Civil Engineering Notes
Civil Engineering Notes
DENIS NYAKERIGA
December 12, 2018
ABSTRACT
Flood damage for cities adjacent to rivers becomes catastrophic if levees fail.
Levee maintenance for the west side of the Columbia River at Richland, Washington
required analysis & design recommendations. A sixteen feet tall levee required
excavation on the slope of the land side. Slope stability and seepage analysis to safely
allow a 15 feet wide excavation indicated the necessity of 22 feet long piles. The piles
chosen were 12x12 inch Douglas fir with ½ inch spacing to produce adequate bracing
during construction. The piles remained in place after maintenance to provide a paved
ABSTRACT 3
LIST OF FIGURES 5
LIST OF TABLES 6
ACKNOWLEDGEMENT 7
1.0 INTRODUCTION 8
5.0 COST 23
6.0 FUTURE 25
SUMMARY 26
BIBLIOGRAPHY 27
APPENDIX A 28
APPENDIX B 44
Page |4
ACKNOWLEDGEMENT
recorded. hurricane Katrina, as it was later referred to, was grouped under category 5.
Other than being a major natural disaster it also caused savior damage to property, New
Orleans was one of the cities affected by this hurricane. The lack of maintenance of the
levees, that were majorly built for protection against flooding was not able to withstand
the impact. “Healthy” levees maintenance helps to prevent the impact that may be caused
Maintenances of levees is paramount this study has looked into the maintenance
of Levee 2C in the Richland area. Levee 2C in Richland Washington is one other levee
that needed maintenance. Over grown vegetation on the neighboring side of the levee,
confirmed that maintenance was paramount. An analysis was conducted to ensure safe
maintenance for Levee. . Levee 2 C required a seepage slope, which would help in the
stability and pile spacing, considerations for various stages of construction were also not
ignored.
this project was conducted on. A levee is made up of two distinct sections as shown in
Figure 2. The pervious section at the two ends of the levee consisted mostly of gravel and
sand, which allows seepage to occur. The less-pervious levee core consists of silt clay.
The middle section is critical towards keeping the land side of the levee from flooding.
Page |8
2.1 GEOMETRY
Figure 2 - Geometric size of the cross-section of Levee 2C. (Not drawn to scale)
Levee 2C was built in 1942, thus, not all information about its size and construction is
still available. However, the geometry of the cross-section of the levee is shown in Figure
2. Levee 2C has a crest width of 32 feet and an average height of 15 feet. The top of the
levee has 18 inches dumped stone to protect against wave erosion. The land side of the
levee has a horizontal to vertical slope of 3 to 1 and the river side of the levee slopes at
impeding lateral water flow from the river. The levee was built in 1942, thus, as-built
information is limited. There was no budget for extensive soil sampling and laboratory
analysis. Therefore, possible ranges of soil properties were used to predict the worst-case
scenario. Values were chosen from Van Genuchten and Guarracino (2007), NRCS (2???),
P a g e | 10
and shell hydraulic conductivities, soil unit weight, and internal friction values.
Table 1 – Combinations of Soil Parameters Used for Seepage and Slope Stability
Key:
K= Hydraulic conductivity
Ft = Feet
Lb = Pounds
Sec = Seconds
S.f = Safety Factor
P a g e | 11
2.3 SEEPAGE
An analysis of different combination of cohesive friction of soil, hydraulic
conductivity and the unit weight of the sand and silt was done. From Table 2 it could be
observed that, on a high-water level the seepage on trial 10, 12, 14 and 16 had the highest
because the water level is high than usual. Not much can be done about seepage because
stopping or trying to reduce seepage would create a back pressure that would be a
was to find the Safety Factor. It can be observed from Table 3 trail 14 gave a worrying
Safety Factor. Which could be concluded that the combination on trial 14 was the most
critical. The lowest Safety Factor was on the high level which was 1.22, combined with
the highest seepage. This became the most critical situation and for that reason a Stability
P a g e | 13
analysis had to be done on trail 14 combination when the levee has been excavated as
shown in Figure 4.
vegetation to make sure that the roots don’t get to the impervious section of the levee.
Analysis will be done on the excavated levee in terms of Seepage and Slope Stability. On
The seepage was relatively lower than before. This is because the levee has a smaller
surface are and hence the change of seepage. This is expected, and the seepage should be
allowed to continue to prevent back pressure which will devastating if there will be back
pressure.
two feet below the top of the levee. The method of slice estimated the Safety Factor
against slope failure. The analysis resulted in a lowest safety factor of 0.816 as shown in
Figure 5.
∑ ( c × ∆ L I +W i ×cos ∝i ×tanφ)
i=0
Safety Factor = n Equation 1
∑ (W I ¿ ×sin ∝i) ¿
i=0
P a g e | 16
Figure 5 Slope stability failure of the excavated slope for a Safety Factor of 0.816
created a safety issue that must be addressed. This meant that piles had to be used to
P a g e | 17
address this safety issue. Therefore, piles must be put on the excavated edge. Strong pile
should be used to raise the safety factor of the excavated slope. The length, strength and
the material to be used, are what needs to be focused when designing piles for the slope.
