Mech Checklist Ceiling Cassette Units

This document provides a checklist for inspecting ceiling cassette units during a material delivery at the IMU Hospital Bukit Jalil project. The checklist includes 9 items to inspect such as checking for damage, verifying models match approved submissions, and inspecting components like the remote control, casing cover, and ducting. The inspection results found the delivery to be acceptable with minor remedial work needed but no further inspection required. The inspection was carried out by M.C Low on June 15, 2020 at 12pm.

Uploaded by

Azwan Sunline
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
776 views

Mech Checklist Ceiling Cassette Units

This document provides a checklist for inspecting ceiling cassette units during a material delivery at the IMU Hospital Bukit Jalil project. The checklist includes 9 items to inspect such as checking for damage, verifying models match approved submissions, and inspecting components like the remote control, casing cover, and ducting. The inspection results found the delivery to be acceptable with minor remedial work needed but no further inspection required. The inspection was carried out by M.C Low on June 15, 2020 at 12pm.

Uploaded by

Azwan Sunline
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

PEMBINAAN MITRAJAYA SDN BHD

TITLE: ACMV SERVICES


SERVICES

Title : Material Delivery Inspection

Project Title : IMU Hospital Bukit Jalil WIR No :

Check List: Ceiling cassette unit (Daikin)

Location: OKU Toilet Block : Hospital Level: 1st Floor Grid Line : All

Item Description Of Inspection Acceptability


PMJ Consultant
Yes No Yes No
1. Check Material deliver as good condition

2. Wire remote control

3. Ceiling cassette casing cover

4. Pressure Independent Balancing & Control Valve


(FlowCon)
5. Volume control damper (Edwincon)
6. Round duct: 100mm (Edwincon)
7. Ball valve & strainer (Tozen)
8. Check material for damage.
9. Model as per approved submission

Inspection Result:

1. Overall Inspection Acceptable Not Acceptable


2. Minor remedial work needs to be done but no further inspection required
3. Major remedial work needs to be done and re-inspection is required

Comments:

Work Carried Out By: Checked by: Verified / Witnessed by:


Name: M.C Low Name: Name:
Date: 15-06-2020 Date: Date:
Time: 12pm Time: Time:

-------------------------- ----------------------------- ---------------------------


Sub-Contractor Main Contractor IOW/Owner’s Representative

1
2