1) The document describes a software development project with activities A through F and their durations in weeks. It provides an activity on node (AON) network diagram and calculates the early, late, and float times for each activity. There are two critical paths identified: A-B-C-E and A-B-D. 2) A cost baseline is developed based on the early start times for each activity. With a developer cost of $5,000 per week, the total cost is calculated for each activity by multiplying the duration by the number of developers and their weekly cost. 3) The total project cost baseline comes to $115,000 based on the sums of the total costs for each activity

Uploaded by

Mohammad Nauman
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views

Personal Task 1 June 1, 2020

1) The document describes a software development project with activities A through F and their durations in weeks. It provides an activity on node (AON) network diagram and calculates the early, late, and float times for each activity. There are two critical paths identified: A-B-C-E and A-B-D. 2) A cost baseline is developed based on the early start times for each activity. With a developer cost of $5,000 per week, the total cost is calculated for each activity by multiplying the duration by the number of developers and their weekly cost. 3) The total project cost baseline comes to $115,000 based on the sums of the total costs for each activity

Uploaded by

Mohammad Nauman
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Personal Task

1 June 1, 2020
Question
Consider a software development project with the following information. Suppose the cost
rate for developer is $5000/week.
1)Construct the project activity network using AON methodology.
Pattern

ES: Early Start


EF: Early Finish
LS: Late Start
LF: Late Finish
SL: Slack (also called float value)
D: Duration
ID: Activity ID
AON

2)Calculate the early, late and float times for each activity. Identify the critical path.
Activity Duration ES EF LS LF Float
(weeks)
A 4 0 4 0 4 0
B 2 4 6 4 6 0
C 2 6 8 6 8 0
D 3 6 9 6 9 0
E 5 8 13 8 13 0
F 7 0 7 0 7 0
Critical Path:
There are two critical oath in this network diagram, these paths are highlighted with red
color.
Critical path1: A-B-C-E
Critical path2: A-B-D

3)Develop the Cost baseline for the project based on the early start times(ES)
Cost Baseline
Developer cost= $5000/week
Activity Duration Number of Developer Fixed Cost $ Total Cost $
(weeks) Developer Cost $
A 4 2 40,000 40,000
B 2 1 10,000 10,000
C 2 2 20,000 20,000
D 3 1 15,000 15,000
E 5 2 20,000 20,000
F 7 1 10,000 10,000

Baseline