Victoria Gold
Victoria Gold
December 2018
T S X .V V I T | V I T G O L D C O R P. C O M
1
Agenda
TSX-V: VIT
1. HS&E (Ayranto) 4. Eagle Operations (Rouleau)
Org Chart & Team To-date
vitgoldcorp.com
2. Eagle Construction (George) Systems
Infrastructure Ramp-up
Crushing System Open Pit Mining
Leach Facility
Gold Recovery Plant 5. Resource Update (Gray/Ayranto)
Schedule
CAPEX 6. Exploration Update (Gray)
2
HS&E
3
HS&E
TSX-V: VIT
Through the end of Oct H&S states:
vitgoldcorp.com
Current project hours: exceed 950,000 hrs
Over 600,000 hrs without a LTI
No major environmental infractions
4
Eagle Construction
5
Project Progress
TSX-V: VIT
Overall project is 60% complete
vitgoldcorp.com
Gold in H2 2019
6
Site Layout
TSX-V: VIT
Secondary &
Gold HLF Tertiary Crushers
vitgoldcorp.com
Recovery
Plant Primary
Crusher
Camp Warehouses
Waste Handling
and Incinerator Power Plant &
Sub-Station
7
Infrastructure
8
Site Infrastructure 69kV Powerline
TSX-V: VIT
Communications
tower
450 person camp (220 for
operations)
vitgoldcorp.com
45km 69kV powerline
5MW Power plant (Q1 2019)
Warehousing & Workshops
Warehouses &
Waste facilities including and Workshop
incinerator
Water management facilities
McQuesten sub-station
Upgraded access road
Camp
9
Crushing System
10
Primary & Secondary / Tertiary Crushing
TSX-V: VIT
Tertiary Crusher
Stockpile Primary Crusher
vitgoldcorp.com
Secondary & Tertiary
Crusher Facility
11
Primary Crusher
TSX-V: VIT
vitgoldcorp.com
Primary crusher concrete tower complete Steel erection and mechanical
Design ….. to ……Realisation installations commence
December
12
Course Ore Stockpile & Reclaim
TSX-V: VIT
vitgoldcorp.com
13
Secondary & Tertiary Crusher Frame Installation
TSX-V: VIT
vitgoldcorp.com
14
Overland Conveyor & Ore Preparation
TSX-V: VIT
Crushing facilities
vitgoldcorp.com
HLF
15
Heap Leach Facility
16
17
18
19
21
22
TSX-V: VIT
Key Commissioning Milestones
2018 2019
Activity J F M A M J J A S
vitgoldcorp.com
YEC McQuesten upgrades complete
24
Operations
25
Organizational Readiness
TSX-V: VIT
Operations Leadership Team
General
Manager
Dave Rouleau
vitgoldcorp.com
Mine Process Technical Maintenance Health & Site Services Human
Supply Chain Safety Manager Resources
Operations Operations Services Manager
Manager Manage
Manager Manager Manager Doug Manager Mike Gunn
Kirk McLellan Eileen Olivier
Kelly Parker Barry Carlson Steve Tang Desaulniers Vacant
TSX-V: VIT
Function No Type
Loading 2 CAT 6040 Excavators
2 CAT 993 Loaders
vitgoldcorp.com
Drilling 2 CAT 6290 Drill
1 SmartROC D65 Drill
Hauling 11 CAT 785 Haul Trucks
Support 4 CAT D10 Dozers
2 CAT 16M Graders
1 CAT 390 Backhoe
27
Open Pit and Waste Dump Layout
TSX-V: VIT
vitgoldcorp.com
28
Mine Development Sequence
TSX-V: VIT
Mine Development 2019 Main Pit Access Road
• Construction of main pit access road to
open pit will commence early January
• Pre-strip of starter pit will start in March
vitgoldcorp.com
• Ore available mid Q2 in advance of
commissioning crushing and
conveyance systems
29
Operating Systems
TSX-V: VIT
Engineering Planning /Survey Systems
• Mine design and planning system in place (MineSight)
• High precision guidance system planned to implemented starting
in 2020
vitgoldcorp.com
Production Support Systems
• Establish a wireless network access in 2019 in support for
implementations for a light fleet management system
• Other production/continuous improvement systems will be
evaluated for implementation over the first 3 years of operation
ERP System
• Integrate management of core business processes
• Maintenance planning, purchasing, inventory, finance and human
resources main focus
• Implement and execute ERP system Q1 2019
30
Resource Update
31
2018 Eagle Resource Update - Overview
TSX-V: VIT
Eagle Geologic Model –
Eagle Resource Model and Local Drill hole Locations Perspective View Looking Northeast
vitgoldcorp.com
32
Resource Comparison – 2016 FS to 2018 Update
TSX-V: VIT
Following the Feasibility study, additional holes were drilled during Victoria Gold’s 2017 Dublin
Gulch Exploration campaign, with 58 new holes located within and around the area of the Eagle
Zone
vitgoldcorp.com
Measured + Indicated Inferred
Avg Au Avg Au
Tonnage Content Tonnage Content
Zone Grade Grade
tonnes oz tonnes oz
g/t g/t
2016
180,720,000 0.625 3,631,000 17,430,000 0.492 276,000
Feasibility
2018 Update 198,720,267 0.639 4,082,573 12,780,597 0.490 204,631
33
Resource Comparison – 2016 FS to 2018 Update
Discussion
TSX-V: VIT
The new Eagle drillholes have indicated a continuation of the mineralization in Eagle and
defined mineralization within the margins of the Resource Pit; the updated model is slightly
wider on the periphery and to depth.
