M/D Totco'" Inell: 1 Part Number 26-61 Revision A
M/D Totco'" Inell: 1 Part Number 26-61 Revision A
I Revision A
M/D TOTCO’”
iNell
INSTALLATION, OPERATION, AND MAINTENANCE
PAGE ISSUE
NO. DATE
A
INSTRUCTION MANUAL 26-6 1
INSTRUCTION MANUAL 26-61
SI UNIT CONVERSION FACTORS
KILOPASCALS (kPa)
x 0.001 = Pascals (Pa)
x 0.001 = Newtons per square metre (N/m2>
INCHES (in.)
x 2.540 = Centimetres (cm)
ii
INSTRUCTION MANUAL 26-61
TABLE OF CONTENTS
Section Page
iii
INSTRUCTION MANUAL 26-61
TABLE OF CONTENTS (Cont’d)
Section Page
III 3-25 . . Gauge Disassembly (Box Mount, Clamp Mount and . . . . . 3-9
(Cont'd) Tong Mount 90')
3-26 . . Gauge Reassembly (Box Mount, Clamp Mount and . . . . . 3-11
Tong Mount 90')
3-27 . . Gauge Disassembly (Panel-Mount) . . * . * * . . . . . . 3-12
3-28 . . Gauge Reassembly (Panel-Mount) * . * * . . . . . . . . 3-14
3-29 . . Low-Pressure, Panel-Mount Damper Disassembly . . . . . 3-14
3-30 . . Low-Pressure, Panel-Mount Damper Reassembly . . . . . . 3-15
3-31 . . High-Pressure, Panel-Mount Damper Disassembly . . . . . 3-16
3-32 . . High-Pressure, Panel-Mount Damper Reassembly . . . . . 3-17
3-33 . . Low-Pressure, Gauge-Mount Damper Disassembly . . . . . 3-17
3-34 . . Low-Pressure, Gauge-Mount Damper Reassembly . . . . . . 3-17
3-35 . . High-Pressure, Gauge-Mount Damper Disassembly . . . . . 3-17
3-36 . . High-Pressure, Gauge-Mount Damper Reassembly . . . . . 3-19
3-37 . . Linkage Disassembly. . . . . . . . . . . . . . . . . . 3-19
3-38 . . Linkage Reassembly . . . . . . . . . . . . . . . . . . 3-20
3-39 Calibration . . . . . . . . . . . . . . . . . . . . . . . . 3-20
3-40 .General.. -. . . . . . . . . . . . . . . . . . . . . . 3-20
3-41 . . Gauge Calibration. - . . . . . . . . . . . . . . . . . 3-21
IV TROUBLESHOOTING ......................... 4-l
4-l . General. ........................ 4-l
LIST OF ILLUSTRATIONS
Figure Page
iv
INSTRUCTION MANUAL 26-61
LIST OF TABLES
Table Page
RELATED PUBLICATIONS
Publication
Number Title
v/vi
INSTRUCTION MANUAL 26-61
SECTION I
PURPOSE AND DESCRIPTION
l-l INTRODUCTION
1-3 PURPOSE
l-4 Joint torque systems are designed to indicate the torque applied to drill
pipe, drill collars, tubing and casing when making up the joints. The
entire success of the drilling operation and a long, successful working life of
the well depends on a properly run string of pipe. When running casing or tubing
with power tongs, the joint torque system gives the tong operator the torque being
applied to each joint and assures uniform and proper make-up of the entire string.
l-5 DESCRIPTION
l-6 GENERAL
l-7 The system consists of the following: tension load cell, indicating gauge,
interconnecting hydrualic hose and mounting hardware. The system is
totally hydraulic and requires no electrical power or connections (See Figure l-l).
Refer to Table l-l for leading particulars.
