0% found this document useful (0 votes)
52 views8 pages

Leaking Underground Storage Tank Program: Use of In-Situ Slow-Release Oxygen Compound Injection

The document provides guidance on using in-situ slow-release oxygen compound injection to remediate groundwater contaminated by leaking underground storage tanks. It outlines preliminary site considerations like ensuring sufficient microorganisms, low levels of free product and heavy metals, and appropriate pH and nutrients. It also details requirements for characterizing the contaminant plume, including delineating extent and measuring contamination levels via soil and groundwater sampling. Designers must calculate the mass of contaminants to be treated in order to determine oxygen demand and proper remediation system design.

Uploaded by

Nurul Khas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
52 views8 pages

Leaking Underground Storage Tank Program: Use of In-Situ Slow-Release Oxygen Compound Injection

The document provides guidance on using in-situ slow-release oxygen compound injection to remediate groundwater contaminated by leaking underground storage tanks. It outlines preliminary site considerations like ensuring sufficient microorganisms, low levels of free product and heavy metals, and appropriate pH and nutrients. It also details requirements for characterizing the contaminant plume, including delineating extent and measuring contamination levels via soil and groundwater sampling. Designers must calculate the mass of contaminants to be treated in order to determine oxygen demand and proper remediation system design.

Uploaded by

Nurul Khas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

State of Illinois

Rod R. Blagojevich, Governor

Illinois Environmental Protection Agency


Douglas P. Scott, Director

Bioremediation Guidance

LEAKING UNDERGROUND STORAGE TANK PROGRAM:


Use of In-Situ Slow-Release Oxygen Compound Injection

A. INTRODUCTION

The intent of the information provided is to lay a framework from which Illinois EPA can
review these types of projects in a consistent manner across the Leaking Underground
Storage Tank Section. This basic framework should provide enough information to form a
design decision that has a reasonable chance of remediating a site. This information is
provided as a guide in reviewing in-situ, slow-release oxygen compound injection proposals
for groundwater remediation. This information provides a consistent approach to site
investigation and design requirements for these activities.

B. PRELIMINARY SITE CONSIDERATIONS

The following conditions can limit the success of bioremediation at the site and should be
considered in the initial assessment and the design. Site conditions that do not comply with
these general criteria should be taken into account in the design. Soil (below the
groundwater table) and groundwater samples required for these determinations can be
collected during the Site Investigation phase or as part of the plume sampling under
paragraph F below. The presence of microorganisms, free product amounts, pH of the
groundwater, soil porosity, heavy metal levels in the groundwater, and nutrients in the
groundwater are important considerations for the design of the remediation and are
discussed below:

1. Microorganisms

A soil sample should be collected at or just below the groundwater surface in an area of
the site with little or no impact from the release (outside the contaminant plume). A
greater number of microorganisms will be found attached to the soil. There is not a need
to test a groundwater sample for the presence of microorganisms. Sufficient
microorganisms must be present in the soil. Generally, 1000 colony-forming units (CFU)
per gram or more are sufficient. Microorganisms may be added (bioaugmentation) to
meet this requirement; however, the designer should know why the indigenous
microorganisms were limited and correct this problem, or bioaugmentaion may also not
work.

Illinois Bureau of Land April 2007


Environmental 1021 North Grand Avenue East
Protection Agency Springfield, Illinois 62702
2. Free Product

Free product must not be present to any great extent (not beyond a sheen). Based on
the information provided to the Illinois EPA to date, the remediation of free product with
slow-release oxygen compounds is generally ineffective.

3. pH

The upper foot of the groundwater surface should be tested (one sample). This sample
should be collected from an area of the contaminant plume with the highest levels of
contaminants. In most cases, the pH should be between six and eight. If it is not, the
designer must address what impact the pH will have on the bioremediation process.

4. Soil Porosity

A soil sample from the contaminated zone should be collected and tested for soil
porosity. This soil sample should be collected at or near the groundwater surface in the
saturated zone. Porosity is a measure of the void space between soil particles and is
used to estimate the volume of dissolved contaminants in the saturated zone.

5. Heavy Metals

Heavy metals can be toxic to microorganisms. Testing should be conducted on the


groundwater (sample at or near the groundwater surface) for iron, zinc, lead, arsenic,
barium, cadmium, chromium, mercury, selenium, and silver. This sample should be
collected from an area of the contaminant plume with the highest levels of contaminants.
Groundwater levels for iron above 10 mg/l, zinc above 20 mg/l, and lead above 900 mg/l
have been shown to inhibit bioremediation. Also, the U.S. EPA recommends that total
heavy metals (arsenic, barium, lead, cadmium, chromium, mercury, selenium, and silver)
not exceed 2500 mg/l. If heavy metals are present in excess of these amounts, the
designer should discuss their impact on the bioremediation process.