vitgoldcorp.com
A completely unbiased, new interpretation of the mineralized zone at the Eagle Deposit was
carried out from first principals. Excellent agreement with original model, well behaved,
consistently mineralized deposit.
The overall shape of two mineralized lobes on the western portion joining in the central area
and forming a single orebody in the eastern half was maintained.
Slightly Smaller composite length (1.52m instead of 2.5m) was used.
The capping (18.0 g/t Au) was carried out on the composites, compared to the capping of the
original samples performed for the Feasibility study (16.0 g/t) – negligible differences.
Ordinary Kriging with a different set of parameters based on strict variography statistical
approach was used in the updated estimation with less restrictions applied to the sample
selection strategy (no octant or maximum of holes restrictions).
The classification scheme for the resource update was based on the average sample distance
away from the block center. A set of 2 distances based on the variogram range were utilized
to separate measured, indicated, and inferred resources
34
Section 459,280E
TSX-V: VIT
October 2018 Update - MII 2016 Feasibility - MII
vitgoldcorp.com
35
Section 459,280E
TSX-V: VIT
2018 Additional Estimates in Measured+Indicated (>= 0.15 g/t Au)
vitgoldcorp.com
36
Section 459,680E
TSX-V: VIT
October 2018 Update - MII 2016 Feasibility - MII
vitgoldcorp.com
37
Section 459,680E
TSX-V: VIT
2018 Additional Estimates in Measured+Indicated (>= 0.15 g/t Au)
vitgoldcorp.com
38
Section 459,880E
TSX-V: VIT
October 2018 Update - MII 2016 Feasibility - MII
vitgoldcorp.com
39
Section 459,880E
TSX-V: VIT
2018 Additional Estimates in Measured+Indicated (>= 0.15 g/t Au)
vitgoldcorp.com
40
Section 460,280E
TSX-V: VIT
October 2018 Update - MII 2016 Feasibility - MII
vitgoldcorp.com
41
Section 460,280E
TSX-V: VIT
2018 Additional Estimates in Measured+Indicated (>= 0.15 g/t Au)
vitgoldcorp.com
42
Longitudinal Section Looking North – Northern Lobe
TSX-V: VIT
October 2018 Update - MII 2016 Feasibility - MII
vitgoldcorp.com
43
Longitudinal Section Looking North – Northern Lobe
TSX-V: VIT
2018 Additional Estimates in Measured+Indicated (>= 0.15 g/t Au)
vitgoldcorp.com
44
Exploration Update
45
Dublin Gulch Exploration - 2018
2018 Targets & Programs
TSX-V: VIT
Dublin Gulch Block
1. Olive-Shamrock – Au 4
vitgoldcorp.com
1,921.31m in 10 holes
1,007m Trenches + Access
2. Bluto – Au
1,940.21m in 11 holes
2,004m Trenches/Access
1,730 Soils
3. Nugget – Au + Ag-Pb
1,524.16m DDH
1,363m Trenches
2,553 Soils
IP, VLF-EM and Downhole Geophysical Surveys
>3 km Access Construction
2 3
1
Regional Work
TSX-V: VIT
vitgoldcorp.com
47
Dublin Gulch Infrastructure Upgrades
TSX-V: VIT
Bluto
Mag Low
vitgoldcorp.com
Olive-Shamrock
Nugget
Eagle
Lynx
48
Olive-Shamrock-Spinach
TSX-V: VIT
2018
Planned • 14.3m of 1.04 g/t Au from 85.3m DG17-866C
DDH • 9.1m of 1.19 g/t Au from 33.5m DG17-862C
• 6.1m of 2.38 g/t Au from 24.4m DG17-860C
• 5.0m of 4.26 g/t Au from 81.9m DG17-857C
• 32.0m of 0.78 g/t Au from 22.9m DG17-853C
vitgoldcorp.com
2016 F.S.
TSX-V: VIT
Sericitization
with Later
Silicification
vitgoldcorp.com
Folioform
Arsenopyrite
Within Clear
Structural
2018 Planned Associations
DDH
52
Bluto 2018 – Drill and Trench Program
TSX-V: VIT
vitgoldcorp.com
14 m at 4.87 g/t Au from 86 to 100 metres
53
2018 Dublin Gulch Soils Geochemical Programs
TSX-V: VIT
vitgoldcorp.com
54
2018 Dublin Gulch Soils Geochemical Results
As
TSX-V: VIT
vitgoldcorp.com
Au
55
Nugget
Nugget
Eagle
VBW