SYSTEM
TENSION-TYPE LOAD CELL 3.68, 4.0 and 6.53 sq in. free spin
2,500, 5,000, 7,500, 10,000, 12,000
15,000, 20,000, 25,000, 30,000, 50,000
and 100,000 ft-lbs
l-l
INSTRUCTION MANUAL 26-61
8
A B
BOX MOUNT TONG MOUNT
PANEL DN~OUNT
TO STEEPLE
(PANEL MOUNTED GAUGE) PIPE THREADS
OR
TO DAMPER
(BOX, TONG, OR CLAMP
MOUNTED GAUGE1
LOAD CELL
ASSEMBLY
1. Hydraulic Hose
2. Shackle
3. Shackle Pin
4. Load Cell
l-8 TENSION TYPE LOAD CELL. The load cell consists of a heavy duty cylinder,
piston, and piston rod. The load cell converts the line pull into a hy-
draulic pressure signal that is transmitted through a hydraulic hose to the indicating
gague.
l-9 INDICATING GAUGE. The indicating gauge is a pressure sensing gauge that
uses a Bourdon tube to drive the pointer. The gauge has a six-inch dial
and is fluid filled to reduce extreme pointer movement and to lubricate and protect
working parts. The gauge incorporates an adjustable target pointer that can be
set for desired torque. An adjustable damper regulates pointer sensitivity.
l-12 GENERAL. The load cell is installed in the snub line at the back-up post
or derrick leg. The indicating gauge is installed in the weight indicator
box, drilling console or other location clearly visible to the driller.
l-3
INSTRUCTION MANUAL 26-61
l-13 With the system properly installed, any line pull placed on the load cell
results in a hydraulic fluid displacement from load cell into the inter-
connecting hose. This hydraulic signal is transmitted through the hydraulic hose
to the indicating gauge. The gauge applies this signal to the Bourdon tube that
drives the pointer to a position that equals total torque in ft-lbs on the gauge
dial.
l-4
INSTRUCTION MANUAL 26-61
SECTION II
INSTALLATION AND ADJUSTMENT
2-l INSTALLATION
2-2 GENERAL. This section contains procedures for installing the joint torque
system (See Figure 2-l). Components of the joint torque system are weather
resistant, and have been field tested for continuous operation in hot and cold
temperature extremes. The components are shipped individually or as complete
systems and simple installation procedures are all that is necessary to complete
a system (See Figures 2-2, 2-3, 2-4 and 2-5).
2-3 LOAD CELL. The tension-type load cell is installed in series with the
snub line and anchored to the derrick leg or post. The length of the snub
line should be such that the tongs operate at a right angle to the line. Load
cells vary in sizes (3.68, 4.0, and 6.53 inches). Determine your need, remove
shackle pins (3, Figure 2-l), shackle (4) and install load cell. Reinstall shackles
(4) and pins (3).
WARNING
2-4 INDICATING GAUGE. The indicating gauge can be mounted in different positions
and locations, for example: box-mount, clamp-mount, bracket-mount, or
panel-mount. The gauge should be installed at either the driller's position (the
weight indicator box or console) or the tongs. Ensure no load is on the system
and proceed as follows:
2-5 INDICATING GAUGE AND DAMPER (PANEL-MOUNT). Ensure that no load is on the
system and proceed as follows:
2-l
INSTRUCTION MANUAL 26-61
2-6 HYDRAULIC HOSE INSTALLATION (BOX, CLAMP, AND BRACKET MOUNT). Routing of
the hydraulic hose should be carefully selected. Avoid areas where moving
machinery and rig personnel are working. Clamp or tie hose clear of water, mud
and walkways where it may sustain damage. Clean all hose connections, apply
Loctite high performance pipe sealant (Refer to Approved Expendable Item List) to
pipe threads (See Figure l-1) and proceed as follows:
a. Connect hose (E, 1, Figure l-l) to load cell (4), and connect
hose to gauge (A, B, C, or D).
