0% found this document useful (0 votes)
118 views

Project Outline: Office of The Municipal Engineer

The document outlines a project to improve and rehabilitate JP Neri Street in Mambajao, Camiguin by providing drainage and slope protection. The project will be funded by PHP 1,200,000 from the municipality's 20% Development Fund for 2019 and implemented by the Municipal Engineering Office.

Uploaded by

ARMA G. TANGAPA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
118 views

Project Outline: Office of The Municipal Engineer

The document outlines a project to improve and rehabilitate JP Neri Street in Mambajao, Camiguin by providing drainage and slope protection. The project will be funded by PHP 1,200,000 from the municipality's 20% Development Fund for 2019 and implemented by the Municipal Engineering Office.

Uploaded by

ARMA G. TANGAPA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Republic of the Philippines

Province of Camiguin
Municipality of Mambajao

OFFICE OF THE MUNICIPAL ENGINEER

PROJECT OUTLINE
I. Sector : Infrastructure Services
II. Project Title : Improv’t./Rehab. of JP Neri Street
III. Project Location : Mambajao, Camiguin
IV. Project Proponent : Local Government of Unit of Mambajao
V. Funding Source : 20% Development Fund CY 2019
VI. Total Project Cost : Php 1,200,000.00

Project Description

The project is the Improv’t./Rehab. of JP Neri Street located at Poblacion, Mambajao,


Camiguin. It has an existing concrete pavement with no line canal, hence, this project will provide the
drainage system with slope protection on both sides of the road.
Thus, the Municipal Government of Mambajao has allocated funds in the amount of One
Million Two Hundred Thousand Pesos (Php 1,200,000.00) from the 20% Development Fund CY 2019
to support the Improv’t./Rehab. of JP Neri Street of this municipality.

VII. Project Objective : To rehabilitate/improve the municipal road along


Jp Neri Street
VIII. Budgetary Requirements:
Materials and Labor = Php 1,200,000.00

IX. Implementing Unit : Municipal Engineering Office

X. Expected Output : JP Neri Street improved and rehabilitated.

Prepared by:

ELVIS V. CIMACIO
Municipal Engineer