Offshore Container (Pipe Basket) Design Approval Report
Offshore Container (Pipe Basket) Design Approval Report
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 1 of 13
Rev. Status Reason for issue Revision Date Issued by Reviewed by Approved by
Revision History
DESIGN REPORT/CALCULATION NOTE
OFFSHORE PIPE BASKET
Document Number :
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 2 of 13
Table of Contents
1. GENERAL ................................................................................................................................... 4
1.1. Operational Environment ...................................................................................................... 4
1.2. Standards and Regulation .................................................................................................... 4
1.3. Design Approval ................................................................................................................... 4
2. DIMENSIONS AND RATINGS .................................................................................................... 4
2.1. External Dimensions ............................................................................................................. 4
2.2. Internal Dimensions .............................................................................................................. 4
2.3. Forklift Pocket ....................................................................................................................... 4
2.4. Inside Cubic Capacity ........................................................................................................... 4
2.5. Ratings ................................................................................................................................. 4
3. MATERIAL AND CONSTRUCTION ........................................................................................... 5
3.1. Bottom Rail ........................................................................................................................... 5
3.2. Corner Post .......................................................................................................................... 5
3.3. Top Rail ................................................................................................................................ 5
3.4. Intermediate Post ................................................................................................................. 5
3.5. Bracing ................................................................................................................................. 5
3.6. Forklift Pocket ....................................................................................................................... 5
3.7. Base Plate ............................................................................................................................ 5
3.8. Pad Eye ................................................................................................................................ 6
3.9. Pad Eye Cheek Plate ........................................................................................................... 6
3.10. Properties of Steel Material ............................................................................................... 6
3.10.1. Chemical Properties ...................................................................................................... 6
3.10.2. Mechanical Properties ................................................................................................... 6
4. PRESERVATION ........................................................................................................................ 7
4.1. Surface Preparation of Steel Part ......................................................................................... 7
4.1.1. Prior to Assembly .......................................................................................................... 7
4.1.2. After Assembly .............................................................................................................. 7
4.2. Painting ................................................................................................................................. 7
5. MARKING .................................................................................................................................... 8
5.1. Owner’s code and serial number .......................................................................................... 8
5.2. Weight .................................................................................................................................. 8
DESIGN REPORT/CALCULATION NOTE
OFFSHORE PIPE BASKET
Document Number :
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 3 of 13
5.3. Owner’s logo ......................................................................................................................... 8
5.4. Other ..................................................................................................................................... 8
5.5. Identification plate. ................................................................................................................ 8
6. TESTING AND INSPECTION ..................................................................................................... 9
6.1. Prototype Container .............................................................................................................. 9
6.2. Testing item and load ........................................................................................................... 9
Lifting from the top Padeye ............................................................................................................. 9
- All Padeye ................................................................................................................................... 9
Lifting from the Forklift pocket ........................................................................................................ 9
Vertical Impact Test .......................................................................................................................... 9
6.3. Production Line Container .................................................................................................... 9
7. SCREEN DUMP SHOWING STAADPRO MODEL AND RESULTS ........................................ 10
8. DESIGN CALCULATION FOR LIFTING SETS AND PAD EYE............................................... 13
8.1. Objective ............................................................................................................................. 13
8.2. Design Reference ............................................................................................................... 13
8.3. Basis of Design ................................................................................................................... 13
8.4. Conclusion: ......................................................................................................................... 13
8.4.1. Master Link Assembly Dimension: .............................................................................. 13
8.4.2. Sling Leg Dimension: .................................................................................................. 13
8.4.3. Shackle Information/Dimension: .................................................................................. 13
8.4.4. Pad Eye Information/Strength: .................................................................................... 13
DESIGN REPORT/CALCULATION NOTE
OFFSHORE PIPE BASKET
Document Number :
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 4 of 13
1. GENERAL
2.5. Ratings
Maximum Gross Weight:6,900 kgs (TBC)
Maximum Payload:5,500 kgs
DESIGN REPORT/CALCULATION NOTE
OFFSHORE PIPE BASKET
Document Number :
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 5 of 13
Estimated Tare Weight: 1400 kgs (Hollow sections + Plating)
3.5. Bracing
Material : ASTM A500 Grade B or equivalent quality
Geometry : Square hollow section
Size : Nil (Not applicable)
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 6 of 13
Size: 6.0 mm
DESIGN REPORT/CALCULATION NOTE
OFFSHORE PIPE BASKET
Document Number :
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 7 of 13
4. PRESERVATION
4.1. Surface Preparation of Steel Part
4.2. Painting
The offshore basket is airless sprayed outside using zinc rich primer and acrylic top
coat, which is the converted at 60oC.
