This project execution plan outlines the major construction works for developing a port, which includes building road access, gas facilities, a metering station, pipelines, and a supervisory control system to monitor the new infrastructure. The construction will be carried out across 6 major lines - road/pavement, buildings/foundations, equipment installation, piping, electrical, and instrumentation work. A chart schematically illustrates the general sequencing of these construction lines.

Uploaded by

FH Gan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
115 views

Project Execution Plan

This project execution plan outlines the major construction works for developing a port, which includes building road access, gas facilities, a metering station, pipelines, and a supervisory control system to monitor the new infrastructure. The construction will be carried out across 6 major lines - road/pavement, buildings/foundations, equipment installation, piping, electrical, and instrumentation work. A chart schematically illustrates the general sequencing of these construction lines.

Uploaded by

FH Gan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

Project execution plan

1 General

The major construction works involved in this tender for short term
development of the port comprises the followings:

(1)Road access to the marine facilities

(2 )Gas facilities & associated utilities to receive the high pressure gas
delivered by the FSRU, to transport the gas over a short distance to a
Metering Station

(3)The Metering Station

(4)The Pipelines Offtake AGI (Above Ground Installation)

(5)The 16’’ pipeline to Port Sudan power station

(6)The Gas Offtake AGI (metering) at the power station

( 7 ) A Supervisory Control And Data Acquisition (SCADA) and


telecommunication systems to monitor the above facilities and capable of
expansion for the future pipeline to Khartoum & beyond.

2 General Construction Process

It is planned to carry out the construction works for this project in 6 major
construction lines in general , including construction of road and
pavement, building and foundation work、equipment installation, piping
work 、 electrical work and instrument work. The general construction
sequences for these major construction lines are schematically illustrated
in Following chart.