2-2
INSTRUCTION MANUAL 26-61
I‘ 12.50
(6.35 CM)
A
Ml
-2.50-r
1.35 CM
-
1 .$O I
r
(1.27 CM)
0 0
0 0
45d
VP)
0 0
0 0
t- 9.62
(24.43 CM)
2-3
INSTRUCTION MANUAL 26-61
2.62
(6.65 CM)
-1
.87
I--
+5.37-4 4.50-l
(2.21 CM)
(13.64 CM) (11.43 CM)
t
8.12 k-6.75-4
26-61 -6
(20.62 CM) (17.14 CM)
2-7 HYDRAULIC HOSE INSTALLATION (PANEL MOUNT). After routing the panel mount
hydraulic hose (Refer to Paragraph 2-6) (See D, Figure l-l), proceed as
follows:
NOTE
2-4
INSTRUCTION MANUAL 26-61
(6.72 CM)
l.64 .261
CM)
(19.68 CM) c
I V-J:37
l/4 NPT
(39.0 CM)
1.$3
I (4.14 CM)
1.12-
(2.84 CM)
2.38
(6.05 CM)
.25-l
l/4 NPT
2-5
INSTRUCTION MANUAL 26-61
NOTE
2-6
INSTRUCTION MANUAL 26-61
SECTION Ill
PERIODIC INSPECTION, FIELD MAINTENANCE,
SHOP MAINTENANCE AND CALIBRATION
3-2 Joint torque systems are built to give long, trouble-free service with a
minimum of maintenance and inspection. To keep the system in best operating
condition, periodic inspections must be carried out. Maintenance personnel should
establish a suitable inspection cycle based on usage and operating environment of
the system.
3-4 GENERAL. Carry out a general visual inspection of the entire joint torque
installation, checking for damage, wear, and loose parts. Correct all
discrepancies and replace defective components. Carefully check the load cell,
the hose, gauge, and all connections. A thorough inspection should be made at
each rig up. For periodic inspection, cleaning, lubrication, and service of joint
torque system, Refer to Table 3-l.
3-l
INSTRUCTION MANUAL 26-61
3-7 SYSTEM RELOADING. The system is reloaded with instrument fluid (M-15)
(Refer to Approved Expendable Item List) through the filling connection
at the top of the indicating gauge. Reloading should only be attempted when there
is no load on the load cell. System reloading is accomplished as follows:
NOTE
a. Fill hand pump bowl with instrument fluid (M-15) and connect hand
pump to filling connection on gauge.
NOTE
b. During loading, loosen vent screw (3, Figure 3-l) on load cell body (4)
to permit entrained air to bleed from the system.
C. Pump instrument fluid into the system until the piston rod (2) on the
load cell extends no more than l/4-inch from the body (4) as shown.
d. Once the system is loaded, tighten load cell vent screw (3) and
remove hydraulic hand pump.
3-2
INSTRUCTION MANUAL 26-61
3-8 SYSTEM LOADING WITH PANEL-MOUNTED GAUGE. Reload system with panel-mounted
gauge in the same manner as a system without panel-mounted gauge except,
connect hydraulic hand pump to filling steeple located on side of drilling console
and repeat steps b. thru d., paragraph 3-7.
3-9 HYDRAULIC HOSE REMOVAL (BOX, TONG AND CLAMP MOUNT)(FIGURE 3-2). Ensure
that no load is on the system and proceed as follows:
3-10 HYDRAULIC HOSE REMOVAL (PANEL MOUNT). Ensure that no load is on the
system and proceed as follows:
NOTE
3-11 HYDRAULIC HOSE INSTALLATION (BOX, TONG AND CLAMP MOUNT). Clean all hose
connections; apply Loctite high performance pipe sealant (Refer to Ap-
proved Expendable ItemsList) to pipe threads (See Figure 3-2) and proceed as
follows:
a. Connect hose to load cell (E, 4, Figure 3-2) and connect hose to
manifold (if hose has quick-disconnect, apply Loctite to pipe threads,
install quick-disconnect, and connect quick-disconnect to manifold).
