NS189
NS189
Document No : NW000-S0034
Amendment No : 3
NETWORK Approved By : Head of AEP&S
Approval Date : 03/11/2017
Review Date : 03/11/2020
ISSUE
For issue to all Ausgrid and Accredited Service Providers’ staff involved with the design of oil containment systems at major
substations, and is for reference by field, technical and engineering staff.
Ausgrid maintains a copy of this and other Network Standards together with updates and amendments on www.ausgrid.com.au.
Where this standard is issued as a controlled document replacing an earlier edition, remove and destroy the superseded document
DISCLAIMER
As Ausgrid’s standards are subject to ongoing review, the information contained in this document may be amended by Ausgrid at
any time. It is possible that conflict may exist between standard documents. In this event, the most recent standard shall prevail.
This document has been developed using information available from field and other sources and is suitable for most situations
encountered in Ausgrid. Particular conditions, projects or localities may require special or different practices. It is the responsibility
of the local manager, supervisor, assured quality contractor and the individuals involved to make sure that a safe system of work is
employed and that statutory requirements are met.
Ausgrid disclaims any and all liability to any person or persons for any procedure, process or any other thing done or not done, as a
result of this Standard.
All design work, and the associated supply of materials and equipment, must be undertaken in accordance with and consideration
of relevant legislative and regulatory requirements, latest revision of Ausgrid’s Network Standards and specifications and Australian
Standards. Designs submitted shall be declared as fit for purpose. Where the designer wishes to include a variation to a network
standard or an alternative material or equipment to that currently approved the designer must obtain authorisation from the Network
Standard owner before incorporating a variation to a Network Standard in a design.
External designers including those authorised as Accredited Service Providers will seek approval through the approved process as
outlined in NS181 Approval of Materials and Equipment and Network Standard Variations. Seeking approval will ensure Network
Standards are appropriately updated and that a consistent interpretation of the legislative framework is employed.
Notes: 1. Compliance with this Network Standard does not automatically satisfy the requirements of a Designer Safety Report. The
designer must comply with the provisions of the Workplace Health and Safety Regulation 2011 (NSW - Part 6.2 Duties of designer
of structure and person who commissions construction work) which requires the designer to provide a written safety report to the
person who commissioned the design. This report must be provided to Ausgrid in all instances, including where the design was
commissioned by or on behalf of a person who proposes to connect premises to Ausgrid’s network, and will form part of the
Designer Safety Report which must also be presented to Ausgrid. Further information is provided in Network Standard (NS) 212
Integrated Support Requirements for Ausgrid Network Assets.
2. Where the procedural requirements of this document conflict with contestable project procedures, the contestable project
procedures shall take precedent for the whole project or part thereof which is classified as contestable. Any external contact with
Ausgrid for contestable works projects is to be made via the Ausgrid officer responsible for facilitating the contestable project. The
Contestable Ausgrid officer will liaise with Ausgrid internal departments and specialists as necessary to fulfil the requirements of this
standard. All other technical aspects of this document which are not procedural in nature shall apply to contestable works projects.
INTERPRETATION
In the event that any user of this Standard considers that any of its provisions is uncertain, ambiguous or otherwise in need of
interpretation, the user should request Ausgrid to clarify the provision. Ausgrid’s interpretation shall then apply as though it was
included in the Standard, and is final and binding. No correspondence will be entered into with any person disputing the meaning of
the provision published in the Standard or the accuracy of Ausgrid’s interpretation.
KEYPOINTS
This standard has a summary of content labelled “KEYPOINTS FOR THIS STANDARD”. The inclusion or omission of items in this
summary does not signify any specific importance or criticality to the items described. It is meant to simply provide the reader with a
quick assessment of some of the major issues addressed by the standard. To fully appreciate the content and the requirements of
the standard it must be read in its entirety.
Where there are changes to this standard from the previously approved version, any previous shading is removed and the newly
affected paragraphs are shaded with a grey background. Where the document changes exceed 25% of the document content, any
grey background in the document is to be removed and the following words should be shown below the title block on the right hand
side of the page in bold and italic, for example, Supersedes – document details (for example, “Supersedes Document Type
(Category) Document No. Amendment No.”).
This standard details general design This section lists the basic design assumptions Specific design requirements are addressed as Specific design requirements are addressed
requirements for oil containment for major and principles used to design oil containment listed: as listed:
substations with the limitations as listed below systems within Ausgrid:
and the associated risks as indicated: Typical oil containment layouts given for For CBD and other major indoor
Basic design assumptions listed in Cl. 6.1 CBD and suburban major substations substations fire-fighting water
Applies to new and existing major New and existing systems reviewed in Cl. Bunding areas designed to minimise entry containment capacity shall be made for
substations with primary voltages of 6.2 of clean stormwater up to 90 minutes of expelled fire-fighting
33kV, 66kV and 132kV. For existing major substations, all areas Bunding designed to prevent burning fuel water
Controls apply to both normal operations with any oil-filled equipment containing spreading fire to adjoining equipment. For both non-rural and rural sites, the
and during emergency situations more than 1000 litres of oil will require oil Spray screens may be required if bund minimum containment storage for non-
Maintenance and operation of oil containment facilities unable to contain spray discharge. fixed firefighting is 20 minutes of one
containment facilities is specified For equipment less than 1000 litres or in Transformer roadways may have bunding hose with foam at 4 l/s
separately in NS190 Oil Containment areas designated low risk containment requirements The required minimum storage can be
Operational Requirements for Major may not be necessary. Bunding design requirements identified inclusive of volume available in bunded
Substations For new substation sites all oil-filled Secondary containment requirements areas plus any secondary storage or
Consideration given to different types of equipment will be bunded unless indicated determined by Ausgrid risk management overflow areas.
oil containment plant for various otherwise. assessment. Burn down rates can be included in
situations found in major substations. Due consideration to minimise Oil spill kits to be available for every major calculations for provisions of storage
All materials and equipment used in contamination of stormwater. substation where a full bund oil fire occurs.
construction of Ausgrid assets must be Principles for addressing three main risks Section 12 identifies requirements for oil Capacitors have specific containment
asbestos free. Selection criteria for oil containment water separators and oil containment provisions.
Three main risks to be addressed: systems based on Life Cycle Cost. tanks After an emergency, oil containment and
Catastrophic failure causing Criteria for preferred designs indicated for Section 13 identifies requirements for containment tanks must be emptied and
prolonged fire greenfield sites. drainage and associated structures remediation work undertaken.