2017 LiDAR and Structural Interpretation
TSX-V: VIT
Outcropping
Silver-Galena
Veins
vitgoldcorp.com
Mag Anomalies
Nugget
Stock
57
Nugget – 2018 Exploration – DDH + Trenches
TSX-V: VIT
vitgoldcorp.com
NG18-001C
NG18-002C
NG18-003C
NG18-004C VG
NG18-005C
NG18-007C
NG18-006C
NG18-008C
Nugget – 2018 Exploration – Updated Geology Map
TSX-V: VIT
vitgoldcorp.com
Nugget – 2018 Exploration – DG18-006C
TSX-V: VIT
vitgoldcorp.com
A’
A Looking West A’
Hole ID From (m) To (m) Length (m) Gold (g/t) Silver (g/t) NOTES
NG18- Entire
006C 3.4 207.6 204.2 0.32 1.44 Hole
From
including 3.4 104.9 101.5 0.57 2.27
surface
and with 39.6 41.0 1.4 9.60 48
and
61.8 94.8 33.0 1.03 3.46
including
with 61.8 78.0 16.2 1.76 1.54
or 61.8 71.9 10.1 2.79 8.6
including 61.8 63.0 1.1 12.10 28.8
and 93.8 104.9 11.1 0.64 2.57
including 93.8 94.8 1.0 4.95 22.0
and
180.1 191.3 11.2 0.49 4.91
including
with 180.1 180.9 0.8 4.43 35.1
Nugget As-In-Soils Results
TSX-V: VIT
vitgoldcorp.com
61
Nugget As-In-Soils Results
TSX-V: VIT
vitgoldcorp.com
62
Nugget Au-In-Soils Results
TSX-V: VIT
vitgoldcorp.com
63
Nugget Au-In-Soils Results
TSX-V: VIT
vitgoldcorp.com
64
Falcon
TSX-V: VIT
SUMMARY
vitgoldcorp.com
EPH
Au Soil Anomaly
66
VBW 2017 Soils Grids on 2017 Airborne Magnetics
TSX-V: VIT
vitgoldcorp.com
67
All Soils Grids Results: Gold-in-soils
TSX-V: VIT
vitgoldcorp.com
68
Hawk Recon Program
TSX-V: VIT
approximately 30km north of the Dublin Gulch
claim block.
• Gossanous outcrops along a 12 km NW trend.
vitgoldcorp.com
• Identified from newly available satellite imagery
(2015).
• Geochemical data indicate anomalous gold and
base metal responses in the creeks that drain the
area.
• Potential for gold-bearing stratabound,
structurally-controlled Carbonate Replacement
(Tiger Deposit), Manto Style (Ocelot Showing), or
structurally hosted vein-fault (McKay Hill)
mineralization.
• 2018 YMEP funding for $40k
71
72
TSX-V: VIT
vitgoldcorp.com
73
Hawk 2018 Ridge and Spur Soils - Au
TSX-V: VIT
vitgoldcorp.com
74
Structural Evolution
TSX-V: VIT
1. Thrusting (NW directed)
Intrusive uplift and emplacement
(Wolf Tungsten,
vitgoldcorp.com
Bluto camp IRGS style of mineralization)
2. Normal Faulting NE directed)
Shamrock
3. Shallow Angle detachments (NW directed)
Wolf
Olive
4. Normal Faulting E directed)
5. Dilation Jog (WSW directed
extension), subvolcanic intrusions.
alkalic epithermal style of
Eagle
mineralization
6. Listric faults (SSE directed)
(reactivation of Thrust faults as normal faults)
Reactivated stacked thrust
faults as normal faults
76
Structural Movement
TSX-V: VIT
vitgoldcorp.com
Bluto
Potato Hills Wolf
Shamrock
Olive
Eagle Mine
77
Structural Evolution
TSX-V: VIT
Thrusting (NW directed)
Intrusive uplift and emplacement
(IRGS style of mineralization)
vitgoldcorp.com
Eagle Mine
Normal Faulting NE directed)
Shallow Angle detachments (NW directed) Wolf
78
Structural Reconstruction
79
Dublin Gulch Structural Analysis
TSX-V: VIT
Reconstruction
Olive-Shamrock
vitgoldcorp.com
Eagle Mine
Wolf
Tungsten
Resistivity 200K
Olive-Shamrock Shamrock
Olive
Eagle Mine
Wolf
Wolf
Tungsten
Eagle
80
Structural Reconstruction
TSX-V: VIT
Reconstruction
AFTER RECONSTRUCTION…
vitgoldcorp.com
Olive-Shamrock are a continuous deposit
81
Detachment Evidence
TSX-V: VIT
vitgoldcorp.com
Upper block displaced northwesterly
Wolf
82
New Eagle Target
TSX-V: VIT
Resistivity 200K
Placer
X
vitgoldcorp.com
mine
Placer
mine
X
Slide block with 90 degree counter
clockwise rotation
Same resistivity signature as the other
block matching same position
Same basement folding axis closure and direction