Test Report For LV Panel
Test Report For LV Panel
PROJECT
WITH INFRASTRUCTURE WORKS
CLIENT ABU DHABI HOUSING AUTHORITY EQUIPMENT LV PANEL
END USER AL AIN DISTRIBUTION COMPANY.
CONSULTANT ALTORATH INTERNATIONAL
MAIN CONTRACTOR NAEL GENERAL CONTRACTING EST
HYDROPOWER ENERGY &GENERAL
SUB CONTRACTOR SCHEME NO ND-11-18-116
CONSTRUCTION LLC.
SUBSTATION No AH1010 LOCATION Al HAYER
1. GENERAL CHECKS:
S. No. Description Checked
1 Inspect switchgear and all components for any physical damage / defects. OK
2 Check manufacturer name plate information for correctness. OK
3 Inspect enclosures for proper alignment, levelness and cable entry access. OK
4 Verify the fuses size/rating against the panel drawings. OK
5 Verify that all the interconnection control wires connected correctly. OK
6 Verify that appropriate anchorage, fixation and area clearances are provided. OK
7 Verify ON/OFF operation of Incomer 1 & 2, Buscoupler Isolators OK
8 Verify correct phase markings wherever required. OK
9 Check for the tightness of Busbar. OK
10 Verify earthing of LV panel. OK
11 Check panel for overall cleanliness including the interior. OK
SIGNATURE
DATE 26.06.2019
Page 1 of 8
DESIGN AND BUILD OF 30 VILLAS EMIRATI HOUSING PROJECT IN AL HAYER
PROJECT
WITH INFRASTRUCTURE WORKS
CLIENT ABU DHABI HOUSING AUTHORITY EQUIPMENT LV PANEL
END USER AL AIN DISTRIBUTION COMPANY.
CONSULTANT ALTORATH INTERNATIONAL
MAIN CONTRACTOR NAEL GENERAL CONTRACTING EST
HYDROPOWER ENERGY &GENERAL
SUB CONTRACTOR SCHEME NO ND-11-18-116
CONSTRUCTION LLC.
SUBSTATION No AH1010 LOCATION Al HAYER
Incomer # 1 to Incomer #1 23 21 25 23
Bus #1 Isolator closed
Incomer # 2 to Incomer #2 25 22 20 26
Bus # 2 Isolator closed
Bus # 1 to
Bus coupler closed 54 53 54 60
Bus #2
3. AMMETER TEST
COMPANY Tested by Witnessed by Witnessed by Witnessed by Approved by
Hydropower
Alpha Power Altorath AADC AADC
Energy
NAME BALAKUMAR
SIGNATURE
DATE 26.06.2019
Page 2 of 8
DESIGN AND BUILD OF 30 VILLAS EMIRATI HOUSING PROJECT IN AL HAYER
PROJECT
WITH INFRASTRUCTURE WORKS
CLIENT ABU DHABI HOUSING AUTHORITY EQUIPMENT LV PANEL
END USER AL AIN DISTRIBUTION COMPANY.
CONSULTANT ALTORATH INTERNATIONAL
MAIN CONTRACTOR NAEL GENERAL CONTRACTING EST
HYDROPOWER ENERGY &GENERAL
SUB CONTRACTOR SCHEME NO ND-11-18-116
CONSTRUCTION LLC.
SUBSTATION No AH1010 LOCATION Al HAYER
INCOMER - 1
1. AMMETER DETAILS
MAKE CROMPTON FULL SCALE 3000 A
RANGE 0 – 3000A CT RATIO 2500 / 5 A
SL.NO R 709711-615 Y 709711-588 B 709711-591
INCOMER - 2
1. AMMETER DETAILS
MAKE CROMPTON FULL SCALE 3000 A
RANGE 0 – 3000A CT RATIO 2500 / 5 A
SL.NO R 709711-610 Y 709711-604 B 709711-612
SIGNATURE
DATE 26.06.2019
Page 3 of 8
DESIGN AND BUILD OF 30 VILLAS EMIRATI HOUSING PROJECT IN AL HAYER
PROJECT
WITH INFRASTRUCTURE WORKS
CLIENT ABU DHABI HOUSING AUTHORITY EQUIPMENT LV PANEL
END USER AL AIN DISTRIBUTION COMPANY.
CONSULTANT ALTORATH INTERNATIONAL
MAIN CONTRACTOR NAEL GENERAL CONTRACTING EST
HYDROPOWER ENERGY &GENERAL
SUB CONTRACTOR SCHEME NO ND-11-18-116
CONSTRUCTION LLC.
