Itp For Installation of Pressurization Unit

This inspection and test plan outlines the quality control process for installing chilled water expansion tanks and pressurization units at an unspecified project location. It lists 4 key activities to be inspected: documentation approval, material inspection, installation inspection, and testing/commissioning. Inspections will check that materials and installation conform to approved submittals and project specifications. The contractor and consultant must sign off to approve the inspection levels and results.

Uploaded by

victor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
508 views1 page

Itp For Installation of Pressurization Unit

This inspection and test plan outlines the quality control process for installing chilled water expansion tanks and pressurization units at an unspecified project location. It lists 4 key activities to be inspected: documentation approval, material inspection, installation inspection, and testing/commissioning. Inspections will check that materials and installation conform to approved submittals and project specifications. The contractor and consultant must sign off to approve the inspection levels and results.

Uploaded by

victor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION & TEST PLAN

Project Name & Details REF. NO.

REV. NO. 0
DATE :
PAGE : 1 OF 1

ACTIVITY: INSTALLATION OF CHILLED WATER EXPANSION TANKS & PRESSURIZATION UNITS

AREA/LOCATION:

ITP approved by CONTRACTOR's QA/QC: ITP approved by Consultant:


Signature: Signature:
Date: Date:
INSPECTION LEVEL
SERIAL NO. DESCRIPTION FREQUENCY SPECIFICATION/CRITERIA VERIFICATION RECORD
ITL CONTRACTOR Consultant

1 DOCUMENTATION

Once (Approval prior to


1.1 Material Approval
start of activity) Project specification and drawings. -- H H

1.2 Shop Drawing Approval Each Shop Drawing Project specification and drawings. -- H H

Once (Approval prior to


1.3 Method Statement Approval
start of activity) Project specification and drawings. -- H H

2 MATERIAL INSPECTION

2.1 Check the Material as per approved submittal. Each Delivery Project specification and drawings. -- H H

3 INSTALLATION INSPECTION

Check the installation as per approved drawing. Check the Area Wise or As
3.1
physical Installation of equipment. instructed by Consultant. Project specification and drawings. -- H H

Area Wise or As
4 TESTING & COMMISSIONING
instructed by Consultant. Project specification and drawings. -- H H

LEGEND: H: HOLD W: WITNESS S: SURVEILLANCE R: REVIEW


ITP Sign-Off post completion of Works
CONTRACTOR APPROVAL Consultant APPROVAL

NAME : NAME :

SIGN : SIGN :
DATE: DATE: