizontal shear of 8 2 50 800 kN, a lateral deflection of
800
0.01824 m or 18.24mm is obtained, which is very close to the value
43851.85
obtained by direct analysis of 18.19mm. For rotation, the coefficient interpolated in
Table HO-2(b) is 0.5446 for Worked Example HO-2. When this coefficient is
multiplied by b3G , the rotational stiffness is 0.5446 83 1851.85 516361 kNm.
Upon application of the torsional moment of 1200kNm, the rotation is
1200
0.002324 rad which is again close to the value obtained by direct analysis
516361
of 0.002297rad.
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 1.356 – – – – – – – – – – –
0.2 1.674 1.615 – – – – – – – – – –
0.3 1.929 1.903 1.745 – – – – – – – – –
0.4 2.154 2.139 2.039 1.832 – – – – – – – –
0.5 2.359 2.351 2.276 2.137 1.896 – – – – – – –
0.6 2.551 2.546 2.487 2.378 2.211 1.946 – – – – – –
0.7 2.735 2.732 2.681 2.591 2.458 2.270 1.986 – – – – –
0.8 2.912 2.909 2.864 2.786 2.674 2.523 2.319 2.019 – – – –
0.9 3.080 3.081 3.040 2.970 2.871 2.742 2.576 2.359 2.046 – – –
1.0 3.245 3.245 3.210 3.145 3.056 2.942 2.800 2.622 2.393 2.070 – –
1.1 3.406 3.406 3.373 3.315 3.232 3.129 3.002 2.848 2.660 2.423 2.090 –
1.2 3.563 3.563 3.532 3.478 3.404 3.306 3.191 3.053 2.890 2.694 2.448 2.107
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 1.426 – – – – – – – – – – –
0.2 1.755 1.686 – – – – – – – – – –
0.3 2.018 1.984 1.818 – – – – – – – – –
0.4 2.250 2.229 2.123 1.908 – – – – – – – –
0.5 2.462 2.448 2.369 2.223 1.974 – – – – – – –
0.6 2.661 2.651 2.587 2.474 2.300 2.026 – – – – – –
0.7 2.850 2.842 2.788 2.694 2.556 2.362 2.067 – – – – –
0.8 3.033 3.026 2.978 2.896 2.780 2.624 2.413 2.102 – – – –
0.9 3.209 3.204 3.160 3.087 2.985 2.851 2.680 2.455 2.131 – – –
1.0 3.379 3.375 3.336 3.268 3.177 3.058 2.911 2.727 2.491 2.155 – –
1.1 3.545 3.541 3.506 3.445 3.359 3.252 3.121 2.962 2.768 2.522 2.176 –
1.2 3.707 3.704 3.670 3.614 3.537 3.436 3.317 3.175 3.007 2.803 2.549 2.195
O-7
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HO
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 1.505 – – – – – – – – – – –
0.2 1.847 1.768 – – – – – – – – – –
0.3 2.119 2.078 1.905 – – – – – – – – –
0.4 2.360 2.332 2.222 1.998 – – – – – – – –
0.5 2.579 2.560 2.477 2.326 2.067 – – – – – – –
0.6 2.786 2.770 2.704 2.586 2.407 2.122 – – – – – –
0.7 2.982 2.970 2.912 2.816 2.673 2.473 2.167 – – – – –
0.8 3.171 3.160 3.110 3.026 2.907 2.745 2.527 2.204 – – – –
0.9 3.355 3.344 3.299 3.224 3.119 2.982 2.805 2.572 2.235 – – –
1.0 3.532 3.524 3.482 3.414 3.319 3.198 3.046 2.856 2.611 2.261 – –
1.1 3.705 3.697 3.660 3.596 3.510 3.400 3.265 3.101 2.899 2.644 2.284 –
1.2 3.874 3.867 3.831 3.774 3.693 3.592 3.469 3.322 3.149 2.937 2.673 2.304
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 1.596 – – – – – – – – – – –
0.2 1.952 1.865 – – – – – – – – – –
0.3 2.235 2.188 2.009 – – – – – – – – –
0.4 2.485 2.453 2.339 2.108 – – – – – – – –
0.5 2.715 2.691 2.606 2.451 2.183 – – – – – – –
0.6 2.930 2.911 2.843 2.723 2.539 2.243 – – – – – –
0.7 3.135 3.119 3.062 2.963 2.817 2.610 2.292 – – – – –
0.8 3.333 3.319 3.268 3.183 3.061 2.895 2.669 2.333 – – – –
0.9 3.525 3.512 3.466 3.390 3.284 3.143 2.960 2.719 2.367 – – –
1.0 3.711 3.700 3.657 3.589 3.493 3.370 3.214 3.017 2.762 2.397 – –
1.1 3.891 3.882 3.845 3.780 3.693 3.581 3.443 3.274 3.065 2.799 2.422 –
1.2 4.069 4.060 4.025 3.967 3.885 3.782 3.657 3.507 3.327 3.107 2.832 2.445
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 1.702 – – – – – – – – – – –
0.2 2.074 1.983 – – – – – – – – – –
0.3 2.371 2.321 2.138 – – – – – – – – –
0.4 2.633 2.599 2.485 2.248 – – – – – – – –
0.5 2.874 2.849 2.764 2.608 2.332 – – – – – – –
0.6 3.101 3.081 3.014 2.893 2.706 2.399 – – – – – –
0.7 3.317 3.300 3.244 3.146 2.999 2.786 2.455 – – – – –
0.8 3.525 3.511 3.462 3.379 3.256 3.087 2.854 2.502 – – – –
0.9 3.727 3.714 3.671 3.597 3.492 3.349 3.162 2.911 2.542 – – –
1.0 3.925 3.912 3.873 3.807 3.713 3.588 3.429 3.226 2.961 2.577 – –
1.1 4.116 4.107 4.070 4.009 3.924 3.812 3.672 3.498 3.282 3.004 2.607 –
1.2 4.303 4.295 4.263 4.205 4.127 4.025 3.898 3.745 3.559 3.331 3.042 2.633
O-8
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HO
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 0.188 – – – – – – – – – – –
0.2 0.260 0.229 – – – – – – – – – –
0.3 0.326 0.299 0.247 – – – – – – – – –
0.4 0.387 0.362 0.320 0.258 – – – – – – – –
0.5 0.443 0.419 0.384 0.333 0.265 – – – – – – –
0.6 0.502 0.477 0.442 0.398 0.342 0.270 – – – – – –
0.7 0.554 0.534 0.501 0.458 0.408 0.348 0.273 – – – – –
0.8 0.616 0.589 0.558 0.516 0.467 0.415 0.353 0.276 – – – –
0.9 0.665 0.639 0.613 0.574 0.528 0.475 0.421 0.357 0.278 – – –
1.0 0.721 0.693 0.663 0.630 0.586 0.536 0.481 0.425 0.360 0.280 – –
1.1 0.763 0.746 0.717 0.680 0.642 0.595 0.543 0.486 0.429 0.362 0.281 –
1.2 0.804 0.799 0.770 0.733 0.692 0.651 0.602 0.548 0.490 0.431 0.364 0.282
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 0.196 – – – – – – – – – – –
0.2 0.270 0.238 – – – – – – – – – –
0.3 0.338 0.311 0.257 – – – – – – – – –
0.4 0.401 0.375 0.333 0.268 – – – – – – – –
0.5 0.460 0.434 0.398 0.346 0.275 – – – – – – –
0.6 0.520 0.495 0.458 0.414 0.356 0.281 – – – – – –
0.7 0.575 0.554 0.519 0.475 0.424 0.362 0.284 – – – – –
0.8 0.639 0.611 0.579 0.536 0.486 0.432 0.367 0.287 – – – –
0.9 0.690 0.663 0.636 0.596 0.548 0.494 0.438 0.371 0.289 – – –
1.0 0.747 0.719 0.688 0.654 0.609 0.557 0.501 0.442 0.374 0.291 – –
1.1 0.791 0.773 0.744 0.706 0.666 0.618 0.565 0.506 0.446 0.377 0.293 –
1.2 0.834 0.828 0.798 0.762 0.719 0.676 0.626 0.570 0.510 0.449 0.379 0.294
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 0.205 – – – – – – – – – – –
0.2 0.282 0.248 – – – – – – – – – –
0.3 0.352 0.324 0.269 – – – – – – – – –
0.4 0.418 0.391 0.347 0.281 – – – – – – – –
0.5 0.479 0.453 0.416 0.362 0.289 – – – – – – –
0.6 0.542 0.516 0.479 0.433 0.372 0.294 – – – – – –
0.7 0.599 0.578 0.542 0.497 0.444 0.380 0.298 – – – – –
0.8 0.665 0.637 0.604 0.561 0.508 0.452 0.385 0.301 – – – –
0.9 0.719 0.692 0.664 0.623 0.574 0.518 0.459 0.389 0.304 – – –
1.0 0.779 0.750 0.719 0.683 0.637 0.584 0.525 0.464 0.393 0.306 – –
1.1 0.825 0.807 0.777 0.738 0.697 0.647 0.591 0.530 0.468 0.396 0.307 –
1.2 0.870 0.864 0.834 0.796 0.752 0.708 0.656 0.598 0.535 0.471 0.398 0.309
O-9
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HO
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 0.216 – – – – – – – – – – –
0.2 0.296 0.261 – – – – – – – – – –
0.3 0.370 0.340 0.283 – – – – – – – – –
0.4 0.438 0.410 0.366 0.297 – – – – – – – –
0.5 0.503 0.476 0.438 0.382 0.305 – – – – – – –
0.6 0.569 0.542 0.504 0.456 0.394 0.312 – – – – – –
0.7 0.628 0.607 0.571 0.524 0.469 0.402 0.316 – – – – –
0.8 0.698 0.669 0.636 0.591 0.537 0.479 0.408 0.320 – – – –
0.9 0.755 0.728 0.699 0.657 0.606 0.548 0.486 0.413 0.323 – – –
1.0 0.818 0.789 0.757 0.720 0.673 0.617 0.556 0.492 0.417 0.325 – –
1.1 0.867 0.849 0.818 0.779 0.736 0.684 0.626 0.562 0.496 0.420 0.327 –
1.2 0.915 0.909 0.879 0.840 0.795 0.748 0.694 0.633 0.567 0.500 0.422 0.328
K2 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
K1
0.1 0.228 – – – – – – – – – – –
0.2 0.313 0.277 – – – – – – – – – –
0.3 0.391 0.361 0.302 – – – – – – – – –
0.4 0.463 0.435 0.390 0.318 – – – – – – – –
0.5 0.532 0.505 0.466 0.409 0.328 – – – – – – –
0.6 0.602 0.575 0.537 0.488 0.422 0.335 – – – – – –
0.7 0.665 0.644 0.608 0.559 0.503 0.432 0.341 – – – – –
0.8 0.740 0.711 0.678 0.632 0.576 0.514 0.439 0.345 – – – –
0.9 0.802 0.774 0.744 0.702 0.649 0.588 0.522 0.445 0.348 – – –
1.0 0.868 0.839 0.808 0.769 0.720 0.662 0.597 0.529 0.449 0.351 – –
1.1 0.920 0.904 0.873 0.833 0.788 0.734 0.673 0.605 0.534 0.453 0.353 –
1.2 0.974 0.967 0.937 0.898 0.852 0.802 0.745 0.681 0.611 0.539 0.456 0.355
The translational stiffness and rotational stiffness of the pile cap are useful as input to
analysis of the pile group against lateral shear as demonstrated in the worked example
in Appendix HQ. They can also be inputted into computer mathematical models for
analysis.
O-10
Appendix HP
The basic equation governed by elastic beam theory is used, by which the pile is treated
as a beam and the lateral deflection of the pile v , as related to the elastic support, can be
described by the differential equation as follows, without consideration of P-d effect :
d 4v
E p I p 4 = − K hv (Eqn HP-1)
dz
(Eqn HP-1) is in fact a particular case of (Eqn HI-1) of Appendix HI for study of the
buckling of a pile with the axial load P set to zero, i.e. the axial load effect is ignored.