6. Nutrients

Nutrients are required for cell growth. A sample of groundwater, from an area of the
contaminant plume with the highest levels of contaminants, should be analyzed for
nitrogen and phosphorus. See discussion in paragraph I for nutrient design
requirements.

C. WHAT ARE THE CONTAMINANTS OF CONCERN (COC)?

The COC for petroleum leaking underground storage tanks (USTs) are defined in the
regulations. The focus of this guidance is primarily benzene, ethylbenzene, toluene, xylenes
(BTEX) and polynuclear aromatics (PNAs). There is not a lot of information available on
bioremediation of PNAs; however, an allowance must be made to account for their

2
bioremediation in conjunction with BTEX. PNAs will also require a longer time frame for
remediation. The remediation objectives to be achieved are outlined in the Tiered Approach
to Corrective Action Objectives (TACO), Part 742 regulations. Leaking UST Section project
managers will use a goal of complete destruction (non-detect) of the COC even though such
levels may not be required to meet Part 742. This will build in a level of conservatism.

D. HAS THE PLUME BEEN DELINEATED?

The estimated limits of the groundwater plume must be known. This information should
include:

1. The dissolved level in the groundwater.

2. The adsorbed level on soil below the groundwater table (this includes the capillary
fringe). The adsorbed levels and dissolved levels must be considered (levels above the
soil sorption capability will eventually be desorbed to the groundwater).

3. The level in the unsaturated soil zone above the groundwater. If this soil is not removed,
it will continue to act as a source of contaminants and should be considered in the
design. Modeling (i.e., TACO) of the concentration of these contaminants can be used to
predict their impact on the groundwater concentrations. Based on the information
provided to the Illinois EPA to date, the remediation of the unsaturated zone with slow-
release oxygen compounds is generally ineffective.

E. HYDRAULIC CONDUCTIVITY

This information is required for all impacted zones that are saturated with groundwater and
are going to be bioremediated. A hydraulic conductivity of greater than 1x10-7 cm/sec is
recommended. The hydraulic conductivity will affect the amount of time that will be required
to inject the remediation material and the number of injection points.

F. WHAT ARE THE CONTAMINATION LEVELS?

For contaminant plumes of one-half acre or less, five borings should be completed and
groundwater and soil samples (below the water table – upper one foot of the saturated zone)
collected. One boring should be located at the upgradient (based on groundwater flow
direction) edge of the contaminant plume, one from the downgradient edge, and three across
the center of the plume (perpendicular to the direction of groundwater flow). These five
groundwater and saturated soil samples should be tested for Total Petroleum Hydrocarbons
(TPH), Chemical Oxygen Demand (COD), and eight heavy metals (total in soil, dissolved in
groundwater). The eight heavy metals are arsenic, barium, cadmium, chromium, lead,
mercury, selenium, and silver. The groundwater at each of these locations should also be
analyzed for nitrogen and phosphorus. If the plume is greater than one-half acre, one
additional boring (for a saturated soil and groundwater sample) should be collected for each
additional one-half acre, or portion thereof. Additional samples can be located based on the

3
plume shape, dimensions, and locations of previous borings to best characterize the
contaminant levels in the plume.

G. WHAT IS THE MASS OF CONTAMINANTS TO BE TREATED?

Using the information obtained from the borings, find an average concentration of
contaminants in the saturated soil and groundwater. The higher level of either TPH or COD
should be used to find this average. The amount of oxygen required to remediate the site
must satisfy the oxygen demand of all oxygen users (COD) found in the borings, not just the
petroleum constituents (TPH). In most cases, the COD will be higher than the TPH values at
a leaking UST site. Once the average concentration in the saturated soil and groundwater is
known, the mass of contaminants to be treated can be calculated. Although a portion of the
contaminants adsorbed to the saturated soil will not dissolve into the groundwater, use of the
average amount in the saturated soil is conservative. The mass of contaminants in the
saturated soil samples should be greater than the mass found in the groundwater samples.
Then, calculate the mass of contaminants requiring remediation using the higher of the
saturated soil or groundwater TPH or COD concentrations. The following example
demonstrates how to calculate this amount:

Highest average concentration (TPH or COD) = 5.4 ppm


Volume of contaminated mass (groundwater plume) = 1,000 cy

[Assume saturated clay weighs 118 lb/cf (3,186 lb/cy) and sand weighs 124 lb/cf (3348
lb/cy)]

The total mass of contaminants is conservatively estimated to be:

5.4 x (3200 lb/cy x 1000 cy) = 17 lbs


1 x 106

H. WHAT AMOUNTS OF OXYGEN ARE REQUIRED TO REMEDIATE THE COC?

Once the total mass of contaminants is known, the amount of oxygen required can be
calculated. As a rule of thumb, three pounds of oxygen are required per one pound of
hydrocarbon. The stoichiometric amount of oxygen required for each contaminant could be
calculated and added together to get the amount of oxygen required. As an example, the
amount of oxygen needed to degrade benzene is:

C6H6 + 7.5 O2 = 6CO2 + 3 H2O

[Molecular weights: C = 12, H = 1, and O = 16]

C6H6 (12 x 6) + (1 x 6) = 78
7.5 O2 [7.5 x (16 x 2)] = 240

4
Therefore, it would take 240 pounds of oxygen to degrade 78 pounds of benzene, or 3.08
(240/78) pounds of oxygen per pound of benzene.

Illinois EPA assumes three pounds of O2 are required per pound of contaminant (TPH or
COD). From the example in paragraph G, it was determined that 17 lbs of contaminants
require remediation; therefore, 51 lbs (17 lb X 3 lb O2/lb of contaminant) of oxygen would be
needed.

I. ARE NUTRIENTS REQUIRED?

The following two tables demonstrate a method for calculating whether macronutrient
addition may be required for bioremediation at the site. The carbon amount can be based on
the TPH/COD level used to calculate the amount of contamination. These calculations
provide information as to the amount of macronutrients required to grow new cells and
increase the bacterial colony. Biomass will continue to form as long as a continuous supply
of carbon and nutrients exists. For estimating purposes, use an approximate mass ratio of
C:N:P = 1:0.176:0.024 (carbon, nitrogen, phosphorous).

TABLE 1 - EQUIVALENT MASS CALCULATION OF


MICROORGANISM STOICHIOMETRY

ELEMENT CARBON NITROGEN PHOSPHORUS

Molar Ratio 106 16 1


(moles)

Molecular Wt. 12 14 31
(grams/mole)

Mass Ratio 1272 224 31


(grams)

Per Gram of 1 0.176 0.024


Carbon

TABLE 2 - SAMPLE MASS BALANCE CALCULATION


TO DETERMINE NUTRITIONAL NEEDS

CALCULATION CARBON NITROGEN PHOSPHORUS


STEP

(1) Mass of 5.4


Carbon Present

(2) Mass of Carbon 5.4 0.95 0.13


Present to
Bionutrients
Required
(mg/l)

(3) Nutrients Present 5.4 0.2 0.03


(mg/l)

5
(4) Bionutrient 0 0.75 0.1
Deficiency (mg/l)
Step (2) - (3)

J. HOW MUCH PRODUCT IS REQUIRED?

1. The amount of oxygen by weight (in percent) in the product and an estimate of how much
will actually be released for bioremediation should be provided. Manufacturers provide
the amount of oxygen contained in their product. Normally this information is provided in
a lb/lb ratio. For example, if a manufacturer claims the product contains ten percent
oxygen by weight, the product will have one pound of oxygen available for every ten
pounds of product.

The difficult part is estimating how much of this actual oxygen content will be released
during the process. Using the calculated oxygen requirement of 51 lbs from paragraph H
above, the amount of this product that will be required is 510 lbs [51 lb/0.1 (10 percent)],
assuming all available oxygen is released. A reasonable discussion of the amount of
oxygen available in the product versus the amount released under field conditions is
required. Since it is unlikely the total amount of oxygen available will be released, Illinois
EPA will allow a factor of safety of 20 to 30 percent increase in the amount of product
required. So if 510 lbs of a product are required from the calculations, this amount may
be increased to 665 lbs [510 lbs x 1.3 (30 percent)].

2. The amount of nutrients to be added is calculated using the tables and example under
paragraph I above.

3. Always ensure the products injected will not cause violations of the groundwater quality
standards for constituents in the product. A thorough knowledge of the impurities and
additives in a product and their potential impact on the groundwater is required.

K. RADIUS OF INFLUENCE, NUMBER OF INJECTIONS, AND LAYOUT OF INJECTION


PATTERN

1. What radius of influence can be achieved?

Four feet in one hour may be acceptable; however, four feet in six hours may make for an
extremely long remediation. There are design changes that can improve delivery time
such as changing the injection pressure.

