Personal Task 1 June 1, 2020
Personal Task 1 June 1, 2020
1 June 1, 2020
Question
Consider a software development project with the following information. Suppose the cost
rate for developer is $5000/week.
1)Construct the project activity network using AON methodology.
Pattern
2)Calculate the early, late and float times for each activity. Identify the critical path.
Activity Duration ES EF LS LF Float
(weeks)
A 4 0 4 0 4 0
B 2 4 6 4 6 0
C 2 6 8 6 8 0
D 3 6 9 6 9 0
E 5 8 13 8 13 0
F 7 0 7 0 7 0
Critical Path:
There are two critical oath in this network diagram, these paths are highlighted with red
color.
Critical path1: A-B-C-E
Critical path2: A-B-D
3)Develop the Cost baseline for the project based on the early start times(ES)
Cost Baseline
Developer cost= $5000/week
Activity Duration Number of Developer Fixed Cost $ Total Cost $
(weeks) Developer Cost $
A 4 2 40,000 40,000
B 2 1 10,000 10,000
C 2 2 20,000 20,000
D 3 1 15,000 15,000
E 5 2 20,000 20,000
F 7 1 10,000 10,000
Baseline