Using also Terzaghi (1955)’s theory for the coefficient of horizontal subgrade reaction
and the finite difference method, (Eqn HP-1) can be similarly formulated as (Eqn HI-7)
by setting P = 0 leading to
L 5 i
vi −2 − 4vi −1 + 6 + 5 vi − 4vi +1 + vi + 2 = 0 (Eqn HP-2)
T N
The formulation of the support conditions of the pile ends are also identical to that in
Appendix HI except that for the free conditions as summarized in Table HP-1.
Table HP-1 – Restraint Conditions on Lateral Load Analysis on Pile by the Finite Difference
Method
The formulation of moments and lateral shears in the finite difference method is as
follows at the pile head are as follow :
d 2v v − 2v1 + v−1 1 L 2 MT 2
M = EpI p 2 = EpI p 2 ⇒ v − 2v + v = 2 (Eqn HP-3)
dz ( L / N )2
2 1 −1
N T p p
E I
Thus 4 additional equations comprising 2 at pile head (for support condition and / or
application of external shear or moment) and 2 at pile tip (both support conditions) can be
P-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
formed by the equations listed in Table HP-1 and (Eqn HP-2) to (Eqn HP-4) in regards to
the end restraint conditions at the head and tip of the pile, making up altogether N + 5
equations for solving all the N + 5 nos. of v values. Subsequently, the rotation,
v −v
moment and shear at the ith node can be back-calculated respectively as θ i = i +1 i −1 ;
2(L / N )
d2y vi +1 − 2vi + vi −1 d3y v − 2vi +1 + 2vi −1 − vi −2
M i = EI 2 = EI and Si = EI 3 = EI i + 2 .
dz ( L / N )2
dz 2( L / N )3
The lateral or rotational stiffnesses at the pile head can be determined by dividing the
applied shear or moments by the lateral displacement or rotation respectively obtained by
solving the N + 5 equations.
HP.2 Design Charts and Tables based on the Finite Difference Method
Design charts based on the solution of the equations described in HP.1 have, however,
been given in various publications including DM-7 (1971), Tomlinson (2001). In the
preparation of these charts, the equations for applied moment and shear used for analysis
were transformed from (Eqn HP-3) and (Eqn HP-4) to (Eqn HP-5) and (Eqn HP-6) as
follows with the incorporation of E p I p and nh into T as T = 5 E p I p nh so that the
whole set of equations is based on L / T and N only where N dictates accuracy.
2
1 L
v2 − 2v1 + v−1 = (for applied shear at pile head) (Eqn HP-5)
N2 T
3
2 L
v3 − 2v2 + 2v−1 − v−2 = 3 (for applied moment at pile head) (Eqn HP-6)
N T
vi +1 − vi −1 vi +1 − vi −1 ST 3 1 ST 2 MT 2 1 MT
× = × =
2(L / N ) 2(L / T ) / N
Rotation
EpI p T EpI p EpI p T EpI p
v − 2v + 2v − v v − 2vi +1 + 2vi −1 − v− 2 ST 3 EpI p MT 2 E p I p M
Lateral Shear E p I p i+2 i +1 i −1 −2 i+2 × =S × =
2(L / N )3 2(L / T )3 / N 3 EpI p T3 EpI p T3 T
Table HP-2 – Use of Coefficients for Determination of Displacements, Rotations, Shears and
Moments in Piles by the Finite Difference Method
P-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
Deflection Coefficient of Pile (Free Top Free Tip) under Moment Coefficient of Pile (Free Top Free Tip) under
Lateral Shear at Top of Pile with Different L/T Ratios Lateral Shear at Top of Pile with Different L/T Ratios
L/T=2 L/T=3 L/T=4 L/T=5 L/T=7 L/T=10 L/T=2 L/T=3 L/T=4 L/T=5 L/T=7 L/T=10
1 1
2 2
Deflection
3 of Pile = 3
Depth of Pile as a Multiple of T
6 6
7 7
8 8
9 9
10 10
In this Appendix, analysis by the Finite Difference Method as described in HP.1 and HP.2
has been carried out which takes into account the cases where the pile cut-offs are below
ground and the pile tip is either free or restrained from rotation or translation. Similar
coefficients are obtained which need to be multiplied by the constants listed in the last 2
columns of Table HP-2 to obtain the true values of deflections, rotations, shears and
moments as appropriate. Coefficients for the lateral deflections and moments for pile
cut-off levels at certain depths beneath ground and under lateral shear at the cut-off level
with different pile tip restraint conditions are listed in Tables HP-3(a) to (f), for various
L/T values. Intermediate values can be interpolated. It should be noted that the
moment coefficient is for determination of the maximum moment along the pile shaft
P-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
which takes place at the pile head if the pile head is restrained from rotation and at certain
depth below the pile head if the pile head is free to rotate.
Lateral Deflection Coefficient at Cut-off Level (dp) Coefficient for Maximum Moment (Mp)
Pile Length
as Multiple Ratio of Depth between Ground and the Cut-off Ratio of Depth between Ground and the Cut-off
of L/T Level of the Pile to the Total Pile Length Level of the Pile to the Total Pile Length
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.00 0.05 0.10 0.15 0.20 0.25 0.30
2 4.739 3.850 3.247 2.812 2.482 2.224 2.016 0.513 0.468 0.438 0.416 0.399 0.386 0.375
3 2.728 2.218 1.878 1.635 1.452 1.310 1.195 0.704 0.628 0.577 0.539 0.511 0.488 0.469
4 2.442 1.933 1.611 1.388 1.224 1.098 0.998 0.768 0.659 0.589 0.541 0.505 0.477 0.455
5 2.433 1.837 1.489 1.260 1.098 0.976 0.881 0.772 0.640 0.564 0.513 0.477 0.450 0.428
7 2.431 1.676 1.299 1.070 0.916 0.805 0.720 0.772 0.606 0.522 0.472 0.437 0.411 0.391
10 2.431 1.488 1.097 0.881 0.742 0.645 0.573 0.772 0.564 0.478 0.429 0.396 0.373 0.355
15 2.431 1.260 0.881 0.69 0.573 0.493 0.435 0.772 0.514 0.429 0.384 0.355 0.334 0.318
20 2.431 1.097 0.742 0.573 0.472 0.404 0.356 0.772 0.478 0.396 0.355 0.328 0.309 0.295
30 2.431 0.881 0.573 0.435 0.356 0.303 0.266 0.772 0.429 0.355 0.318 0.295 0.278 0.265
40 2.431 0.742 0.472 0.356 0.290 0.246 0.216 0.772 0.396 0.328 0.295 0.273 0.258 0.246
Table HP-3(a) – Deflection and Moment Coefficients for Pile with Free Head and Tip Unrestrained
from both Lateral Movement and Rotation due to Horizontal Shear at Cut-off Level
Table HP-3(b) – Deflection and Moment Coefficients for Pile with Head Restrained from Rotation and
Tip Unrestrained from both Lateral Movement and Rotation due to Horizontal Shear at Cut-off Level
Table HP-3(c) – Deflection and Moment Coefficients for Pile with Free Head and Tip Restrained from
Lateral Movement but Free to Rotate due to Horizontal Shear at Cut-off Level
P-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
Table HP-3(d) – Deflection and Moment Coefficients for Pile with Head Restrained from Rotation and
Tip Restrained from Lateral Movement but Free to Rotate due to Horizontal Shear at Cut-off Level
Table HP-3(e) – Deflection and Moment Coefficients for Pile with Head Pinned and Tip Restrained
from both Lateral Movement and Rotation due to Horizontal Shear at Cut-off Level
Table HP-3(f) – Deflection and Moment Coefficients for Pile with Head Restrained from Rotation and
Tip Restrained from both Lateral Movement and Rotation due to Horizontal Shear at Cut-off Level
Similarly, coefficients for rotation due to moments applied at the cut-off level are
determined and tabulated in Table HP-4(a) to (c). Again the coefficients should be
multiplied by the constants as listed in Table HP-2 for the determination of rotation.
P-5
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
Rotation Coefficient for Pile Restrained from Rotation Coefficient for Pile Free to Translate at
Pile Length Translation at Head Head
as Multiple Ratio of Depth between Ground and the Cut-off Ratio of Depth between Ground and the Cut-off
of L/T Level of the Pile to the Total Pile Length Level of the Pile to the Total Pile Length
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.00 0.05 0.10 0.15 0.20 0.25 0.30
2 0.747 0.727 0.709 0.693 0.679 0.666 0.654 3.213 2.801 2.516 2.305 2.142 2.012 1.905
3 0.686 0.669 0.654 0.640 0.627 0.616 0.605 1.819 1.666 1.559 1.479 1.417 1.366 1.324
4 0.674 0.652 0.633 0.616 0.601 0.588 0.576 1.751 1.592 1.484 1.405 1.344 1.294 1.252
5 0.668 0.642 0.621 0.602 0.586 0.571 0.558 1.750 1.559 1.439 1.355 1.291 1.240 1.198
7 0.667 0.633 0.605 0.582 0.563 0.546 0.532 1.747 1.504 1.369 1.279 1.213 1.162 1.120
10 0.667 0.621 0.585 0.558 0.536 0.517 0.501 1.747 1.438 1.291 1.197 1.131 1.080 1.038
15 0.667 0.601 0.557 0.525 0.500 0.480 0.464 1.747 1.349 1.196 1.103 1.038 0.988 0.949
20 0.667 0.585 0.535 0.501 0.475 0.454 0.437 1.747 1.290 1.131 1.038 0.974 0.926 0.888
30 0.667 0.558 0.501 0.464 0.437 0.417 0.400 1.747 1.197 1.038 0.949 0.888 0.843 0.807
40 0.667 0.536 0.475 0.437 0.411 0.391 0.375 1.747 1.131 0.975 0.888 0.830 0.787 0.753
Table HP-4(a) – Rotation Coefficients for Pile Tip Unrestrained from both Lateral Movement and
Rotation due to Moment at Pile Head
Rotation Coefficient for Pile Restrained from Rotation Coefficient for Pile Free to Translate at
Pile Length Translation at Head Head
as Multiple Ratio of Depth between Ground and the Cut-off Ratio of Depth between Ground and the Cut-off
of L/T Level of the Pile to the Total Pile Length Level of the Pile to the Total Pile Length
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.00 0.05 0.10 0.15 0.20 0.25 0.30
2 0.614 0.609 0.604 0.599 0.595 0.590 0.586 1.896 1.730 1.612 1.523 1.454 1.398 1.351
3 0.685 0.667 0.652 0.637 0.624 0.612 0.601 1.707 1.591 1.507 1.442 1.389 1.345 1.308
4 0.668 0.647 0.629 0.613 0.598 0.585 0.573 1.751 1.592 1.484 1.405 1.343 1.293 1.251
5 0.667 0.642 0.620 0.602 0.585 0.571 0.558 1.748 1.558 1.438 1.354 1.290 1.239 1.197
7 0.667 0.633 0.605 0.582 0.563 0.546 0.532 1.747 1.504 1.369 1.279 1.213 1.162 1.120
10 0.667 0.621 0.585 0.558 0.536 0.517 0.501 1.747 1.438 1.291 1.197 1.131 1.080 1.038
15 0.667 0.601 0.557 0.525 0.500 0.480 0.464 1.747 1.354 1.197 1.104 1.038 0.989 0.949
20 0.667 0.585 0.535 0.501 0.475 0.454 0.437 1.747 1.290 1.131 1.038 0.974 0.926 0.888
30 0.667 0.558 0.501 0.464 0.437 0.417 0.400 1.747 1.197 1.038 0.949 0.888 0.843 0.807
40 0.667 0.536 0.475 0.437 0.411 0.391 0.375 1.747 1.131 0.975 0.888 0.830 0.787 0.753
Table HP-4(b) – Rotation Coefficients for Pile Tip Restrained from Lateral Movement but Free to
Rotation due to Moment at Pile Head
Rotation Coefficient for Pile Restrained from Rotation Coefficient for Pile Free to Translate at
Pile Length Translation at Head Head
as Multiple Ratio of Depth between Ground and the Cut-off Ratio of Depth between Ground and the Cut-off
of L/T Level of the Pile to the Total Pile Length Level of the Pile to the Total Pile Length
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.00 0.05 0.10 0.15 0.20 0.25 0.30
2 0.487 0.485 0.484 0.482 0.48 0.479 0.477 1.645 1.573 1.512 1.459 1.413 1.372 1.336
3 0.636 0.625 0.615 0.605 0.596 0.587 0.579 1.691 1.569 1.481 1.413 1.360 1.315 1.278
4 0.666 0.646 0.628 0.612 0.598 0.585 0.573 1.733 1.578 1.474 1.397 1.337 1.288 1.247
5 0.667 0.642 0.620 0.602 0.585 0.571 0.558 1.747 1.557 1.438 1.354 1.290 1.239 1.197
7 0.667 0.633 0.605 0.582 0.563 0.546 0.532 1.747 1.504 1.369 1.279 1.213 1.162 1.120
10 0.667 0.621 0.585 0.558 0.536 0.517 0.501 1.747 1.438 1.291 1.197 1.131 1.080 1.038
15 0.667 0.601 0.557 0.525 0.500 0.480 0.464 1.747 1.354 1.197 1.104 1.038 0.989 0.949
20 0.667 0.585 0.535 0.501 0.475 0.454 0.437 1.747 1.290 1.131 1.038 0.974 0.926 0.888
30 0.667 0.558 0.501 0.464 0.437 0.417 0.400 1.747 1.197 1.038 0.949 0.888 0.843 0.807
40 0.667 0.536 0.475 0.437 0.411 0.391 0.375 1.747 1.131 0.975 0.888 0.830 0.787 0.753
Table HP-4(c) – Rotation Coefficients for Pile Tip Restrained from both Lateral Movement and
Rotation due to Moment at Pile Head
The coefficients listed in Tables HP-4(a) to (c) are useful in determining the “rotational
stiffness” of a pile embedded in soil so that rotational restraints can be applied to the pile
cap for analysis in which the piles are assumed to be rigidly jointed to the pile cap. The
assumption of rigid joint connections between the pile and the pile cap can often
P-6
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
significantly reduce lateral deflection of the pile cap. In addition, Tables HP-5(a) to (c)
are given below for determination of the maximum shear forces on pile shafts due to a
moment acting at the pile head. The maximum shears exist at the pile head when the pile
is restrained from translation at the pile head. The coefficients are useful when assigning
translation stiffnesses to piles during lateral load analysis.
