Work Execution Schedule (L4) For DM Water Storage Tank A & B

This schedule outlines the planned execution of work for building two demineralized water storage tanks (Tank A and Tank B) between May 16th and August 13th, 2017 for the 400 MW Bibiyana-III Gas Based Combined Cycle Power Plant project. Key activities include mobilization on May 16th, excavation from May 17th-18th, plumbing from May 19th-25th, concrete works from May 26th-31st, and testing/commissioning from August 10th-13th.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
555 views2 pages

Work Execution Schedule (L4) For DM Water Storage Tank A & B

This schedule outlines the planned execution of work for building two demineralized water storage tanks (Tank A and Tank B) between May 16th and August 13th, 2017 for the 400 MW Bibiyana-III Gas Based Combined Cycle Power Plant project. Key activities include mobilization on May 16th, excavation from May 17th-18th, plumbing from May 19th-25th, concrete works from May 26th-31st, and testing/commissioning from August 10th-13th.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Bibiyana-III 400 MW Gas Based CCPP Project

Schedule for the Execution of DM Water Storage Tank (A & B)

16-May-17
17-May-17
18-May-17
19-May-17
20-May-17
21-May-17
22-May-17
23-May-17
24-May-17
25-May-17
26-May-17
27-May-17
28-May-17
29-May-17
30-May-17
31-May-17

10-Aug-17
11-Aug-17
12-Aug-17
13-Aug-17
14-Aug-17
15-Aug-17
16-Aug-17
10-Jun-17
11-Jun-17
12-Jun-17
13-Jun-17
14-Jun-17
15-Jun-17
16-Jun-17
17-Jun-17
18-Jun-17
19-Jun-17
20-Jun-17
21-Jun-17
22-Jun-17
23-Jun-17
24-Jun-17
25-Jun-17
26-Jun-17
27-Jun-17
28-Jun-17
29-Jun-17
30-Jun-17

1-Aug-17
2-Aug-17
3-Aug-17
4-Aug-17
5-Aug-17
6-Aug-17
7-Aug-17
8-Aug-17
9-Aug-17
10-Jul-17
11-Jul-17
12-Jul-17
13-Jul-17
14-Jul-17
15-Jul-17
16-Jul-17
17-Jul-17
18-Jul-17
19-Jul-17
20-Jul-17
21-Jul-17
22-Jul-17
23-Jul-17
24-Jul-17
25-Jul-17
26-Jul-17
27-Jul-17
28-Jul-17
29-Jul-17
30-Jul-17
31-Jul-17
1-Jun-17
2-Jun-17
3-Jun-17
4-Jun-17
5-Jun-17
6-Jun-17
7-Jun-17
8-Jun-17
9-Jun-17

1-Jul-17
2-Jul-17
3-Jul-17
4-Jul-17
5-Jul-17
6-Jul-17
7-Jul-17
8-Jul-17
9-Jul-17
Starting Finished
Work Description UOM Quantity Manpower Movement
Date Date

