Seminar Report PDF
Seminar Report PDF
CHAPTER:1
1.1 INTRODUCTION
Construction of segmental bridge started in Europe in 1950. The first attempt of
cast-in-place segmental concrete bridge was conducted across the Lahn River in
Balduinstein, Germany, in 1950. however, the primary precast segmental concrete bridge
was constructed in 1962, across the River Seine in France. Later, this construction method
gained worldwide recognition. Bridge construction time, facilitating construction, and
minimizing the traffic disruption are the main advantages of precast construction in
contrast to cast in-situ construction. Precast segmental concrete bridges are normally
constructed in low seismic areas. Numerous precast segmental concrete columns and pier
constructions have been carried out in the US in low seismic regions such as the states of
Texas and California in the United States.
Construction of longer span bridges is increasing in the United States to satisfy
requirements of function, economics, safety, and aesthetics. The long span potential of
prestressed concrete cannot be fully developed in pretensioned I-girder and composite
slab systems. These systems have practical limits in the 120 feet span range. However,
substantially longer span prestressed concrete bridges have been built by utilizing precast
and cast-in-place box girder bridges erected using various techniques.
In precast segmental bridge construction, the structure is constructed by post-
tensioning together precast segments which are usually manufactured as short
longitudinal sections of the box girder cross section. Balanced cantilever erection was the
early predominant method of constructing segmental bridges. In a number of recent
applications, the span-by-span method with segments assembled on a falsework truss has
seen wide use. The popularity of precast concrete segmental bridge construction has
grown worldwide in the last few decades. A broader understanding of these structures and
basic outline of the processes for construction of prestressed concrete bridges are detailed
in the report.
Fig 1.2 Percentage of bridges built annually with three major construction
materials
1. Reinforcement:
Using welded wire reinforcement (WWR) would speed rebar cage production rates and
lower labor cost. Shop drawings would detail custom fabricated rebar mats that would be
shipped straight for cost purposes and bent on-site. The potential drawback is that it could
compromise durability.
2. Concrete:
The admixture industry has introduced self-compacting concrete (SCC) with the
development of modified polycarboxylates. SCC is extremely cohesive and flowable
without the use of vibration; thereby eliminating internal vibrator marks on vertical
concrete surfaces normally associated with congested reinforcement. Using SCC will
speed the casting process and enhance the aesthetic appearance. In addition, these
admixtures will greatly reduce concrete repairs by reducing voids and entrapped air. This
refinement will also lower casting costs by reducing crew size and equipment needs.
Designing the segments with a higher compressive strength concrete would reduce the
concrete cross-sectional area and thereby provide weight savings. The use of lightweight
concrete could further decrease the overall span weight, reducing post-tensioning
requirements. These modifications provide cost savings in segment delivery and erection.
The next plateau of development will be dramatic gain in early concrete mix design
strength leading toward utilizing the casting form twice a day. Achieving high early
strength concrete is not difficult, but maintaining a low heat of hydration will avoid a
differential thermal gradient causing structural cracks and warping. Achieving this goal
would effectively reduce the project casting time by 50 percent
a. Cast-in-Situ Method
This method prefers for short bridges. Time consuming is large in cast-in-situ
construction as it involves following steps: -
Erection on ground supported staging.
Casting of concrete.
Dismantling of staging.
They are built on-site using formwork supported by temporary falsework or form
travelers. Numerous projects have been constructed in this manner.
Fig 1.4 Form travelers used for casting in Cast in-situ method.
The commonly used method for casting segments in place is with the use of form
travelers. Form travelers are moveable forms supported by steel cantilever trusses
attached to previously completed segments. After finishing all work on a segment, the
form traveler is detached from the previous position and moved forwards on rails that are
mounted on the bridge superstructure.
Formwork creates the shape of the concrete section and any internal voids or
diaphragms. Reinforcement and posttensioning ducts are installed in the forms and then
the concrete is placed, consolidated and cured. When the concrete attains sufficient
strength, post-tensioning strands are installed and stressed to predetermined forces.
Longitudinal post-tensioning is typically comprised of multi-strand tendons draped along
the length of the girder to a designed profile. post-tensioning anchors are arranged
vertically so that the resultant of the tendon anchor force passes close to the centroid of
the section.
However, cost for the pre-casting yard, storage, transportation, and installation of
precast segments needs to be evaluated in comparison with cost for the form travelers for
cast-in-place construction to achieve an economical solution. The pre-casting yard
requires investment in equipment. Adjustable formwork to form the bridge geometry and
alignment needs to be installed. Lifting equipment is also required to put the segments
into the storage area and later load them on truck to be hauled to the construction site.