Shear Coefficient (Sp) for Pile Head Restrained Shear Coefficient (Sp) for Pile Head Unrestrained
Pile Length from Translation from Translation
as Multiple Ratio of Depth between Ground and the Cut-off Ratio of Depth between Ground and the Cut-off
of L/T Level of the Pile to the Total Pile Length Level of the Pile to the Total Pile Length
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.00 0.05 0.10 0.15 0.20 0.25 0.30
2 0.721 0.734 0.746 0.757 0.768 0.778 0.788 0.874 0.837 0.813 0.797 0.785 0.777 0.770
3 0.645 0.670 0.694 0.716 0.737 0.757 0.776 0.556 0.536 0.528 0.527 0.529 0.533 0.538
4 0.664 0.697 0.727 0.754 0.779 0.802 0.823 0.475 0.480 0.491 0.504 0.517 0.530 0.543
5 0.667 0.706 0.742 0.773 0.802 0.828 0.852 0.478 0.487 0.501 0.517 0.533 0.548 0.562
7 0.667 0.721 0.767 0.807 0.843 0.875 0.904 0.479 0.492 0.514 0.536 0.556 0.575 0.592
10 0.667 0.741 0.802 0.852 0.896 0.934 0.969 0.479 0.501 0.533 0.562 0.587 0.611 0.632
15 0.667 0.773 0.853 0.916 0.970 1.016 1.056 0.479 0.517 0.561 0.597 0.631 0.660 0.686
20 0.667 0.802 0.896 0.969 1.029 1.081 1.126 0.479 0.533 0.588 0.632 0.669 0.702 0.730
30 0.667 0.852 0.969 1.056 1.126 1.185 1.237 0.479 0.562 0.632 0.686 0.730 0.767 0.800
40 0.667 0.896 1.029 1.126 1.203 1.269 1.325 0.479 0.587 0.669 0.730 0.779 0.820 0.856
Table HP-5(a) – Shear Coefficients for Pile Tip Unrestrained from both Lateral Movement and Rotation
due to Moment at Pile Head
Shear Coefficient (Sp) for Pile Head Restrained Shear Coefficient (Sp) for Pile Head Unrestrained
Pile Length from Translation from Translation
as Multiple Ratio of Depth between Ground and the Cut-off Ratio of Depth between Ground and the Cut-off
of L/T Level of the Pile to the Total Pile Length Level of the Pile to the Total Pile Length
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.00 0.05 0.10 0.15 0.20 0.25 0.30
2 0.615 0.629 0.643 0.656 0.668 0.681 0.693 0.928 0.874 0.833 0.801 0.775 0.752 0.732
3 0.652 0.679 0.704 0.727 0.748 0.768 0.787 0.473 0.466 0.469 0.476 0.485 0.495 0.506
4 0.669 0.701 0.730 0.756 0.780 0.803 0.824 0.472 0.480 0.493 0.507 0.520 0.533 0.546
5 0.667 0.706 0.741 0.773 0.801 0.828 0.852 0.480 0.487 0.502 0.517 0.533 0.548 0.562
7 0.667 0.721 0.767 0.807 0.843 0.875 0.904 0.479 0.492 0.514 0.536 0.556 0.575 0.592
10 0.667 0.741 0.802 0.852 0.896 0.934 0.969 0.479 0.501 0.533 0.562 0.587 0.611 0.632
15 0.667 0.774 0.853 0.916 0.969 1.015 1.056 0.479 0.515 0.561 0.600 0.632 0.661 0.686
20 0.667 0.802 0.896 0.969 1.029 1.081 1.126 0.479 0.533 0.587 0.632 0.669 0.702 0.730
30 0.667 0.852 0.969 1.056 1.126 1.185 1.237 0.479 0.562 0.632 0.686 0.730 0.767 0.800
40 0.667 0.896 1.029 1.126 1.203 1.269 1.325 0.479 0.587 0.669 0.730 0.779 0.820 0.856
Table HP-5(b) – Shear Coefficients for Pile Tip Restrained from Lateral Movement but Free to Rotation
due to Moment at Pile Head
Shear Coefficient (Sp) for Pile Head Restrained Shear Coefficient (Sp) for Pile Head Unrestrained
Pile Length from Translation from Translation
as Multiple Ratio of Depth between Ground and the Cut-off Ratio of Depth between Ground and the Cut-off
of L/T Level of the Pile to the Total Pile Length Level of the Pile to the Total Pile Length
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.00 0.05 0.10 0.15 0.20 0.25 0.30
2 0.793 0.800 0.807 0.813 0.820 0.827 0.833 0.426 0.467 0.501 0.53 0.555 0.576 0.593
3 0.665 0.687 0.709 0.729 0.748 0.766 0.783 0.540 0.526 0.521 0.521 0.524 0.529 0.534
4 0.666 0.699 0.728 0.755 0.779 0.802 0.823 0.475 0.480 0.491 0.504 0.517 0.530 0.542
5 0.667 0.707 0.742 0.773 0.802 0.828 0.852 0.478 0.486 0.501 0.517 0.533 0.548 0.562
7 0.667 0.721 0.767 0.807 0.843 0.875 0.904 0.479 0.492 0.514 0.536 0.556 0.575 0.592
10 0.667 0.741 0.802 0.852 0.896 0.934 0.969 0.479 0.501 0.533 0.562 0.587 0.611 0.632
15 0.667 0.774 0.853 0.916 0.969 1.015 1.056 0.473 0.515 0.561 0.600 0.632 0.661 0.686
20 0.667 0.802 0.896 0.969 1.029 1.081 1.126 0.479 0.533 0.587 0.632 0.669 0.702 0.730
30 0.667 0.852 0.969 1.056 1.126 1.185 1.237 0.479 0.562 0.632 0.686 0.730 0.767 0.800
40 0.667 0.896 1.029 1.126 1.203 1.269 1.325 0.479 0.587 0.669 0.730 0.779 0.820 0.856
Table HP-5(c) – Shear Coefficients for Pile Tip Restrained from both Lateral Movement and Rotation
due to Moment at Pile Head
P-7
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
For layered soils, different nh values can be applied at respective levels of the pile for
the determination of lateral restraint, for analysis purpose by the finite difference method
using (Eqn HP-2) and others or the stiffness method. However, as the top level of the
soil plays the most important part in lateral restraint, the result will be conservative if the
whole mass of soil is taken as that of the top layer which generally has the smallest nh
values.
It can also be shown readily that the translational and rotational stiffness of a pile can be
determined respectively by
E I
KT = p p3 (Eqn HP-7)
δ pT
EpI p
Kθ = (Eqn HP-8)
M pT
HP.5 Illustration for the Use of the Tables HP-3 and HP-4
The use of the Tables HP-3 and HP-4 is illustrated by Worked Example HP-1 as follows :
Consider a driven H-pile 305×305×223 Section of length 20m embedded in loose fill and
in the presence of closely spaced piles. The effective value of the constant of horizontal
subgrade reaction is nh = 1300 × 0.25 = 325 kN/m3 (Table 5.2 of the Code). The cut-off
level is at 3.5m below ground. Applied load at cut-off level is S = 100 kN in the
direction to causing bending about the major axis of the pile. E p = 205× 106 kN/m2;
I p = 52700 × 10 −8 m4 so that E p I p = 205 × 106 × 52700 × 10−8 = 108035 kN/m2
The depth factor representing cut-off level to total pile length is 3.5/20 = 0.175
(i) The pile is a floating pile, i.e. not driven to rock and hinged at top level to the pile
cap.
From Table HP-3(a), the interpolated deflection coefficient is
δ p = 1.062 .
Deflection at cut-off level due to the applied shear is
ST 3 100 × 3.1943
vT = δ p × = 1.062 × = 0.03203 m = 32.03mm
EpI p 108035
S 100
So the shear stiffness of the pile is = = 3122 kN/m
vT 0.03203
P-8
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
(ii) The pile is restrained from rotation at the cut-off level and restrained from rotation
and lateral displacement at the tip
From Table HP-3(f), the interpolated deflection coefficient is
δ p = 0.483 .
Deflection at cut-off level due to the horizontal shear is
ST 3 100 × 3.1943
δp × = 0.483 × = 0.01457 m = 14.57mm
EpI p 108035
From Table HO-3(f), the interpolated moment coefficient is M p = 0.672
Maximum moment on the pile shaft is
M p × ST = 0.672 × 100 × 3.194 = 214.64 kNm.
(iii) Rotational stiffness of the floating pile in (i) restrained from translation at the pile
head is to be found. The appropriate coefficient is interpolated from Table HP-4(a)
which is 0.5804. So the rotation due to unit moment applied at the pile head is
0.5804 × MT / E p I p = 0.5804 × 1× 3.194 / 108035 = 17.159 × 10−6 rad
Thus the rotational stiffness is 1 / 17.159 × 10 −6 = 58278 kNm/rad.
Alternatively, the pile can be idealized as a strut member carrying the E p I p value of the
pile laterally supported by a series of elastic “point springs” simulating the lateral support
of the soil as shown in Figure HP-2. The structure can then be solved by the stiffness
method as is included in many commercial softwares.
