OK CHAPTER 4 C. Technical - Aspect
OK CHAPTER 4 C. Technical - Aspect
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
TECHNICAL ASPECTS
A. PROJECT DESCRIPTION
Plastic pipe has gained widespread acceptance after it has in many ways
proven itself to be superior as sewer pipe line material. Test indicated that plastic
pipe will last for more than 50 years under normal condition.
Comparatively, the plastic pipe weigh about 1/5 of the metal pipe
Plastic pipes are cast in longer length and easy to cut as well as
easy to install
39
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
form. The reason is to retard the even flow of the waste and to
that the depth should not be deeper than the natural ground water
table.
1. Minimum width= 90 cm
40
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
BASIC ASSUMPTION
1. The unit costs contained are for normal and customary installations. If
unusual circumstances exist, the unit cost must be adjusted to account for
41
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
Table shows the detailed cost estimate for construction of a Low Pressure
System.
EARTHWORKS
42
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
MASONRY WORKS
REINFORCEMENT WORKS
PAVING
43
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
SIGNAGE
B. DESIGN CONSIDERATIONS
LAND USE
majority of which are Low Density Residential (LDR) area. The area consists of
approximately 75 households. The land-use map for the area is provided in Figure
3.
44
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
FIGURE 3
45
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
inches) or as required and as measured from the final ground surface to the top of
The septic system site plan is typically drawn right on top of the property
survey showing the septic tank 'setbacks' with tank 5-10 feet from the house, the
leach field at least 20 feet from the house, at least 100 feet away from wells and
streams, 25 feet away from dry gulches, and 10 feet away from the property lines or
whatever the local regulatory officials require, so always check with the county first
The home's sewer line drain pipe needs to slope 1/4 inch per foot downhill
to the inlet side of the septic tank and the outlet pipe needs to flow at least 1/8 inch
per foot downhill to the leach field, where the septic tank effluent enters a manifold
or distribution D box. Beyond the manifold or D box the leach field trenches (for an
Infiltrator chamber system) are excavated perfectly level at a depth of at least seven
inches below the grade of the manifold pipes or D box (for chambers) and covered
with at least one foot of soil atop the trench or chamber. Trenches can be deeper, if
the site dictates, but rarely more than three feet below finish grade.
46
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
a) General
Excavations shall comply with all Local rules, regulations and ordinances
Construction (OSHA).
b) Trench Excavation
The width of trenches must provide adequate space for workmen to place,
joint and backfill the sewer pipe properly, but should be kept to a minimum. If
unsuitable pipe bedding material is exposed within the sewer pipe zone of the
required and should be replaced with suitable fill materials. The material used to
backfill the trench is referred to as flowable fill. This is a cementious material with a
low water/cement ratio that is delivered to the jobsite by a ready-mix truck. The
material flows straight from the truck chute into the trench
47
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
c) Rock Excavation
Where rock is encountered in the trench at the level where the sewer pipe is
below the sewer pipe line and the over-excavation refilled with a suitable pipe
the depths specified above should be refilled with concrete, crushed stone or other
suitable material.
d) Excavation Backfill
such other grades as may be required. Backfilling, unless otherwise specified, should
be done with materials free from waste, objectionable organic matter, rubbish,
roads, etc. As far as possible try to carry excavation and filling simultaneously to
avoid double handling. Select and stack the required material in such a place that it
should not obstruct other construction activities. The excess or unwanted material
48
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
After completion of the compaction under blinding, tie beams and ground
slab. Back filling shall commence using similar excavated material. Care shall be
taken to remove bolder, vegetation’s and any other deleterious materials. But prior
to back filling, the compacted surface shall be accepted by the Engineer. The
thickness of the back fill shall not be greater than 300mm. The sub-grade once
approved, the excavated materials or any material source approved by the Engineer
shall be placed in layers not more than 300 mm thick followed by compaction test
when surface level is ready. In-situ dry density test (compaction test) shall be
performed at the rate indicated in the specification. Back filling followed with
a) General
where grade or alignment changes require offsets greater than those recommended
manufacturer for compatibility with the sewer pipe. Prior to installation sewer pipe
and fittings should be cleaned, inspected, and examined for defects. All
imperfections on the face of the spigot, tongue end or the shoulder should be cut
49
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
During the sewer main construction all open sewer main pipelines should be
sealed with appropriate plugs when actual construction is not in progress. Mud, silt,
gravel and other foreign material shall be kept out of the pipe and off the jointing
surface. All pipe laid shall be retained in position so as to maintain alignment and
joint closure until sufficient backfill has been completed to adequately hold the pipe
in place.