Catastrophic failure large amounts For brownfield retrofit sites the preferred including pits, pipework, flame traps, Clean up should comply with
oil spreading off-site oil containment system is a closed valves, and pumps environmental guidelines and legislation
Minimise oil pollution during normal drainage PPS system. Requirements for decommissioning tanks
operation Drainage design philosophy for closed are provided.
systems and gravity drainage reviewed.
Some existing and temporary sites may
adopt an alternative approach.
Designer Safety Report required.
Site selection criteria to limit impact of oil
loss.
Oil containment discharge to Stormwater
and Sewer may have Regulatory Where to for more information?
requirements Section 14, 15, 16, 17
Network Standard
NS189
Oil Containment for Major Substations
Contents
1.0 PURPOSE
Network Standard NS189 details the general requirements for oil containment for major
substations. The objective of this standard is to specify the design requirements for oil containment
on site during the day to day operation of major substations as well as in emergency situations.
This standard also aims to provide consistency of design and to minimise the spread of fire.
2.0 SCOPE
This Standard covers the design of oil containment systems for new and existing major substations
with primary voltages of 132, 66 and 33 kV.
This Standard also considers the different types of treatment plant for the various situations found
in major substations.
This Standard also defines the performance criteria of a containment system based on discussions
between the Environment Protection Authority (EPA) and Ausgrid.
Maintenance and operation of oil containment facilities is specified in NS190 Oil Containment
Operational Requirements for Major Substations.
This Standard does not include provisions for pole top transformers and capacitors, distribution and
customer substations, kiosks, regulators, tap changer auto transformer substations, reclosers or oil
filled cables and their associated pressure vessels.
3.5 Literature
EMS 350: Environmental Management Strategy 350, Oil Filled Equipment.
Fire Safety Study Guideline, Hazardous Industry Planning Advisory Paper No. 2, Department of
Planning NSW Fire Brigades.
EG 100: Oil Handling and Spill Response Guideline.
4.0 DEFINITIONS
Accredited Service An individual or entity accredited by the NSW Department of Industry, Division of
Provider (ASP) Resources and Energy, in accordance with the Electricity Supply (Safety and Network
Management) Regulation 2014 (NSW).
ARI Average Recurrence Interval. This is the long-term number of years between the
occurrence of a flood as big as or larger than a selected event.
Bund A wall/barrier of sufficient height constructed around fluid filled equipment to contain
spillage of liquids.
Business An Ausgrid internal integrated policy and procedure framework that contains the
Management approved version of documents.
System (BMS)
Butterfly valve The valve used to close the outlet of an oil containment tank.
Closed Drainage A drainage system designed to retain liquids within a bunded area for treatment or
disposal as required.
Document control Ausgrid employees who work with printed copies of document must check the BMS
regularly to monitor version control. Documents are considered “UNCONTROLLED IF
PRINTED”, as indicated in the footer.
EGOWS Enhanced Gravity Oil and Water Separator. An oil containment tank developed by the
UNSW. The tank contains stainless steel baffles and flow retarding devices.
Fire Sprinklers Low flow rate water discharge nozzles not generally used on transformers.
2
First Flush 1 in 1 year ARI of 5 minutes duration plus 10mm/m of the catchment.
Flame trap A pit with a down turned pipe used as a fire quenching mechanism.
Gravity Drainage A drainage system designed to remove liquids to a remote location, such as an oil
containment tank, for retention and/or treatment prior to discharge.
Gravity separation Oil-water separation without the use of chemicals or mechanical means ie using
gravity only based on Stokes law. Single, double, triple stage separators and all PPSs
use gravity separation.
High Velocity A high velocity fire water sprinkler with a typical flow rate of 50 to 90 L/s, usually
Water Spray surrounding transformers.
Infiltration Trench filled with gravel used to discharge stormwater into groundwater.
trenches
Major Substation For the purpose of this document, major substation means zone and sub-
transmission substations with primary voltages of 132, 66 and 33 kV.
Neat Oil Where the flow of liquid through the system is predominantly oil.
Network Standard A document, including Network Planning Standards, that describes the Company's
minimum requirements for planning, design, construction, maintenance, technical
specification, environmental, property and metering activities on the distribution and
transmission network. These documents are stored in the Network Category of the
BMS repository.
Non Return Valve Also called a flap valve, it is a one way valve that prevents flow back up into the pipe.
Oil containment The oil containment system refers to the transformer bunds, together with a suitable
combination of flame traps, pipes, oil containment tank and Parallel Plate Separator
system as required. The oil containment system is not designed as an oil storage system. It is
designed for emergency situations and the treatment of minor oil contamination from
transformer bunds.
Parallel Plate Parallel Plate Coalescing Separator also known as a PPS. PPSs are gravity
Separator (PPS) separation separators.
PPM Parts per million. An oil-water concentration of 10ppm equals 10mg/l which is
equivalent to a mixture that is visibly free of oils and greases, i.e. no visible oil.
Review date The review date displayed in the header of the document is the future date for review
of a document. The default period is three years from the date of approval. However a
review may be mandated at any time where a need is identified due to changes in
legislation, organisational changes, restructures, occurrence of an incident or
changes in technology or work practice.
Sensitive Any parcel of land or waterway that has environmental attributes that contribute to the
environment retention and or creation of wildlife habitat, soils stability, or other vital ecological
functions. Examples of sensitive environment are national parks, wetlands and nature
reserves.
Surcharge A condition where the hydraulic capacity of the drain system is temporarily exceeded
and the amount of liquid that enters the system exceeds the conveyance capacity
Tank Refers to a vessel made from concrete or masonry that is usually wholly or partially
buried, that provides containment of lost oil and can also be an oil/water separator.
Waste Captured oil and sediment within the oil containment system.
Waterway Any river, stream, lake, lagoon, swamp, wetlands, unconfined surface water, natural
or artificial watercourse, dam or tidal waters (including the sea), or
Any water stored in artificial works, any water in water mains, water pipes or water
channels, or any underground or artesian water.
5.0 ASBESTOS
All materials and equipment used for construction of Ausgrid’s assets are to be free from Asbestos
and or Asbestos related products. Suppliers are expected to comply with the Work Health and
Safety Act 2011 (NSW) together with the Work Health and Safety Regulation 2011 (NSW) and
confirm in writing that all products supplied to Ausgrid contain no Asbestos related materials.
