MOM 08-05-2018

1. The minutes summarize a meeting that took place on May 8, 2018 at 12:00 hours at the TREC office to discuss the Ratimanzil Matunga project. 2. Key action items included instructing MS Enterprises to implement proper safety precautions and appoint a safety person by May 15th. MS Enterprises was also tasked with properly stacking materials and removing scrap from the site by May 15th. 3. Girder level slab construction was scheduled to be completed by June 13, 2018 according to the meeting. MS Enterprises was asked to submit building information modeling (BBS) data by the day of the meeting.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views

MOM 08-05-2018

1. The minutes summarize a meeting that took place on May 8, 2018 at 12:00 hours at the TREC office to discuss the Ratimanzil Matunga project. 2. Key action items included instructing MS Enterprises to implement proper safety precautions and appoint a safety person by May 15th. MS Enterprises was also tasked with properly stacking materials and removing scrap from the site by May 15th. 3. Girder level slab construction was scheduled to be completed by June 13, 2018 according to the meeting. MS Enterprises was asked to submit building information modeling (BBS) data by the day of the meeting.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

MINUTES OF MEETING

RATI MANZIL MATUNGA


Date & Time of Meeting : 08-05-2018 at 12:00 Hours. Venue of Meeting : TREC OFFICE
Meeting No.-MAY-01
Prepared By : RANJAN

Sr. No. Attendees Member Present Designation Project Team

1 √ Mr. Karan Jogani Joint MD RJ Realtors


2 √ Mr. Gulzar Malhotra COO TREC
3 √ Mr. Prem Kumar Bagalkot Planning Manager TREC
4 √ Ms. Akshata Parvatikar Sr. Engineer Planning TREC
5 √ Mr. Manoj K Pandey Project Manager TREC
6 √ Mr. Ranjan Project Engineer RJ Realtors
7 √ Mr. Rajkumar Prajapati Sr. Supervisor RJ Realtors
8 √ Mr. Bali Bhandari Partner M/s. M S Enterprises.
9 √ Mr. Shakeel Ghanchi Partner M/s. M S Enterprises.

Sr. no. Action Required Action By Status Remarks

Department Wise
A HSE

MS Enterprises has been strictly instructed to


Implement the proper safety measures at
1 Safety precautions implementation MS WIP construction. Incase there is no adherence to it
Enterprises
penalty is levied. Safety person to be appointed
by 15-05-2018

Material should be stacked in proper manner


MS
2 Removing of extra material from site. Enterprises WIP and same to be supervised by site team. Scrap
to be removed by 15-05-2018

B QA/QC
The activity is under progress and rectified by
MS
1 RCC Related repairs WIP MS Enterprises. Site team to take the strict
Enterprises action.
D Execution

Girder level slab to be completed by 13-Jun-


1 Progress Review for GIRDER level MS WIP 2018 as per Meeting held at TREC office on
Enterprises
dated 08-05-2018.

MS
2 Submition of BBS upto Girder & Whole Building Enterprises OPEN By today itself as disscused in meeting.

Site logistic plan to be prepared jointly with MS


MS
3 Mansoon preparation Enterprises OPEN Enterprises & Same shall be followed. Expected
Date 20-05-2018 for Mansoon
E Others

1 Micro Schedule upto Girder slab TREC OPEN

Next Meeting on : 15-05-2018