II - Project Implement Stage
II - Project Implement Stage
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Project
Work
Approved Change Management
Performance
Orders Information
Data
System
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Project Management
Expert Judgment Change Order
Plan
Work
Analytical Performance
Schedule Forecasts
Techniques Data
Project Project
Management Management
Cost Forecasts
Information Plan
System (Updates)
Project
Project Monitor &
Implement Approved Change
Integration Control
(EPC) Order
Management Project Work
Stage
Work Performance
Information
Project
Meetings Documents
KNPC Policies and (Updates)
Procedures
Projects Department’s
Procedures and
Practices
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Approved
Project Management Expert
Change
Plan Judgment
Order
Change Order
Project Perform
Project Project
Implement Integrated
Integration Management
(EPC) Change
Management Plan
Stage Control KNPC Policies and (Updates)
Procedures
Change Control
Tools
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Stakeholder Communication
Issue Log
Management Plan Methods
Communications
Change Order
Management Plan
Interpersonal
Project Manage Skills
Implement Project Stakeholder
Stakeholder
(EPC) Stakeholder Change Log Management
Management
Stage Management Plan (Updates)
Engagement
Projects Department
Project
Processes, Procedures, Management
Documents
& Historical Skills
(Updates)
Information
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Document
Work
Project Management Information
Performance
Plan Management
Information
System (DIMS)
Expert Judgment
Project
Monthly Project
Management
Project Control Progress Report
Project Plan (Updates)
Implement Stakeholder
(EPC) Stakeholder
Management
Stage Management
Engagement
Project
Documents
(Updates)
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Requirements
Documentation
Change
Order
Project
Monthly Progress
Documents
Report
(Updates)
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
- During first two months of EPC stage Contractor shall undertake FEED verification to check existing
drawings/documents with respect to actual plant conditions. Any discrepancy found in the drawings with respects
to site conditions, pertaining to the Scope of work should be highlighted to KNPC for correction and execution by
the Contractor.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Monthly
Project Management
Progress
Plan
Report
Requirements
Documentation
Change Order
Project
Implement Project Scope Project Acceptance Variance
(EPC) Control Scope Plan
Management Analysis
Stage
Monthly Progress
Report
Project
Management
Plan
Projects Department’s
(Updates)
Procedures and
Practices
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
The Project Schedule Management Plan as part of the Bid sets the format and establishes criteria for further developing
and controlling the Project schedule during implementation stage. Post Contract award during Implementation Stage,
Schedule Management Plan shall be finalized by EPC Contractor with the help and support of KNPC project
coordination team. This will be an agreement between all parties how the EPC Contract will be managed in the
timeframe for the undertaken project.
Project Schedule Management will be repetition of the steps as done in the FEED phase for of the following
processes:
1. Plan Schedule Management
2. Schedule Development
3. Control Schedule: This process purely belongs to project implementation phase.
Responsibility
EPC Contractor
EPC Contractor is responsible to further develop Schedule Management Plan & Project Schedules (Min. level 6) using
Rolling Wave Plan technique in addition to the tools and techniques as indicated in Part I of this Guideline.
KNPC
Dedicated KNPC Project Planning Engineer shall be assigned to every capital project based on the size and
complexity. KNPC Planning Engineer will coordinate & review the schedule at various stages. KNPC Project Planning
Engineer assigned to Capital Project shall do close follow up with EPC Contractor on Project Float/Buffer
Management for both near critical and non-critical activities. EPC Contractors resources estimate must be compared
with the FEED resource estimate and shall be presented to KNPC PCG, if required gap analysis shall be done for major
positive / negative variations. KNPC Team Leader of the contract has overall responsibility for the quality of Schedule
Management process. Team Leader of the contract should make sure the schedule verification during base lining and
regular reviews are conducted by subject matter experts outside the project team to have cold eye review.
It is recommended to have an integrated Project Planning effort. EPC Contractor has to follow the Rolling wave plan
philosophy, broad guidelines for development sequence is given below.
All planning deliverables must be updated parallel to the Project master schedule development. EPC Contractor must
work with KNPC for interface management and comply with KNPC interdependency schedule.