Fabrication and Erection of DM Water Storage Tank-A & Tank-B MT 48.93 16-May 16-Aug
Welder Qualification Test 16-May 25-May
Mobilization of Tools and Equipment 16-May 24-May
Mobilization of Workforce Team 16-May 23-May
Site Clean and Prepare Material Storage Area 16-May 20-May
Receiving and Storage of Material at Work Site 16-May 1-Jun
Foundation Check, Preparation and Handover-Tank A & B 17-May 18-May
Bottom Plate Fabrication and Erection for Tank- A & B MT 6.64 19-May 1-Jun
Bottom Plate Fabrication-Tank A MT 3.32 19-May 21-May
Laying of Bottom Plate for Storage Tank-A MT 3.32 19-May 19-May
Marking as Per Cutting Plan Nos. 14.00 19-May 19-May
Assembly Match Mark and Welding Joint Marking Nos. 15.00 19-May 19-May F-1, G-1, H-3, P/C-1, B/Op.
Inspection of all marking and cutting plan marking 19-May 19-May
Plate Cutting RM 35.36 19-May 20-May
Grinding Work (Weld Edge Preparation, Cleaning etc) RM 35.36 20-May 21-May
Bottom Plate Erection-Tank A 21-May 24-May
Lifting and Laying of Bottom Plate plus inspection MT 3.32 21-May 21-May
Plate Fit-Up and Inspection Nos. 14.00 21-May 21-May F-4, G-2, W-7, H-6, R-4
Short Seam Welding & Cleaning RM 19.72 21-May 21-May
Long Seam Welding & Cleaning RM 98.68 22-May 23-May
Vacuum Box Test 23-May 24-May
Bottom Plate Fabrication-Tank B MT 3.32 21-May 24-May
Laying of Bottom Plate for Storage Tank-A MT 3.32 21-May 21-May
Marking as Per Cutting Plan Nos. 14.00 21-May 21-May
Assembly Match Mark and Welding Joint Marking Nos. 14.00 21-May 21-May F-1, G-1, H-3, P/C-1, B/Op.
Inspection of all marking and cutting plan marking Nos. 14.00 21-May 22-May
Plate Cutting RM 35.36 22-May 23-May
Grinding Work (Weld Edge Preparation, Cleaning etc) RM 35.36 23-May 24-May
Bottom Plate Erection-Tank B 24-May 28-May
Lifting and Laying of Bottom Plate MT 3.32 24-May 25-May
Short Seam Welding & Cleaning Single Pass RM 19.72 25-May 26-May F-4, G-2, W-7, H-6, R-4
Long Seam Welding & Cleaning Single Pass RM 98.68 26-May 27-May
Vacuum Box Test 27-May 28-May
Prepare Master Template and Check by Quality 23-May 24-May F-1, H-2
Shell Plate, Roof Fabrication and erection Work, Tank- A & B (3rd, 2nd & 1st Top Shell) MT 28.22 24-May 8-Jun
Fabrication and erection of Top-3 Shell Plate-Tank A MT 1.76 24-May 28-May
Laying, marking cutting plan, Tracibility marking Nos. 5.00 24-May 24-May
Inspection, Cutting & Weld Edge Preparation RM 1.50 24-May 24-May F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 24-May 25-May
Plate lifting, Fit-Up and Inspection Single Pass RM 22.50 26-May 27-May
Welding Vertical Joint Single Pass RM 22.50 26-May 27-May F-4, G-2, W-7, H-6, R-4
NDT 27-May 27-May
Fabrication and Erection of Top-3 Shell Plate- Tank B MT 1.76 25-May 29-May
Laying, marking cutting plan, Tracibility marking Nos. 5.00 25-May 25-May
Inspection, Cutting and Weld Edge Preparation RM 1.50 25-May 25-May F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 25-May 26-May
Fit-Up and Inspection Single Pass RM 22.50 27-May 28-May
Welding Vertical Joint Single Pass RM 22.50 28-May 28-May F-4, G-2, W-7, H-6, R-4
NDT 28-May 28-May
Fabrication and Erection of Top-2 Shell Plate-Tank A MT 1.00 27-May 30-May
Laying, marking cutting plan, Tracibility marking Nos. 5.00 27-May 27-May
Inspection, Cutting and Weld Edge Preparation RM 30.70 27-May 27-May F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 27-May 28-May
Fit-Up and Inspection RM 34.11 29-May 30-May
Welding Vertical Joint & NDT Single Pass RM 12.75 30-May 30-May F-4, G-2, W-7, H-6, R-4
Welding Horizontal Joint between Top-3 & Top-2 Shell Plate Single Pass RM 89.58 30-May 31-May
Radiographic Test of T-joint Nos. 10.00 31-May 31-May
Fabrication and Erection of Top-2 Shell Plate-Tank B MT 1.00 28-May 1-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 28-May 28-May
Inspection, Cutting and Weld Edge Preparation RM 30.70 28-May 28-May F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 28-May 29-May
Fit-Up and Inspection RM 34.11 30-May 31-May