Ground Level
Figure HP-2 – The Winkler’s Spring Model for Piles under Lateral Load
P-9
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
The frame method is used to analyze the pile in Worked Example HP-1. The elastic spring
values worked out follow (Eqn HI-4) as K h = nh z . However, as (Eqn HI-4) in Appendix
HI is the spring value per unit length, each of them has to be multiplied by the tributary
length which is the sum of half the distance between the spring above and the spring below
to obtain the value of a “point support” for stiffness method analysis. As a counter-check,
the problems in Worked Example HP-1 are re-done below by the stiffness method.
The pile in Worked Example HP-1 is divided into 40 equal segments laterally supported by
41 elastic point springs. The point spring values are worked out using K h d = nh zd
where d is the tributary length equal to d = 20 / 40 = 0.5 m. So the spring value at z
below ground is 325 z × 0.5 = 162.5 z in which starting at z = 3.5 m for the first spring.
The values at the first spring and the last spring are, however, halved as
162.5 × 3.5 × 0.5 = 284.375 and 162.5 × 23.5 × 0.5 = 1909.375 due to the halved tributary
lengths.
Frame analysis is carried out accordingly to give the solution for comparison with results of
Worked Example HP-1 as listed in Table HP-6. It can be seen that the two sets of results
are very close.
HP-1 HP-2
Pile Head
Parameter for Comparison From Tables By Frame
Connection
4 and 5 Analysis
Pile Head Deflection (mm) 32.02 31.52
Pinned Pile Head
Pile Shaft Max Moment (kNm) 149.80 148.48
Connection
Pile Head Rotation (rad) at unit Mt 17.16×10-6 17.13×10-6
Fixed Pile Head Pile Head Deflection (mm) 14.57 14.42
Connection Pile Head Moment (kNm) 214.64 213.71
Table HP-6 – Comparison of Results between Worked Examples HP-1 and HP-2
The 1st order linear analysis has ignored the effects of axial load on the lateral deflection
as per the foregoing analysis in this appendix, both by the finite difference and stiffness
approaches. However, for a pile under lateral load, the axial load in the pile can in fact
create additional eccentric moments (axial load × the lateral displacement of the pile) on
the pile and subsequently further lateral displacements. Alternatively it can be regarded
that the axial load decreases the stiffness of the pile thus produce greater lateral
displacements.
Nevertheless, if the analysis is based on (Eqn HI-1) for the finite difference method in
Appendix HI so that (Eqn HP-2) can be modified as follows, P-∆ effects can then be
accounted for.
P-10
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
Pr 2 Pr L 5 i P
⇒ vi + 2 − 4 − 2 vi +1 + 6 − 2 + 5 vi − 4 − r2 vi −1 + vi −2 = 0 (Eqn HP-9)
N N T N N
Other equations for support conditions and application of loads and moments remain
unchanged and the full set of equations can then be analyzed which would include the
effects due to P-∆. Similarly, for the stiffness method, if the combined stiffness (the
conventional stiffness matrix + the geometric matrix) as listed in (Eqn HI-12) is used,
P-∆ effects can also be accounted for.
Figure HP-3 shows the difference in deflection profiles and bending moments of a 40m
long 305×305×223 pile with free head embedded in soil of nh = 1100 kN/m3 under a
horizontal shear of 90kN with and without an axial load of 5500kN. There are significant
differences under such a comparatively high axial load.
Nevertheless, the differences are significantly reduced when the pile head is restrained
against rotation as shown in Figure HP-4. The proportion of stiffness reduction is
smaller when the pile head is fixed.
P-11
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HP
P-12
Appendix HQ
Pile Cap
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HQ
The determination of the distribution of lateral shear forces among the piles and the
pile cap of a piled foundation is based on the compatibility of lateral deflections of the
piles and the pile cap at the pile cut-off levels. To simplify calculation, infinite
in-plane stiffness of the pile cap is usually assumed.
The elastic theory is adopted to determine the lateral load distribution among the piles
and the pile cap. The lateral stiffness of the pile group (which is the load to produce
unit displacement) is first determined based on the summation of the lateral
stiffnesses of the individual piles. Consider a pile group of N piles no. 1, 2, 3, …
i, …… N located respectively at coordinates x1 , y1 , x2 , y2 , …..
xi , yi , …… xN , yN with reference to a pre-determined rectangular co-ordinate
system on X and Y axes. The lateral stiffness of each pile in each of the X and Y
directions is pre-determined as K px1 , K px 2 ,….. K pxi , ….. K pxN and K py1 ,
K py 2 ,….. K pyi ,….. K pyN respectively in accordance with the approach discussed in
Appendix HP.
The lateral stiffness of the pile cap, which may also experience restraint from the
embedded soil can be pre-determined in accordance with the approach discussed in
Appendix HO, if rectangular on plan. The pre-determined lateral stiffnesses and
on-plan rotational stiffness of the cap with respect to the global X and Y axes are
K capx , K capy , K capz and the centroidal axes are at xcap and ycap .
(i) The “shear centre” of the pile group and the pile cap is to be located with
respect to the pre-determined coordinate system as
X cg
K pyi xi K capy xcap (Eqn HQ-1)
K pyi K capy
Ycg
K y K
pxi i capx ycap
(Eqn HQ-2)
K K pxi capx
(ii) The external applied load in the directions parallel to the global X and Y
directions are denoted by S X and SY respectively. Any unbalanced on plan
torsion calculated about the shear centre is denoted by T which is taken as
positive if it is acting anti-clockwise;
(iii) The total lateral stiffness of the piled foundation system in the X and Y
directions are respectively
K X K pxi K capx (Eqn HQ-3)
Q-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HQ
Physically the two stiffnesses are the forces required to produce unit
displacements in the directions under consideration when the resultant external
loads acts at the “shear centre”;
Physically it is the moment required to produce unit rotation at the shear centre;
(v) To ensure compatibility of the lateral displacements of the pile cap and the piles,
the lateral shears of the pile i in the X and Y directions will respectively be
K K y Y
S pxi S X pxi T pxi i cg ; (Eqn HQ-6)
KX J
K K x X cg
S pyi SY pyi T pyi i ; (Eqn HQ-7)
KY J
(vi) The lateral shears in the X and Y directions and torsion acting on the pile cap
are respectively
K K y Y
Scapx S X capx T capx cap cg ; (Eqn HQ-8)
KX J
K K x X cg
S capy SY capy T capy cap (Eqn HQ-9)
KY J
K
M cap T capz (Eqn HQ-10)
J
(vii) As compatibility of displacements of the pile group and the pile cap is ensured,
the lateral displacements (in the global X and Y directions) and rotation of the
shear centre can be worked out as
S S T
X X ; Y Y ; Z (Eqn HQ-11)
KX KY J
The distribution of lateral loads on a piled foundation comprising a pile cap covering
26 nos. of H-piles of section 305×305×223 grade S450 piles is analyzed as Worked
Example HQ-1. The piles are 30m long and assumed pinned at the cut-off levels to
the pile cap. The pile cap is 1.5m thick, of plan size 10m by 10m and is buried 1.5m
below the ground surface. Soil restraint on the pile cap can only be considered in
the Y direction. In the X direction where there are foundations of adjacent buildings,
there will be no restraint assumed by the soil on the pile cap. The layout is shown in
Figure HQ-1.
Q-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HQ
Soil of 1.5m
10
Young’s
P23 P24 P25 P26 Modulus
9 5000kPa &
1.5m
P20 P21 P22 Poisson
Ratio 0.35
8 P17 P18 P19 Pile Cap
P16
7
P13 P14 P15
Typical Pile
Distance in m
6
P12
P8 P9
3
P6
2 P7
P5
1 P1 P2 P3
Y P4
0
0 1 2 3 4 5 6 7 8 9 10
Pile Section
X Distance in m
Figure HQ-1 – Piling Layout Plan and Details for Worked Example HQ-1
Design Data :
Soil parameters above pile cut-off level : Esoil 5000 kPa; 0.35 ;
Gsoil Esoil 21 1851.85 kPa;
Soil below cut-off level nh 4400 kN/m3; Cap width b 10 m
(i) The lateral stiffness of the pile cap is determined by the approach discussed in
Appendix HP. The lateral stiffness of the pile cap in the X-direction is taken as
zero (no soil restraint in the X-direction) and 2.474 bGsoil 45815 kN/m in the
Y direction (Table HO-1(b) with K1=23/10=0.6 and K2=21.5/10=0.3). The
rotational stiffness is 0.414 b 3Gsoil 766667 kNm/rad (Table HO-2(b));
(ii) The lateral stiffnesses of the individual piles are first determined in accordance
with the method discussed in Appendix HP. As discussed the constant of
horizontal subgrade reaction is to be discounted with respect to pile spacing in
accordance with Table 5.2 of the Code. The values arrived at are tabulated in
Table HQ-1. As the ratio of cut-off level depth to pile length is 3/30 = 0.1 and
the piles are floating piles with a pinned connection at the pile heads, Table
HP-3(a) is used to find the lateral deflection coefficients px and py in accordance
with the L/T ratios as tabulated in Table HQ-1. The determination of the pile
shear stiffnesses is in accordance with (Eqn HP-7) in Appendix HP.
Q-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HQ
Table HQ-1 – Lateral Stiffness of the Piled Foundation of Worked Example HQ-1
(iii) The shear centre and stiffness of the piled foundation are worked out by Table
HQ-2 as follows.
Table HQ-2 – Summary of Stiffness of the Piled Foundation of Worked Example HQ-1
Q-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HQ
From Table HQ-2, the total translational stiffnesses of the piled foundation in the
X and Y directions are K X 448270 kN/m and K Y 282569 kN/m respectively
(as sum of the 2nd and 3rd columns respectively)
By (Eqn HQ-1) and (Eqn HQ-2), the shear centre is located at
X cg
K pyi xi K capy xcap 1385227 4.902 m from the origin,
K pyi K capy 282569
Ycg
K y pxi i K capx y cap
2536700
5.659 m from the origin.