3-3
INSTRUCTION MANUAL26-61
8
A I3
BOX MOUNT TONG MOUNT
TO STEEPLE
(PANEL MOUNTED GAUGE) PIPE THREADS
OR
TO DAMPER
(BOX, TONG, OR CLAMP DISCONNECT
MOUNTED GAUGE)
3-4
INSTRUCTION MANUAL 26-61
1. Hydraulic Hose
2. Shackle
3. Shackle Pin
4. Load Cell
NOTE
3-13 SHACKLE AND LOAD CELL REMOVAL (3.68, 4.0 AND 6.53 INCH LOAD CELLS). Ensure
that no load is on the system (See Figure 3-2) and proceed as follows:
b. Remove shackle pins (3), shackles (2) and load cell (4).
C. Inspect shackles (2) and pins (3) for cracks, bends, wear and
deterioration. If defective, replace the item.
3-5
INSTRUCTION MANUAL 26-61
3-14 SHACKLE AND LOAD CELL INSTALLATION (3.68, 4.0 AND 6.53 INCH LOAD CELLS).
Ensure that no load is on the system and proceed as follows:
WARNING
a. Insert shackles into cable loops (See Figure 2-l); place open end of
shackles (3, Figure 3-2) over connecting end of load cell (4) and
secure with shackle pins (2).
3-15 GAUGE REMOVAL (BOX, CLAMP AND TONG MOUNT). Remove all load from the joint
torque system. Disconnect hydraulic hose (Refer to Paragraph 3-9); proceed
as follows:
a. Remove three screws (5, Figure 3-2), washers (6), box or tong mount
bracket (7) and remove gauge (8) from bracket (7).
b. Remove three nuts (5), three bolts (6), gauge (7), setscrew (8)
and clamp mount bracket (9).
3-16 GAUGE INSTALLATION (BOX, CLAMP, AND TONG MOUNT). Ensure that no load is
on the system (See Figure 3-2); proceed as follows:
a. Secure gauge (8) to bracket (7)(B ox or Tong) with three lockwashers (6),
and three screws (5). Bolt bracket (7)(Box or Tong Mount) and gauge
in place with three lockwashers (6) and three screws (5).
b. Place clamp mount bracket (9) onto selected position and secure
with two setscrews (8); install gauge (7) into bracket (9), secure
with three bolts (6) and three nuts (5).
a. Disconnect tubing and remove the following: roll pin (9), two
bolts (lo), two washers (11) and damper assembly (12); four nuts
(6), four screws (7) and gauge assembly (8).
3-6
INSTRUCTION MANUAL 26-61
a.Install gauge (8) into panel and secure with four bolts (7) and
four nuts (6). Install damper assembly (12) into panel adjacent
to gauge, secure it with two washers (11) and two bolts (10). Connect tubing (5)
between gauge (7) and damper (12). With gauge and damper properly installed, system
must be reloaded (Refer to Paragraph 3-7).
3-21 LOAD CELL DISASSEMBLY (3.68, 4.0 AND 6.53 SQUARE INCH LOAD CELLS). To
disassemble the load cell, apply a small amount of tension on rod end
and drain instrument fluid into an approved waste container, clamp cylinder head
into a vise (See Figure 3-3) and proceed as follows:
a.Remove elbow (l), setscrew (2); with cylinder head spanner wrench
(Refer to Related Tools and Test Equipment); unscrew head (3) from
body (16). Remove gasket (4), screw (5) and stat-o-seal (6). Take cylinder
head (3) from vise, place it on clean work bench and secure piston rod (9) in
the vise.
b. Remove setscrew (7) and with spanner wrench (Refer to Related Tools
and Test Equipment); unscrew and remove piston (8) from rod (9).
Slide body (16) from piston rod (9). Remove rod o-ring (lo), piston o-ring (ll),
rod-to-piston o-ring (12) and dust seal (13), drive screws (14) and identification
plate (15).
NOTE
WARNING
3-22 Carefully clean all load cell parts (use trichlorethylene), remove all
foreign matter, taking care not to damage any internal surfaces or moving
parts. Replace all o-rings, gaskets and seals.