Determining the location and number of injection wells required for a one-time application
is the critical factor in the design of in-situ bioremediation. The design considerations are
based on a one-time injection of oxygen. Injection wells and/or infiltration galleries
should be located to provide distribution of the electron (O2) acceptor and nutrients
throughout the area targeted for remediation. Determining the area of influence is a key
parameter for proper distribution of the product into the ground. Injection pressure,
hydraulic conductivity (K), hydraulic gradient (i), and porosity (n) are important elements

6
to calculate an approximate area of influence. Darcy’s Law can be used to estimate the
area of influence. Assuming the length (Δl) is half of the radius of influence, use the
injection pressure (psi) and an initial estimate of the radius of influence (ft) to calculate
the time required to achieve this radius. The amount of time required should be
evaluated for reasonableness. An example of this type of calculation follows:

v = K Δh/Δl, where v = Darcy Velocity

va = Ki/n, where va = Interstitial Velocity, (ft/sec)


K = Hydraulic Conductivity, (ft/sec)
i = Hydraulic Gradient, Δh/Δl (ft/ft)
n = Porosity of Aquifer Material, (percent)

Generally, the product is injected into the ground with a pressure ranging from 250 to
2500 psi. To simplify the calculations, several assumptions are made to calculate the
area of influence and interstitial velocity. Assuming a pressure of 1500 psi, an
approximate area of influence of 4 feet, and K = 1 x 10-4 cm/sec, as well as the given
density of water, 62.4 lb/ft3:

va = Ki/n = 3.28X10-6 ft/sec X 3847 = 0.0126 ft/sec = 0.76 ft/min

where K = 1X10-4 cm/sec = 3.28X10-6 ft/sec


Δh = (1500 lb/in2 x 144 in2/ft2) / (62.4 lb/ ft3) = 3462 ft
Δl = 2 ft (half of the design influence)
i = Δh/Δl = 3462 ft/2 ft = 1731 ft/ft
n = 45 percent (assumed)
i/n = 1731/0.45= 3847

Based on the assumptions, it is calculated that a four-foot (0.76 ft/min. x 5 min. = 3.80 ≈ 4
feet) radius of influence can be achieved in five minutes with an injection pressure of
1500 psi. Is this time frame reasonable? Is it reasonable to expect the design pressure
(psi) to be applied for the required time (in this example, 5 minutes) at each injection
point? The time required per injection can be decreased by increasing the injection
pressure and/or reducing the design radius of influence. Location of the injection points
should maximize the area of influence from each injection point (i.e., offset or staggered
centers).

2. How many injections are required?

Knowing the radius of influence, a layout of an injection pattern can be developed to


cover the plume that has been defined.

3. How much is injected per point?

The initial plume samples can then be used to lay out (estimate) the amounts of product
required in each area (based on the levels of contaminants).

7
L. WHAT MONITORING WILL BE REQUIRED?

It is recommended that sampling of the groundwater occur within a month prior to the
injection date, once after six months, and a final sampling at 12 months. Additional
injections would only be allowed if it is demonstrated that a reasonable level of remediation
has been achieved or the designer has provided justification for the lack of success. The
initial injection report should include a plan to improve the results. If the failure of the initial
injection cannot be addressed, future injections are discouraged. Sampling and analysis
should be conducted for the contaminants of concern (BTEX, PNA, etc.) during these
events.

M. USE OF MANUFACTURER’S CALCULATION SHEETS

Illinois EPA will not accept the calculation sheets provided from the manufacturer without
adequate documentation. The documentation should present a step-by-step breakdown of
each equation used in the spreadsheet, an explanation of each input parameter for each
equation, and where the parameter comes from (site-specific and/or default numbers). The
inputs must be specific to the site in question. If the source of an input parameter cannot be
checked for accuracy or the calculations can’t be duplicated, Illinois EPA will request
additional information.

N. CLOSURE

Sampling of the groundwater must show compliance with the applicable Part 742
remediation objectives.

O. OTHER ITEMS TO CONSIDER

The proposed injection points are considered Class V wells and are regulated by the
Underground Injection Control (UIC) Program pursuant to 35 Ill. Adm. Code 704.148.
Therefore, a Class V Injection Well Inventory Form must be submitted. The form,
instructions, and well codes may be downloaded from
http://www.epa.state.il.us/land/regulatory-programs/underground-injection-control.html.

For additional information regarding the UIC Program, please contact Bur Filson at 217-782-
6070.

You might also like