The sewer pipe, unless otherwise approved by the city, shall be laid up grade
from point of connection on the existing sewer or from a designated starting point.
The sewer pipe shall be installed with the bell end forward or upgrade. When pipe
laying is not in progress the open end of the pipe shall be kept tightly closed with an
approved temporary plug. Pressure sewer main installation will be approved only in
b) Jointing
All pipes shall be installed to the homing mark on the spigot. The city shall
be given an opportunity to check all joints in this manner before backfilling. Unless
otherwise specified, all joints of all drainage pipes are generally required to be soil
50
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
tight. Joints that will permit the transport of soil at any time during its service life
must be expected to cause problems related to erosion of invert and spring line
support.
a) System Inspection
Pipe installation, like any other engineered system, can benefit from frequent
performance of the pipe. Standard ASTM tests define the materials, processes and
procedures for determining in-place field density tests by the following methods:
sand cone, nuclear, sand replacement, water replacement, rubber balloon, drive
b) Field Testing
The engineer may require additional testing of the pipe’s deflection performance.
For pipes large enough for entry of personnel, diameter changes may be determined
by direct measurement. For smaller diameter pipes, a mandrel may be pulled from
51
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
manhole to manhole. As long as the deflection does not exceed the mandrel
In the event of isolated areas of deflection greater than specification limits, re-
rounding of the pipe with special equipment, without any excavation, should be
considered. Long lengths of pipe with deflection levels greater than permitted are
most likely due to compaction deficiencies. Material around the pipe may have to be
excavated and replaced with proper material, properly compacted. A pipe that has
not deflected to the point of reverse curvature can be re-rounded and reused.
installation. Air or water can be used, although air is the most common because of
safety considerations. Test requirements may vary from region to region, but most
require the pipe to be pressurized to at least 3.5 psi (24.1 kPa) and held for a period
of time based on the length and diameter of pipe. A small drop in pressure is usually
52
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
a) Roadway crossings
to construction.
Under normal conditions, sewer lines crossing under potable water supply
between the bottom of the water main and the top of the pressure sewer.
When local conditions are such that pressure sewer mains crossing under
water mains will have less than 457 mm (18 inches) of vertical separation the
pressure sewer main shall be concrete encased or installed within a carrier pipe for
potable water supply main. When pressure sewer mains cross over potable water
supply mains, additional protection of the potable water supply shall be achieved by
either providing adequate structural support for the pressure sewer main to
prevent excessive deflection of joints and settlement and centering the pressure
sewer main pipe at the crossing such that the joints will provide about 3 m (10 feet)
of clear distance from the potable water supply main. Under normal conditions all
pressure sewer mains shall be located with at least a 3 m (10 foot) horizontal
53
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
method of installation.
Operation and Maintenance costs for the reservoir have been broken down
1. Operations Labor –includes the normal daily visits to the site to perform
the Bureau of Utilities, this has been assumed as 6 hrs/d, 6 d/wk, 52 wks/yr.
normal conditions, pumping of tanks should be every 1-3 years based upon the
number of people using the reservoir. Generally, pumping will take around 30-
45 minutes.
life and replacement needs, the estimated costing of materials to be used and
54
RAMON MAGSAYSAY TECHNOLOGICAL UNIVERSITY
IBA, ZAMBALES
COLLEGE OF ENGINEERING AND ARCHITECTURE
55