3-7
INSTRUCTION MANUAL 26-61
3-23 LOAD CELL REASSEMBLY (3.68, 4.0 AND 6.53 SQUARE INCH LOAD CELLS). To re-
assemble the load cells (See Figure 3-3) proceed as follows:
a.If identification plate (15) was replaced, ensure that correct data is
recorded on new plate. Position identification plate over mounting
holes on the cylinder body (16) and secure with drive screws (14).
b. Install o-ring (10) and dust seal (13) in cylinder body (16); o-ring (12)
into piston (8) and o-ring (11) onto piston (8). Secure piston rod (9)
in a vise and carefully lower cylinder body (16) onto piston rod (9).
3-8
INSTRUCTION MANUAL 26-61
3-24 With the load cell reassembled, shackles must be reinstalled (Refer to
Paragraph 3-14). For rig installation, Refer to Paragraph 2-3.
3-25 GAUGE DISASSEMBLY (BOX MOUNT, CLAMP MOUNT AND TONG MOUNT 90°)(FIGURE 3-4).
Maintenance is the same for box-, clamp- and tong-mount gauges; proceed
as follows:
NOTE
a. Remove dust cap (l), male coupling (2), elbow (3), nipple (4), cap
plug (5) and tee (6). Place gauge on clean work surface with dial
face up, and remove four screws (8), case ring (7) and glass assembly. Drain M-8
fluid into approved waste container.
NOTE
c. Remove two screws (23), two nuts (24), two washers (25) and linkage
assembly (22)(Refer to Paragraph 3-37 thru 3-38 for maintenance).
Remove screw (27), washer (28), tube stop (26), two screws (30) and movement
assembly (29); two bolts (32), two washers (33), damper assembly (31) with tube
(34). Disconnect male connector (35) and remove tube (34)(Refer to Paragraph 3-29
thru 3-36 for damper disassembly and reassembly). Remove screw (37), washer (38),
tube stop (36), screw (39) and stat-o-seal (40) from gauge case (41). With dis-
assembly complete, replace all o-rings, seals, gaskets and defective parts.
3-9
INSTRUCTION MANUAL 26-61
\ \
\ \
\
3-26 GAUGE REASSEMBLY (BOX MOUNT, CLAMP MOUNT AND TONG MOUNT 900). Reassembly
procedures for the box-, clamp- and tong-mount gauges follow the same
order. To reassemble (See Figure 3-4), place gauge case (41) on clean work surface
face up and proceed as follows:
C. Stand gauge in upright position and install tee (6), cap plug (5),
nipple (4), elbow (3) and male coupling (2). Calibrate gauge assembly
in accordance with calibration procedures in paragrpah 3-39. After calibrating,
install dial (16) and secure with three lockwashers (18), three screws (17). Use
automatic center punch to stake pointer (15) on pinion shaft. Pointer hub should
be flush with pinion end, not to exceed .03 max. Install o-ring (14).
3-11
INSTRUCTION MANUAL 26-61
a. Remove cap plug (8), elbow (9), screw (lo), and stat-o-seal (11).
Invert the gauge and drain the fluid into an approved waste container.
b. Place gauge on work surface face up and remove four screws (13), case
ring (12). If inspection reveals that glass assembly must be dis-
assembled, remove setscrew (14), knob (15), o-ring (16), and target pointer (17)
from glass (18). Remove o-ring (19), pointer (20), three screws (22), washer (23),
and dial (21). Disconnect male connector (41) from Bourdon tube (24), remove
three screws (25), o-rings (26) and Bourdon tube assembly (24).
NOTE
3-12
INSTRUCTION MANUAL 26-61
3-13
INSTRUCTION MANUAL 26-61
C. Remove two screws (28), two nuts (29), two washers (30) and linkage
assembly (27)(Refer to Paragraph 3-37 for maintenance). Remove
screw (32), washer (33), tube stop (31), two screws (35) and movement assembly (34);
two bolts (37), two washers (38), junction block (36) with tube (40) and gasket
(39) * Disconnect male connector (41) and remove tube (40). Remove screw (43),
washer (44) and tube stop (42). With disassembly complete, replace all o-rings,
seals, gaskets and defective parts.