At existing substation sites, a site contamination and hazardous materials audit may be required
prior to work commencing on site.
Particular care shall be exercised when handling or working in the vicinity of existing asbestos
products. Items containing asbestos shall be disposed of properly. Ausgrid’s Asbestos Product /
Location Register shall be consulted prior to work commencing to identify relevant plant and
equipment. Asbestos related work shall only be carried out by suitably trained personnel and in
accordance with Ausgrid Network Standard NS211 Working with Asbestos Products.
6.0 INTRODUCTION
6.1 General
This document outlines Ausgrid’s minimum requirements for oil containment at major substations.
This Standard does not document sections from the relevant Australian Standard or requirements
of these standards unless a specific departure from the standard is required for major substation
specific purposes.
The provision of oil containment at major substations is based on the following basic assumptions:
Only one transformer will rupture at the one time releasing its entire contents into the oil
containment tank or into the bunded area where there is no gravity drainage.
No major rain event occurs simultaneously with an emergency situation.
The oil containment system is appropriately maintained and is free of excessive residual oil in
the tank i.e., less than 10% volume of the largest transformer.
Oil filled equipment is in good working order and does not continually leak significant amounts
of oil.
Oil containment tanks are designed for short term emergency oil retention only. The tanks do
not meet the design and legislative requirements for long term oil storage.
Replacement transformers and other oil filled equipment will not increase the volume of oil
requiring containment;
Major substations are generally not staffed, requiring the oil containment system to operate
automatically or to be a passive system wherever possible;
Oil-water concentration of 10ppm is equivalent to a mixture that is visibly free of oils and
greases, i.e. no visible oil.
The oil containment system is assumed to have a maintenance regime and operational
performance that is in accordance with NS190.
Gravity separation will not separate oil and foam contaminated water. In such cases,
secondary containment will be used.
Gravity separation systems will not work with oil degreasers or surfactants.
The oil water separator does not retain any contaminants other than transformer oil, e.g. it will
not remove dissolved pollutants or particles.
The use of a secondary containment area or emergency response process to manage the flow
of water when firefighting.
For all sites except CBD substations, a minimum of 20 minutes firefighting medium
containment is required by AS 1940. The flow rates shall be a minimum of 4 L/s (using foam)
but the overall volume shall be rounded up to 5,000 litres. Refer also to Section 14.
CBD sites shall have 90 minutes of firefighting water containment at the flow rate of the high
velocity water spray system. Refer also to Section 14.
For all sites, a risk assessment shall be undertaken to determine if greater containment
volumes are needed and shall consider the cost/ease of providing the additional containment
and the benefit from a risk reduction perspective.
Controlled overflow or surcharge into other bunds, or into secondary containment areas on the
site, are both acceptable under the application of firefighting medium. Refer also to Section 14
and Annexure A.
Foam is corrosive and therefore potentially damaging to other assets where overflow or
surcharge is allowed to occur.
1. Generally, older sites (pre 1990) have single, double or triple stage tank systems. Some ex-
Electricity Commission of NSW sites use a PPS system.
2. A few older sites have early PPS systems installed and were purposely used as trial sites to
determine the most appropriate system to install.
3. For new substation sites, one type of oil containment system uses a closed drainage design
with bund storage and a PPS system.
4. An alternative EGOWS gravity drainage system and tank uses a delayed release principle to
separate the oil and water.
5. Retrofit substation sites normally use a closed drainage PPS system with bund storage.
For existing major substations, all areas with any piece of oil filled equipment containing more than
1000 litres of oil generally require oil containment facilities. If the piece of equipment has less than
1000 litres or if the location with this piece of equipment is designated low risk by Ausgrid, then
containment may not be necessary. In this case, the equipment should be located such that it is not
in a drainage path to a waterway, or such that any oil lost will not create a hazardous situation to
the public, neighbouring buildings or equipment in accordance with AS 1940.
Due consideration must be made to minimise the potential for stormwater to become contaminated
with oil.
For new substation sites, all oil filled equipment shall be bunded, unless indicated otherwise by this
Network Standard.
High voltage capacitors generally do not require oil containment because they are sealed units that
contain minimal free oil. Refer also to Section 15 of this Standard.
The following principles shall be adopted to address the three main risks identified:
In a catastrophic failure, the oil containment system shall reduce the risk of fire spread
off site by containing the oil in the bund.
The PPS shall be designed to shut down upon neat oil flow through the separator. This
can be achieved by diverting the neat oil directly to the waste oil tank, filling it, and
triggering a shut-down of the equipment and the waste oil tank high level alarm.
In a catastrophic failure, the oil containment system shall reduce the risk of prolonged
fire (hence fire spread) by containing oil spillage and/or providing a quick draining route
for oil.
Oil containment bunds shall have a floor slope of 1% and pipes designed for the flow
rate of the firefighting water, which also facilitates the quick removal of oil from the
bund. Each oil containment bund is drained via a flame trap reducing the potential for
fire to reach the oil containment tank.
The oil containment tank provides an oil spill retention area away from the fire.
Bunds shall have capacity for the contents of the transformer plus approximately 5000
litres of firefighting medium. Some sites may require more than 5000 litres of additional
containment.
Oil shall be removed from the bund as soon as possible to avoid the risk of leakage to
other parts of the site.
Bunds shall contain oil in the area of loss thus preventing burning oil migrating off-site.
The oil containment bunds are designed to hold 100% of the oil volume to provide
adequate drainage time in the event that the pipes are partially blocked.
The bund shall be drained to an oil containment tank. The tank is designed to retain
110% volume of oil from one transformer.
EGOWS oil containment systems shall be fitted with a manual or automatic shut-off
valve at the outlet of the tank to facilitate the closing of the oil containment system to
prevent discharge of the firefighting medium. Overflow from the oil containment shall be
managed by directing it to a secondary containment area or by the emergency response
process.
Providing oil filled equipment is maintained in good working order and is not continually
leaking, the system shall minimise the day to day loss of oil to the environment.
During normal operation a stormwater discharge less than 10ppm of oils and greases
shall be achieved in all storm events. Larger storm events will cause the water to rise
inside the bunds while treated discharge from the PPS will continue at a constant rate.