Welding Vertical Joint & NDT Single Pass RM 12.75 31-May 31-May F-4, G-2, W-7, H-6, R-4
Welding Horizontal Joint between Top-3 & Top-2 Shell Plate Single Pass RM 89.58 31-May 1-Jun
Radiographic Test of T-joint Nos. 10.00 1-Jun 1-Jun
Fabrication and Erection of Top-1 Shell Plate-Tank A MT 0.96 29-May 2-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 29-May 29-May
Inspection, Cutting and Weld Edge Preparation RM 30.66 29-May 29-May F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 29-May 30-May
Fit-Up and Inspection RM 33.95 31-May 1-Jun
Welding Vertical Joint & NDT Single Pass RM 12.26 1-Jun 1-Jun F-4, G-2, W-7, H-6, R-4
Welding Horizontal Joint between Top-2 & Top-1 Shell Plate Single Pass RM 89.58 1-Jun 2-Jun
Radiographic Test of T-joint Nos. 10.00 2-Jun 2-Jun
Fabrication and Erection of Top-1 Shell Plate-Tank B MT 0.96 30-May 3-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 30-May 30-May
Inspection, Cutting and Weld Edge Preparation RM 30.66 30-May 30-May F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 30-May 31-May
Fit-Up and Inspection RM 33.95 1-Jun 2-Jun
Welding Vertical Joint & NDT Single Pass RM 12.26 2-Jun 2-Jun F-4, G-2, W-7, H-6, R-4, S-5
Welding Horizontal Joint between Top-2 & Top-1 Shell Plate Single Pass RM 89.58 2-Jun 3-Jun
Radiographic Test of T-joint Nos. 10.00 3-Jun 3-Jun
Fit-Up, Welding of Top Angle with Top Shell & NDT- Tank A Single Pass RM 59.72 4-Jun 5-Jun F-4, G-2, W-7, H-6, R-4, S-5
Fit-Up, Welding of Top Angle with Top Shell & NDT- Tank B Single Pass RM 59.72 6-Jun 7-Jun F-4, G-2, W-7, H-6, R-4, S-5
Roof Structure & Roof Plate Fabrication and Erection Work MT 20.79 24-May 21-Jun
Blasting and Painting of Roof Structure Material, Roof Plate Sq. M 342.00 24-May 31-May B/C-5
Fabrication (Welding, cutting, grinding, drilling etc.)-Tank A & B MT 6.66 31-May 5-Jun F-3, H-6, W-2
Erection of Roof Structure-Tank A MT 3.33 4-Jun 8-Jun F-4, G-2, W-7, H-6, R-4
Erection of Roof Structure-Tank B MT 3.33 6-Jun 9-Jun F-4, G-2, W-7, H-6, R-4
Fabrication & Erection of Roof Plate-Tank A MT 7.07 6-Jun 9-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 6-Jun 6-Jun F-1, G-1, H-3, P/C-1, B/Op.
Inspection, Cutting and Weld Edge Preparation RM 35.36 6-Jun 7-Jun
Fit-Up and Inspection RM 177.60 7-Jun 8-Jun F-4, G-2, W-7, H-8, R-4
Welding Single Pass RM 177.60 8-Jun 9-Jun
NDT 9-Jun 9-Jun
Fabrication & Erection of Roof Plate-Tank B MT 7.07 8-Jun 11-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 8-Jun 8-Jun
F-1, G-1, H-3, P/C-1, B/Op.
Inspection, Cutting and Weld Edge Preparation RM 35.36 8-Jun 9-Jun
Fit-Up and Inspection RM 177.60 9-Jun 10-Jun F-4, G-2, W-7, H-8, R-4
Welding Single Pass RM 177.60 10-Jun 11-Jun
NDT 11-Jun 11-Jun
Install Lifting Device for Tank A 11-Jun 12-Jun Full Team
Lifting of top part (Roof top, 3rd, 2nd & 1st top shell, Roof)-Tank A MT 14.11 12-Jun 12-Jun Full Team
Install Lifting Device for Tank B 16-Jun 17-Jun Full Team
Lifting of top part (Roof top, 3rd, 2nd & 1st top shell, Roof) Tank B MT 14.11 17-Jun 17-Jun Full Team
Fabrication and Erection of Remaining Shell Plate MT 14.08 13-Jun 8-Jul
Fabrication & Erection of 4th Shell Plate-Tank A MT 1.76 13-Jun 16-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 13-Jun 13-Jun
Inspection, Cutting & Weld edge preparation RM 1.50 13-Jun 13-Jun F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 13-Jun 14-Jun
Fit-Up and Inspection RM 37.36 14-Jun 15-Jun
Welding Vertical Joint Single Pass RM 22.50 15-Jun 15-Jun
Welding Horizontal Joint Between Shell 3-4 Single Pass RM 89.58 15-Jun 16-Jun F-4, G-2, W-7, H-8, R-4
Radiographic Test of T- Joint Nos. 10.00 16-Jun 16-Jun
Lifting MT 1.76 16-Jun 16-Jun
Fabrication & Erection of 4th Shell Plate-Tank B MT 1.76 17-Jun 20-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 17-Jun 17-Jun
Inspection, Cutting & Weld edge preparation RM 1.50 17-Jun 17-Jun F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 17-Jun 18-Jun
Bibiyana-III 400 MW Gas Based CCPP Project
Schedule for the Execution of DM Water Storage Tank (A & B)