The offshore basket is airless sprayed inside using zinc rich primer and epoxy
polyamide finish, which is the converted at 60oC.
The paint system and thickness are as follows:
DESIGN REPORT/CALCULATION NOTE
OFFSHORE PIPE BASKET
Document Number :
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 8 of 13
5. MARKING
All offshore baskets are to be marked in accordance with the EN 12079-1:2006,
requirements as well as certain customers marks, and logos as indicated below.
The marking applied on the offshore basket will be self-adhesive decal of cast vinyl and
seven years life.
Unless otherwise specified, all markings included in this guideline/specification are to be in
decal.
5.1. Owner’s code and serial number
The offshore basket serial number must be placed in accordance with owner’s requirements.
5.2. Weight
The weight of the offshore basket is positioned on the right-hand door in such a manner that
no information is hidden by door hardware. The weight shown is the maximum gross weight
of the pipe basket, the tare weight of the container and maximum designed cargo weight or
payload. All weights are to be expressed in kilograms and pounds.
5.4. Other
Other markings are affixed in accordance with owner’s requirements.
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 9 of 13
6. TESTING AND INSPECTION
6.1. Prototype Container
Prototype container manufactured in accordance with this specification will be tested
according to the standard classification container procedures. The deflection of the
components during test are measure with scaled and dial gauges. Upon completion of the
test, the basket will be certified by the society with a test report showing the deflection and
variations within the criteria of the permissible values specified in the society’s rules.
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 10 of 13
7. SCREEN DUMP SHOWING STAADPRO MODEL AND RESULTS
3D Model
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 11 of 13
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 12 of 13
XXXX-XXXXX-XXX-XXX-XX
Document Title:
Rev: 0 Status: IFF
DESIGN REPORT/CALCULATION NOTES FOR
Rev. Date:
OFFSHORE PIPE BASKET 28 June, 2019
Page 13 of 13
8. DESIGN CALCULATION FOR LIFTING SETS AND PAD EYE
8.1. Objective
To determine quad assembly (master link & intermediate), sling & shackle.
To determine minimal required breaking strength of lifting sets and padeye strength.
8.4. Conclusion:
If R = 6900 kg, find the minimum required working load limit (WLLmin)
WLLmin = 11,73 kg
FH
2.0 Reference
Design Code : API RP 2A ( WSD ), 21 st Edition, December, 2000Section 2.4.2.
a 5% lateral load is assumed
th
: AISC ASD 9 Edition
DNV 2.7-1
BS EN 12079
BS EN ISO 10855
Design Guide : Applied Offshore Structural Engineering, Teng H. Hsu, 1984
Selected Quad Assembly (Master Link + Intermediate) from EN 1677-4 WLLs Link = WLLmin/(2 x cosθ) 8.29 Tons
Master Link Dimension (Nominal size - 12) : d1 36.00 mm
Intermediate Dimension (Nominal size - 12) : d2 26.00 mm
Actual Minimum Working Load Limit of Quad Assembly : WLLLINK 12.00 Tons
WLLmin > Pw SAFE!
4.0 PADEYE DESIGN DIMENSION
4.1 Determination of Padaye Main Plate Thickness ( Check to Allowable Bearing Stress at pin hole )
2
Minimum Bearing Area Required : Abr( min ) = FR / Fbr 277.47 mm
Limiting Value of Plate Thickness req'ed (Bearing contact area assumed at an arc of 9 : tmin = Abr(min)/(πB/4) 13.91 mm
Plate Thickness Selected : T 30.00 mm
Cheek Plate 1 thickness : Cheek Plate 1 0.00 mm
Cheek Plate 2 thickness : Cheek Plate 2 0.00 mm
Total Plate Thickness, Tp : Tp = tmp + (2 x tcp) 30.00 mm
Total Plate Thickness check : TP ≥ 75% of inside width of shackle (A). 27.45 mm Tp is Ok
2
Bearing Area Available (Bearing contact area assumed at an arc of 90 degrees) : Abr = (πB/4) x Tp 598.47 mm
Unity Check for Bearing stress at pin hole : UC = Abr(min)/Abr 0.46 UC<1 OK !