Compliance of PPS discharges is dependent on proper maintenance in accordance with
NS 190.
Providing oil filled equipment is maintained in good working order and is not continually
leaking, the system shall minimise the day to day loss of oil to the environment.
During normal operation a stormwater discharge less than 10ppm of oils and greases
shall be achieved. In some higher rainfall events higher oil and water discharges may
be experienced.
The LCC analysis shall capture all site specific capital costs and include O&M costs that accurately
reflect the activities required to maintain the functional performance of the equipment.
For Greenfield sites the following criteria will typically determine the preferred oil containment
system when assessed in conjunction with a LCC analysis;
Urban locations in the vicinity of Ausgrid’s Services Maintenance depots where response and
travel times are low and operation and maintenance costs are reduced.
Locations where effective gravity drainage is difficult or costly to achieve.
Congested sites where a gravity system either cannot be readily accommodated, or would
constrain an efficient site layout for plant and equipment.
Sites where the EGOWS tank cannot be located adjacent to, or in close proximity (10m to
15m) of, the transformer bunds.
Sites where the EGOWS tank requires extra strengthening to support mobile crane outrigger
loadings (e.g. in the vicinity of TX bays).
Locations where difficult site conditions such as rock, low soil strength, high water table,
restricted access etc. adds significant costs to the civil works.
Locations where early civil works for gravity systems are an expected critical path item and a
significant project benefit can be realised through reduced program duration and site costs.
Environmentally sensitive areas where strict discharge limits cannot be satisfied by gravity
systems under all conditions (e.g. high flowrates).
b. Gravity drainage systems may be preferred for -
Rural locations where response and travel times are high and O&M costs are increased for
PPS systems.
Sites where sufficient space is available to locate the gravity system without significant impact
on the efficient site layout of plant and equipment.
Sites where the EGOWS tank can be optimally located, namely;
a) adjacent to, or nearby (10m to 15m), the transformer bunds, and
c) without additional strengthening of the tank to support mobile crane outrigger loadings.
Locations with suitable geotechnical conditions and good site access that enable low cost civil
construction
Locations where the civil works for gravity systems will have minimal impact on the program
duration.
High hazard locations where the continuous removal of fuel by gravity drainage may provide a
reduced fire risk following a major oil spill.
CBD and other locations which require a high velocity water spray system for the transformer
area.
Sites where significant LCC benefits can be realised by combining the functions of an EGOWS
with required On-Site Stormwater Detention (OSD) into one tank unit.
For a generic Greenfield site, a closed drainage PPS system using bund storage can be
comparable, on a LCC basis, with a gravity drainage system using an EGOWS tank. Selection of
the preferred oil containment system should therefore be based on the site specific criteria
indicated above, together with a LCC analysis.
For existing Brownfield retrofit sites the preferred oil containment system is typically a closed
drainage PPS system. The alternative gravity drainage system is generally less favourable and can
incur significant additional costs and construction risk due to existing underground services,
together with increased site disturbance and site works duration.
For all oil containment systems, the design should be optimised for each site. This will generally
require;
Early incorporation into the substation site layout design to optimise all aspects of the
substation design and associated works.
A system design that is as compact as possible.
Innovation in design to take advantage of any multi-use functions (e.g. combined EGOWS and
OSD where possible).
For gravity drainage systems, all drainage shall be accomplished by gravitational action where
possible. In cases where gravity systems are required but complete gravity drainage is not possible
(e.g. CBD substations), fixed pumps may be used at the outlet of an oil containment tank or
storage tank.
Allowance should be made for run-off from a significant rainfall event for the region. The retained
water may be contaminated and require disposal off-site.
The use of a PPS system on a temporary basis should be considered. The PPS can be reused at
another site upon decommissioning of the temporary installation.
The design of the oil containment system shall consider the relevant WHS requirements for
construction, operation and maintenance of the system.
The Designer Safety Report shall comply with the requirements of NS 210 and shall be prepared at
the completion of the design development process.
A Trade Waste Agreement (TWA) is required and may have specific monitoring and discharge
requirements. Refer to relevant authorities for all TWA requirements and conditions.
Ausgrid currently adopts a discharge requirement of 10ppm for oils and greases. Refer to the
TWA for the relevant criteria.
Discharge of treated water to sewers is not preferred and shall only be done so when connection to
stormwater is not practical.
9.2 Stormwater
For oil containment discharge to stormwater:
Ausgrid currently adopts a discharge requirement of 10ppm for oils and greases.
No licence is required for connection to stormwater in accordance with the current
environmental management strategy, EMS 350.
Ensure appropriate Approvals are sought for new connections to Local Council, Sydney Water
or Hunter Water Corporation Stormwater Systems.
Each transformer has a bund which is drained to a storage tank or designated overflow area. The
tank is designed to take a minimum of 90 minutes of high velocity water spray from one of the
transformer bays and 110% of the oil volume of the largest transformer. The tank may overflow into
the cable basement or other area in the event of high velocity water spray operation greater than a
minimum of 90 minutes. The overflow is taken from the bottom of the tank.
Where stormwater can enter the system, the contents of the tank are pumped to a PPS and treated
prior to discharge to stormwater or sewer.
During emergency situations in existing CBD substations with PPS systems, the PPS is designed
to be shut down by the operation of the transformer protection system and activation of the high
velocity water spray system.
Refer to Clause 12.1 for a description of PPS shut down modes under emergency operation.
CBD capacitor bays containing capacitors with oil shall also have bunds and may be fitted with
sprinklers. Where sprinklers are fitted, the bunded areas shall be connected to an independent
storage tank designed for 90 minutes of sprinkler discharge. The contents of this tank are not
treated. Any waste collected, is taken and disposed of off-site. A tank pump out point is provided
for tanker access.
Elevation
The management of stormwater, and of any potential oil contamination, will vary depending on
whether a closed or gravity drainage system is adopted for oil containment.
The transformers are individually bunded and any discharge points are kept normally closed.
Automatically operated pumps are provided within the bunds together with suitable bund sumps
and above ground pipes constructed to the requirements of Clause 13.1.1. All liquids are pumped
to a PPS oil/water separator and treated prior to discharge to stormwater. Further details of the
PPS system are provided in Clause 12.1.