K pxi K capx 448270
Based on the worked out location of the shear centre, the coordinates of the piles
and the pile cap are shifted (the 8th and 9th columns) relative to the shear centre as
the origin. The rotational stiffness of the pile cap is therefore worked out as
J K pxi yi Ycg K pyi xi X cg K capz K pxi yci K pyi xci K capz
2 2 2 2
2144763 4454486 766667 7365916 kNm/rad by (Eqn HQ-5)
(iv) The applied external lateral wind load about the shear centre are worked out as :
Wind X (kN) Wind Y (kN) On-plan Moment (kNm)
Wind Load in X-direction 2260 0 1755.449
Wind Load in Y-direction 15 1890 680.7435
(v) The shears and moments acting on the piles and the pile cap are worked out for
two wind load cases in accordance with (Eqn HQ-6) to (Eqn HQ-10) and
tabulated in Tables HQ-4(a) and HQ-4(b) as follows :
Shear (kN) Moment Coeff. Max. Moment (kNm)
Pile No /
Cap Due to Direct Shear Due to Torsion Total along along
Mpxi Mpyi
X-X Y-Y X-X Y-Y X-X Y-Y X-X Y-Y
P1 64.801 0.000 15.803 -6.036 80.604 -6.036 0.436 0.398 73.68 -3.66
P2 64.801 0.000 15.803 -0.370 80.604 -0.370 0.436 0.398 73.68 -0.22
P3 64.801 0.000 15.803 5.295 80.604 5.295 0.436 0.398 73.68 3.21
P4 84.865 0.000 20.695 6.614 105.560 6.614 0.426 0.420 87.61 5.08
P5 92.987 0.000 19.709 -9.827 112.696 -9.827 0.424 0.398 90.55 -5.96
P6 92.987 0.000 16.742 -6.995 109.729 -6.995 0.424 0.420 88.17 -5.37
P7 92.987 0.000 16.742 6.614 109.729 6.614 0.424 0.420 88.17 5.08
P8 92.987 0.000 10.808 -6.995 103.795 -6.995 0.424 0.420 83.40 -5.37
P9 92.987 0.000 10.808 6.614 103.795 6.614 0.424 0.420 83.40 5.08
P10 92.987 0.000 3.138 -9.073 96.124 -9.073 0.424 0.412 77.24 -6.35
P11 92.987 0.000 3.138 8.580 96.124 8.580 0.424 0.412 77.24 6.01
P12 92.987 0.000 -0.695 4.434 92.291 4.434 0.424 0.404 74.16 2.86
P13 92.987 0.000 -4.532 -6.995 88.454 -6.995 0.424 0.420 71.07 -5.37
P14 92.987 0.000 -4.532 1.154 88.454 1.154 0.424 0.407 71.07 0.77
P15 92.987 0.000 -4.532 6.614 88.454 6.614 0.424 0.420 71.07 5.08
P16 92.987 0.000 -7.499 4.667 85.487 4.667 0.424 0.420 68.69 3.58
P17 92.987 0.000 -10.466 -6.995 82.520 -6.995 0.424 0.420 66.31 -5.37
P18 84.865 0.000 -9.552 2.719 75.313 2.719 0.426 0.420 62.51 2.09
P19 84.865 0.000 -9.552 6.614 75.313 6.614 0.426 0.420 62.51 5.08
P20 92.987 0.000 -13.433 -9.827 79.553 -9.827 0.424 0.398 63.92 -5.96
P21 84.865 0.000 -12.260 1.154 72.605 1.154 0.426 0.407 60.26 0.77
P22 84.865 0.000 -12.260 4.667 72.605 4.667 0.426 0.420 60.26 3.58
P23 84.865 0.000 -14.968 -6.995 69.897 -6.995 0.426 0.420 58.01 -5.37
P24 84.865 0.000 -14.968 -6.036 69.897 -6.036 0.426 0.398 58.01 -3.66
P25 84.865 0.000 -14.968 2.719 69.897 2.719 0.426 0.420 58.01 2.09
P26 84.865 0.000 -14.968 6.614 69.897 6.614 0.426 0.420 58.01 5.08
Pile Cap 0.000 0.000 0.000 1.067 0.000 1.067 – – – –
Sum 2260.00 0.000 0.000 0.000 2260.00 0.000
Table HQ-4(a) – Summary of Pile and Pile Cap Reactions to Wind in X-direction
Q-5
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HQ
Table HQ-4(b) – Summary of Pile and Pile Cap Reactions to Wind in Y-direction
The shear in the pile cap is given in the Table whilst the torsion on the pile cap
has to be worked out using (Eqn HQ-10) as
K 766667
M cap T capz 1755.449 182.71 kNm for Wind in the X-direction
J 7365916
K 766667
M cap T capz 680.74 70.85 kNm for Wind in the Y-direction
J 7365916
(vi) The displacement of the shear centre of the piled foundation is determined by
(Eqn HQ-11) as
Table HQ-5 – Summary of Pile and Pile Cap Displacements to Wind Loads
Q-6
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HQ
to the coordinate system with the shear Centre as the origin and the axes parallel
to the X and Y axes can be determined as
The approach as described above is for hand calculations with or without the use of
spreadsheets. Nevertheless, with the inputs of the stiffnesses of the piles and the pile
cap into computer mathematical models, the analysis can also be carried out by
computer software. Nowadays analysis based on 3-dimensional mathematical
models can analyze in-plane (due to shear) and out-of-plane loads simultaneously
enabling load combinations to be carried out for structural design.
Q-7
Appendix HR
c P Ground Level
R2
Ground Level
A
z
Z R1 R1 x 2 y 2 z c 2
Y B R2 x 2 y 2 z c 2
v is the Poisson’s ratio of the
Medium
y
X x
(Eqn HR-2)
P 1 2v z c 1 2v z c 3z c 3 33 4v z z c 2 3cz c 5 z c 30cz z c 3
z (Eqn HR-3)
8 1 v
R13 R2 3 R15 R2 5 R2 7
R-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HR
The effects due to loaded area can then be obtained by integrating the effects over the
whole area which can be idealized as comprising a series of point loads. For
example, if the exerting stress of an area of load at a location of coordinate x, y is
u z x, y by which we can define a point load dP u z x, y dxdy acting at the point
and by applying the relevant formula in Figure HR-1, we can calculate the effect, say
the vertical stress at another point X due to the point load as
d z dPI z x, y u z x, y dxdyI z x, y where I z x, y is the coefficient of P in (Eqn
HR-3). The total effect due to the area load at X will then be
d z u z x, y I z x, y dxdy .
A A
A rectangular footing of plan area 40m by 30m is exerting a linearly varying “net”
ground pressures at 3m below ground. That is, the pressures are due to the weight of
the structure minus the weight of soil displaced. The “net” pressures at the 4 corners
of the footing are 125kPa, 155kPa, 45kPa and 75kPa as shown in Figure HR-2 in
which a coordinate system with the origin at the centre of the footing is shown. The
ground pressure at any point x, y within the footprint of the footing can then be
defined by the equation P x, y 2 x y 100 . The horizontal and shear stresses of
a wall at location shown in Figure HR-2 with its top level at the ground and bottom
level 15m below ground are to be determined.
Pressure = A
45kPa Y
20m 20m Pressure =
125kPa
10m
Footing Grd Level
15m
3m
15m
X
15m
Section A-A
10m
15m 10m Pressure =
155kPa
Pressure =
75kPa A Underground Wall
where Stresses are
to be found
Plan
The normal stresses of the wall (stresses in the global Y direction of Figure HR-2) are
calculated for points in on the wall at 1m gird (in both global X and Z directions) and
the stress contour is plotted is Figure HR-3. Analytical solutions have not been
R-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HR
found for the integrals. Instead numerical solutions based on the software Mathcad
(2001) have been used for calculation and plotting. Alternatively, other software
including Microsoft excel can be used.
Ground
5m below
Ground
10m below
Ground
Figure HR-3(a) – Normal Stress Contours in kPa on the Wall of Worked Example HR-1
Similarly, the shear stresses on the wall are also calculated and plotted in Figure
HR-3(b)
Grd
5m below Grd
Figure HR-3(b) – Shear Stress Contours in kPa on the Wall of Worked Example HR-1
R-3
Appendix HS
By the theory of water seepage through soil, the following governing differential
equation can be derived which is found in many text books.
2h 2h
Kx 2 Ky 2 0 (Eqn HS-1)
x y
In the equation, h is the total head (the sum of elevation head and pressure head in
the Bernoulli Theorem with the velocity head ignored due to its insignificant
contribution, K x and K y are the coefficients of permeability of the soil in the X
and Y directions defined by the Darcy Law as :
h h
vx K x ; vy K y (Eqn HS-2)
x y
where v x and v y are respectively the velocities of flow of water in the soil in the X
and Y directions.
Though numerical methods can always be used to solve (Eqn HS-1), analytical
solutions of the equation can also be found for certain cases where the geometries of
excavations involving impermeable walls are simple. The following Worked
Examples HS-1 and HS-2 illustrate the use of analytical solutions for two simple but
common geometries by which water pressures on the wall and the “criticalities” of
water seepage can be estimated. However, in these 2 examples, the ground water
levels are assumed to be at constant levels on the upstream sides so that constant
values of total head h can be prescribed at the levels as boundary conditions to the
differential equation at (Eqn HS-1) for solution. The assumption in fact transforms
the problem to a “confined flow” problem where the water is flowing through fixed
boundary. On the other hand, if the assumption is not adopted where the flow
becomes an “unconfined flow”, the ground water level is not constant but drops
towards the sheetpile and the solution has to be based on a trial and error process
which will be discussed in the later part of this appendix. Nevertheless, the analysis
will be more critical in terms of water pressure and flow under the “confined flow”
assumption which can be adopted as a conservative design for excavation supported
by sheetpile.
In the example, the head and criticalities of an excavation shown in Figure HS-1
where the flow is at steady stage are to be estimated. The impermeable soil layer is
taken at depth infinity and the soil is homogeneous and isotropic. It is also intended
to keep the water level at the downstream side constant at 0.5m (by pumping) below
ground.
S-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HS
Hu = 1.5m
GWL
A
T is at most measured to the ground H = 3m
level of the upstream side even if the T = 3m
water level is above ground level while
H is measured to the water level on the 0.5m C
upstream side, regardless whether the
B z=0
water level is above or below ground. So d = 2.5m
T = H if the water level is below ground
on the upstream side, otherwise T < H. F
Analytical solutions for the geometry have been derived and are listed in Azizi (2000)
and the following steps can be followed :
(i) Determine from (Eqn HS-4) listed below (by trial and error)
d
tan (Eqn HS-4)
T
(ii) Determine hF (head at F which is the toe level of the impermeable wall) by
hF H (Eqn HS-5)
H T
(iii) Determine ; ; (Eqn HS-6)
coshF /
(iv) The equation relating total head hz along the wall and depth z is
h h
z z sin z (Eqn HS-7)
where z is taken as zero at the downstream water level. It should be noted
that the equation is applicable both upstream and downstream. When hz
increases along the flow from upstream to downstream, z will change from
decreasing to increasing at the upstream course.
(v) The average hydraulic gradient at the upstream side at the wall at level z is
h h
iuz A z (Eqn HS-8)
T z
where hA is the total head at the ground surface of the upstream side.
(vi) The average hydraulic gradient at the upstream side at the wall at level z is
S-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HS
hz hB
iud (Eqn HS-9)
z
where hB is the total head at the water surface of the downstream side.
The calculated results at the various levels on the upstream and downstream sides are
tabulated as :
The calculated hydrostatic pressure profiles are plotted in Figure HS-2 as follows :
S-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HS
Downstream
Water Pressure
on Wall Stem
with Seepage
The total forces and moments on the wall due to the seeping water on both sides are
summed and tabulated as :
Force (kN) per metre width Moment (kNm) about wall toe per metre width
Up Stream Down Stream Net Up Stream Down Stream Net
116.8 42.99 73.81 218.33 35.19 183.14
The average hydraulic gradient at downstream is 0.5. The “Quick sand” effect can
be assumed not to take place as the gradient is less than the critical value of the ratio
of buoyant density of soil over density of water divided by 1.5 which is
19 10 / 10 / 1.5 0.6 . It should be pointed out that the water pressures at both
sides at the wall toe must be equal. Thus adoption of the “No seepage” hydrostatic
pressure for design will be very conservative.
Worked Example HS-1 is modified with the impermeable layer at finite depth as
shown in Figure HS-3 and re-analyzed as Worked Example HS-2.
S-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HS
Hu = 1.5m
A
H = 3m
0.5m C
B
d = 2.5m
T = 9m
D = 6m
F
L = 3.5m
The analytical formulae are different from those of Worked Example HS-1 which are
listed as follows. z 0 is set at the level of the impermeable layer.
H
(i) Calculate (Eqn HS-9)
T T 2 D D2
ln 1 ln 1
L L2 L L2
z z2
(ii) Along upstream side AF, the head is hz ln 2 1 (Eqn HS-10)
L L
z z2
(iii) Along downstream side AF, the head is hz ln 2 1 (Eqn HS-11)
L L
T T2
(iv) Determine the head at A hA ln 1 ; and head at B
L L2
D D2
hB ln 1 and it can be shown that hA hB H
L L2
S-5
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HS
The calculated hydrostatic pressure profiles are plotted in Figure HS-4 as follows :
Downstream
Upstream Water
Water Pressure on
Pressure on Wall
Wall Stem
Stem without
without Seepage
Seepage
Downstream
Water Pressure
on Wall Stem
with Seepage
S-6
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HS
Summing the total force and moments on the wall due to the seeping water on both
sides :
Force (kN) per metre width Moment (kNm) about wall toe per metre width
Up Stream Down Stream Net Up Stream Down Stream Net
121.0 41.76 79.24 229.67 33.56 196.12
As compared with Worked Example HS-1, there is a slight increase in the forces and
moments.