It is common practice to use the match-cast method to achieve high accuracy in
segment prefabrication. Match-casting means that the segments are cast in the formwork
between a “bulkhead at one end and a previously cast segment at the other” (Levintov
1995, p46). Segment joint faces need to be clean of any dirt for match-casting.
Fig 1.4.1 Schematic representation of short line match casting system. The usual rate
of production is four segments per week per set of forms.
All the casting methods to be discussed utilize the concept of match casting. The
basic premise of match casting is to cast the segments so their relative erected
position is identical to their relative casting position. This requires a perfect fit
between the ends of the segments and is accomplished by casting each segment
directly against the face of the preceding one using a debonder to prevent bonding
of the concrete. The segments are then erected in the same sequence they were
cast. The most common method for match casting segments is called the "short
line" method.
The length of the side forms is equal to the length of the segment being cast plus
1 or 2 in. (25 or 51mm) to seal around the match cast joint. The side forms have
the capability of being folded back away from the segment to permit removal of
the segment. This is done either with screw jacks or hydraulic rams.
For the sake of explaining the casting procedure, assume today is Wednesday. The
older segment was cast on Monday and is now cured and ready for the storage
yard. The old segment was cast yesterday or Tuesday and was match cast against
Monday's segment. Today a new segment will be cast against Tuesday's segment.
this is an alternative to the previously discussed short line system is the long line
system. The system is similar except that a continuous soffit the length of a
cantilever is built.
All the segments are cast in their correct relative position with the side forms
moving down the line as each segment is cast.
Geometry control is established by adjusting the side forms and soffit. Variable
depth structures may be cast by varying the elevation of the soffit, curves are cast
by curving the soffit.
When considering a long line system several things must be taken into account.
First of all, substantial space is required. The minimum length of soffit
required is generally a little more than one-half the longest span of the
structure.
Fig 1.4.1 Schematic representation of long line casting system. Side forms move along
a permanent soffit to cast individual segments.
The foundation must be strong and relatively settlement free because the
segment weight to be supported can be 5 tons per lineal foot or more.
Any curing and handling equipment must be mobile since the side forms
travel along the soffit.
The contractor must set up a monitoring system and adjust the soffits
periodically to correct for any settlement.
After casting the segments are stored at staking yard and curing of segments
will be done.
1.5 Prestressing
Prestressing is used for giving the final strength to bridge.
Application of prestressed concrete for bridge construction was developed by
French engineer Eugène Freyssinet.
The basic principle of prestressing is to induce an initial compressive force in the
concrete that will balance tensile stresses that occur in the member under service
conditions before any tensile stresses occur in the concrete and cause cracking.
two methods of inducing these stresses in the structure:
• By imposed forces from reinforcing steel that is prestressed to a certain degree.
• By imposed “artificial displacements of the supports”, e.g. bearings.
The second method according to is much less used because of high losses of the
prestressing force due to concrete creep and shrinkage.
Prestressing tendons that are used for the first method consist of high-strength
steel and are fabricated as wires, strands, or bars.
For a continuous beam on several supports, most tension will occur in the lower
fibers of the cross-section around midspan and in the upper fibers above
intermediate supports.
It is therefore most useful to place tendons in the locations where tensile stresses
will occur in the structure under service. This thought naturally leads to the idea of
implementing longitudinal tendons in the beam that are not simply straight but
follow a curve from the top above supports to the bottom at midspan and back to
the next support.
Prestressing basically can be carried out as pre-tensioning and post-tensioning
referring to the time when the prestressing force is imposed with respect to
casting.
Post-tensioning denotes the method of stressing the tendons only after the
concrete has reached a specified strength.
Two different ways of construction exist for post-tensioning.
The prestressing tendons located inside the concrete is called internal
post-tensioning.
The prestressing tendons located outside the concrete is called external
post-tensioning.
In Internal post-tensioning, to allow for the necessary movement of the
tendons inside the concrete they are installed in tendon ducts that are made
from steel or polyethylene. The ducts need to be fixed to the normal
reinforcement to prevent misalignment during casting.
After post-tensioning the ducts are filled with cement grout under pressure for
and protection against corrosion of the tendons. Grouting the ducts will
introduce bond between the steel and the surrounding grout.
construction:
1. Anchorages
fig shows a cut-away view of a multi-plane anchorage system. These systems are
commonly confined with spiral reinforcement around the anchor.
fig shows the components of the anchorage system for a four-strand tendon in flat
duct, commonly used in slabs.