The bund storage is sized to retain all oil spills, with a suitable margin for rainwater and/or fire-
fighting medium. Any overflow from the bund area will be directed to a secondary containment
storage area or managed by the emergency response process. Secondary containment storage
areas shall be designed to the requirements of Clause 11.6 or as specified by a risk management
approach, determined by Ausgrid.
Plan
The EGOWS is manually closed by a butterfly valve at the tank outlet upon application of
firefighting water. The overflow from the oil containment tank shall be directed to a secondary
containment area or managed by the emergency response process. Secondary containment areas
shall be designed to the requirements of Clause 11.6 or as specified by a risk management
approach, determined by Ausgrid.
Elevation
Elevation
The extent of bunds shall be such that burning fuel cannot propagate the spread of fire to adjoining
transformers, structures and adjacent premises and shall meet the requirements of AS 1940.
Where the transformer radiators are positioned in very close proximity to the transformer roadway,
spray screens need only be placed to a maximum height of 1.5 m above the bund wall.
Spray screens near the transformer radiators shall be louvered to allow sufficient air flow around
the radiators. These spray screens are to be removable to allow access for maintenance.
At existing sites, this requirement also applies, but only where it is practicable without the need for
laying of new drainage pipes.
For sites of restricted size, it may be viable to use smaller transformer bay areas and drain the
transformer roadway within the 1:2 spray zone directly to an oil containment tank. The required
tank size may increase as a result due to higher stormwater inflows. A risk assessment and LCC
analysis shall be provided to evaluate the alternative oil containment arrangements and site
layouts.
Permanent bunds shall be constructed from reinforced concrete. In instances where the bunds will
be temporary, earthen bunds are permitted.
All bunds shall be able to take loading from a spray screen. This allows flexibility for placing larger
transformers in bunds and maintaining AS 1940 requirements.
Removable bund walls may need to be provided at some locations as specified by Ausgrid.
Generally, these locations will be limited to sites with raised transformer plinths.
Any openings in the bund floor for power cables shall be raised above the bund floor, or otherwise
the floor sloped away from the opening to avoid ponding. All seals to the openings shall be gas
tight. Refer to drawing A4-190509 for typical design details.
Where secondary cables pass through a bund floor opening, the opening shall be raised using
internal bunding to a minimum 50 mm above the bund wall height. Refer to drawing A3-225716 for
typical design details.
The Ausgrid currently accepted PPS unit is the Ovivo “EnviroSEP OS 7500” supplied by Ovivo or
an approved equivalent. The PPS shall be correctly installed and fully commissioned on site with a
minimum 12 months defects liability period to ensure effective long term operation of the system.
Refer to Annexure C for the inspection requirements and hold points associated with PPS system
installation and commissioning.
The PPS control panel, and the motor-pump arrangement that supplies the PPS, shall be installed
above the bund high water level in order to prevent the equipment flooding in the event of bund
filling. The control panel shall also be installed in a location accessible from outside the bund
The PPS shall be fitted with waste oil tank that triggers the pump to stop when full. Testing and
maintenance specifications shall be supplied and verified by the manufacturer.
The PPS power supply shall be dedicated and fitted with a Residual Current Device (RCD) unit at
the point of supply.
The PPS system shall provide alarm signals to the PPS control panel for the following conditions
as a minimum:
For Item c) the high level float switch shall be located in the sump just clear of the grate. The alarm
signal to SCADA is to be delayed by four hours.
Should any of these alarms activate, a flashing light mounted on top of the control panel is to
activate. In addition, suitable signals can be sent via the communications network identifying the
type of fault and any further data as required.
Only one alarm signal shall be sent to the control room via SCADA.
a) shut down when the waste oil tank high level is activated, and
During higher intensity storm events the EGOWS could discharge oil/water of up to 100ppm or
greater. However, these events are rare and generally the discharge concentrations would be
much lower.
In environmentally sensitive areas the EGOWS tank may need to be increased in size where it is
necessary to achieve the required discharge limits for these higher intensity storm events.
Alternatively, where the site layout permits, a non-overflow tank design can be installed that
complies under all storm events. This system maintains a constant discharge and allows the inflow
to surcharge into the bund areas. The EGOWS tank will generally require access covers that are
raised to bund height.
EGOWS systems shall be installed in accordance with a site specific design to be provided by
Ausgrid for each substation. Refer to Annexure C for the inspection and hold points associated with
oil-water separator system installation and commissioning.
Closure of the valves will allow the oil containment system to surcharge in such a way as to allow
overflow to be directed to a secondary containment area, whilst retaining bulk oil in the oil
containment tank. Alternatively, the flow can be surcharged into the transformer bund areas which
will provide a large secondary containment volume.
Where secondary containment is not viable an emergency plan response process will be required
to manage the surcharge overflow.
All tanks shall have 1.8m internal head clearance and shall contain internal vertical ladders or step
irons.
Enclosed tanks are confined spaces and will require signage and confined space entry procedures
in accordance with AS 2865 and WHS Regulation 2011. Refer to NS 190 for further details.
Tanks shall be provided with a 500 mm wide concrete slab at each end of the tank for the complete
width of the tank. This will allow erection of the fall arrest/confined space rescue supporting frame.
Where possible, allow 1 metre minimum access space around the access points of the tank for the
erection of fall arrest equipment.
All tanks are to be labelled with confined space signage located just inside the access covers on
the side edge of the roof slab.
All tanks shall be suitably located to allow for removal of hatches and to enable ready access by
maintenance crews and cleanout tankers
For closed drainage PPS systems a detailed commissioning procedure and checklist is provided in
Annexure B.
Pipework shall be constructed using the following materials and designed to the appropriate
criteria;
Construction of above ground pipework is also preferred where a PPS system is being retrofitted to
an existing site or where buried pipework or gravity drainage is impractical. In such cases, the
appropriate pipework materials as indicated above shall be used.
All pipe joints with rubber seals shall use Nitrile rubber or other oil resistant material.
Pipes are to be laid above ground on supports where possible or in trenches with removable
covers (similar to secondary cable trenches). Pipe trenches shall be drained to the stormwater
system.
For existing Brownfield sites, buried pipework using heavy-duty PVC, or cast iron can be direct laid
as a temporary measure to suit the phasing of construction works where required.
For Brownfield sites, suitable exposed pipes that are laid on supports within existing cable trenches
can be considered where minimal ground disturbance is necessary. However, this approach will be
subject to achieving an acceptable design solution, and will require a site based risk assessment
and specific approval for each site.