The exercise is re-done by decreasing the depth between the wall toe and the
impermeable layer to 1.5m as Worked Example HS-3 and the summation of force and
moment become as follows which only slightly greater than Worked Example HS-2:
Force (kN) per metre width Moment (kNm) about wall toe per metre width
Up Stream Down Stream Net Up Stream Down Stream Net
123.37 41.60 81.76 234.58 33.30 201.28
Again the average hydraulic gradient which is 0.5 < 0.6 as in Worked Example HS-1.
(Eqn HS-1) can in fact be solved by the finite difference method. The 2-dimensional
soil medium is first divided into a regular rectangular mesh with “nodes” at which the
total head h as defined in para. HS.1 are to be determined. Formulation in
accordance with (Eqn HS-1) in accordnce with the h value of a point at the location
i, j denoted as hi , j as illustrated in Figure HS-5 can be as follows :
hi , j 1 2hi , j hi , j 1 hi 1, j 2hi , j hi 1, j
Kx Ky
0 (Eqn HS-16)
x 2 y 2
where x and y are the intervals between adjacent points in the X and Y
directions along the rectangular mesh as shown in Figure HS-5.
hi-1,,j
hi,,j hi,,j+1
hi,,j-1
y
hi+1,,j The ith row
x
hN-1,,j
Impermeable
hN,,j Layer
S-7
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HS
(i) Total head h remain constant at the nodes along the top “free surface” of the
upstream and downstream sides which are respectively 9m and 6m;
(ii) At the nodes along a vertical edge considerably far away from the wall, the
hydrostatic conditions are considered normal without flow, i.e. the total head h
remain constant. The total head at a node at z below the top surface along
the far vertical edge at the upstream side, the elevation head is 9 z and the
pressure head is z so that the total head remains at h 9 z z 9 .
Similarly for the downstream side the total head at the nodes along the far edge
remains at h 6 . The far edges are taken as 10m from the wall;
(iii) The speed of flow in (1) the vertical direction (Y-direction) at the impermeable
layer and (2) the horizontal direction at the wall are 0, i.e. by (Eqn HS-2) for (1)
h hN 1, j hN 1, j
vy K y 0 0 hN 1, j hN 1, j where hN 1, j and hN 1, j
y 2y
are respectively the heads at the nodes just above the impermeable layer and at
the “fictitious nodes” beneath the impermeable layer as illustrated in Figure
HS-5 above. Similar boundary conditions can be formulated for (2).
The solution yields the total head contours (or equi-potential lines) in Figure HS-6. A
set of “flow-lines” perpendicular to the total head contours are superimposed onto the
total head contours to form the “flow net”.
Volume of flow summed
Variation of
up is 2.06m3/day per
Flow rate
metre width of
excavation
Very Low
Flow Rate
0.495m/day
Figure HS-6 – “Flow net” Analysis of Worked Example HS-2 by the Finite Difference Method
S-8
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HS
In addition, the water flow rate at coordiante y j at the top level of the downstream
h hM , j hM 1, j
side can be calculated by v y K y Ky where hM , j is the head at
y y M y
the top of the downstream surface. Taking K y 2 10 5 m/sec, the flow rates at
various points are calculated and plotted in Figure HS-6. The total seepage volume
can be determined numerically at 2.06m3/day.
The “pressure head” can, however be obtained by subtracting the elevation head from
the total head as determined previously. The hydrostatic pressure can then be
determined by multiplying the pressure head by the density of water and the pressure
contour is plotted in Figure HS-7.
The flow can also be solved analytically by the finite element method in which the
soil medium is “meshed” into an assembly of polygonal elements similar to that of
structural analysis. The commonest elements are the triangular element and
rectangular element and solution at the nodes are the total head. For a rectangular
element of sides 2a and 2b , the “seepage stiffness” matrix of isotropic material is
a2 b2 2a 2 b 2 a 2 2b 2 a 2 b2
3ab 6ab 6ab 6ab
2a b a2 b2 a 2 b2 a 2 2b 2
2 2
With the formulation of “seepage stiffness” matrix for each element and the entire
S-9
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HS
matrix for the soil mass can be assembled in the same manner as that for structural
analysis. Conditions at boundaries can also be similarly prescribed for solution of the
total head h at the joining nodes of the elements.
If the assumption of prescribed constant ground water level on the upstream side is
not adopted resulting in “unconfined flow”, the upstream profile becomes another
unknown to be solved. So the upstream top water level is not prescribed to a
constant total head but instead only under the condition that the vertical flow velocity
is zero as similar to the impermeable layer below. However, total head values less
than the elevation heads resulting in negative hydraulic pressure heads will be
resulted at certain nodes at the upper portion of the upstream side. In the finite
difference approach, these nodes have to be eliminated for re-analysis as shown in
Figure HS-8. The iterative process should go on until only one layer of negative
hydraulic pressure heads are obtained and the zero hydraulic pressure head can be
obtained by interpolation between the negative head nodes and the next positive head
nodes. In the finite element approach, however, as any rectangular element with one
or more negative hydraulic pressure head values have to be eliminated altogether
resulting finally with all positive values, the zero hydraulic pressure head profile has
to be obtained by extrapolation for the zero values. The zero hydraulic pressure
head profile is obviously the final ground water level.
Figure HS-8 – Finite Difference Mesh after Elimination of Nodes of Negative Water Heads
and Final Water Profile
S-10
Appendix HT
Excavation
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HT
The calculation is based on Schneebeli’s Method as quoted by Hajinal I. et. al.’s “Construction of
Diaphragm Walls”. The method is applicable to both cohesive and cohesionless soils.
(i) Trench stability is ensured when the “net bentonite pressure” (which is the pressure
exerted by the bentonite inside the trench less the ground water pressure outside)
achieves a factor of safety 1.2 (in line with many temporary work practices) over
the effective lateral soil pressure. Mathematically, it is expressed as :
Pb Pw
FOS 1.2 (Eqn HT-1)
'h
(ii) In (Eqn HT-1) above, Pb is the pressure exerted by the bentonite inside the trench.
It varies with hb (which is the depth below the top level of the bentonite) as
Pb b hb (Eqn HT-2)
where b is the density of the bentonite
Similarly Pw which is the pressure by the water outside the trench at depth hw
below the ground water level can be calculated by
Pw w hw (Eqn HT-3)
where w is the density of water.
(iii) 'h is the lateral earth pressure to be supported by the net bentonite pressure. It is
1 sin
conventionally related to the coefficient of active soil pressure K a ,
1 sin
vertical effective stress 'v and cohesion c as
Determination of 'v can take into account the “vertical arching effect” which is
significant over the relatively short length of a barrette. The arching effect serves
to reduce the effective vertical pressure from the pure overburden weight of the soil
and surcharge by (Eqn HT-5) :
sL
'v
sin 2
1 e sin 2 . z / L q0e sin 2 . z / L (Eqn HT-5)
T-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HT
It can be shown that the first term of (Eqn HT-5) will tend to s z and the second
term tend to q0 when L tends to infinity.
(iv) The equations listed in (iii) are for homogeneous soil. For layered soil, 'v
needs to be assessed layer by layer with q0 being the vertical stress at the top level
of the layer.
The following worked example serves to demonstrate the use of the equations in HT.1.
T-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HT
The results are tabulated in Table HT-1. The following observations can be drawn :
(i) The vertical stresses and hence the horizontal pressures in the soil become more or
less constant at greater depths instead of increasing linearly. The arching effect is
thus very significant;
(ii) The factor of safety of 1.2 can be achieved at all levels, except at the top first metre
which is safeguarded by the existence of the guide walls.
T-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HT
T-4
Appendix HU
Photo HU1.1 – Welding of Pile Photo HU1.2 – HU2.1 Photo HU1.3 – Installation of Pile in
Shoes Correct Position
Photo HU1.4 – Checking Verticality Photo HU1.5 – Pitching of Pile Photo HU1.6 – Connection of Pile by
(by Hydraulic Hammer) Welding
Photo HU1.7 – Test of Weld Photo HU1.8 – Pitching to the Photo HU1.9 – Installing
Required Depth Transducers on Pile for the PDA
Test
U-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU1.10 – Pile Driving Analyzer Photo HU1.11 – Final Set Photo HU1.12 – Close-up of Final
Test Data Displaced on Screen Measurement Set Measurement
Photo HU1.13 – Static Loading Test – Set-up Photo HU1.14 – Static Loading Test –
with Kentledge Close-up of Load Cell on Top of Pile
Photo HU2.1 – Setting-Out of Pile on Ground Photo HU2.2 –Set up the Hydraulic Oscillator with Crawler
Crane and Drive the Temporary Steel Casing into the Ground
U-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU2.3 – Excavation using Hammer Grab inside Temporary Steel Casing.
Photo HU2.4 – Extending the Temporary Steel Casing by Bolting or Welding Connections
Photo HU2.5 – Excavation of rock or similar hard material using Reverse Circulation Drilling Rig for Formation of
the Rock Socket.
U-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU2.6 – Formation of Bellout by Hydraulic Bellout Bit using Reverse Circulation Drilling Rig
Photo HU2.7 – Installation of Permanent Liner (usually in Zone of Weak Soil) inside the Temporary Casing to Avoid
“Necking”
Photo HU2.8 – Installation of Steel Reinforcement Cage inside the Bored Pile Shaft using Crawler Crane
U-4
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU2.9 – Cleaning of Pile Base using Airlifting Photo HU2.10 – Placing Tremie Concrete with Gradual
Method by Compressed Air Extraction of the Temporary Steel Casing Concurrently
Photo HU2.11 – Rotary Drilling Rig for Photo HU2.12 – Sonic Logging Photo HU2.13 – Sample of
Concrete Core Test Test Concrete / Rock Interface
Photo HU3.1 – Drilling with the first Photo HU3.2 – Checking Alignment Photo HU3.3 – Drilling Works by
Temporary Casing ODEX Method
U-5
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU3.4 – ODEX Drilling Bit Photo HU3.5 – Prefabrication of Steel Photo HU3.6 – Double Shelter for Noise
H-pile for Socket Length Portion and Dust Reduction during Piling
Photo HU3.7 – Casing Joint Preparation Photo HU3.8 – Splicing of Temporary Photo HU3.9 – Splicing of Steel
Casing H-pile
Photo HU3.10 – Obtaining Rock Photo HU3.11 – Preparation Works for Photo HU3.12 – Air-lifting before
Sample after Completion of Drilling Grouting Work Grouting Work
Operation
U-6
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU3.13 – Cement Grouting for Photo HU3.14 – Extracting Photo HU3.15 – Extracting
the Socketed H-Pile Temporary Steel Casing by Vibrating Temporary Steel Casing by Hydraulic
Hammer Jack under Adverse Condition
HU.4 Mini-pile
Photo HU4.1 – Drilling Rig for Mini-pile on Working Platform Photo HU4.2 – Drilling Work in Progress
(Vertical Mini-pile)
U-7
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU4.3 – Drilling Work in Photo HU4.4 – Checking Alignment of Photo HU4.5 – Splicing of Steel Casing
Progress (Raking Min-pile) Mini-pile
Photo HU4.6 – Collecting Rock Photo HU4.7 – Air Lifting at Photo HU4.8 – Prefabrication of Steel
Sample at Founding Level Completion of Drilling Bars
U-8
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU5.1 – Setting Out of Pile Photo HU5.2 – Auger Drilling Rod Photo HU5.3 – Drilling Work in
Progress
Photo HU5.4 – Extension of Auger Photo HU5.5 – Drilling Completed to Photo HU5.6 – Grouting Work of Pile
Drilling Rod the Required Depth of Pile
Photo HU5.7 – Flow Cone Test for Photo HU5.8 – Initial Setting Time Photo HU5.9 – Grout Cube
Grout Test for Grout Compression Test
U-9
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU5.10 – Completion of Photo HU5.11 – Prefabricated Steel Photo HU5.12 – Installation of
Grouting Work Cage Steel Cage into the Pile Shaft
Photo HU5.13 – Surveying of the Photo HU5.14 – Stabilizing the Steel Photo HU5.15 – Inspection of Grout
Top Level of Steel Bar Cage (in Grout) by U-bolts at Top Level of Pile before Backfill
Photo HU6.1 – Shallow Trench Photo HU6.2 – Silos on Site for Photo HU6.3 – The Hydromill
formed and surrounded by Guide Re-circulation of Bentonite Slurry Machine for Trench Excavation
Walls and filled by Bentonite Slurry
U-10
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU6.4 – Cutter at the bottom Photo HU6.5 – Excavation by Photo HU6.6 – Scrapers used to
of The Hydromill Machine Hydromill within Guide Walls Clean Trench sides by Removing
Excess Filter Cake
Photo HU6.7 – Reinforcement Photo HU6.8 – Lifting Photo HU6.9 – Lowering Reinforcement
Cage Pre-fabricated on Site Reinforcement Cage Cage into Excavation Trench
Photo HU6.10 – Tremie Concreting for Photo HU6.11 – Finished Barrette after
Barrette Concreting / Grouting
U-11
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU7.1 – Open Excavation for Raft Footing Photo HU7.2 – Blinding the Bottom Level of the
Construction Raft Footing
Photo HU7.3 – Reinforcement Fixing for the Photo HU7.4 – Concreting for the Bottom Slab
Bottom Slab
Photo HU7.5 – Reinforcement Fixing for the Photo HU7.6 – Concreting for the Walls
Walls
U-12
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HU
Photo HU7.7 – Formwork Erection and Photo HU7.8 – Concreting for the Top Slab
Reinforcement Fixing for the Top Slab
U-13
Appendix HV
HV.1 Introduction
A pile under vertical load will settle and “drag” the soil around it downwards and thus
will create further settlement on adjacent piles. So the settlement of a pile is that due to
its own and the effects from others. The phenomenon is termed as “pile interactions”.
The mechanism is difficult to quantify even under the elastic theory by which the soil is
idealized as an elastic continuum. Poulos & Davis (1980) has developed an approach
based on Mindlin’s Equations originated from effects due to point loads in an elastic
continuum. However, the approach involves lengthy and tedious mathematical
manipulations. Randolph (1977), nevertheless, has developed a much simplified
approach which has been popularly used by designers and researchers.
Basically, Randolph assumes the soil deforms by shear due to the shear stress on the pile
shaft and that the effects on soil will be considered negligible beyond a distance rm
(defined below) for determination of pile settlement due to soil friction. The following
Figure HV-1 and (Eqn HV-1) are extracted from GEO Publication 1/2006 (Figure 6.26)
which explains the assumption. It should be noted that the formula is based on linearly
varying shear modulus of soil with depth.
Figure HV-1 – Extract from GEO 1/2006 (Figure 6.26) to Explain Randolph’s
Approach in Settlement Determination
1 vs L ro
V-1
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HV
4 r tanh L L
1
1 v s L ro
t P (Eqn HV-2)
4 r 2 tanh L L r G
o L
1 v s L ro
Again by Randolph’s approach, the settlement at the soil surface at distance S pi away is
ln rm S pi
i t (Eqn HV-3)
where ln rm ro as defined above.
By the elastic theory, this settlement can be imposed onto a pile at the same distance from
the original pile. The phenomenon is explained by Figure HV-2 which is an extract of
Figure 7.9 of GEO Publication 1/2006.
V-2
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HV
Figure HV-2 – Extract from GEO 1/2006 (Figure 7.9) to Explain Randolph’s
Approach in Pile Interaction of Settlement
So for the application to piles undergoing tension test, the settlement due to a test pile
carrying a compression load created onto the test pile will be calculated which should be
deducted from the up-rise of the pile.
Consider a socketed H-pile of cross section undergoing tension load test in soil as
indicated in Figure HV-3.
Reaction
pile E0 = 10MPa
1.5m E value
of Soil
Profile
Test pile
L=30m 305305223 H-pile
1.5m
Total pile perimeter is 1.3272m.
Reaction The diameter of the circle with
pile the same perimeter is
EL = 200MPa d = 1.3272/=0.4225m.
Plan View
Eb = 5GPa (rock) 5m AE of the pile is 2051060.0284
= 5822000kN,
So equivalent E of the circular
v of soil and rock are 0.35 pile is 5822000/(0.42242/4)
= 41534532 kNm2.
V-3
An Explanatory Handbook to Code of Practice for Foundations 2017
Appendix HV
The maximum test tension load on the socketed pile is 6100kN so that each reaction pile
carries 3050kN compression. The followings are calculated for estimation of settlement
of the reaction pile by (Eqn HV-1) :
r d b d 1.0
E0 10000
E0 10000 kPa G0 3703.7 kPa
21 v 21 0.35
EL 200000
EL 200000 kPa GL 74074.07 kPa
21 v 21 0.35
Eb 5000000
Eb 5000000 kPa Gb 1851851.85 kPa
21 v 21 0.35
GL Gb 0.04 (ratio of soil and rock shear moduli at rock top level)
G GL 3703.7 74074.07 / 2 / 74074.07 0.525
E p GL 41534532 74074.07 560.716
rm 0.25 2.5 1 v 0.25 L
0.25 2.5 0.5251 0.35 0.25 0.0430 8.224 m
ln2rm d ln2 8.224 / 0.4225 3.6618
L 2 2 L d 2 2 3.6618 560.716 30 0.4225 4.4326
ro 0.5d
4 r tanh L 2 L
1
1 v s L d 2P
So t
4 r 4 tanh L L dG L
1 v s L d
8 r tanh L L
1
1 v L d P
So t 0.00405 m
2 r 2 tanh L L dG L
1 v L d
By (Eqn HV-3), the settlement induced on the test pile at S pi 1.5 m away is
(Note : in reality the variation of the G values of soil is not linear. An approximation
can be made by fitting a best line with least error through the G values measured at
different levels by the mathematical technique of linear regression.)
V-4
An Explanatory Handbook to Code of Practice for Foundations 2017 References
References
1. Attewell, P.B. and Farmer, L.W. Attenuation of Ground Vibrations from Pile Driving.
Ground Engineering, Vol. 6, No. 4, pp 26 – 29. (1973)
2. Azizi Fethi. Applied analysis in geotechnics, E & EN Spon Press, (2000).
3. Berezantsev, V.G.; Khristoforov, V.S.; Golubkov, V.N. Load Bearing Capacity and
Deformation of Piled Foundation, Proc, 5th Int. Conf. Soil Mechanics (1961). Vol. II pp11-15
4. Borowicka, H., Druckverteilug unter elastischen Platten. Ingenieur Archiv, Vol. X, No. 2, pp
113 – 125 (1939)
5. Bowles J.E. Foundation Analysis and Design. 5th Edition. The McGraw-Hill Companies, Inc.
(1996)
6. Braja M. Das Advanced Soil Mechanics Third Edition. Taylor & Francis London and New
York (2007)
7. British Standard Institute (BSI), CP2004 : September 1972 – Code of Practice for
Foundations. (1972)
8. British Standard Institute. BS5228-2:2009 Code of Practice for Noise and Vibration Control
on Construction and Open Sites Part 2: Vibration. (2009)
9. British Standard Institute. BS8004:1986 Code of Practice for Foundations. (1986)
10. British Standard Institute. BSEN 1538:2010+A1:2015 Execution of special geotechnical
works : Diaphragm Walls (2000)
11. British Standard Institute BSEN10025-1:2004 – Hot Rolled Product of Structural Steel (2004)
12. British Standard Institute BSEN14199-2005 – Execution of special geotechnical works –
Micropile Annex D (2005)
13. British Standard Institute BSEN1997-1:2004 Eurocode 7 – Geotechnical design (2004)
14. British Standard Institute BSEN1997-2:2007 Eurocode 7 – Geotechnical design (2007)
15. Broms, B.B. Lateral Resistance of Piles in Cohesive Soils, J.S.M.F.D., ASCE Vol. 90, SM2:
27 – 63 (1964a)
16. Broms, B.B. Lateral Resistance of Piles in Cohesionless Soils, J.S.M.F.D., ASCE Vol. 90,
SM3: 123 – 156 (1964b)
17. Building (Construction) Regulations (2012) The Government of SAR. Hong Kong (2012)
18. Building (Construction) Regulations (1985) The Government of SAR. Hong Kong (1985)
19. Buildings Department. Code of Practice for Foundations. The Government of SAR. Hong
Kong (2004).
20. Buildings Department. Code of Practice for Structural Use of Concrete 2013. The
Government of SAR. Hong Kong (2013).
21. Buildings Department. Code of Practice for Structural Use of Concrete 1987. The
Government of Hong Kong (1987).
22. Buildings Department. Code of Practice for Dead and Imposed Loads 2011. The
Government of SAR. Hong Kong (2011).
23. Buildings Department. Code of Practice for Structural Use of Steel 2011. The Government
of SAR. Hong Kong (2011).
24. Buildings Department. Explanatory Report to the Code of Practice for the Structural Use of
Steel 2005. The Government of SAR. Hong Kong (2005).
25. Buildings Department. Code of Practice for Structural Use of Steel 1987. The Government
of Hong Kong (1987).
26. Buildings Department. Code of Practice for Site Supervision 2009. The Government of SAR.
Hong Kong (2009).
27. Building Department. Practice Notes for Authorized Persons and Registered Structural
Engineers.
Ref 1
An Explanatory Handbook to Code of Practice for Foundations 2017 References
28. Burland J.B. and Wroth C.P. Settlement of Buildings and Associated Damage. Settlement of
Structures, Pentech Press, London (1975).
29. Canadian Geotechnical Society (CGS). Canadian Foundation Engineering Manual (1978)
30. Canadian Geotechnical Society (CGS). Canadian Foundation Engineering Manual 3rd
Edition (1992)
31. Canadian Geotechnical Society (CGS). Canadian Foundation Engineering Manual 4th
Edition (2006)
32. Chan, Y.C. Classification and Zoning of Marble Sites, GEO Publication No. 29, GEO.
(1994).
33. Cheng, Y.M. PLATE User Manual. (2013)
34. Chung, K.F. Study of Load Transfer Mechanism of Rock-Socketed Steel Piles. Design or
Rock-socketed Piles (Editor, Victor Li), HKU SPACE and Centre for Research &
Professional Development, pp. 19 – 25 (2005)
35. Civil Engineering and Development Department. GEO Publication 1/2006 Foundation
Design and Construction. The Government of SAR. Hong Kong (2006)
36. Civil Engineering and Development Department. GEOGUIDE 1 Guide to Retaining Wall
Design. The Government of SAR. Hong Kong (2000)
37. Civil Engineering and Development Department. GEOGUIDE 2 Guide to Rock and Soil
Descriptions. The Government of SAR. Hong Kong (2000)
38. Civil Engineering and Development Department. GEOGUIDE 3 Guide to Site Investigations.
The Government of SAR. Hong Kong (2000)
39. Civil Engineering and Development Department. GEOSPEC 1 Model Specification for
Prestressed Ground Anchors . The Government of SAR. Hong Kong (1989)
40. Civil Engineering and Development Department. Port Works Design Manual. The
Government of SAR. Hong Kong (2002)
41. Civil Engineering and Development Department – Standing Committee on Concrete
Technology (SCCT). Construction Standard CS1:2010 Volume 1 and 2. The Government of
SAR. Hong Kong (2010)
42. Civil Engineering and Development Department – Standing Committee on Concrete
Technology (SCCT). Construction Standard CS2:2012. The Government of SAR. Hong
Kong (2012)
43. Clark L.A., The provision of Tension and Compression Reinforcement to resist In-Plane
forces, Magazine of Concrete Research, Vol. 28, No. 94, March 1976 (1976)
44. Coates, R.C., Coutie, M.G. and Kong, F.K. Structural Analysis, 2nd Edition, Van Nostrand
Reinhold, pp 293 – 306 (1980)
45. Cornfield, G.M. Discussion on ‘Pile driving analysis by the wave equation’ by Smith.
Journal of the Soil Mechanics and Foundations Division, American Society of Civil
Engineers, vol. 87, no. SM1, pp 63-75. (1961)
46. Craig, R.F. Soil Mechanics, 7th Edition Spon Press, London & New York. (2004)
47. Davisson M.T. High Capacities Piles. Proceedings, Lecture Series, Innovation in Foundation
Construction, SM&FD, ASCE, Illinois Section, Chicago (1972)
48. Department of the Navy Naval Facilities Engineering command Washington. Design Manual
NAVFAC DM-7. March 1971. (1971)
49. Domone P. and Illston J. Construction Materials – their nature and behavior 4th Edition
Spon Press (2010)
50. Douglas D.J. and Davis E.H. The Movement of Buried Footings due to Moment and
Horizontal Load and the Movement of Anchor Plates. Géotechnique Vol. 14, pp115 – 132
51. Fellenius, B.H. Unified design of piles and pile groups. Transportation Research Board, no.
1169, pp 75-82. (1989).
