The document discusses chapter assignments in MS Project involving creating a Gantt chart and resource scheduling. It provides details of tasks, resources, durations, dependencies, and expected costs that could be used to create a Gantt chart and resource usage report in MS Project. Creating the Gantt chart and resource usage report as instructed would show the planned timing of tasks, resource assignments, and expenses per task to date based on the percentage of work completed.

Uploaded by

tan lee hui
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views

12.1 Consider A Project Gantt Chart With The Following Conditions

The document discusses chapter assignments in MS Project involving creating a Gantt chart and resource scheduling. It provides details of tasks, resources, durations, dependencies, and expected costs that could be used to create a Gantt chart and resource usage report in MS Project. Creating the Gantt chart and resource usage report as instructed would show the planned timing of tasks, resource assignments, and expenses per task to date based on the percentage of work completed.

Uploaded by

tan lee hui
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Module 6 Chapter Assignments:

12.1 Consider a project Gantt chart with the following conditions

(see Figure 12.22). Susan is your only programmer

and she is responsible for Activities 3 and 4, which overlap.

In resource-leveling the project so that Susan is only

working a maximum of 8 hours each day, what would the

new Gantt chart look like? What would be the new project

completion date?

A: The duration in days is with 8 hours per day.

Susan is the only programmer currently working on both activity 3 and 4; these activities cannot overlap
and need to be in series.

Activity 4 needs to be postponed by 2 days. With the new start state being Thursday, July 3.

Thereafter activity 6 starts after the completion of both 4 and 6 – with the new start date for 6 being set
one-day layer.

The new project completion should be the date Thursday, July 10 th.

13.1 Using the following data, enter the various tasks and create a Gantt chart using MS Project. Assign
the individuals responsible for each activity, and once you have completed the network, update it with
the percentage complete tool. What does the MS Project output file look like?
13.2 Now, suppose we assign costs to each of the resources in the following amounts:

Create the resource usage statement for the project as of the most recent update. What are project
expenses per task to date?

Resourc Resourc % Start End Expected


e Cost Activity Duration Pre e Completion Time Time Cost Used

Tom 50 A 6 NA Tom 100% 0 6 300 300

Liz 55 B 4 A Liz 75% 6 10 220 165

Rich 18 C 5 A Rich 50% 6 11 90 45


Gary 12.5 D 4 B,C Gary 0% 11 15 50 0

660 510

Progress 77.3%