A risk assessment shall be undertaken when adopting buried pipework to determine the risk of soil
contamination. The risk assessment shall consider issues such as site conditions, sensitive
environments, design life and ease of replacement.
Pipework in cable basements shall be subject to specific approval and will generally only be
acceptable in CBD major substations. Pipework in cable basements may also be considered at
sites where the transformers are adjacent to the substation building basement area. Stainless steel
or cast iron shall be used for all internal pipework in basements.
13.1.4 Design
Generally, a minimum of 0.5% fall is to be maintained for all drainage channels and pipework
draining to an oil containment tank.
Oil containment pipes for gravity drainage shall be 150mm in diameter, except for CBD substations
where larger diameter pipes may be necessary to cater for the high velocity water spray system.
As a guide, the oil containment tank should be sized such that oil globule sizes of 33 microns or
larger are contained within the tank for the following rainfall events:
1 in 1 year ARI storms of 1 hour, 12 hour, 24 hour, 48 hour and 72 hour duration, and
1 in 20 year ARI storm of 5 minute duration.
The various flow rates for firefighting medium are discussed in Clause 6.1. For CBD substations
the oil containment pipes shall have sufficient capacity for the transformer high velocity water spray
system flowrates.
At suburban locations the pipework can be designed to allow the transformer bund area to
surcharge during firefighting flows. At these locations a butterfly valve is provided to shut off the oil
containment tank discharge to stormwater before firefighting commences (refer to Clause 13.3.2).
For gravity drainage systems that adopt the use of pits at junctions (refer to Clause 13.2.1), the
pipework shall be designed to ensure any downstream pits do not surcharge in the event that all
the oil from one transformer is lost instantaneously within one bunded area. During such events it is
assumed there will be no additional flow from a storm event or activation of fire hoses.
An alternative gravity drainage system that uses buried pipework with pits at junctions may also be
viable, but is generally not preferred . Where adopted (e.g. to retrofit existing sites) the associated
pits shall be cast in-situ and a hydrophilic seal placed around the pipe and cast into the pit.
Hydrophilic seals shall also be used on any concrete joints in the pit construction.
The finish on the inside of pits and drainage channels shall be watertight. If a watertight structure
has not been achieved, a suitable concrete sealant shall be applied to achieve a seal. The sealant
used shall be resistant to transformer oil and remain effective for the life of the pit or drainage
channel.
Pipe trenches that are used to protect oil containment pipelines are not considered to be drainage
channels and the above requirements for watertightness do not apply.
Flame traps are required for gravity drainage systems and should be located as close to the
transformer as possible to:
(b) reduce oil drainage paths across the bunded area; and
Flame traps must be cast in-situ with a hydrophilic seal around the pipe. Concrete joints should be
avoided in flame traps, but where they are required hydrophilic seals shall be used.
13.3 Valves
13.3.1 Closed drainage PPS systems
PPS systems shall use a ball valve to facilitate maintenance and removal of the pump. The ball
valve material shall be suitable for connection to the adjoining pipework
The butterfly valve shall be located such that it can be safely operated manually during a fire. A
suitable separation distance or a fire resistant barrier should be provided to reduce the radiant heat
exposure to an acceptable level. Refer to NS187 Passive Fire mitigation Design of Substations.
Where adequate fire segregation cannot be provided for the butterfly valve location, a risk
assessment shall be undertaken for the site.
The location of the butterfly valve can allow for a reduced fire front area based on the bunds being
gravity drained. The radiant heat level can be based on a transformer tank fire (sides and top)
together with a small pool fire along the flow path from the transformer to the sump. Modelling of a
full bund oil fire is not required during operation of the butterfly valve.
The position of the valve within a tank outlet area depends on the secondary containment method.
If the tank is to be used as secondary containment, the valve is positioned on the inlet to the valve
pit. If the secondary containment is a separate area, the valve needs to be positioned appropriately
to direct flow.
The equipment shall be capable of withstanding the conditions expected on site including potential
water/oil temperatures in a fire and be corrosion resistant. Valves shall also be low maintenance,
simple to operate, and all automatic shut off valves shall have a manual override.
The use of non–return valves should be avoided wherever possible, however they may be required
if the system is likely to be effected by:
The “Hume-King Flood Gate” or approved equivalent is recommended for use as a non-return
valve.
A stainless steel non-return valve is the only type acceptable for use in the major substation
environment.
13.4 Pumps
13.4.1 General
All pumps to be used on low lift oil containment systems shall be diaphragm pumps.
Diaphragm pumps are preferred for low lift applications. The system should be designed to ensure
that dirty water is low lift and this may mean relocating the discharge point closer to the influent
source.
Where high lift is required, a non-emulsifying screw pump may be used. These are prone to seizing
from debris and do not tolerate no flow conditions. Therefore, it is preferred to redesign the system
to facilitate the use of diaphragm pumps wherever possible.
For both non-rural and rural sites, the minimum containment storage time for non-fixed system
firefighting is 20 minutes. The assumed firefighting method shall be one hose with foam at 4 L/s.
For both non-rural and rural sites, the required minimum containment storage can be inclusive of
the volume available within the bunded areas, plus any secondary containment or overflow areas
available on site. Refer also to Annexure A.
Where a full bund oil fire may occur, a suitable volume allowance can be made based on a
nominated burn down rate of 100mm per hour applied across the surface area of the bund. Actual
burn down rates may vary based on conditions and the use of higher values shall be subject to
approval by Ausgrid.
15.0 CAPACITORS
15.1 General
High voltage capacitors contain either Jarylec or Faradol fluid for the purpose of insulation. With a
specific gravity of 1.006 and 1.001 respectively, these fluids are slightly heavier than water and
therefore, standard gravity separation is impractical. Stormwater run-off from capacitor bank areas
shall not pass into the standard oil containment catchments or oil containment tanks.
If there is a significant risk of leaking capacitors, the use of a concrete perimeter bund may be
required and a risk assessment should be undertaken.
Evidence of leaking oil should be visible on founding concrete slabs or the ground around them and
should be inspected during oil containment maintenance.
Following the emergency use of the system, the system will need to be re-commissioned.
a) removed, or
b) drained, steam cleaned and completely filled with an inert solid material (e.g. sand, backfill
mortar).
