100% found this document useful (1 vote)
315 views2 pages

Pc-Me-F-0011-000 Inspection Report Underground Piping Check

The inspection report summarizes the inspection of underground piping for a project. It lists 16 items that were inspected, including the formation surface condition, pipe level, supports installed, holiday test, installation according to drawings, NDE completion, visual inspection, cleaning, partial backfill, hydrotest or NDE of field welds, wrapping joints, flushing, complete backfill, and other items. Space is provided for comments from the sub-contractor, Repco, and owner representatives who inspected or witnessed the inspection.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
315 views2 pages

Pc-Me-F-0011-000 Inspection Report Underground Piping Check

The inspection report summarizes the inspection of underground piping for a project. It lists 16 items that were inspected, including the formation surface condition, pipe level, supports installed, holiday test, installation according to drawings, NDE completion, visual inspection, cleaning, partial backfill, hydrotest or NDE of field welds, wrapping joints, flushing, complete backfill, and other items. Space is provided for comments from the sub-contractor, Repco, and owner representatives who inspected or witnessed the inspection.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

INSPECTION REPORT Date : _________________

Page. ________ of _______


UNDERGROUND PIPING CHECK
Rev. : _________________

Project Name : _______________________________ Owner : __________________________________

Application For Inspection No. : _____________________________________________

Dwg / Line No. : Location :


Result
Item Description Remark
Accept Reject
1 Formation Surface Condition
2 Formation Level Correct
3 Pipe Level Correct
4 Supports Installed
5 Holiday Test
6 Installed to Drawings
7 N.D.E. Complete
8 Visual
9 Clean Out
10 Partial Backfill for Anchors
11 Hydro Test or N.D.E. Field Welds
12 Wrapping Joints and Holiday Test
13 Flushing
14 Backfill Completely
15 Others