2.4.3 Key Elements, which must be taken care during various phases of EPC Schedule development
OVERALLL
• It is recommended to have the Schedule WBS in standard EPC format where the 2nd level of should be
Engineering, Procurement & Sub-Contract, Construction, Pre-Commissioning & Commissioning
• Calendar shall be defined for the entire duration of the project taking into consideration all factors effecting the
project timeline including but not limited to public Holidays, Summer time restrictions, Ramadan windows,
Shutdown windows etc.
• Schedule Risk Analysis must be done each time the schedule is revised adding details or revision for slippage
recover is undertaken. EPC Contractor is also responsible to install Schedule Risk Assessment Software on KNPC
Server.
• Project Interdependency check for any overlap between KNPC and projects outside KNPC or shutdown activities.
• Remaining duration of balance works to be mentioned in days separately apart from remaining work percentage.
ENGINEERING
• EPC contractor to optimize the duration of document review cycle and identify list of critical documents at early
project stage (FEED Phase).
• EPC Contractor to submit the list of critical documents after signing the contract along with plan on how to track
and optimize the review cycle with Project End User.
PROCUREMENT
• RFQs issue to vendors must be planned early in the lifecycle of project, it is recommended that once the contractor
receives comments on the MRs from KNPC, they must issue the MRs to Vendors also incorporating the comments.
Any further comments by KNPC shall be transmitted to Vendor as addendum. Approved MRs are required prior to
finalizing the POs. The above will give longer time for bidding/evaluation etc. and avoid delays.
• Key Vendor Documents must be approved prior to actual Manufacturing however Vendor shall commence all Pre-
Manufacturing activities including Material sourcing, finalizing of Sub-Orders etc. once the PO is placed. These are
parallel activities to Vendor Document review.
• Spares part list activity shall be schedule early giving time to KNPC for finalization and decision to purchase.
• Show Packing and Ex-Delivery activities, typically 1-2 week long activity happens after FAT and before
commencement of Shipping.
• Material Record Book (MRBs) preparation to be planned much early in the procurement lifecycle and first
submission shall be done within a week of FAT. MRBs must be delivered to site before Equipment delivery to
support the Installation, Pre-Commissioning and Commissioning.
• SAT should be included in Construction section of schedule.
• Procurement and Sub-contracting section shall be loaded with man-hours in order to be able to have a complete
manpower histogram.
PROJECT MANAGEMENT
• Project Organization Chart Approved
• Project Co-ordination Procedures Approved
• Project Schedule & Cost Control Procedures Approved
• Project Invoicing & Payment Procedures Approved
• E&P Schedule Approved
• Project Document Register (PDR) Approved
• Procurement Tracking Register (PTR) Approved
• Project QA/QC Plan Approved
• Project HSSE Plan Approved
• Pre-Commissioning and Commissioning Execution Plan Approved
ENGINEERING
• P&IDs Issued for Review
• P&IDs Issued for HAZOP
• P&ID Issued for Design
• P&ID Issued for Construction/Final
• Issue First Bulk Material MTOs
• Issue all Bulk Material MTOs
• 30% Model Review
• 60% Model Review
• 90% Model Review
• HAZOP Completed
• HAZOP corrective actions cleared
• First Set of Civil GA AFC
• Last Set of Civil GA AFC
• First Set of Structural Steel GA AFC
• Last Set of Structural Steel GA AFC
• First Set of Piping GA AFC
• Last Set of Piping GA AFC
• First Set of Piping Isometrics AFC
• Last Set of Piping Isometrics AFC
• First Set of Piping Support AFC
• Last Set of Piping Supports AFC
• First set of SLDs AFC
• First Set of E&IT GA AFC
• First set of Instrument Location. Diagram GA AFC
• All E&IT Gas issues
• All SLDs issued AFC
• All Inst. Location Diagrams issued AFC
PROCUREMENT
• ITT's for all Long Lead Items Issued
• PO's for all LLI's Awarded
• Award Civil / Building Works Contract
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Project
Implement Project Schedule Variance
Control
(EPC) Schedule Analysis &
Schedule Project
Stage Management Project Calendars Modeling Management
Simulation for Plan (Updates)
Recovery Plan
Critical Chain
Schedule Data
Method
Mont-Carlo Project
Simulation Baseline &
Projects Technique Documents
Department’s (Updates)
Procedures and
Practices Scheduling Tool
(EVM)
Note :
- Purple text refers to attached template.