All pipework shall be disconnected and removed from the tank, drained and the open ends sealed
off.
Due to the nature of an oil containment tank, there is potential for oil leakage during the service life
and resulting contamination of the surrounding soil and groundwater. When oil containment tanks
are decommissioned and/or removed the potential for contamination shall be investigated.
Contact Ausgrid's Environmental Services for more information regarding the management of
contaminated land.
19.0 RECORDKEEPING
The table below identifies the types of records relating to the process, their storage location and
retention period.
Table 1 – Recordkeeping
Approved copy of the network BMS Network sub process Standard – Unlimited
standard Company
Draft Copies of the network HPRM Work Folder for Network Unlimited
standard during Standards (HPRM ref. 2014/21250/216)
amendment/creation
* The following retention periods are subject to change eg if the records are required for legal
matters or legislative changes. Before disposal, retention periods should be checked and
authorised by the Records Manager.
1 Allow for the burn Adopt a burn down Dependant on bund Available volume is time
down rate due to a rate of 100mm/hr surface area and dependant
3
full bund oil fire over the full bund time. (e.g. 12m for a
2
surface area 60m bund after 2
hours)
2 Raise bund height Raise bunds to a Minimum 5000 litres - Higher bunds means
height to meet risk maximum depends greater heights for persons
assessment on maximum to traverse into the bund.
containment volumes. allowable bund This may create a WHS
height. risk.
3 Provide controlled Needs connection to Available volume has Some residual fire risk to
overflow into neighbouring bunds to be calculated for neighbouring assets if the
neighbouring bunds via pipework valves each site, but overflow control is normally
or underflow weirs. generally will be “open”.
approximately 40,000 Foam is corrosive. Some
litres. damage may occur to the
neighbouring assets.
Would require a clean-up
after an incident.
Extensive pipework may be
required where bunds are
not adjacent to one
another.
Preferred only where
FSWs are in place.
5 Direct overflow to Requires the Depends on the Some residual fire risk to
the cable basement basement to be made basement size. cable basement if the
watertight or keep a Generally in excess overflow control is normally
zone 300 mm from of 30,000 litres. “open”.
the floor penetration Corrosive foam could
free. cause damage to the
Requires appropriate assets in the basement.
shut off valves and Requires extensive
additional drainage pipework.
lines.
Many sites do not have
Requires appropriate suitable cable basements.
warning alarms to
evacuate the Requires a clean-up of the
basement. area following an incident.
1 Utilise the Needs the tank outlet shut off Approximately Needs bolt down covers
freeboard in the valve to be fitted. The valve is 5000 litres. which are a minor
tank to be shut prior to application Actual volume inconvenience for
of fire-fighting medium. depends on the maintenance.
Needs the drainage system tank size. Watertight systems may
from the bunds to the tank to exclude FRC pipe systems.
be watertight to prevent loss.
All pits must have bolt down
gas lids.
3 Utilise the Same as option 1, except for Limited by bund Same as option 1, except the
freeboard in the the addition of raised bunds. height increased WHS risk of
tank and raise restrictions on raising bunds must be
bunds site considered.
4 Provide an Requires tank outlet pit outlet Limited only by Suitable containment area
overflow area shut-off valve. This will direct site constraints must be available at the site.
flow to another area. (topography and Would require clean-up after
Alternatively, the tank can site use). an incident.
overflow to the secondary
containment area and the
outlet from that area is
provided with a shut off valve.
5 Direct overflow to Requires the basement to be Depends on the Some residual fire risk to
the cable made watertight - or keep a basement size. cable basement if the
basement zone 300 mm from the floor Generally in overflow control is normally
penetration free. excess of “open”.
Requires appropriate shut off 30,000 litres. Corrosive foam could cause
valves and additional drainage damage to the assets in the
lines. basement.
Requires appropriate warning Requires extensive
alarms to evacuate the pipework.
basement. Some sites do not have
suitable cable basements.
Would require a clean-up
after an incident.
1 Utilise the Needs a tank outlet shut off Approximately Potentially expensive.
freeboard in the valve to be fitted. The valve is 5000 litres. Existing drainage lines may
tank to be shut prior to application Actual volume not be watertight in most, if
of fire-fighting medium. depends on the not all, cases.
Needs a watertight drainage tank size.
system.
All lids must have bolt down Existing drainage lines may
gas tight lids. not be watertight in most, if
not all, cases.
Would require a clean-up
after an incident.
Extensive pipework may be
required where bunds are
not adjacent to one another.
Preferred only where FSWs
are in place.
3 Utilise the Same as option 1, except for Limited by bund Same as option 1, except the
freeboard in the the addition of raised bunds. height increased WHS risk of
tank and raise restrictions on raising bunds must be
bunds site. considered.
4 Provide an Requires tank outlet pit outlet Limited only by Suitable containment area
overflow area shut-off valve. This will direct the site must be available at the site.
flow to another area. constraints. Containment areas will
Alternatively, the tank can require maintenance and
overflow to the secondary monitoring.
containment area and the Would require a clean-up
outlet from that area is after an incident.
provided with a shut off valve.
5 Direct overflow to Requires the basement to be Depends on the Some residual fire risk to
the cable made watertight. basement size. cable basement if the
basement Requires appropriate shut off Generally in overflow control is normally
valves and additional drainage excess of “open”.
lines to divert flow to the 30,000 litres. Corrosive foam could enter
basement. and cause damage to the
Requires appropriate warning assets in the basement.
alarms to evacuate the Requires extensive
basement. pipework.
Many sites do not have
suitable cable basements.
Would require a clean-up
after an incident.
Figures B1 and B2 provide an outline of the key roles and responsibilities within Ausgrid from initial
design up to the practical completion stage.
B2 Key responsibilities
1. Parallel Plate Separator systems
There are a number of manufacturers and types of PPS oil containment systems. The PPS unit
currently being installed in major substations for Ausgrid is the Ovivo EnviroSEP OS 7500 Oil
Separator.
The design principle is generally consistent across all substations but may require variations to the
final placement of some components due to local equipment and conditions.