Ref 2
An Explanatory Handbook to Code of Practice for Foundations 2017 References
52. Fleming K. Weltman A. Randolph M.F. Elson K. Piling Engineering 3rd Edition Taylor &
Francis London and New York. (2008)
53. Foster S.J., Marti, P., and Mojsilović N. (2003) Design of Reinforced Concrete Solids Using
Stress Analysis ACI Structural Journal November – December 2003.
54. Fox, E.N. The Mean Elastic Settlement of a Uniformly Loaded Area at a Depth below the
Ground Surface, Proceedings of the Second International Conference on Soil Mechanics and
Foundation Engineering, Rotterdam, Netherlands, Vol. 1, pp 129 – 132 (1948).
55. Fung, W.K., Wong, C.T. and Wong, M.K. (2004). A study on capacity for driven piles. The
HKIE Transactions Vol. 11, No. 3, pp 10-16.
56. Goran Camitz (2009). Corrosion and protection of steel piles and sheet piles in soil and
water Excerpt and translation of Report 93, Swedish Commission on Pile Research.
57. Hajnal, I., Morton, J., and Regele, Z., (1984) Construction of Diaphragm Walls – John Wiley
& Sons Inc.
58. Highways Department, Structural Design Manual for Highways and Railways Third Edition.
The Government of SAR. Hong Kong (2005)
59. Hiley, A. (1925), Rational Pile Driving Formula and its Application in Piling Practice
Explained, Engineering, 657 and 7
60. Hiller D.M., and Crabb G.I. Groundborne vibration caused by mecahnised construction
works. TRL Report 429. Wokingham: TRL, (2000).
61. Hirsch T.J. Modulus of Elasticity of Concrete Affected by Moduli of Cement Paste Matrix
and Aggregate Journal of the American Concrete Institute March 1962 (1962)
62. Housing Department, Standard Specific Specifications. The Government of SAR. Hong
Kong (2010).
63. Institution of Civil Engineers (ICE) (1954), Civil Engineering Codes of Practice No. 4 –
Foundations.
64. Johansen, K.W. Yield Line Theory, Cement and Concrete Association, London, (1962)
65. Lam, J. (2007). Termination criteria for high-capacity jacked and driven steel H-piles in
Hong Kong, PhD Thesis, University of Hong Kong.
66. Lam S.C., Law C.W., Cheng Y.M Elasto-plastic Analysis of Footing Structures by the
Stiffness Method with Subgrade Structure Interaction. The HKIE Transactions Vol. 16, No.
3 , September 2009 (2009)
67. Lam S.C., Law C.W., Discussion on the Design of RC Plate Bending Structures by the
‘Stress’ and ‘Node Force’ Methods. The HKIE Transactions Vol. 16, No. 2, June 2009
(2009)
68. Law C.W., Cheng Y.M., Su R.K.L., Approach for Reinforcement Design in Reinforced
Concrete Structures Based on 3-Dimensional Stress Field. The HKIE Transactions Vol. 14
No. 2, June 2007 (2007)
69. Law C.W., Parametric Studies on Buckling of Piles in Cohesionless Soils by Numerical
Methods The HKIE Transactions Vol. 21 No. 1, March 2013 (2013)
70. Law C.W., Cheng Y.M., Study on the P- Effects of Piles in Cohesionless Soil. The HKIE
Transactions Vol. 22 No. 3, September 2015 (2015)
71. Law C.W., Cheng Y.M., Analysis of piled foundations with piles rigidly jointed to the pile
caps under coupled support stiffness. The HKIE Transactions Vol. 23 No. 2, July 2016
(2016) pp106-117.
72. Law C.W., Li, Victor Bearing Capacity Factor Nq for Piles in Cohesionless Soil by
Berezantsev. Bridging Research and Practice – the VLA experience Edited by Victor Li Vol.
3 (2017)
73. Leung, K.W. Settlement of buildings founded on caissons bearing on soil. Proceedings of the
Fourth International Conference on Tall Buildings, Hong Kong & Shanghai, vol. 1, pp 377-
383 (1988)
Ref 3
An Explanatory Handbook to Code of Practice for Foundations 2017 References
74. Li, Victor. and Lam, J. New criteria for formulating final set table for high-capacity steel H-
piles, Bridging Research and Practice – the VLA Experience, Victor Li (ed.), Centre for
Research & Professional Development, pp 213-237. (2007)
75. Li, K.S. (2007) Use of plate load test for design of shallow foundations – A suggested
alternative practice. Bridging Research and Practice – the VLA Experience, pp191-199.
76. MathSoft Engineering & Education, Inc. Mathcad 2001i User’s Guide with Reference
Manual.
77. Meyerhof, G.G. Discussion on Paper by Skempton, A.W. and Macdonald, D.H., ‘The
Allowable Settlement of Buildings,’ Proc. Instn. Civ. Engrs., Pt. II, vol 5, 774 (1956)
78. Miguel A. Bermùdex and Pilar Alaejos Models for Chloride Diffusion Coefficients of
Concrete in Tidal Zone, ACI Materials Journal Vol 107. No. 1 January – February 2010.
(2010)
79. MTRC MTR New Works Design Standards Manual (2008).
80. Muki, R., Asymmetric problems of the theory of elasticity for a semi-infinite solid and a thick
plate. Progress in Solid Mechanics, Vol. 1, North Holland Publishing Co., Amsterdam. (1961)
81. Mylonakis, G. and Gazetas G. Settlement and Additional Internal Forces of Group Piles in
Layered Soil Géotechnique, 48(1): 55 – 72 (1998)
82. Neville A.M. Properties of Concrete Fourth Edition, Longman Group Limited. (1995)
83. Neville A.M. Neville on Concrete – An examination of Issues in Concrete Practice ACI
International (2003)
84. Ng W.W., Yau L.Y., Li H.M. and Tang W. New Failure Load Criterion for Large Diameter
Bored Piles in Weathered Geomaterials. Journal of Geotechnical and Geoenvironmental
Engineering. June 2001.
85. Poulos H.G. and Davis E.H. Elastic Solutions for soil and Rock Mechanics. John Wiley &
Sons (1974)
86. Poulos H.G. and Davis E.H. Pile Foundation Analysis and Design. John Wiley & Sons (1980)
87. Randolph M.F., A Theoretical Study of the Performance of Piles. A dissertation submitted
for the degree of Doctor of Philosophy at the University of Cambridge. December 1977.
(1977)
88. Randolph M.F., PIGLET A Computer Program for the Analysis and Design of Pile Groups
under General Loading Conditions. (1980)
89. Randolph, M.F. The response of flexible piles to lateral loading. Géotechnique, vol. 31, pp
247-259. (1981).
90. Randolph, M.F. Science and empiricism in pile foundation design: 43rd Rankine Lecture,
Géotechnique, vol. 53 No. 10, pp 847 – 875 (2003)
91. Randolph M.F. PIGLET Analysis and Design of Pile Groups Version 5.1 (Released May
2004, last edited July 2006)
92. Sewell R.J. & Kirk P.A. (2002) Geology of Tung Chung and Northshore Lantau Island.
Hong Kong Geological Survey Sheet Report No. 6, Geotechnical Engineering Office, Civil
Engineering Department, 91 p.
93. Siu, K.L. Review of design approaches for laterally-loaded caissons for building structures
on soil slopes. Proceedings of the Twelfth Annual Seminar, Geotechnical Division, Hong
Kong Institution of Engineers, Hong Kong, pp 67-89. (1992).
94. Skempton, A.W., MacDonald, D.H. Allowable Settlement of Structures, Proc. Instn. Civ.
Engrs., Pt. III, vol. 5, 727 – 768 (1956)
95. Smith E.A.L. Pile-driving Analysis by the Wave Equation – ASCE Transaction Vol. 127
1962 pp.1145 – 1193 (1962).
96. Standards New Zealand Concrete Standard Design Committee P3101 NZS 3101 : Part 1 and
2 Concrete Structures Standard and Commentary (2006)
Ref 4
An Explanatory Handbook to Code of Practice for Foundations 2017 References
97. Steinbrenner, W., Tafeln zur Setzungsberechnung, Die Strasse, Vol. 1, Oct, pp. 121-124.
(1934).
98. Terzaghi K. Evaluation of coefficients of subgrade reactions. Géotechnique, Vol. 5, pp297 –
326 (1955)
99. Terzaghi, K. & Peck, R.B. (1967). Soil Mechanics in Engineering Practice. (Second edition)
Wiley, New York.
100. Tijou, J.C. (1984). Integrity and dynamic testing of deep foundations – recent experiences in
Hong Kong (1981-83). Hong Kong Engineer, Vol. 12, no. 9, pp 15-22.
101. Timoshenko, S., and J. N. Goodier, Theory of Elasticity, 2nd ed., McGraw-Hill, New York
(1951).
102. Tomlinson M.J. Piled Design and Construction Practice 5th Edition. Taylor & Francis
(2008).
103. Triantafyllidis T. On the Application of the Hiley Formula in driving long piles.
Géotechnique 51, No. 10 pp. 891 – 895 (2001)
104. Wang, Y.H., Tham, L.G., Lee, P.K.K. and Yang J. A study on Rock-socketed Piles. Design of
Rock-socketed Piles (Editor, Victor Li), HKU SPACE and Centre for Research &
Professional Development, pp. 1 – 18 (2005)
105. Vaziri H., Simpson B. Pappin J. W. and Simpson L. Integrated forms of Mindlin’s equations.
Géotechnique Vol. 32, Issue 3 pp. 275 – 278 (1982)
106. Vesic, A.S. A study of Bearing Capacity of Deep Foundations Final Rep., Proj, B-189,
School of Civil Eng., Georgia, Inst. Tech., Atlanta, Ga (1967)
107. Vesic A.S. (1973) Analysis of ultimate loads for shallow foundations, Journal of the Soil
Mechanics and Foundations Division, ACSE, Vol.99, No. SM1, 45-73
108. Vesic A.S. (1975) Chapter 3 : Foundation Engineering Handbook, 1st Ed., ed. Winterkorn
and Fang, Van Nostrand Reinhold, 751 pp.
109. Wood R.H. The reinforcement of slabs in accordance with a pre-determined field of moments,
Concrete, 2, pp 69–76, U.K. (1968)
110. Zienkiewicz O.C., Taylor R.L. Zhu J.Z. Nithiarasu P. The Finite Element Method 6th Edition,
Oxford, New York, Elsevier/Butterworth-Heinemann (2005)
111. 王杰賢. 動力地基與基礎,科學出版社(北京)(2001)
112. 鄭大同,地基極限承載力的計算,中國工業出版社 (1979)
Ref 5