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
• EPC Contractor shall utilize effective Schedule Control Tools such as Earned Value Method for schedule
update.
• Schedule Progress update basis for each phase of project is as follows. Document register for Engineering,
Procurement Register / Expediting reports for procurement, Commodity reports for Construction etc. This
shall ease the process of approval for KNPC.
• EPC Contractor shall use Integrated Data base package for handling Progress. Document Control should be
linked with Engineering / Vendor Document Progress. Material Management system should be linked with
Procurement progress. In addition, Pre-commissioning and Commissioning progress at site must be done
through Completions management software.
• Progress data entry shall be done by the data owner namely Document Controller for Engineering,
Designers for 3D Model progress, Expediters for Procurement, Construction progress update shall be done
by QS and Pre-commissioning and Commissioning by Completions team.
• Planning Engineers role shall primarily be in extracting the report from system and verifying it with back-
ups etc. before incorporating in the Weekly /Monthly report for KNPC.
• All Progress Updating and Tracking System has to be set-up on weekly basis. Thursday shall be the weekly
cut-off, EPC Contractor must update the week’s progress over the weekend and by Sunday latest weekly
status report must be issued.
• Baseline and Intermediate Schedule should be maintained and updated periodically with an effective
Recovery Plan wherever medium risk occurs on project overall schedule (i.e. schedule slippage by 10%).
• Project Management peer review by KNPC Subject matter expert from outside the Project team shall be
conducted once every six months.
The overall weightings for WBS Level elements as below shall be based on cost.
o Engineering,
o Procurement,
o Construction, Pre-Commissioning & Commissioning Assistance
Engineering weightage shall be based on Man-hours; Further break-up of Engineering is recommended as below.
o Detailed Engineering
o Vendor Engineering
o 3D Model
Procurement weightage is determined based on Cost; Further break-up of Procurement is recommended as below
o Major Tagged Items
o Other Tagged Items
o Bulk Items
• Construction, Pre Commissioning and Commissioning Assistance weightage shall be 100% linked to the
physical progress. Physical progress shall be based on Man-hours directly derived from Estimated
Quantities. This shall be revised with exact quantities as soon as the Detail Drawings are available.
Site progress report will be submitted on Daily basis in the morning of the following day of work, for construction activities at site and shall include the following:
Note :
- EPC Contractor to finalize the forms as per specific project requirement and put reference numbers
Weekly Progress Report Cutoff date will be Thursday and submission to KNPC on Sunday of the following week.
Weekly Report shall have following sections, which will cover period performance as well as overall performance for all
phases and disciplines.
• Executive Summary narratives for the activities performed during the week. Activities planned for next week. Areas
of concerns and proposed corrective actions for the following.
o HSE & Quality
o Engineering by Disciplines
o Procurement by Discipline
o Sub-Contract
o Offsite Fabrication
o Construction by Area
o Pre-Commissioning
o Commissioning
• Safety statistics for Cumulative and Weekly performance at least for the following.
o Man-hours for Engineering, Project Support, Offsite-Fabrication, Construction
o Lost Time Incident
o Medical Treatment Case
o First Aid Case
o Near Miss Incident
o Property Damage
o Environmental Damage
• Technical Query Status
• Issue Log
• Progress % Plan and Actual for Cumulative and Weekly performance for the following.
o Engineering (Deliverables, 3D Model and Vendor Data)
o Procurement
o Construction , Pre-Commissioning & Commissioning
• Engineering Deliverables Status per discipline showing minimum information as Total Number of Deliverables per
Discipline and status for document submission per discipline, submissions for the period etc.
• Procurement Requisition Status showing cumulative and period performance for Procurement Requisitions per
discipline showing minimum information as Total Number of Requisitions per Discipline, Inquiry Issued, Bid
received, Evaluation done, PO Placed.