A combination of different lengths and strengths (pounds per foot) was used to run a
stability analysis as shown in Table 3. This analysis resulted in the best combination of
the length of the pile and strength of the pile to achieve a Safety Factor of 1.6 to 2.0. A
length of 19 and 20 feet deep and a maximum bending moment resistance force of
Table 3 Stability Safety Factor based on the length and strength of the pile
Pile Pile maximum bending moment force(lb-ft)
length(feet
) 400 4000 6000 8000 10000
There are many types of materials that can be used to make the piles, these are metal
sheet pile, concrete, wood pile. The material that was easily available was wood pile. To
get the right type of wood pile to be used, the design was based on a cantilever wall
P a g e | 19
retaining design. The Active (KA) and Passive (KP) Earth pressure were calculated using
KA=cosβ ¿ ¿ Equation 2
KP=cosβ ¿ ¿ Equation 3
*β-Inclined angel
The unit weight of gravel, the height of the “retaining wall” and the coefficients values
were run in a MATLAB program. The results were the dimensions of the cantilever wall
and the magnitude of the three pressure points. This information was run through RISA
to give a maximum moment and shear values that would be used to design the wood pile
in terms of bending and shear. The three factors to consider while designing for bending
are load duration factor, size factor and incising factor. The same factors apply for shear
except for the size factor. The result was narrowed down to a Douglas Fir 12 X 12 inch
4.1 SEEPAGE
Analysis of the seepage that was done after the excavation shows that, the seepage
was 4.8e^-0.05. This was less than before, which is expected as shown in Figure 7.
expected which means the slope was safe and it would not collapse given the worst
condition. As shown in Figure 8.
4.3 PROCEDURE
Survey is the first thing that’s should be done, to ensure the integrity of the
property. The survey is to get the right measurements and dimension us suggested in the
design. Once the survey is done, the pile must be put in following a certain set of
procedure for safety. A lot of mechanization is needed to ensure that the pile is securely
and properly put in the ground. The excavation is the last thing to be done, which
involves a lot of overhaul. More about the procedure is illustrated in appendix 5.
P a g e | 22
5.0 COST
For any engineering project to succeed they has to be the issues for money which
plays a big role. In this kind of project where 1.2 mile if levee 2c where maintenance is
going to take place, a total of almost $6 million is estimated to be used. The U.S Army
Corp of Engineers uses their expense schedule and the wage determination labor that has
been set by the federal government. The cost estimate is dived into three categories these
are, crew, equipment and material. Details of the estimate are in Appendix 6. For these
projects different type of experts would be needed each task with their own specialty.
Crew include; Field and Office surveying, Crane, Truck and Earthwork operator, and
general labor. Each crew has a different wage bill as set by the federal wage
Excavators, Vibratory Hammer and Dump Truck are needed for construction. Using the
the various equipment were gotten. These rates were charges per hour of the equipment.
An estimate of $64000 would be needed for the rental of all the equipment needed by the
Fuel is a special kind of equipment and it is the expense that take the most funds
off all the expense. To calculate the estimated amount of money that is going to needed
for fuel, three formulas will be used from the construction Equipment’s Ownership and
Operation Expense Schedule. Since all equipment are diesel operated, the pound fuel
consumed per hour (lbs per bph-hr) would 0.34 and the weight of fuel consumed (lbs per
gal) would be 7. Using these two quantities with the Horse power of the equipment, a fuel
P a g e | 23
fuel per gallon in Washington State is $3.40. Using this figure with the calculated fuel
factor and the horsepower of the equipment, the cost of fuel per hour for each equipment
was calculated as shown in Equation 4. The fuel cost for the project is estimated to be
Equation 3
Equation 4
The materials to be used would be the most advantage to this project because half
of the type of the material to be used would be donated by the U.S Air Force and
hence it would not come from the U.S. Army Corps of Engineer fund kitty. These
would be all the 4680 wood piles that would be needed. The other material that
would be needed is the brass cup for each wood pile. The value of each brass cup
purchase of brass cup and this would be the only expense that would be incurred with the
materials needed.
P a g e | 24
of the levee comes about. Things that must be done in the future to make the levee even
more reliable. Drainage and the environmental impact come to focus as a future
consideration. A drain pipe will be design and be placed at the toe of the slope so that
Drain pipe
no other in the project. This would help to note the extent in which the
environment would be affected by the project and the extent incase the
SUMMARY
The stability Levee was not questioned, but maintenance required analysis to
ensure safety during construction. One safety issue that came up was the slope stability.
Which had to be dealt with by using 4680 piles to improve the safety factor of the slope.
