Hydrotest & Pneumatic Test - TRA

The document is a risk assessment worksheet for pressure hydro testing of piping being conducted by Dodsal Engineering & Construction Pte Ltd as a subcontractor. It identifies hazards such as slips, falls, manual handling injuries, and high pressure releases. Controls are outlined to prevent injuries and damage, including obtaining work permits, conducting safety briefings, using calibrated equipment, barricading work areas, and following approved test procedures. Residual risks are lowered through close supervision, emergency response preparations, and ensuring walkways are clear during the work.

Uploaded by

Ows Anish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
80% found this document useful (5 votes)
986 views6 pages

Hydrotest & Pneumatic Test - TRA

The document is a risk assessment worksheet for pressure hydro testing of piping being conducted by Dodsal Engineering & Construction Pte Ltd as a subcontractor. It identifies hazards such as slips, falls, manual handling injuries, and high pressure releases. Controls are outlined to prevent injuries and damage, including obtaining work permits, conducting safety briefings, using calibrated equipment, barricading work areas, and following approved test procedures. Residual risks are lowered through close supervision, emergency response preparations, and ensuring walkways are clear during the work.

Uploaded by

Ows Anish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 6

DODSAL ENGINEERING & CONSTRUCTION PTE LTD

TASK RISK ASSESSMENT WORKSHEET Attachment to Doc.No: TRA - 63

TASK DESCRIPTION Pressure hydro Testing of A/G Piping SUBCONTRACTOR Dodsal Engg. & Const. Pte
Ltd.

TRA TEAM MEMBERS Page 1 of 3 DATE: 20.02.2012

STEP DESCRIPTION OF HAZARD CONSEQUENCES CONTROLS BASELINE ADDITIONAL RESP. RESIDUAL


NO. TASK STEP PEOPLE, ENVIRONMENT, PREVENT, DETECT, CONTROL, MITIGATE RISK CONTROL PARTY RISK
ASSETS, REPUTATION MEASURES /
S P R ACTIONS S P R

 Obtain an appropriate work 4 3 12  Close 3 2 6


01 Hydro testing  Slips  Injury permit from SECL & conduct supervisionl.
 Strains & Sprains  Fatality TBT before commencement of
Water filling for  Manual handling.  Pinch point work  Emergency
Hydrotest  Falling object.  Damage to  Personnel must be undergone Arrangements’
 Trip hazard. existing facilities of Work At Height Training from like First Aid
Pressurization  Slippery surface Takreer/ own SECL Box, First Aider
 Fall from Height properties  Secure all tools & equipment must be
Draining  Hose handling when working elevated height available at
 Trapped air during  Secure all loose objects site.
Housekeeping filling of test  Compressors to be inspected
medium from SECL prior to use.  Ensure

Samsung Electrical supervisor


 High pressure  Hoses and fittings of walkways are
release appropriate pressure rating free from
 Damage to  Use Whip arrestor and safety obstacles
associated pins. Correct lifting
equipments/pipe  Inspection of the hoses and techniques to
lines /valves fittings before use . be used
 Filling and disposal  Area around the pressure test  Proper Earthing
of Test Medium shall be suitably barricaded of equipment
 Failure of system and signs posted to prevent  Electrical
 Over Pressure access to unauthorized equipment to
 Failure of gauges persons be inspected
 Damage of system  Authorized personnel only at by Electrical
 worksite. dept. prior to
 Calibrated gauges shall be use
installed to monitor the  Avoid water
pressure / temp (As per the spillage.
approved procedure).  Ensure spilled
 Pressure test shall be carried water drained
out as per the procedure properly.
approved by Samsung

Page 1 of 6
DODSAL ENGINEERING & CONSTRUCTION PTE LTD

 Air vents shall be opened at Close


the start of the filling to Supervision.
ensure complete air discharge
prior to testing. Emergency
 Pressurizing/depressurizing Arrangements’
shall be performed gradually like First Aid
at a moderate and constant Box, First Aider
rate, as per the test must be
procedure. available at site.
 During pressurizing,
connections/joints shall be  All in line
periodically inspected for valves shall be
leaks. in fully open
 Never strike or subject the condition
testing component to any during pressure
shock during a full over test.

Samsung Electrical supervisor


pressure test.  Apply proper
 Never approach a test manual
component subject to handling
maximum test pressure until techniques
a safe period of time has
elapsed
 Ensure that the blanking off
devices (screwed plugs &
connections) are made of
correct material with strong
screw threads.
 Pressure retaining threads
and tapping should be
inspected for wear and
corrosion using calibrated
thread gauges.
 Ensure that all
linked/networked pipes are
free from pressure and
isolated.
 Suitable pressure rated blinds
shall be used to withstand
test pressure.
 Proper arrangement for filling
the test medium.

Page 2 of 6
DODSAL ENGINEERING & CONSTRUCTION PTE LTD

 Proper arrangement for


containment and disposal of
test water after the Job.
 Ensure that the vent & drains
are opened at the same time.
 Avoid draining to open drain.
 Area to be cleaned for dirt
and waste materials.

