MS-Minor Bridges
MS-Minor Bridges
Construction Package: NS-37 ------- Method Statement for construction of Minor Bridges
1.0 PURPOSE
2.0 SCOPE
This work will consist of furnishing and providing plain or reinforced concrete
foundation, wall and slab in accordance with drawing and specification. The work
will consist of construction of Minor Bridge in the proposed four lane road. Minor
Bridge construction involves :-
1. Construction of Minor Bridges at New Location
2. Reconstruction of Minor Bridges and dismantling the existing Bridge as per
Engineer’s decision.
3.0 REFERENCES
4.0 PROCEDURE
4.1.2 Dewatering
If water table is met with during excavation, attempts will be made to keep
excavated pits dry against seepage and/or rain water accumulation by
bailing or surface pumping and by creating diversion channels. Where
high water table is met i.e. water table is met above the foundation level,
dewatering may be done by well point system.
4.1.3 Excavation
Foundation for Bridge shall be excavated true to the lines and grade as
shown on the drawing. Care shall be taken to prevent the side collapse
and damage. Minor dismantling (if required) of existing Bridge structures
will be carried out using hand tools, jack hammers fitted with compressor.
Excavated earth shall be set aside if it is suitable for reuse as backfilling
material. The width of excavation at the bottom and at the top will be
decided by the ENGINEER considering the material encountered.
(a) Lean Concrete: PCC of required grade and of approved mix design
shall be provided as per drawing or as directed by the ENGINEER
confirming to Clause 2100 of Technical specification.
After sufficient curing of the PCC, the reinforcement fabricated as per the
bar bending schedule will be placed. The clean steel formwork of required
sizes will be fixed by nut bolting to each other and supported with the
props to maintain the structural dimension of foundation/ raft.
For construction of deck slab/ T-Beam, the pipe jacks, props staging will
be installed resting on sufficient harden concrete of foundation/ raft. The
soffit formwork will be fixed to the required height.
The slab will be cast flat and the cross slope in carriageway shall be
maintained by providing Bituminuous Macadam and subsequently laying
of DBM & BC over the slab.
Wearing coat shall be provided as per the drawings after the slab has
been cast and the surface shall be kept rough but true to lines and levels
before the concrete has hardened.
(d) Form Work: The formwork will be made preferably with steel.
Formwork plate sizes will be workout and fabricated for easy and multiple
uses. Forms shall be made sufficiently rigid by the use of ties and bracing
to prevent any displacement or sagging between supports. It shall be
strong enough to withstand all pressure and vibration during placing of
concrete. The formwork shall be so removed as not to cause any damage
of concrete structure, confirming to Clause 1500 of Technical
Specification.
(e) Steel reinforcement: This work shall consist of fabricating and placing
reinforcement of the shape and dimension shown on the drawing
confirming to Clause 1600 of Technical Specification. Reinforcement from
approved source will be brought and stacked above the ground surface on
wooden or steel crate to avoid rusting. Reinforcement will be cut and
fabricated to the approved bar bending schedule at work site only.
Reinforcement will be tied in place with M.S. binding wire of 18 gauge and
using cover blocks of required size & strength to maintain the clear cover.
4.1.5 Bearings
Drainage spout and collection pit assembly shall be fabricated from mild
steel. On completion of fabrication, the complete assembly except grating
shall be given a galvanized coating. Drainage spouts will be fixed after
concreting of Deck Slab according to the position and level as per drawing
or as directed by the Engineer.
The filter Media backfill shall be placed as per IRC 78, 1983, Appendix 6.
and It should be provided over the entire surface behind the Wing Wall,
Abutment & Return Wall as per drawing and Clause 2504 of Technical
Specification.
All personnel shall follow Health and Safety document as would be issued by ITD
from time to time. The existing road side of the culvert and work site will be
barricaded by putting wooden ballies having reflective tape spots over it and will
be tied with the warning tape for night vision also. It will be ensured that no
unauthorized person should enter in the working area.
Generally the one side of two lane wide minor bridge will be constructed first in
all respects. The existing or second side of minor bridge construction will be
taken up only after diverting the traffic on newly constructed part of minor bridge.
During construction of minor bridge, the road width for two lane traffic movement
will be maintained open at all times.