Method Statements InterLock Works

This document provides a method statement for interlock works, outlining the procedures for properly installing interlock or paving blocks on a construction project. The key steps include: 1) Preparing the subgrade and base layers, 2) Installing the interlock tiles according to the approved drawings, ensuring proper thickness, alignment, and levels, 3) Filling the gaps with sand and compacting, and 4) Cleaning up and requesting inspection. Safety measures, required equipment, and reference materials are also specified.
Copyright
© © All Rights Reserved
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
162 views

Method Statements InterLock Works

This document provides a method statement for interlock works, outlining the procedures for properly installing interlock or paving blocks on a construction project. The key steps include: 1) Preparing the subgrade and base layers, 2) Installing the interlock tiles according to the approved drawings, ensuring proper thickness, alignment, and levels, 3) Filling the gaps with sand and compacting, and 4) Cleaning up and requesting inspection. Safety measures, required equipment, and reference materials are also specified.
Copyright
© © All Rights Reserved
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

 

Method Statement for Interlock Works

There are projects that sometimes can proceed for interlock or paving block
works while progressing the main project. This is sometime a technique of the
management to avoid workers to be idle if they have extra people while the
project is at starting stage.

So here are the method statement for interlock work that you might want to learn
how it will be done.

1. Title
Method Statement for Interlock Works

2. Purpose and scope

The purpose of this method statement is to describe the measures and ways of
properinstallation of interlock or paving block within our project. The work will be
as per the projectspecification and approved drawing.

3. Work procedure

1. Preparation
o Before interlock work starts, make sure that sub-grade is compacted
when the area is above natural ground.

o The sub-base shall be compacted with vibratory roller, size of roller


shall be suitable for the area where it could maneuver and can move
back and fort.

o Once compacted and met the specification requirement for


compaction and approved by Engineer, base course shall then be
placed above compacted sub-base but make sure thickness of the
bases are as per approved drawing.

o MEP rough-in or underground embedments (wherever applicable)


shall be in placed before interlock work commences.
o In the areas where there are kerb stone, the blinding shall be
constructed first serve as the base but make sure it shall be as per
drawing.

o The importance of pre-installation of kerb stone is to prevent the


migration or dis-alignment of interlock or block, and it will serve as
reference line or level.

o After compaction of base-course, the black sand shall be laid on it of


50 mm thick. There are cases that the bedding is mixed with cement to
adhere cohesiveness but it will be as per specification requirements.

o
2. Installation of Interlock or Paving block

o The minimum thickness of interlock shall be 60mm with various


colors. Approved interlock or paving block shall be used in
the installation.

o The dimension, thickness and design shall be as per approve shop


drawing.

o Land surveying shall be made to mark the required levels,


alignments, setting out lines for interlock as per approved drawing.
o Once the whole area is completed, fine sand can then laid on
the installed interlock or paving block. Sand shall be spread evenly on
the whole area.

o Plate compactor shall be used to compact the installed interlock or


paving blocks.

o Once compacted,  cleaning shall be followed to remove all excess


sand and damaged pieces.

o Inspection request will then be submitted to the Engineer for


approval.

4. Safety

1. All works shall comply with safety procedure or instruction set out in


project safety plan and Municipality rules and regulations.
2. Basic PPE to be worn by all staff or laborers.
3. All operatives involve in this work shall be inducted before entering
the site.
4. Tool box talk shall be conducted regularly.

5. Equipments and tools


1. Interlock cutter
2. Plate compactor
3. Wheel borrow
4. Meter
6. Materials and references
1. 60mm thick Interlock Tile or paving block
2. Approved Drawing
3. Specification