Procedure For Granting EOT: SCL Delay and Disruption Protocol 2 Edition: February 2017 6
Procedure For Granting EOT: SCL Delay and Disruption Protocol 2 Edition: February 2017 6
6. Effect of delay
For an EOT to be granted, it is not necessary for the Employer Risk Event already to
have begun to affect the Contractor’s progress with the works, or for the effect of the
Employer Risk Event to have ended.
9. Identification of float
The identification of float is greatly assisted where there is a properly prepared and
regularly updated programme, the Accepted/Updated Programmes.