16-May-17
17-May-17
18-May-17
19-May-17
20-May-17
21-May-17
22-May-17
23-May-17
24-May-17
25-May-17
26-May-17
27-May-17
28-May-17
29-May-17
30-May-17
31-May-17

10-Aug-17
11-Aug-17
12-Aug-17
13-Aug-17
14-Aug-17
15-Aug-17
16-Aug-17
10-Jun-17
11-Jun-17
12-Jun-17
13-Jun-17
14-Jun-17
15-Jun-17
16-Jun-17
17-Jun-17
18-Jun-17
19-Jun-17
20-Jun-17
21-Jun-17
22-Jun-17
23-Jun-17
24-Jun-17
25-Jun-17
26-Jun-17
27-Jun-17
28-Jun-17
29-Jun-17
30-Jun-17

1-Aug-17
2-Aug-17
3-Aug-17
4-Aug-17
5-Aug-17
6-Aug-17
7-Aug-17
8-Aug-17
9-Aug-17
10-Jul-17
11-Jul-17
12-Jul-17
13-Jul-17
14-Jul-17
15-Jul-17
16-Jul-17
17-Jul-17
18-Jul-17
19-Jul-17
20-Jul-17
21-Jul-17
22-Jul-17
23-Jul-17
24-Jul-17
25-Jul-17
26-Jul-17
27-Jul-17
28-Jul-17
29-Jul-17
30-Jul-17
31-Jul-17
1-Jun-17
2-Jun-17
3-Jun-17
4-Jun-17
5-Jun-17
6-Jun-17
7-Jun-17
8-Jun-17
9-Jun-17

1-Jul-17
2-Jul-17
3-Jul-17
4-Jul-17
5-Jul-17
6-Jul-17
7-Jul-17
8-Jul-17
9-Jul-17
Starting Finished
Work Description UOM Quantity Manpower Movement
Date Date

