Checklist For Transformer Yard Layout

This checklist is for reviewing the layout of a transformer yard for a project. It contains several sections: A) processes and organizational requirements, B) learning from past projects, C) contractual requirements, D) inputs needed, E) interfacing requirements, F) MTO (material take-off) related items, G) potential holds, H) optimization and value engineering, and I) other items. The checklist aims to ensure all relevant considerations are addressed in developing the transformer yard layout design.

Uploaded by

Rahul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
302 views

Checklist For Transformer Yard Layout

This checklist is for reviewing the layout of a transformer yard for a project. It contains several sections: A) processes and organizational requirements, B) learning from past projects, C) contractual requirements, D) inputs needed, E) interfacing requirements, F) MTO (material take-off) related items, G) potential holds, H) optimization and value engineering, and I) other items. The checklist aims to ensure all relevant considerations are addressed in developing the transformer yard layout design.

Uploaded by

Rahul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Checklist for transformer yard layout

Project:______________________
Date:________________________
Document No:________________
Revision:_____________________
Mention Notes & Details
Reviewed (Yes/No/ Not
Sr. No. Check point against each point, as Remarks
Applicable)
applicable
A) Processes & Organizational requirement :
1 Reviewed the Qualification Criteria (Q-Matrix) ?
Preparer - Min. 'RS', Reviewer - Min. 'Q'
Identification of Reviewer?
[if yes, the check list shall be filled with reviewer. If no, Lead
engineer/responsible engineer shall take care on behalf of reviewer]

2 Study of latest Main & Sub Process(s):


1) EDD-MP-1.05.
2) EDD-MP-1.05.01.
3) EDD-MP-1.05.02.

3 Study & Discussion on relevant PIPs?


4 Study of applicable S&L standard(s) & L&T-S&L SOP(s)? [Optional]
5 Study of applicable standards, codes as mentioned in sub processes?
6 Information provided on budgeted MH, CBS and DBS codes?
7 Discussed client expectation & schedule requirement ?
8 Check for availability of applicable resources ?
1) Requirement of support man power?
2) Availability of CAD software license?

9
10
B) Past project learning & references:
1 Reference project drawings referred (if any)?
2 Shared lesson learnt, good practice from PIP system/past experience ?

3
4
5
C) Contractual requirements:
1 Read DCD/Client Technical Specification?
2 Any Client requirement for transformer removal arrangement?
3
Any Client requirement for power evacuation arrangement (BPI, LA, Gantry
tower, Overhead conductor arrangement etc.) ?
4 Any Client requirement for protective fencing arrangement?
5 Any Client requirement for side/top clearance ?
6
Any Client requirement for Fire wall construction (brick/concrete), thickness
& arrangement ?
7 Any Client requirement for Spare transformer location & arrangement?
8 Any Client requirement for Emergency stop push button ?
9
10
D) Input :
1 Study of Single line diagram?
2
Study of Plot Plan w.r.t. transformer yard arrangement interface with
switchyard, CW piping, road arrangement etc.?
3

Availability, Study & review of Suitability of Transformer(s) vendor


drawing(s) ?
1) General arrangement drawing.
2) Foundation input drawing.
3) Bus duct termination drawing.
4) Individual/Common Marshalling box drawing(s)
5) NGR/NGT drawing(s)
4
Availability, Study & review of Suitability of Bus duct(s) [IPBD/SPBD/NSPBD]
routing & support arrangement drawings?
5
Availability, Study & review of Suitability of Special transformer (i.e.
excitation, SFC etc.) vendor drawing(s)?
6
Availability, Study & review of Suitability of BPI, LA, Cable termination, etc.
supporting arrangement vendor drawing ?
7 Availability, Study & review of Suitability of Cable sizing & cable list ?

8
Availability, Study & review of Suitability of Neutral formation arrangement ?
9
Availability, Study & review of Suitability of Fire protection & Oil water system
arrangement ?
10
E) Interfacing requirements
1 Interface with CW piping coordinated?
2
Interface with Switchyard (i.e. location of gantry tower, BPI/LA, OH Line)
considering skew angle of overhead line coordinated?
3
Interface with gantry tower arrangement (i.e. combined with fire wall)
coordinated?
4 Interface with Bus duct routing & support arrangement coordinated?
5 Interface with various civil drawings coordinated?
6 Interface with cable raceway coordinated?
7
Interface with Fire protection piping, DV shed & Oil water system piping
coordinated?
8
Rail elevation and Grade elevation coordinated as per transformer handling
requirement?
9
10
F) MTO related
1 Fire wall length & height optimized?
2 Bus duct(s) [IPBD/SPBD/NSPBD] length & bends optimized?
1. Distance between A row [TG bldg. first column] to center line of
transformers shall be minimized.

3 Space requirement is optimized?


4 Removal rail quantity optimized?
5 Fence length quantity optimized?
G) Potential HOLD(s)
1 Potential HOLD(s) & non avaialibilty of input identified & listed?
2 Drawing internal issuance (i.e. for civil design) planned ?
3
4
5
H) Optimization and value engineering
1 Distance between A row & Transformer evaluated to optimize fire wall
quantity ?
2 Explored possibility of common support of bus ducts & cable trays ?
3
4
5
I) Any Others
1 Mooring post (winch positions) are identified?
2 Constructability study done with EPC/construction team?
3 Transformer yard arrangement is verified w.r.t. commissioning & back
charging schedule?
4 Amount of detailing is as per client expectation, input quality & commitment
to client?
5

Responsible/ Lead Engineer:______________________ Team member:______________


Sing off:__________________ Sing off:____________________