02 PNEUMATIC  Possible release of  Explosion  Method statement to be 4 4 16  Close 3 3 9


PRESSURE Stored energy  Injury explained to all employees Supervision
TESTING  Brittle fracture of and it must be made available  Testing to be
metal due to low  Sharp edges at the site during the carried out in
temperature of  Pinch point activities part of line
metal  High Noise  Job specific TRA to be made isolated by
 Failure of system  Slipping/Tripping available at the site & control using adequate
 Over Pressure measures to be capacity of
 Failure of gauges,  Damage to communicated to all flanges & blind
Pressure relief existing facilities of personnel involved in the job to withstand
valves Takreer/ own through Tool Box Talk Meeting the test
 Damage of system properties  All necessary documents shall pressure
 Safe distance from  Heat stress attach with the work permit  Ensure that all
dangerous  and made available at the personnel are
pressurized work site aware of the
equipment not  Site Mandatory PPE like hazards and
identified Helmet, goggles, gloves, ear takes
 Lack of protection to be used by all appropriate
Communication employees precautions
/Languages/  All barricading shall be as per  All personnel
Translators the Safety Distance exclusion working for
 Lack of PWHT/NDT zone Ensure that sufficient testing shall
inspection accessibility, proper wear high
 No interpreters barricading is done in the visibility jackets
were used to work area all the time
translate hazards  Place the compressor station  Barricading
 Hazards were not and gauge manifold away shall be yellow
mentioned in the from the testing location. black warning
TRA/ Method  Ensure that compressor tape
statements station is technically inspected 
were mentioned and approved from SECL
 Lack of warning
signs for testing
 Unauthorized
personnel Page 3 of 6
DODSAL ENGINEERING & CONSTRUCTION PTE LTD

 Vehicular  Testing supervisor shall  AIR LEAK


movements ensure the pipes are PWHT TESTING IN
 Insufficient and NDT tested PROGRESS,
accessibility  Place sufficient number of fire KEEP AWAY
 Poor lighting extinguishers near by the sign boards
 Defected tackles compressor station shall be posted
Modified/Home  Testing supervisor shall be  Ensure all are
made tools available in the compressor provided with
 Hose clamps station during the testing water bottles
used/not crimping  Do not allow any unauthorized and all are
fittings personnel entry inside the having it while
 Compressed air barricading working
 Manual handling  Ensure trained and  Remove all
 Damaged experienced operator defected,
equipment assigned for the job modified/modifi
 Dropping pressure  Ensure all tools and tackles ed tools from
gauges are inspected and approved site

Site SAMSUNG Supervisor


 Very heavy flanges by SECL .  Adequate dust
 Sharp edged tools  Ensure all hose connections protection shall
 Defected/Modified are in good condition be worn by the
tools  Whip arrestors shall be fitted operator
 Accumulation of between the compressor and  Care shall be
debris hose connection taken to avoid
 Awful Impression  Protection pins shall be fitted personnel
 Tripping hazards in all hose to hose injuries
 Bolt tightening connections  Ensure all hand
 Personnel  Ensure the Pressure Relief tools are in
entry/control valves are properly calibrated good condition
 Poor lighting which is set for 110% of Test  Disseminate
visibility pressure.Tested and certified the points of
 Personnel entry – manifold (Tested 1.5times emergency
no barricading than the required Test response
 No safe distance pressure)to be used measures
 Faulty gauges  All pressure gauges shall be during Tool Box
 Faulty couplings calibrated & checked by the Talk meeting
 Leaking couplings testing supervisor prior to the  is available at
 Unawareness of testing for it’s proper site and all
emergency operation & Test gauge range employees are
response measures shall be selected to ensure drinking water
 Filling and disposal that the test pressure falls periodically
of Test Medium between 30 to 80% of test  No vehicular
pressure movement is
 Use ear protection during allowed in the
cleaning area
Page 4 of 6
DODSAL ENGINEERING & CONSTRUCTION PTE LTD

 Ensure dead man switch is  Ensure that all


fitted in the end of hose proper PPE
 Ensure all are using necessary while entering
PPE’s while working with hand the
tools area,hearing
 Inform all information about protection
the initial pressurization to  Ensure no
the area authority modified tools
 Care must be exercised to are available at
prevent exceed the specified the site
test pressure by morethan  At elevated
10%. height
 Do preliminary check at Recommended
0.71kg/cm2,Rectify all leaks for 84” dia
prior to start the pipes shall be
pressurization, gradually tested to 100%
increase pressure in steps to NDT
full test pressure  Emergency
 Bolt shall not be tightened contact
while system being tested are numbers shall
pressurized above 2.1 kg/cm2 be available
 Ensure no personnel entry with all crew
inside the barricades during members
air leak testing  Ensure plenty
 At elevated placed above of cool drinking
54” dia pipes must be water
passed 100% NDT test
,any deficit likely to result
in catastrophic event

Remarks :

Reviewed By: Name: Approved By: Name: Approved By: Name:


Sub Contractor Sub Contractor SECL
Sign: Sign: Sign:

Date: Date: Date:

S: Severity, P: Probability, R: Risk


Page 5 of 6
DODSAL ENGINEERING & CONSTRUCTION PTE LTD

Risk Factor Matrix


Probability Methodology
Probability Risk Priority
4 – Probable / Likely to occur immediately or shortly 1. Identify Hazards
3 – Reasonably probable – Probably will occur in time 4 3 2 1 8-16 High Risk 2. List Hazard Events
S
2 – Remote – May occur in time 3. Calculate risk factor with initial risk rating
e 4 16 12 8 4 5-7 Medium Risk
1 – Extremely remote – Unlikely to occur 4. Detail controls and mitigation plan
v
5. Calculate residual risk factor with final risk rating
e 3 12 9 6 3 1-4 Low Risk 6. Enter risk priority
r
7. Evaluate acceptability of risk
I 2 8 6 4 2
t
y 1 4 3 2 1

Severity
4 – Catastrophic – Imminent danger exists, hazard capable of causing death or illness at wide scale
3 – Critical – Hazard can result in serious illness, severe injury, property and equipment damage
2 – Marginal – Hazard can cause illness, injury or equipment damage but the damage is not expected to be serious
1 – Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor first-aid case.

Page 6 of 6