Fit-Up and Inspection RM 37.36 18-Jun 19-Jun


Welding Vertical Joint Single Pass RM 22.50 19-Jun 19-Jun
Welding Horizontal Joint Between Shell 3-4 Single Pass RM 89.58 19-Jun 20-Jun F-4, G-2, W-7, H-8, R-4
Radiographic Test of T- Joint Nos. 10.00 20-Jun 20-Jun
Lifting MT 1.76 20-Jun 20-Jun
Fabrication & Erection of 5th Shell Plate-Tank A MT 1.76 19-Jun 22-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 19-Jun 19-Jun
Inspection, Cutting & Weld edge preparation RM 1.50 19-Jun 19-Jun F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 19-Jun 20-Jun
Fit-Up and Inspection RM 37.36 20-Jun 21-Jun
Welding Vertical Joint Single Pass RM 22.50 21-Jun 21-Jun
Welding Horizontal Joint Between Shell 5-4 Single Pass RM 89.58 21-Jun 22-Jun F-4, G-2, W-7, H-8, R-4
Radiographic Test of T- Joint Nos. 10.00 22-Jun 22-Jun
Lifting MT 1.76 22-Jun 22-Jun
Fabrication & Erection of 5th Shell Plate-Tank B MT 1.76 22-Jun 25-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 22-Jun 22-Jun
Inspection, Cutting & Weld edge preparation RM 1.50 22-Jun 22-Jun F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 22-Jun 23-Jun
Fit-Up and Inspection RM 37.36 23-Jun 24-Jun
Welding Vertical Joint Single Pass RM 22.50 24-Jun 24-Jun
Welding Horizontal Joint Between Shell 5-4 Single Pass RM 89.58 24-Jun 25-Jun F-4, G-2, W-7, H-8, R-4
Radiographic Test of T- Joint Nos. 10.00 25-Jun 25-Jun
Lifting MT 1.76 25-Jun 25-Jun
Fabrication & Erection of 6th Shell Plate-Tank A MT 1.76 25-Jun 28-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 25-Jun 25-Jun
Inspection, Cutting & Weld edge preparation RM 1.50 25-Jun 25-Jun F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 25-Jun 26-Jun
Fit-Up and Inspection RM 37.36 26-Jun 27-Jun
Welding Vertical Joint Single Pass RM 22.50 27-Jun 27-Jun
Welding Horizontal Joint Between Shell 5-6 Single Pass RM 89.58 27-Jun 28-Jun F-4, G-2, W-7, H-8, R-4
Radiographic Test of T- Joint Nos. 10.00 28-Jun 28-Jun
Lifting MT 1.76 28-Jun 28-Jun
Fabrication & Erection of 6th Shell Plate-Tank B MT 1.76 27-Jun 30-Jun
Laying, marking cutting plan, Tracibility marking Nos. 5.00 27-Jun 27-Jun
Inspection, Cutting & Weld edge preparation RM 1.50 27-Jun 27-Jun F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 27-Jun 28-Jun
Fit-Up and Inspection RM 37.36 28-Jun 29-Jun
Welding Vertical Joint Single Pass RM 22.50 29-Jun 29-Jun
Welding Horizontal Joint Between Shell 5-6 Single Pass RM 89.58 29-Jun 30-Jun F-4, G-2, W-7, H-8, R-4
Radiographic Test of T- Joint Nos. 10.00 30-Jun 30-Jun
Lifting MT 1.76 30-Jun 30-Jun
Fabrication & Erection of 7th Shell Plate-Tank A MT 1.76 30-Jun 3-Jul
Laying, marking cutting plan, Tracibility marking Nos. 5.00 30-Jun 30-Jun
Inspection, Cutting & Weld edge preparation RM 1.50 30-Jun 30-Jun F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 30-Jun 1-Jul
Fit-Up and Inspection RM 37.36 1-Jul 2-Jul
Welding Vertical Joint Single Pass RM 22.50 2-Jul 2-Jul
Welding Horizontal Joint Between Shell 6-7 Single Pass RM 89.58 2-Jul 3-Jul F-4, G-2, W-7, H-8, R-4
Radiographic Test of T- Joint Nos. 10.00 3-Jul 3-Jul
Lifting MT 1.76 3-Jul 3-Jul
Fabrication & Erection of 7th Shell Plate-Tank B MT 1.76 2-Jul 5-Jul
Laying, marking cutting plan, Tracibility marking Nos. 5.00 2-Jul 2-Jul
Inspection, Cutting & Weld edge preparation RM 1.50 2-Jul 2-Jul F-1, G-1, H-3, P/C-1, B/Op.
Rolling as per master Template RM 29.86 2-Jul 3-Jul
Fit-Up and Inspection RM 37.36 3-Jul 4-Jul
Welding Vertical Joint Single Pass RM 22.50 4-Jul 4-Jul
Welding Horizontal Joint Between Shell 6-7 Single Pass RM 89.58 4-Jul 5-Jul F-4, G-2, W-7, H-8, R-4