• Material Delivery Status for major Equipment / bulks showing minimum information as Total Quantity, Planned /
Actual Delivery to date, Balance to go. Plan/Actual delivery for period.
• Construction Commodity Summary tables for major Construction Commodity showing minimum information as
Total Commodity, Planned / Actual Liquidated to date, Balance to go. Plan/Actual for period, planned finish date
etc.
Note :
- EPC Contractor to finalize the forms as per specific project requirement and put reference numbers
Narratives Report:
Narrative Report highlighting major accomplishments during current period for HSE & Quality, Engineering by
Disciplines, Procurement by Discipline, Construction by Area, Pre-Commissioning, Commissioning. Activities planned
for next month. Areas of concerns and proposed corrective actions. Schedule Analysis discussing deviations from Master
Plan, items in Critical path with forecast dates, Key Milestone Status.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Monthly
Project Management Earned Value
Progress
Plan Management
Report
Project Funding
Forecasting
Requirements
Payment
Schedule
Performance
Work Performance Data
Reviews
Project
Implement Project Cost
(EPC) Control Cost
Management Change Order
Stage
Project
Projects Department’s Project Management
Processes, Procedures, Management Plan (Update)
& Historical Information Software
Project
Documents
(Updates)
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Quality Management
Change Order
Plan
Quality
Management &
Control Tools
Process Improvement
Plan Project
Management
Project Plan
Implement Perform
Project Quality (Updates)
Quality Quality Metrics Quality Audits
(EPC) Management
Stage Assurance
Quality Control
Measurement
Project
Process Analysis Documents
(Updates)
Project Documents
Note:
- External Project Management peer review to be conducted every six months on each Project Management Functions.
- Random audit will be conducted by subject matter expert to check the quality of comments submitted by both EPC
Contractor and End User.
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Human Resource
Pre-Assignment
Management Plan
Project Staff
Assignments
KNPC Policies and
Negotiation
Procedures
Note:
- Mobilization of dedicated KNPC Project Coordination Group and Project End User to EPC Contractor’s Home Office
during the detailed engineering design in order to close follow-up and expedite approvals of Engineering Deliverables
- KNPC has the right to interview and accept EPC Key Personnel after signing EPC Contract.
- In case of Project demobilization/transfer, progressive handover/takeover should be considered for EPC Contractor
Key Personnel.
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Interpersonal Skills
Human Resource
Management Plan
Training
Personnel
Assessment Tools
Note :
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Human
Project Resource
Project Staff
Performance Management
Assignments
Appraisals Plan
(Updates)
Project
Project Project Team Performance
Documents
Implement Human Manage Project Assessment
Conflict (Updates)
(EPC) Resource Team Management
Stage Management
Issue Log Team
Operating
Agreement
Monthly Progress Interpersonal (Optional)
Report Skills
Projects Department
Personnel Manpower
Processes, Procedures,
Assessment Histogram
& Historical
Tools (Updates)
Information
Note:
- Purple text refers to attached template.
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Team Values and Principles: List values and principles by which the team agrees to operate (i.e. mutual respect, operating from fact
not opinion, etc.)
1.
2.
3.
Meeting Guidelines: Identify guidelines that will keep meetings productive (i.e. decision makers must be present, start on time, stick to
the agenda, etc.)
1.
2.
3.
Communication Guidelines: List guidelines used to make effective communication (i.e. everyone voices their opinion, no dominating
the conversation, no interrupting, etc.)
1.
2.
3.
Decision-Making Process: Describe the process used to make decisions. Indicate the relative power of the project manager for
decision making as well as any voting procedure. Also indicate the circumstances under which a decision can be revisited
Conflict Management Approach : Describe the approach to managing conflict, when a conflict will be escalated, when it should be
tabled for later discussion, etc.