SUBSTATION No AH1010 LOCATION Al HAYER
4. CT PRIMARY INJECTION
INCOMER – 1
1. CT DETAILS :
MAKE HOBUT RATIO 2500/5A
CLASS 0.5 FS10 BURDEN 10 VA
SL.NO R 116607/1/052 Y 116607/1/098 B 116607/1/046
Measured in Ammeter
Injected Primary Expected reading
Sl No (A)
Current (A) (A)
R Y B
1 400 400 400 400 400
2 800 800 800 800 800
INCOMER – 2
COMPANY Tested by Witnessed by Witnessed by Witnessed by Approved by
Hydropower
Alpha Power Altorath AADC AADC
Energy
NAME BALAKUMAR
SIGNATURE
DATE 26.06.2019
Page 4 of 8
DESIGN AND BUILD OF 30 VILLAS EMIRATI HOUSING PROJECT IN AL HAYER
PROJECT
WITH INFRASTRUCTURE WORKS
CLIENT ABU DHABI HOUSING AUTHORITY EQUIPMENT LV PANEL
END USER AL AIN DISTRIBUTION COMPANY.
CONSULTANT ALTORATH INTERNATIONAL
MAIN CONTRACTOR NAEL GENERAL CONTRACTING EST
HYDROPOWER ENERGY &GENERAL
SUB CONTRACTOR SCHEME NO ND-11-18-116
CONSTRUCTION LLC.
SUBSTATION No AH1010 LOCATION Al HAYER
1. CT DETAILS :
MAKE HOBUT RATIO 2500/5A
CLASS 0.5 FS10 BURDEN 10 VA
SL.NO R 116607/1/087 Y 116607/1/084 B 116607/1/050
Measured in Ammeter
Injected Primary Expected reading
Sl No (A)
Current (A) (A)
R Y B
1 400 400 400 400 400
2 800 800 800 800 800
SIGNATURE
DATE 26.06.2019
Page 5 of 8
DESIGN AND BUILD OF 30 VILLAS EMIRATI HOUSING PROJECT IN AL HAYER
PROJECT
WITH INFRASTRUCTURE WORKS
CLIENT ABU DHABI HOUSING AUTHORITY EQUIPMENT LV PANEL
END USER AL AIN DISTRIBUTION COMPANY.
CONSULTANT ALTORATH INTERNATIONAL
MAIN CONTRACTOR NAEL GENERAL CONTRACTING EST
HYDROPOWER ENERGY &GENERAL
SUB CONTRACTOR SCHEME NO ND-11-18-116
CONSTRUCTION LLC.
SUBSTATION No AH1010 LOCATION Al HAYER
INCOMER – 1
Measured Voltage
413.7 414.9 414.6 238.9 239.3 240.0
At kWh meter terminals (V)
Measured Voltage
415 415 415 240 240 240
At Voltmeter (V)
INCOMER –2
Measured Voltage
413.6 414.9 414.7 238.5 239.4 240.1
At kWh meter terminals (V)
Measured Voltage
415 415 415 240 240 240
At Voltmeter (V)
SIGNATURE
DATE 26.06.2019
Page 6 of 8
DESIGN AND BUILD OF 30 VILLAS EMIRATI HOUSING PROJECT IN AL HAYER
PROJECT
WITH INFRASTRUCTURE WORKS
CLIENT ABU DHABI HOUSING AUTHORITY EQUIPMENT LV PANEL
END USER AL AIN DISTRIBUTION COMPANY.
CONSULTANT ALTORATH INTERNATIONAL
MAIN CONTRACTOR NAEL GENERAL CONTRACTING EST
HYDROPOWER ENERGY &GENERAL
SUB CONTRACTOR SCHEME NO ND-11-18-116
CONSTRUCTION LLC.
SUBSTATION No AH1010 LOCATION Al HAYER
REMARKS:
SIGNATURE
DATE 26.06.2019
Page 7 of 8
DESIGN AND BUILD OF 30 VILLAS EMIRATI HOUSING PROJECT IN AL HAYER
PROJECT
WITH INFRASTRUCTURE WORKS
CLIENT ABU DHABI HOUSING AUTHORITY EQUIPMENT LV PANEL
END USER AL AIN DISTRIBUTION COMPANY.
CONSULTANT ALTORATH INTERNATIONAL
MAIN CONTRACTOR NAEL GENERAL CONTRACTING EST
HYDROPOWER ENERGY &GENERAL
SUB CONTRACTOR SCHEME NO ND-11-18-116
CONSTRUCTION LLC.
SUBSTATION No AH1010 LOCATION Al HAYER
S.N
INSTRUMENT NAME MAKE TYPE SERIAL No. DUE DATE
O
1 Digital Multimeter FLUKE 87V 36330028 21.06.2020
2 Multi Func.Primary Inj. Kit OMICRON CPC 100 RD 170Y 17.02.2020
3 IR Tester MEGGER MIT 515 101365331 11.06.2020
4 HV AC Test Kit HIPOT HV PFT 1508 21.01.2020
5 SecondaryInj.Kit PROGRAMMA SVERKER 780 1602371 21.01.2020
6 Digital Clamp meter FLUKE 376 33650057WS 21.06.2020
7 Multifunc. Tester FLUKE 1653 B 1552170 20.01.2020
SIGNATURE
DATE 26.06.2019
Page 8 of 8