Fig 1.5.2 Anchorage system for flat duct tendon (Courtesy of DSI).
2. Ducts
a) Corrugated Steel: -
Corrugated ducts and connectors should be fabricated from galvanized sheet steel
that meets the requirements of ASTM A653, with coating designation G90 (PTI/ASBI
M50.3-12, 2012). The ducts are spirally wound to the necessary diameter from strip steel
with a minimum wall thickness of 0.45mm (26-gauge) for ducts less than 66mm (2-5/8
in) diameter or 0.6mm (24-gauge) for ducts of greater diameter. These ducts are
manufactured with welded or interlocking seams with sufficient rigidity to maintain the
correct profile between supports during concrete placement (Plate.3.13). Ducts should
also be able to flex without crimping or flattening. Joints between sections of duct and
between ducts and anchor components should be made with positive, metallic
connections that provide a smooth interior alignment with no lips or abrupt angle
changes.
c) Corrugated Plastic: -
Corrugated plastic ducts, as shown in Plate.3.14, are also used for tendons
internal to the concrete. These ducts should be seamless and fabricated from polyethylene
or polypropylene (ASTM F405 and D4101) meeting the requirements of Section 4.3.5.2
of “Guide Specification for Grouted Post-Tensioning” (PTI/ASBI M50.3-12, 2012).
e) Prestressing Strand: -
The strand used in post-tensioned bridge systems must meet the requirements of
ASTM A416,“Standard Specification for Steel Strand Uncoated Seven-Wire for
Prestressed Concrete,” and consist of wires having a centre wire enclosed tightly by six
helically placed outer wires with uniform pitch of not less than 12 and not more than 16
times the nominal diameter of the strand. Unless otherwise noted on the contract
documents uncoated Grade 270, low–relation, 7-wire strand (Plate.3.16) should be used
(PTI/ASBIM50.3-12, 2012).
f) Post-Tensioning Bars: -
Bars used in post-tensioned tendons shall conform to ASTM A722, “Standard
Specification for Uncoated High-Strength Steel Bar for Prestressing Concrete.” Bars have
a minimum ultimate tensile strength of 150,000 psi (1035 MPa). Unless otherwise noted
in the contract documents, Grade 150, uncoated, high strength, thread bar shall be used
(PTI/ASBI M50.3-12, 2012).
Fig1.7 Pre-cast concrete segment loaded on 96-wheel trailer for transport to site.
Erection techniques
The precast segments are erected on the sites by following erection techniques: -
a. Balanced Cantilever erection.
b. Progressive Placement erection.
c. Span by Span erection.
d. Incremental Launching erection.
Hydraulic jacks can be attached to the stays to control the stay stresses and
orientation of the cantilever.
An alternate and may be simpler method is to provide jacks beneath the legs of the
vertical steel tower. Thus, the stress in the stays can be varied by raising or
lowering the steel tower.
The primary advantage here is having only two jacks to control the operation.
Progressive placement has advantage of good access to the placement location is
given on the already completed part of the bridge superstructure.
Some disadvantages of the progressive placement method need to be dealt with
during design and construction.
As construction only progresses at the tip of one cantilever, progress is
slower than in balanced cantilevering.
Progressive placement resembles incremental launching in that the
superstructure undergoes stresses very different from the permanent
service conditions, including even stress reversals.
Primarily, the post-tensioning tendons may all be continuous for the total span
length and may be located in a draped manner providing most efficient use of
post-tensioning forces.
Also, only one operation of installing and stressing tendons is required per span.
The span by span erection technique allowed two other modifications of
normal segmental construction procedures.
The Long Key Bridge is the first precast segmental bridge to be
constructed with dry joints. Normal practice is to seal the joints with
epoxy. However, dry joints are not recommended for bridges which
may be subject to freeze-thaw conditions and deicing chemicals.
Also, the post-tensioning tendons are located in the void of the box
girder as opposed to locating the tendons in the concrete walls of the
sections. The tendons are protected with plastic conduits and grout.
This tendon location simplifies the casting of the segments and
eliminates any problems of tendon alignment at the segment joints.
Fig1.9 External tendon corrosion along the free length of the tendon
1.10
Cases of Post-Tensioned Tendon Corrosion
Table 4.1 presents a number of post-tensioned bridges that experienced tendon
corrosion throughout their service life. Included in the table is the bridge name, bridge
type, location of the bridge and observed damage to the tendons. The degree of
damage observed varied included significant tendon corrosion, complete failure of
tendons, and in some extreme cases complete collapse of the bridge.
