Pipe Culverts Check List
Pipe Culverts Check List
Project:
Orbital Highway Mesaieed to Salwa Road
Contract No.: C2013/118
IR Reference No.: Date:
Locations of work/ chainages:
3. Check for the identification marks left on the pipes while inspection and testing of pipes were
carried out in the manufacturing plant.
4. Check for any cracks in the pipes, which might have been caused during transportation or
loading and unloading.
CONSTRUCTION STAGE
a) Excavation
The excavation should be as per drawings but the following should be checked:
• The length of excavation caters for the number of pipes plus the spacing of pipes, which
should be half the diameter of the pipes but not less than 45cms.
• The depth of excavation should cater for the following:
Cushion above pipe of minimum 60cm of half the dia. or the pipe including pavements.
If the required cushion is not available due to low embankment embed the pipe in concrete. A
minimum of 200mm thick PCC or 150mm RCC all round the pipe shall be provided.
Granular/concrete bedding and foundation depending upon the height of embankment as per
relevant IRC clauses, if necessary.1/3 of pipe dia or 300mm will be buried below nala bed to
prevent scour.
• The distances between trenches for foundation of headwalls are such that it suits the
proposed pipe lengths.
c) Placing of Pipes
1. Check spacing between pipes is not less than 1/2 dia. of pipe or 50 cms, which ever is more.
2. Check pipes do not protrude beyond the headwalls.
3. Check cross slope of pipes is as per design.
4. Check joints of pipes properly done using collars or other methods as per specifications.
Joints shall be sealed with mortar, rubber gaskets or other sealing materials.
5. Check pipe joints properly cradled. Joints shall be kept covered and damp for at least 4 days.
d) Headwalls
1. Check headwall foundation is as per drawing.
2. Check headwall constructed as per design. If the same is of un-course rubble ensure
headers are used.
3. UCR masonry cannot be constructed properly to have a watertight joint at outer surface of
pipe at headwalls. In that case the pipes should be encased in 1:2:4 CC near the headwalls
to prevent floodwater from entering around the pipes.
4. Ensure curing for 7 days.