Radiographic Test of T- Joint Nos. 10.00 5-Jul 5-Jul
Lifting MT 1.76 5-Jul 5-Jul
Shell to bottom plate welding and NDT-Tank A Single Pass RM 89.58 6-Jul 7-Jul F-4, G-2, W-7, H-8, R-4
Shell to bottom plate welding and NDT-Tank B Single Pass RM 89.58 7-Jul 8-Jul F-4, G-2, W-7, H-8, R-4
Manhole, Nozzle, Nozzle piping and other remaining Fabrication & Erection Work MT 2.00 7-Jul 18-Jul
Welder Qualification Test for Piping Work Nos. 2.00 5-Jul 6-Jul
Shell and Roof Manhole Fabrication and Erection for Tank-A & B MT 0.67 8-Jul 12-Jul
Fabrication and Erection of Shell Manhole M1A-Tank A MT 0.22 8-Jul 9-Jul
F-1, W-1, H-3, R-4
Fabrication and Erection of Shell Manhole M1B-Tank B MT 0.22 10-Jul 11-Jul
Fabrication and Erection of Roof Manhole M2A-Tank A MT 0.12 9-Jul 10-Jul
F-1, W-1, H-3, R-4
Fabrication and Erection of Roof Manhole M2B-Tank B MT 0.12 11-Jul 12-Jul
Fabrication and Erection of Shell Nozzle Tank A MT 0.67 10-Jul 13-Jul
LT1A Fabrication , Erection, Support Installation & NDT MT 0.01 10-Jul 10-Jul
F-1, W-1, H-3, R-4
N1A Fabrication and Eerection & NDT MT 0.01 10-Jul 11-Jul
N2A Fabrication & Erection & NDT MT 0.12 10-Jul 12-Jul
F-1, W-1, H-3, R-4
N3A Fabrication & Erection & NDT MT 0.20 10-Jul 11-Jul
N4A Fabrication & Erection & NDT MT 0.04 10-Jul 11-Jul
F-1, W-1, H-3, R-4
N5A Fabrication & Erection & NDT MT 0.12 12-Jul 13-Jul
N6A Fabrication & Erection & NDT MT 0.02 12-Jul 13-Jul
F-1, W-1, H-3, R-4
N7A Fabrication , Erection & NDT MT 0.06 12-Jul 13-Jul
N11A Fabrication & Erection & NDT MT 0.00 12-Jul 12-Jul
F-1, W-1, H-3, R-4
N12A Fabrication & Erection & NDT MT 0.08 12-Jul 13-Jul
Fabrication and Erection of Shell Nozzle Tank B MT 0.67 14-Jul 17-Jul
LT1B Fabrication and Eerection & NDT MT 0.01 14-Jul 14-Jul
F-1, W-1, H-3, R-4
N1B Fabrication and Eerection & NDT MT 0.01 14-Jul 15-Jul
N2B Fabrication and Eerection & NDT MT 0.12 14-Jul 16-Jul
F-1, W-1, H-3, R-4
N3B Fabrication and Eerection & NDT MT 0.20 14-Jul 15-Jul
N4B Fabrication and Eerection & NDT MT 0.04 14-Jul 15-Jul
F-1, W-1, H-3, R-4
N5B Fabrication and Eerection & NDT MT 0.12 16-Jul 17-Jul
N6B Fabrication and Eerection & NDT MT 0.02 16-Jul 17-Jul
F-1, W-1, H-3, R-4
N7B Fabrication and Eerection & NDT MT 0.06 16-Jul 17-Jul
N11B Fabrication and Eerection & NDT MT 0.00 15-Jul 15-Jul
F-1, W-1, H-3, R-4
N12B Fabrication and Eerection & NDT MT 0.08 16-Jul 17-Jul
Seal Pot Erection for Tank A & B MT 0.30 13-Jul 14-Jul F-1, H-4, R-4
Earthing Boss, Roof Nozzle, & Name Plate for Tank A MT 0.17 15-Jul 18-Jul
F-1, W-1, H-3, R-4
Earthing Boss, Roof Nozzle, & Name Plate for Tank B MT 0.17 15-Jul 16-Jul
Spiral Staircase, Handrail & Grating fabrication and Erection Work MT 3.45 5-Jun 20-Jul
Grit Blasting and Painting 5-Jun 12-Jun B/C-5
Fabrication 30-Jun 8-Jul F-2, W-1, H-5
Erection MT 3.45 15-Jul 20-Jul F-4, W-4, G-2, H-8, R-4, S-5
Final Touch-Up and Repairing Work (Painting, Cleaning etc.) Tank A & B 12-Jul 20-Jul S-5, P-2
Water Fill Testing of the Tank A & B 21-Jul 14-Aug F-1, H-5
Handover 15-Aug 16-Aug

Designation Sign Unit Quantity Remarks


Fitter F Nos. 5
Dedicated Team for Tank work
Welder W Nos. 7
only, 2 welder will be added later
Plasma Cutter P/C Nos. 1
for piping work, 1 fitter will be
Grinder G Nos. 3
added for roof structure fabrication
Bending M/C Op. B/Op. Nos. 1
work
Helper H Nos. 11
Rigger Team R Nos. 4
General
Scaffolder Team S Nos. 5

Team Distribution UOM Qty Remarks


Fabrication Team Nos 7 F-1, P/C-1, G-1, H-3, B/Op.
F-4, W-7, H-8, G-2, Rigger team,
Field Erection Team Nos 21
Scaf. Team
Note: Schedule may vary depending upon site condition, weather condition & material availability