Other Agreements : List any other agreements or approaches to ensuring a collaboration and productive working relationship among
team members
Signature : Date :
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Project
Communications Communication
Communications
Management Plan Technology
Material
Project
Monthly Progress Communication
Management Plan
Report Models
(Updates)
Project
Implement Project
Manage
(EPC) Communications KNPC Policies Communication
Communications
Stage Management and Procedures Methods
Information
Projects Management
Department System Project Document
Processes, (Updates)
Procedures, &
Historical Performance
Information Reporting
Note :
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Project
Information
Project Management Monthly
Management
Plan Performance
System
Report
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
- EPC Contractor to provide Read-only access to online documentation software system to KNPC assigned project
team
- Project End User should be involve in Project Monthly Progress Meeting and updated with list of Critical Documents
that will be reviewed by next month
Project Project
Main Tools & Output
Management Inputs
Stage Process Techniques Deliverables
Function
Information
Quality Management Plan Gathering
Techniques
Project Documents
SWOT Analysis
KNPC Policies and
Procedure
Note :
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Main Output
Management Inputs Tools & Techniques
Stage Process Deliverables
Function
Expert Judgment
Lessons Learned
System
Note :
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Output
Managemen Main Process Inputs Tools & Techniques
Stage Deliverables
t Function
Risk Management
Plan Data Gathering &
Representation
Techniques
Cost Management
Plan
Schedule
Management Plan Quantitative Risk
Analysis & Modeling
Techniques
Risk Register
Perform
Project Project
Project Risk Quantitative
Implement Documents
Management Risk
(EPC) Stage KNPC Policies and (Updates)
Assessment
Procedures
Projects Department
Processes,
Procedures & Expert Judgment
Historical
Information
Lesson Learned
Systems
Note :
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Output
Manageme Main Process Inputs Tools & Techniques
Stage Deliverables
nt Function
Note :
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Main Tools & Output
Management Inputs
Stage Process Techniques Deliverables
Function
Monthly
Project Management Project
Risk Reassessment
Plan Progress
Report
Risk Audit
Change
Risk Register
Technical Order
Project Performance
Implement Project Risk Control Measurement
(EPC) Management Risks
Stage
Variance and Trend Project
Work Performance Analysis Management
Data Plan
Reserve Analysis (Updates)
Project
Monthly Progress
Expert Judgment Documents
Report
(Updates)
Note :
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Procurement
Performance Change Order
Reviews
Procurement
Documents
Project
Inspection &
Management
Project Audits
Project Plan (Updates)
Implement Control
(EPC) Procurement
Procurements
Stage Management
Performance
Agreements
Reporting
Project
Approved Change
Payment Systems Document
Order
(Updates)
Monthly Project
Change Log
Progress Report
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
- EPC Contractor / Vendor should submit manufacturing progress report for critical equipment on monthly basis.
- EPC Contractor should conduct Procurement Progress review Meeting with KNPC Project Team and Subcontractors/
Vendors in order to ensure accuracy of the Procurement Status Report/Progress.
- EPC Contractor is responsible to notify KNPC about Subcontractor/Vendor with poor performance.
- Contract & Procurement Audit will be conducted every six months by KNPC review contracts and practicing
processes for completeness, accuracy and effectiveness.
- EPC Contractor is responsible to enhance the manufacturing cycle by confirming on the following:
- Identification of Vendors and Suppliers who are on or near the Project Critical Path Schedule.
- Prioritization of Vendor List and obtaining direct feedback.
- Development of action plan for regular visits to Vendor premises for better follow-up and expediting.
- Conducting of Vendor Campaign at EPC Contractor Home Office as and when required.
- Submitting Vendor Status Report for placed POs when required (minimum of monthly basis).
- Submitting of a detailed Vendor’s Manufacturing Schedule.
- Submitting predefined dates for Long Lead Items and payment (action plan).
142 PD Project Management Guideline
Copy Right Reserved Projects Department I - 2016
Part II: Project Management Best Practices – Project Implement Stage
2.10.1 Project Procurement Management Flowchart (Contd.)
Project Project
Tools & Output
Management Main Process Inputs
Stage Techniques Deliverables
Function
Procurement Procurement /
Management Plan Contract Audits
Project
Implement Project
Close Procurement Closed
(EPC) Procurement
Procurements Negotiations Procurement
Stage Management
Procurement
Documents
Records
Management
System
Note:
- The guideline and templates may be customized for applicable input, tools & techniques and desired output.
- Update Project Management Plan (PMP) should be attached to Project Closeout Report.