Measurement Ignition Timing G6

The repair report details work done on generator G6 at a 50 MW power plant. Measurements found the actual ignition timing on cylinders A10 and B10 differed from the panel CPU readings by 0.3°-1.3°. It is suggested to adjust the firing and offset on G6, with proposed new offset settings for each cylinder provided. An attachment includes diagrams of the current firing and offset readings for cylinders A10, B10, and the panel CPU.

Uploaded by

Nico FajRi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
75 views3 pages

Measurement Ignition Timing G6

The repair report details work done on generator G6 at a 50 MW power plant. Measurements found the actual ignition timing on cylinders A10 and B10 differed from the panel CPU readings by 0.3°-1.3°. It is suggested to adjust the firing and offset on G6, with proposed new offset settings for each cylinder provided. An attachment includes diagrams of the current firing and offset readings for cylinders A10, B10, and the panel CPU.

Uploaded by

Nico FajRi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Repair Work Report

Electrical / Mechanical Issues


THIS REPORT MUST BE COMPLETED AFTER INVESTIGATION HAS DONE & SUBMITTED
AFTER ALL HAS FINISHED
FINISHED.

Site: 50 MW Pekanbaru In charge by:

Location: Jl. Tanjung Datuk. PLN Teluk Lembu 1. Niko Fajri, Chaerudin,
udin, Erin Saputra

Date: August 22th , 2019 2. Zulkifli (Spv. site 50MW)

Time: 09:00

Fuel Engine ESN Engine Model Generator Model

Natural Gas 17219 B35:40V20AG2 AMG 1120SM08 DSE

Start date End date Generator ESN Running hour

August 22th 2019 August 22th 2019 4631676 31037

Trip Blackout Troubleshoot Others

Problem Describe

Summary:
Check the actual timing on G6,, Measurement result:
· Timing on panel CPU 95 = 14.0˚Btdc
· Offset on Cyl A10/F2 = 0.0˚ Adv
· Offset on Cyl B10/F1 = 0.0˚ Adv
· Timing on flywheel A10/F2 = 13.1˚Btdc
Btdc (Actual)
· Timing on flywheel B10/F1 = 12.7˚Btdc
Btdc (Actual)

The actual calculation measurement result on timing G6:


G6
Timing on panel CPU (+ -)) on offset Cyl A10 (14.0˚Btdc
( + 0.0˚ Adv = 14.0˚Btdc)) Different from the actual.
Timing on panel CPU (+ -)) on offset Cyl B10 (14.0
(14.0˚Btdc + 0.0˚ Adv = 14.0˚Btdc)) Different from the actual.

Suggestion:
Firing and offset on G6 need to be adjusted.
Cyl Ignition timing OFFSET
no A B

1 -0.3˚ -0.5˚
2 0˚ 0˚
3 0˚ 0˚
4 0˚ 0˚
5 -0.3˚ 0˚
6 0.8˚ 1.3˚
7 0˚ 0˚
8 1˚ 0˚
9 0˚ -1˚
10 0˚ 0˚
Offset on cpu 95

TYPE FAILURE: Mechanical Faulty Electrical Faulty Others


Repair:_
Service: _
Replace Part: _
Done by Vendor: _
Others:_
Reported by: FTS Team Checked by: FTS Dept Head In charge by
Signed: Signed: Signed:
Date: Date: Date:

Vpower format form / applicable for all troubleshoot issues


Attachment

Firing on panel CPU 95 Firing on A-Bank/A10

Firing on B-Bank/B10 Offset B10/F1

Offset A10/F2

Vpower format form / applicable for all troubleshoot issues