The key roles and responsibilities within Ausgrid for the design, installation and commissioning of
PPS oil containment systems are as follows:
1. The installation or upgrade of the PPS system is project managed by the Major Projects or
Capital Programs Group;
2. The design drawings “For Construction” are provided by the Project Development Group;
3. The installation is mainly carried out by Contractors, with power supply and SCADA connections
by Ausgrid Field Technicians;
4. The inspection and commissioning responsibilities are as identified in Annexure C. The
commissioning checklist and procedure are contained in Sections B5 and B6 of this Annexure;
5. The emergency drainage diagram is prepared by Project Development Group to meet the
requirements of NS 186, and is installed by the Services Maintenance group;
6. The operation and maintenance functions are to be carried out by the Services Maintenance
Group. Refer to Annexure A of NS 190.
The PPS oil containment system shall be correctly installed and fully commissioned on site with a
minimum 12 months defects liability period to ensure effective long term operation of the system.
To facilitate this process, and ensure an effective handover of the equipment, the Project Manager
shall obtain the advice and input of the Services Maintenance Group during the delivery,
installation and final inspection of the PPS system.
Certification that the system has been installed in accordance with the design documentation and
manufacturer’s requirements shall be provided by all commissioning parties (including the PPS
manufacturer) at the completion of commissioning works.
3. Final inspection and acceptance of the completed installation is the responsibility of the Project
Development Group (Civil Works), with specialist and technical input for equipment (e.g. oil
sensors) as required by the Services Maintenance Group during installation and commissioning;
4. The emergency drainage diagram is prepared by Project Development Group to meet the
requirements of NS 186, and is installed by the Services Maintenance Group;
5. Operation and maintenance of the complete oil containment system is the responsibility of the
Services Maintenance Group. Refer to Annexure A of NS 190.
Wherever possible all pipes carrying water shall be installed inside the bund area to enable leaks to
be contained.
All conduits and termination boxes for electrical cables shall be in accordance with AS 3000.
Each pump is to be supplied by a dust-tight, immersion-proof (rated IP67 or above) 10A 240v
Switched Outlet accessible from outside the bund.
The PPS shall have a dedicated 240vAC 20Amp supply from a 20A Combination Circuit Breaker
and RCD (Safety Switch) on the Substation main AC Board and be labelled at both ends to identify
the circuit. When commissioned, a single Alarm shall be operational to the System Control Room,
with the contact phone number marked on the Control Panel. The Alarm shall have the provision
inside the Control Panel of being made “Non-Auto” during servicing.
The PPS oil separator tank shall be located in a bunded area and mounted on four 50mm x 15mm
threaded mounting studs so as to provide a height adjustment nut below the support bracket and a
locknut above.
The Control Panel shall be mounted to be accessible from outside the bund area. The Control
Panel door shall be lockable with a lock type that enables fitting of a suitable Abloy lock to be
supplied and keyed by the Oil Containment Group.
The PPS shall have all outflow 50mm Kamlock fittings located for the easy connection of tanker
hoses from the front. Where the PPS is located in confined areas, the use of a detachable 900
elbow with Kamlock fittings is acceptable.
Each bund pump shall have a stainless steel flexible hose approximately 500mm long (end fittings
excluded) to suit the site constraints and located on the outlet side only. Each pump outlet shall
have a ball valve between the flexible hose and rigid pipe. Each pump shall have a stainless steel
weatherproof cover that can be easily removed for servicing and is fitted with ventilation louvres on
three sides adjacent to the motor vents. The pump cover is to be hinged on the opposite side to the
pump pulleys.
Where cables are installed in metal pipes or covers, the ends shall be bushed to prevent cable
damage.
The discharge of the PPS shall be directed to the transformer roadway or other well drained areas
and shall allow sufficient space for future sampling. The discharge shall not be connected directly
to stormwater pipes or pits. Site drainage shall be arranged so as to avoid long term ponding
directly in front of the Control Panel.
The Control Panel shall have an Auto/Off Selector Switch for the PPS Alarm circuit. A Control
Panel Operations Manual and PLC logic diagrams shall be available to enable the interrogation
and calibration of the Control Panel PLC. An electrical circuit diagram for the Control Panel shall
also be available in order to facilitate connection of sensors etc by qualified persons.
High Oil 1. Ensure the Main Supply Circuit Breaker inside the Control Panel is ON
Level 2. Ensure the Pump Isolating Switch on the side of the Control Panel is ON
Alarm 3. Raise High Oil Alarm Float in the Oil Separator and observe alarm
Check operation
4. The High Oil Alarm and Common Flashing Alarm should both light up.
5. Lower the High Oil Alarm Float and both the Alarm Indicators should reset
Pump 1. Ensure the Main Supply Circuit Breaker inside the Control Panel is ON
Supply 2. Ensure the Pump Isolating Switch on the side of the Control Panel is ON
Fail 3. Trip the Circuit Breaker for Pump No.1 inside the Control Panel
Alarm
4. Observe that the Pump Fault Light and Common Alarm Light operate
Check
5. Reset the Circuit Breaker and observe that both alarms reset
6. Repeat this test for each pump
Oil 1. Fill unit with water to almost full
Weir 2. Note the distance from the top of the water to the top of the fixed oil weir
Setting 3. Set the distance from the water to the adjustable oil weir
4. Set the adjustable oil weir with silicon
5. Ensure that the silicon is level across its length
Outlet 1. The Outlet Weir setting determines the level of the water in the separator.
Weir 2. Ensure the Main Supply Circuit Breaker inside the Control Panel is ON
Setting 3. Ensure the Pump Isolating Switch on the side of the Control Panel is ON
4. Turn each Pump Switch on the Control Panel to AUTO
5. Allow the flow to maximise and settle
6. Adjust the Outlet Weir to be 3 – 8 mm below both the oil weirs.
7. Lock the Outlet Weir using an Allen Key on the grub screw.
8. Allow the system to drain each bund which automatically switches each
pump OFF
Discharge 1. Ensure that the oil separator has stabilised and is operating with discharge
Testing water flowing
2. Fill a 500ml sample bottle from the discharge outlet flow for testing
3. Arrange for testing of the discharge sample for Oil, PCB and pH.
Checks 1. Contact Supervisor if the supply RCD Safety Switch does not reset after
completed test.
2. Ensure that all Switches are in AUTO or ON
3. Secure the inside panel and Control Panel door and retrieve all access
keys
4. Restore Alarm then contact System Control Room Operator to confirm
Alarm and Reset
5. Ensure all equipment details are recorded
6. Record any defects, required repairs and items for attention
7. Contact Supervisor if any unsafe condition is found.