0% found this document useful (0 votes)
39 views1 page

Cross Section at CH 11.825 KM: Produced by An Autodesk Student Version

This document appears to contain level data for locations along a river or canal system. It includes offset distances from a reference point and corresponding elevation readings for 29 points ranging from -174 meters to -69 meters. The levels were taken by the Assistant Executive Engineer and Deputy Executive Engineer of the K.P.C Sub-Division No. 2 located in Gajwel.

Uploaded by

bhagyaraju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views1 page

Cross Section at CH 11.825 KM: Produced by An Autodesk Student Version

This document appears to contain level data for locations along a river or canal system. It includes offset distances from a reference point and corresponding elevation readings for 29 points ranging from -174 meters to -69 meters. The levels were taken by the Assistant Executive Engineer and Deputy Executive Engineer of the K.P.C Sub-Division No. 2 located in Gajwel.

Uploaded by

bhagyaraju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PRODUCED BY AN AUTODESK STUDENT VERSION

Datum

OGL's
Stripped Levels

Offset distance

Gajwel
-174.00 513.755 513.460
-171.00 513.735 513.415
-168.00 513.710 513.430
-165.00 513.685 513.395

Asst.Executive Engineer
K.P.C Sub-Division No.2
-162.00 513.655 513.355
-159.00 513.525 513.235
-156.00 513.415 513.120
-153.00 513.345 513.060
-150.00 513.120 512.830
-147.00 512.910 512.615
-144.00 512.935 512.655
-141.00 512.970 512.680
-138.00 512.985 512.700
-135.00 512.940 512.670
-132.00 512.900 512.615
-129.00 512.665 512.395
-126.00 512.675 512.400
-123.00 512.700 512.420
-120.00 512.625 512.330
-117.00 512.665 512.360
-114.00 512.625 512.330
-111.00 512.645 512.345
-108.00 512.475 512.170
-105.00 512.365 512.080
U/S

-102.00 512.355 512.060


-99.00 512.260 511.985
-96.00 512.140 511.860

Gajwel
-93.00 512.110 511.880
-90.00 512.410 512.145
-87.00 512.120 511.870
-84.00 512.060 511.770

Dy.Executive Engineer
K.P.C Sub-Division No.2
-81.00 511.910 511.615
-78.00 511.840 511.540
-75.00 511.790 511.510
-72.00 511.710 511.415
-69.00 511.700 511.400
-66.00 511.620 511.315
-63.00 511.570 511.260
-60.00 511.570 511.270
-57.00 511.720 511.415
-54.00 511.280 510.985
-51.00 511.380 511.080
-48.00 511.470 511.175
-45.00 511.300 511.000
-42.00 511.250 510.945
-39.00 511.290 510.980
-36.00 511.340 511.045
-33.00 511.210 510.905
-30.00 511.100 510.790
-27.00 511.090 510.795
-24.00 510.840
-21.00 510.815
-18.00 510.780
-15.00 510.940

Gajwel
-12.00 510.955
-9.00 510.950
-6.00 510.660

Executive Engineer
K.P.C Division No.7
-3.00 510.640
0.00 510.680
HDR
ALL SOILS

3.00 510.635
6.00 510.640
9.00 510.745
12.00 510.505
15.00 510.440
18.00 510.545
21.00 510.535
24.00 510.445
27.00 510.425
30.00 510.415
33.00 510.320
36.00 510.255
PRODUCED BY AN AUTODESK STUDENT VERSION

39.00 510.270

PRODUCED BY AN AUTODESK STUDENT VERSION


42.00 510.885
45.00 508.790
48.00 509.840
CROSS SECTION @ CH 11.825 KM

51.00 510.450
54.00 510.295
57.00 509.835
60.00 509.780
63.00 509.700
66.00 509.645
69.00 509.535
72.00 509.440
75.00 509.390
78.00 509.355
81.00 509.305
84.00 509.250
87.00 509.210
90.00 509.160
93.00 509.145
96.00 509.110
99.00 509.075
102.00 509.065
105.00 509.050
108.00 508.920
111.00 508.930
114.00 508.880
117.00 508.810
D/S

120.00 508.790
123.00 508.780
126.00 508.770
129.00 508.690
132.00 508.495
135.00 508.460
138.00 508.460
141.00 508.460
FROM 8.425 TO 12.665 KM.

144.00 508.470
147.00 508.470
150.00 508.460
153.00 508.450
508.440
F.R.L
T.B.L

156.00
159.00 508.430
M.D.D.L

508.430
CAPACITY

162.00
165.00 508.420
FREE BOARD

GOVERNMENT OF TELANGANA

168.00 508.420
171.00 508.440
IRRIGATION AND CAD DEPARTMENT

NAME OF AGENCY :- L&T - PRASAD - RK(JV)

174.00 508.400
177.00 508.410
5.20m
50 TMC

NAME OF WORK:SRI KOMURAVELLI MALLANNASAGAR REACH-2

180.00 508.415
+562.200m
+557.000m
+532.165m
RESERVOIR PARTICULARS

PRODUCED BY AN AUTODESK STUDENT VERSION