4.2 Determination of Padeye Plate Dimensions Above Pin Shackle ( Check to Allowable Shear Stress at pin hole )
Estimated Padeye Pin Hole Diameter : d = B + 3 or 1.06B (Lesser) 26.92 mm
Padeye Pin Hole Diameter : Use d 26.90 mm
Main Plate Radius : R 45.00 mm
Main Plate Radius check : R > 1.25d 33.63 mm R is Ok
Main Plate Thickness : T 30.00 mm
Cheek Plate 1 Radius : r1 0.00 mm
Cheek Plate 1 Thickness : t1 0.00 mm
Cheek Plate 2 Radius : r2 0.00 mm
Cheek Plate 2 Thickness : t2 0.00 mm
2
Minimum Shear Area requiered : As ( min ) = FR / (2xFs) 312.16 mm
2
Shear Area provided - main Plate : 1 x (R-d/2) x T 946.50 mm
2
Shear Area provided - Cheek Plate 1 : 2 x (r1-d/2) x t1 0.00 mm
2
Shear Area provided - Cheek Plate 2 : 2 x (r2-d/2) x t2 0.00 mm
2
Available Shear Area : As 946.50 mm
Unity Check : UC 0.33 UC<1 OK !
4.3 Determination of Padeye Plate Dimensions ( Check to Allowable tensile Stress at pin hole )
Main Plate Radius : R 45.00 mm
Main Plate Thickness : T 30.00 mm
Cheek Plate 1 Radius : r1 0.00 mm
Cheek Plate 1 Thickness : t1 0.00 mm
Cheek Plate 2 Radius : r2 0.00 mm
Cheek Plate 2 Thickness : t2 0.00 mm
Padeye Pin Hole Diameter (Eye) : d 26.90 mm
2
Tensile Area for section A-A : ATA-A = 2 x [(R-d/2)T + (r1-d/2)t1 + (r2-d/2)t2] 1893.00 mm
Tensile Stress at pin hole (Actual) at section A-A : FTA-A = FR/ATA-A 45.51 MPa
2
Shear Area provided - Cheek Plate 1 : ATB-B = [(2 x R) + (π x -r1/4) + (π x -r2/4)] x T 2700.00 mm
Shear Area provided - Cheek Plate 2 : FTB-B = FR/ATB-B 31.91 MPa
Allowable Tensile Stress : FTP 155.25 MPa
Unity Check : UC 0.29 UC<1 OK !
4.4 Hertz/Contact/Eye Stress Check at pin hole (Check to Allowable Hertz Pressure)
KB : d x B/(d-B) 455.51 mm
1/2
Hertz Pressure : pH = 0.591 x ((FR x E) / (TP x KB)) 663.64 MPa < 2.0 Fy
Unity Check : UC 0.96 UC<1 OK !
4.5 Determination of Hertz stress (Check to Allowable Hertz Pressure - method 2)
Padeye Design Load : FR 8.79 mT
Design Load per unit length : p = FR/Tp 0.29 mT/mm
Modulus of Elasticity : Es 200000 MPa
Poisson's Ratio : ⱱ 0.3
Pin Diameter : B 25.40 mm
Eye Pin Hole Diameter : d 26.90 mm
2 1/2
Hertz Stress at Pin Hole : pH = [{p x E x (d-B)}/{π x (1-ⱱ ) x d x B}] 664.13 MPa
Unity Check : UC 0.96 UC<1 OK !
The shortest distance from centre of bolt holes to edge of padeye in mm : H 45.00 mm
Total Plate Thickness : TP 30.00 mm
Bolt hole diameter in mm : d 26.90 mm
Tear-out Stress : 85.94 MPa
Allowable Tensile Stress : 345 MPa
Unity Check : 0.25 UC<1 OK !
C1 C
of Pin
Padeye
Pin
C2
4.9 Weld Size of Cheek Plate 1 (Weld check at cheek plate weld)
Load on Cheek Plate : Tc = FR x (t1+t2) / TP 0.00 N
Minimum Weld Thickness for Cheek Plate : T weld =Tc/(2π x r1 x 0.707 x Fsw) N/A mm
Provide Weld Size : refer to drawing 0.00 mm
UC SUMMARY
- Shear in-plane stress UC 0.330 UC<1 OK !
- Bearing UC 0.464 UC<1 OK !
- Tensile stress UC 0.293 UC<1 OK !
- Hertz Pressure unity check 0.962 UC<1 OK !
-Tear-out Stress unity check 0.249 UC<1 OK !
- Contact Stress 0.563 UC<1 OK !
OK
4-Legged Sling
ForeRunner
1110 mm