Fill
g. gauge with instrument fluid (M-8)(Refer to Approved Expendable
Item List) (holding gauge upright, fill with fluid to within .25 in.
of inner ring diameter, approx .75 quart). Install stat-o-seal (ll), screw (lo),
elbow (9), and cap plug (8).
a. Remove hex plug (3), and male connector (4), loosen retainer nut (7)
and remove stem assembly (5 thru 8).
3-14
INSTRUCTION MANUAL 26-61
b. Remove o-ring (5), roll pin (6), and retainer nut (7) from damper
stem (8).
a. Install o-ring (5) and retainer nut (7) onto damper stem (8); install
roll pin (6).
b. Install damper body (9) into console and secure with two washers (2),
two bolts (1); insert stem assembly (5 thru 8) into damper body (9),
and secure with retainer nut (7).
3-15
INSTRUCTION MANUAL 26-61
a. Remove hex plug (3) and male connector (4); loosen nut (9) and
remove high pressure stem assembly (5 thru 10). Remove o-ring (5),
back up ring (6), roll pin (7), stem cap (8), and retainer nut (9) from stem
assembly (10).
b. Clean all metal parts with trichloroethylene, taking care to remove
all foreign material, corrosion, etc. Replace o-ring and any other
worn, damaged, or defective parts.
11
3-16
INSTRUCTION MANUAL 26-61
a. Install o-ring (5), back up ring (6), retainer nut (9), stem cap
(8) on high pressure stem (10); align hole in stem cap (8) with roll
pin holes and secure with roll pin (7).
Install
b. male connector (4) and install plug (3). Install damper body
(11) into console; secure with two washers (3) and two bolts (2).
Install high pressure stem assembly (5 thru 10) through console and into damper
body (11); secure with high pressure nut (9).
a. Remove gasket (3), hex plug (4), male connector (5) and low pressure
stem assembly (6 thru 9). Remove o-ring (6), roll pin (7), retainer
nut (81, from damper stem (9).
a. Install o-ring (6) and retainer nut (8) onto low pressure stem
assembly (9), and install roll pin (7).
b. Insert stem assembly (9) into damper body (10) and secure with
retainer nut (8). Install male connector (5), hex plug (4), and
gasket (3).
a. Remove gasket (3), hex plug (4) and male connector (5); loosen nut (lo),
back up ring (7), roll pin (8), stem cap (9), and high pressure nut (10) from stem
assembly (11).
3-17
INSTRUCTION MANUAL 26-61
1. Bolt 6. O-Ring
2. Lockwasher 7. Roll Pin
3. Gasket 8. Nut
4. Plug 9. Stem
5. Male Connector 10. Body
3-18
INSTRUCTION MANUAL 26-61
26-62, -12
a.
Install o-ring (6), back-up ring (7), nut (lo), stem cap (9) on high
pressure stem (11); align holes in stem cap (9) with roll pin holes
and secure with roll pin (8). Insert high pressure stem assembly (6 thru 11)
into damper body (13) and secure with retainer nut (10). Install male con-
nector (5), hex plug (4), and gasket (3).
3-37 LINKAGE DISASSEMBLY. To disassemble the linkage assembly (See Figure 3-10)
proceed as follows:
a. Remove two slotted nuts (l), shoulder screw (3), shoulder screw (4),
two washers (2), two nuts (5), two washers (6) and slide (7).
3-19
INSTRUCTION MANUAL 26-61
3-38 LINKAGE REASSEMBLY. To reassemble the linkage assembly (See Figure 3-10)
proceed as follows:
a. Place slide (7) on top of linkage (8) with slotted end over adjusting
weldment screws, and secure with two washers (6) and two nuts (5);
install washers (2), shoulder screws (3)(4) and slotted nuts (1).
3-39 CALIBRATION
3-20
INSTRUCTION MANUAL 26-61
3-41 GAUGE CALIBRATION. To calibrate the joint torque indicating gauge (See
Figure 3-11) place on clean work bench and proceed as follows:
b. Center the linkage (10) on the slotted end of the Bourdon tube tip (9),
and on the slotted end of the movement quadrant (11). Adjust the
linkage slide (10) so that the quadrant arm (7) is parallel with top plate of the
movement assembly (6). Tighten linkage slide nuts (8) and attaching nuts (12).