This would reduce the chance of having a fatal crisis on the crew working on the levee. It
was determined that the biggest expense in this project is fuel. This was an estimated
amount that would be used to provide fuel for the machinery. The amount estimated
might be more or less depending on the current fuel prices at the time of the project. This
indicates that fuel is a major aspect in this project and the type of machinery or horse
power that would be used in this project. Would determine the estimated amount of fuel
that would be used. After all the excavation has been done a drain pipe would be put.
Were the seepage water will flow into, the drain pipe will have a pump which would
pump out the water. This would still allow the flow of seepage and reduce back pressure.
The completion of this project would ensure that the levee is “healthy” and strong enough
to control flooding.
P a g e | 26
BIBLIOGRAPHY
Guarracino, Luis. “ Estimation of saturated Hydraulic Conductivity K S
from the Van Genuchten shape Parameter” Water Resource 43,
no.11(2007).doi:10.1029
USS Steel Sheet Pilling Design Manual. Washington, D.C.: U.S. Dept. of
Transportation, 1984.
APPENDIX A
1.0 SOIL PROPERTIES
Appendix A 2-4 Slope stability calculation for excavated slope Factor of Safety
%test.m
%Script to find sheet pile retaining wall depth
%Based on Jumikis, A. R., "Foundation Engineering", Scranton, Intext
%Educational Publishing, 1971. (p. 140)
%User input
h=5;%ft
gamma=120;%pcf
ka=0.35;%active pressure coeff.
kp=1.76;%passive pressure coeff.
%Guess for d
%d=7.6241;
d=17;
%Calculations
p1=gamma*h*ka;
p2=gamma*(h+d)*kp-gamma*d*ka;
z=(kp*d^2-ka*(h+d)^2)/((kp-ka)*(h+2*d));
m=p1/(gamma*(kp-ka));
Q=d-m-z;
p3=Q/m*p1;
R=p2*z/(p2+p3);
S=p3*z/(p2+p3);
eh = 5.4570e-12
em= -5.6545e+04
APPENDIX B
Area: Richland
Owners: City of Richland
Location:
Beginning of Project (BOP):
46° 17’35.03”N
119°16’09.35”W
Elevation 369 feet
End of Project (EOP):
46°16’55.78”N
119°16’19.36”W
Elevation 358 feet
E.O.P
BOP
B.1.2 Control points shall be established on the toe of the embankment as the Beginning
B.1.3 A topographic survey shall establish eighteen line segments defining the toe of the
embankment from the BOP to the EOP, approximately 352 feet long.
B.1.4 Points of Intersection (P.I) shall be marked with the aid of software and a G.P.S
B.1.5 The first pile position shall be established 15 feet east perpendicular from the
(B.O.P)
B.1.6 Eighteen segments of 352 feet shall be staked with ½ inch diameter steel rods, each
B.1.7 A total of 260 wood stakes shall be placed at increments of 16 inches in each
B.1.8 Each stake shall be numbered with segment number and the stake numbers.
B.2 PILE:
B.2.1 Pressure treated Douglas fir or southern pine piles with a cross-section of 12 X 12
B.2.2 The piles shall be examined when delivered and immediately before driving.
P a g e | 45
B.2.3 A driving cap of 12-1/2 inches by 12-1/2inches shall be used to cover the top of the
pile.
B.2.4 The woodpiles shall taper at the base to a point over a length of 6 to 8 inches
B.2.5 The contractor shall perform tests to determine the right size of hammer and
B.2.6 The piles shall be driven continuously without interruption exceeding five minutes
B.2.7 If the pile fails to reach the required pile tip elevation because of resistance the
engineer in charge will be informed and will determine the procedure to be followed
Pile dimensions
Pile length
Tip elevation
B.2.9 The pile shall be driven flush with the embankment slope.
B.3 EXCAVATION:
B.3.1construction fence and tape shall cordon off the area of excavation.
B.3.2 Excavation shall be done to a depth five feet below top of the pile.
P a g e | 46
B.3.4 All excavated material (approximately 8800 cubic yards) shall be hauled
to
2.0 COST
number of Total
Proffesion Rate/hr($) hours charge
Survey 42.8 40 1712
Tech Survey 26 40 1040
Tech Survey 26 40 1040
Tech Survey 26 40 1040
Crane driver 30.41 160 4865.6
Labour(land
scape) 14 200 2800
Labour(land
scape) 14 200 2800
Labour(land
scape) 14 200 2800
Bull dozer driver 27 40 1080
Truck driver 20 40 800
Truck driver 20 40 800
Total crew ($) 20777.6
Appendix B 2-1 Amount estimate need for wages of crew
Appendix B 2-2 Amount estimated for machinery rental and fuel total cost
P a g e | 47
cost/pile($ NUMBER OF
Material ) PILES Total
pile Donated 4680 0
brass cup 5 4680 23400
TOTAL CREW COST 20777.6
TOTAL EQUPMENTS
COST 63314.8
5842431.4
TOTAL FUEL COST 8
5949923.8
PROJECT TOTAL COST 8
Appendix B 2-3 Total estimated amount for the whole project.
P a g e | 48