In these cases, there are several causes of post-tensioning corrosion like voids and
moisture between strands and between wires, water bleeding from grout, grout
segregation, water penetration from anchorage pocket, water penetration due to
floods, chloride contaminated grout, soft grout, high corrosive ion concentration and
dissimilar grouts in the same tendon. Corrosion incidents were usually found to be
associated with poor details and execution generally in the presence of aggressive
environment. In cases where the tendons did not reach the point of failure the tendon
corrosion observed was significant enough to cause bridge closures and/or require
repairs to the system.
Observed
Bridge Name Bridge Type Location Year Causes of Corrosion
Damage
Transverse joints
between segments
Segmental Bridge
Ynys-Y-Gwas Whales 1985 filled with dry mortar
PT Collapse
caulking allowing
water infiltration.
Precast
Water infiltration into
Niles Channel Segmental Tendon
Florida 1999 tendon anchorage with
Bridge PT Box Failure
voids.
Girder
Poor grout
Precast quality/practices, voids
Segmental near anchorage,
Sunshine Tendon
PT Box Florida 2000 cracked HDPE ducts,
Skyway Failure
Girder / water infiltration
Cable Stay through segmental
joints.
Precast
Cracked PT ducts and
Mid Bay Segmental Tendon
Florida 2000 exposed strand along
Bridge PT Box Failure
water bleed trails.
Girder
Cable Stay
Varina-Enon Tendon Voids in tendons and
with PT Box Virginia 2001
Bridge Failure absence of grout.
Girder
Disadvantages:
Need high safety precautions during construction.
Extra cost due to more prestressing.
CHAPTER 2:
LITERATURE REVIEW
(Podolny 1982; Baur 1977). the “modern” approach to launching concrete bridges was
developed. The first concrete bridge constructed by launching was built over the River
Caroni in Venezuela and was completed in 1963 The bridge was a post-tensioned
concrete box girder bridge with a main span of 315 ft. The construction of this bridge was
considered so successful that the launching method was utilized to construct a nearly
identical bridge a few years later.
The first steel bridge to be launched in the United States is believed to be a Kansas City
Southern Railroad box girder bridge near Redland, OK in 1970 (Durkee 1972). The nine-
span continuous bridge is 2,110 ft. long with a main span of 330 ft. This bridge was
launched in two trains, one from each side of the river. Closure of the bridge was
accomplished at mid-span of the main span.
During the launching operation, the bridge superstructure is supported by a series of
rollers or sliding bearings. These rollers are removed following the launching and the
bridge is lowered to rest on permanent bearings identical to those used for a
conventionally constructed bridge. The thrust required to launch the bridge forward can
be provided by a variety of jacking systems, including hydraulic pistons or hollow-core
strand jacks more commonly used for posttensioning.
IRC 18-2002 it provide information about stages of prestressing and grouting operations
and storage and handling of prestressing material.
IRC SP 65-2005 provides guidelines for design and construction of segmental bridge in
India. It deals with various construction of precast segmental bridge. It gives insights in
to the various construction requirement ,detailing of prestressing, various design aspect.
Turmo J et al. (2005) inspected the joints between segments in many precast
concrete.Bridges constructed by balanced cantilever method during construction and in
service. Site investigations of 5 major bridges during construction and in service over the
past 15 years showed that the joints between segments perform adequately if proper
construction procedures are followed.
Kavin kumar et al. (2008) gives an insight into the automated geometry control of
segmental bridges. The short line method of pre casting concrete segments has proved to
be most versatile and reliable way to building pre-cast segmental bridges. Advantages and
disadvantages of segmental bridges, transportation of segments to construction site,
erection techniques.
(Gohler 2013), It is estimated that over 1,000 bridges worldwide have been constructed
by the incremental launching method the vast majority of which have been post-tensioned
concrete box girder bridges. Their main application has been in Europe, but the method
has now spread around the world and the technology has been applied to steel I-girder.
It includes prefabricated segments, transportation and set into place with an appropriate
lifting device and a launching gauntry.
CHAPTER 3
3.1 A CASE STUDY OF SUTONG BRIDGE CHINA
4. CONCLUSION
This method is ideal for bridge construction bridge give Aesthetical view or good
quality.
Longer span bridge now possible.
Longer bridge over water now possible.
Construction of long bridges now easy.
Construction time is less.
Environment friendly construction.
Construction line is highly mechanized by this method.
REFERENCES