C. Install dial (2) and center it over mounting holes (do not install
dial mounting hardware). Check pointer pinion shaft (5); it should
be in the center of the hole in the dial face (1). If not centered, remove dial
(2), loosen movement mounting screw (4) and position the movement (6) to a position
that will center pointer pinion shaft (5) when the dial (2) is installed. Tighten
movement mounting screws (4), install dial (2), and recheck centering. Repeat the
above procedure until pointer pinion shaft is centered.
d. Connect the gauge to the high pressure test bench (Refer to Related
Publications) using the special hardware supplied (elbow, hex nipple,
or male quick-disconnect fitting, whichever is required)(Refer to Related Tools
and Test Equipment). Check the damper assembly on the bracket-mount gauge only
(not required on panel-mount gauge), it should be in the full open position.
NOTE
3-21
INSTRUCTION MANUAL 26-61
aY
3-22
INSTRUCTION MANUAL 26-61
1. Apply calibration pressure for 270' (3/4 scale) indication and note
test gauge; now apply calibration pressure for 360° (full scale) in-
dication. If the indication is less than 268O (314 scale) and 358' (full scale),
release the pressure and loosen the linkage slide nuts (8), and shorten the
linkage (10). If the indication is above 272' (3/4 scale) and 362' (full scale),
lengthen the linkage (10). Tighten linkage slide nuts (8) and recheck calibra-
tion.
3-23
INSTRUCTION MANUAL 26-61
k. Place zero stop (A, Figure 3-11) against quadrant arm (7), and place
enough tension on quadrant arm (7) with zero stop (A) to bring pointer
(3) to zero. Tighten zero stop.
1. Apply full scale pressure and install maximum stop (B). Maximum stop
should be installed in suchaposition to allow the pointer to travel
20' beyond maximum (38OO).
m.
Relieve the pressure and remove calibration dial and pointer. Remove
special hookup connections if used, and refer to Paragraph 3-26 or
3-28 to complete gauge reassembly.
FULL SCALE
DIAL CAPACITY HANDLE LENGTH LOAD CELL CALIB PRESS
GAUGE PN (FT-LBS) (IN. > (SQ IN.) (PSIG)
3-24
INSTRUCTION MANUAL 26-61
FULL SCALE
DIAL CAPACITY HANDLE LENGTH LOAD CELL CALIB PRESS
;AUGE PN (FT-LBS) (IN.) tSQ IN.) (PSIG)
3-25
INSTRUCTION MANUAL 26-61
FULL SCALE
DIAL CAPACITY HANDLE LENGTH LOAD CELL CALIB PRESS
GAUGE PN (FT-LBS) (IN.1 (SQ IN.) (PSIG)
3-26
INSTRUCTION MANUAL 26-61
3-27
INSTRUCTION MANUAL 26-61
3-28
INSTRUCTION MANUAL 26-61
I------
LOAD CELL
HANDLE LENGTH DIAMETER
GAUGE PN (IN.1 (SQ IN. >
214330-101 24 4.0 3,688
214330-102 36 4.0 2,459
214330-103 42 4.0 2,107
214330-104 48 4.0 1,844
214331-101 36 4.0 4,180
214331-102 42 4.0 3,582
214331-103 48 4.0 3,135
214332-101 48 6.53 3,812
214332-102 52 6.53 3,519
3-29/3-30
INSTRUCTION MANUAL 26-61
SECTION IV
TROUBLESHOOTING
4-l GENERAL. The indicating gauge serves as the best troubleshooting device.
No indication or erroneous indication on the gauge will define the major
trouble areas. A list of probable causes for these troubles is given in Table 4-l.
Under normal operating conditions, and with proper care, few troubles will be en-
countered with the joint torque system.
NOTE
4-l/4-2