Pile Foundations - Introduction
Pile Foundations - Introduction
Pile Foundations
Principles of Foundation Engineering by Braja M. Das (7th SI Edition)
PILE FOUNDATIONS
Pile Foundations:
• Deep foundations (Df ≥ 5Bf)
• Structural members made of steel, concrete or timber
• Cost more than shallow foundations
1
30-Oct-18
3. When expansive and collapsible 4. When foundations are 5. When foundations are subjected to
soils are present at the site subjected to uplift forces loss support due to scouring / erosion
4
2
30-Oct-18
6. When soils around foundations 7. When fender systems are 8. When future excavations are
are subjected to liquefaction required to protect bridge planned which would require
during seismic events piers from vessel impact underpinning of shallow foundations
Steel piles
Concrete piles (PCC, RCC, PSC)
Wooden (timber) piles
Composite piles
6
3
30-Oct-18
STEEL PILES
• Pipe piles or rolled steel H-section piles
• Wide-flange and I-section steel beams can also be used
• In many cases, pipe piles are filled with concrete after driving
4
30-Oct-18
Provide:
10
5
30-Oct-18
Advantages:
• Easy to handle w.r.t. cutoff and extension to desired length
• Can stand high driving stresses
• Can penetrate hard layers (dense gravel / soft rock)
• High load-carrying capacity
Disadvantages:
• Relatively costly
• High noise during pile driving
• Subject to corrosion
• May be damaged/deflected during driving through hard layers
11
CONCRETE PILES
i. Precast piles
ii. Cast in-situ piles
PRECAST PILES
a. Ordinary Reinforcement (RCC)
b. Precast Prestressed (PSC)
Reinforcement is provided to resist the bending
moment developed during pick up and transportation,
the vertical load, and the bending moment caused by
lateral loads
12
6
30-Oct-18
13
14
7
30-Oct-18
Single-bulb Multi-bulb
15
General Facts:
• Usual length: 5 m to 15 m (Max. length: 30m to 40 m)
• Usual load: 200 kN to 500 kN (Approx. max. load: 800 kN)
Advantages:
• Relatively cheap
• Allow for inspection before pouring concrete
• Easy to extend
Disadvantages
• Difficult to splice after concreting
• Thin casings may be damaged during driving
Allowable Load:
Qall = As fs + Ac fc
16
8
30-Oct-18
General Facts:
• Usual length: 5 m to 15 m (Max. length: 30m to 40 m)
• Usual load: 300 kN to 500 kN (Approx. max. load: 700 kN)
Advantages:
• Initially economical
• Can be finished at any elevation
Disadvantages
• Voids may be created if concrete is placed rapidly
• Difficult to splice after concreting
• In soft soils, the sides of the hole may cave in, squeezing the concrete
Allowable Load:
Qall = Ac fc
17
TIMBER PILES
• Tree trunks whose branches and bark are carefully
trimmed off
• Timber should be straight, sound, and without any
defects
ASCE Classifications:
18
9
30-Oct-18
• Maximum length: 10 m to 20 m
• Usual load: 300 kN to 500 kN
19
COMPOSITE PILES
• Steel – Concrete
• Timber – Concrete
20
10
30-Oct-18
21
22
11
30-Oct-18
b) Friction Piles
23
c) Compaction Piles
24
12
30-Oct-18
25
Drop Hammer
13
30-Oct-18
27
28
14
30-Oct-18
At ultimate load,
Q(z=0) = Qu
Thus,
Q1 = Qs & Q2 = Qp
29
15