BGAS Grade 1 Course
BGAS Grade 1 Course
-
rvrn
Training & Examination Services Granta
park, Great Abington, Cambridge CB1 6AL, UK
In Association with Waugh Technical & Education Services © Copyright
Waugh Technical & Education Services, 1999
WAUGH TECHNICAL_ & EDUCATION SERN'ICES
COURSE CONTENTS FOR PAINTIPAINTING INSPECTOR COURSE GRADE I
PAGE
Zones of an Offshore Structure Illustrations of Various Platform
Types Definitions and Abbreviations Offshore Working
Safety Offshore
L ,o t v r A-sTV-b"oMNc ~'t
I
- L
TWI ~? ~Ol
stabilizing colunin
S e a t a n k g r a v i t y
s t r u c t u r e
logging unit
drav.^works
shale shaker desanding and degassing unit
anchors
derrick
gear units
'"
elevating
/ racks
cranes
legs tilting ~hinges
legs
helicopter deck
living quarters
spud __ tanks
CASING OR TUBING
~ Pipes which are drilled through, them cemented in place to form a fixed pipe
through which the oil/gas will flow.
ACELLAR DECK
Deck at intermediate level or the first deck on the platform.
-C'ONDUCTOR
Lpr' "- ~ N4Q "4 ~\ -6 \ "C.61
The part of the structure that joins the
oil/gas we to the topsides pipework
~HELIDECK
Area designated for take off and landing of helicopters.
RISER
The part of the structure that joins the ;subsea pipeline to the topsides pipework.
SPIDER DECK
Braces between conductors, normally to be found within the splash zone.
XMAS TREE
Val.ve assembly connected to the conductor enabling the well to vice wireline
operators and enabling the well lo , be-closed ~M.~
OFFSHORE WORKING
Much of inspection work onshore applies to the offshore situation, excepting that the
environmental and working dangers created mean that safety procedures and working
practices are much more formal and must be strictly adhered to. Of the dangers and
problems created by the environment are:
Tidal changes
e. Drilling operations.
f. Production operations.
g. The handling and storage of acids, caustic alkalis, explosives, radioactive
and other dangerous substances.
Any other unusual or dangerous operation.
A list of all such persons must be placed where it can be read by others:
All personnel working offshore have a duty with regard to safety to themselves
and others.
Such stringent safety rules prevail offshore as extra dangers are in evidence.
Examples - Danger of falling into the sea, explosion, fire risk and the time involved in
getting people to hospital from the offshore situation.
10
WAUGH TECHNICAL & EDUCATION SERVICES
Being passed medically fit to work offshore is most important, a person must be fully
fit to work in what can often be a 'harsh environment, in addition when people fall ill
it can take some time for their removal to hospital. It is a requirement of the UKOOA
document - Guidelines for Medical Aspects of Fitness for Offshore Work that people
are passed as medically fit prior to attending emergency training courses.
Personnel must be passed as medically fit prior to working offshore and - Every three
years if less than 40 years of age. Every two years if
between 40 and SO years of age. Every year if over 50
years of age.
The final decision on medical fitness for offshore employment or as a visitor lies with
the operator who must heed the medical advice received.
14
EMERGENCY PROCEDURES
~ In an emergency an in_tennittant siren and flashing light means Prepare to Abd
the PI a tfo
an on rm.
'A continuous siren and red light means Abandon the Platform
SAFETY - ESCAPE ROUTES
When working in the above entry permits may be required these are in addition to the
hot or cold permits demanded.
In addition to an entry permit a competent person will be required to catry out gas
testing to check that in excess of [/o oxygen exi _sts_-'_._~ A stand by person must be
present at the point of entry in case of emergencies. A K9 sniffer is used to determine
m~'umum explosion levels.
,
Reference must also be made to the M.E.L. and O.E.L. contained in the C.O.S.H.H.
Regulations.
17
SCAFFOLDING
Regulations concerning scaffolding are to be found in the Construction (Working
Places) Regulations 1966 . The correct erection and safe use of scaffolding in an
offshore situation represents one of the greatest measures of safety that can be achieved.
Seaffolders must be green card holders (issued by C.LT.B.).
Each erected scaffold must be checked by a scaffolding supervisor who signs off a
Green tag when he considers the scaffolding safely erected. This tag is held in a plastic
wallet attached to the scaffold. If the supervisor does not consider the scaffold safe a
Red tag is displayed.
The S 1 1019 requires working platforms to be at least 65 cm wide, with a toe board 15
cm high where practicable. When the working height is over 2 m or when personnel can
fall into the sea three guard rails must be present. Safety nets are required when guard
rails are not practicable and a safety belt and line is required, when a safety net is not
practicable. Life Jackets are required for over the side working when there is a danger
of falling into the sea or when a responsible person considers they should be worn.
Scaffolding must be checked before use, at least every seven days and each time
adverse weather has occurred. Particular attention is paid to fixings and the condition
and placement of scaffolding~boards,1, When working in the splash zone boards are
removed as work finishes each day and replaced for work the following day.
Normally the erection of scaffolding would not normally be permitted at night.
Over the side safety measures in brief.
Guard Rails Safety Nets Safety
Belt and Line Life Jackets
Standby Boat
Radio Link to Standby Boat
j The usual type of fire offshore would by hydrocarbon which is capable of *ducing
thermal shock - that is, reach a temperature of 1250°C in a short time.
FLAME SPREAD SPECIFICATION
All materials used in building carry a flame spread classification. This is laid down by
the building regulations. BS 476 Part 7 lays down the method of assessing materials
so that they can be given a "Class" of flame spread. The method is dependent on the
distance a flame will travel across a sample of material of a given size. The classes of
flame spread are as follows:
19
B 51 'Class divisions are those divisions formed by bulkheads, ceilings and ~'
linings which comply with the following:
30 minute period of a standard fire test, the average temperature on the unexposed face
will not increase at any time during the first 15 minutes of the test by more than 139°C
above the initial temperature on the face nor shall the temperature at any point,
including any joint, rise more than 225°C above the initial temperature.
c. All materials entering into the construction and erection of B-15 class divisions
shall be non-combustible.
H-120 class divisions are those divisions formed by decks and bulkheads which comply
with the following:
a. They shall be constructed of steel or other equivalent material.
FIREPROOFING MATERIALS
Fireproofing to achieve a reduced or non existent flame spread can be by coatings or
material applied. Any term used to describe a fireproof co~ting means that it is
applied in order to slow down the tendency of heat and flames to pass across a
surface. There are two basic coatings used in fire protection
~. cementitious and intumescent, applications vary for the two systems and special
safety measures must be observed during application as some types are highly toxic.
In general fireproof coatings do not have anti-corrosive properties and are therefore
usually applied over anti-corrosion coatings, in order to bring about both non-rusting
and fire proofing qualities. Fireproofing also exists in the form of pre-formed panels,
mineral wool, foam etc.
CEMENTITIOUS FIREPROOFIN G COATINGS
Cement based system typically of portland cement and vermiculite, these can be
applied by spray, hawk and trowel or both depending on the system. Coating
thicknesses vary widely depending on the protection required eg. 10 mm for 1 hour
protection and 50 mm for 4 hours protection. Thicker coatings are usually applied to
mesh which is studded or pinned to the surface requiring protection. Cementitious
coatings are very alka.line, PH values can be as high as 12.5 and are very porous thus
usually requiring a Lseale~ cracking and spalling are likely defects. (This type is often
applied by grams per m2)
INTUMESCENT FIREPROOFING COATINGS
Most fireproofing offshore is by this method. Under heat typically around 200°C the
coating swells to many times its dry thickness and provides a barrier of carbonaceous
char. Thickness again depends on requirements. Some
systems require mesh to hold the char in position during a fire also to take account of
coating disbondment due to differential expansion between the steelwork and
coating. This type of coating is quite porous and requires sealing and epoxy type of
intumescent coatings are used extensively for offshore applications.
FIREPROOF SYSTEMS
The main considerations for choosing fireproof systems are as follows:
a. Heat barrier properties.
SAFETY COLOURS
24
~ T W I MY
SAFETY SIGNS
1 rr 1 V79,1
SAFETY SIGNS
This standard uses colours taken from BS 4800 references to identify what any
particular pipe or conduit is carrying.
Differing colours identify a particular liquid, gas or electrical service. This ensures
that during maintenance work, or in the event of fire or other emergencies even in
complex pipework systems it can be quickly established what those pipes are carrying,
and be traced to source in the event of the pipes having to be shut off.
Basic Identification is by painting the whole of the pipe, or, by painting bands of
colour or attaching coloured adhesive tape at all junctions, both sides of valves, wall
penetrations or wherever identification is necessary. Sometimes other bands of colour
are painted onto the specified base colour in order to more closely identify what the
pipe is carrying, say in the case of different types of water. :
BASIC IDENTIFICATION
Drainage
Electrical Services Orange 06-E-51
Fresh Water Auxili Blue ~ . 18-E-53
BRITISH GAS OFFSHORE PAINTING/COATING SPECIFICATIONS
The following three British Gas documents make up the technical specifications
which relate to the painting and coating of offshore structures. Changes to these
specifications are currently under consideration.
CP-C-155 - Coatings and Paints - Company Practices and Specifications.
BG/OS1PS/12-068 - Properties and Performance of Paints and Coating
The document CP-C-155 is the specification which defines the mi.nimum technical
requirements for the materials, surface preparation, application, testing and inspection
to be used on new works and maintenance painting and coating of structural steel,
decks, modules, production facilities, process equipment, piping, electrical equipment,
instrumentation, flares and conductors. It does not apnly to submarine pipelines,
submerged equipment, piping etc below - 2.5 m of L.A.T. But is applicable to primary
and secondary submerged structural steel. -
The document 12-06JB refers to paint, coating materials and testing, all must meet the
requirements laid out in 12-06/B.
Documents Where conflict arises between documents the order of precedence is as
follows,
1. Statutory requirements.
The contractor must verify that all paint and coating materials have been supplied by
one approved vendor. The vendor must supply up to date data and product safety sheets
prior to painting/coating.
Thinners of a quality and quantity recommended by the manufacturer may be used only,
and only under British Gas supervision.
Equipment For blast cleaning must meet the same requirements as for onshore work
Scaffolding Must be left in position for access and signed off as safe by green tag, every
seven days.
Equipment Protection and Masking Same as for onshore work and will include valve
spindles, glass, machinery cables, stainless steel pipework, gratings, control desks and
panels, exposed threads etc, plus any other items not being prepared and painted at that
time.
Cleaning up As for onshore work plus facilities for collection and disposal of waste as
this is not allowed to be dumped at sea.
Surface Preparation Ury Abrasive Blasting is preferred, other methods by the approval
of British Gas.
All blast cleaning carried out to BS 7079 (OS-59-00)
Minimum blast cleaning grade S.A. 2 1/2
Grade SA3 required during construction for internal surfaces of diesel,
potable water and sea water storage tanks, and for the internal coatings
on production caissons.
Amplitude range of 50 - 75 l.un unless otherwise specified. Blast
cleaning shall overlap existing coatings by SO mm in order to provide a
key.
WET BLAST CLEANING
When British Gas specify the use of wet blast cleaning the following agplies:
a.
1*-- Motive power must be pneumatic or hydraulic only.
b. Blast cleaning equipment must incorporate a water storage tank which can be
continuously agitated by mechanical means.
c. Pressure vessels must be accompanied by current test certificates.
d. The equipment must include an inline flow meter to measure the rate of delivery
of the water to the blast nozzle, a means of monitoring the total amount of water
transferred and a valve to allow rapid flushing of the tanks.
e. Water usage must not exceed 3 litres per minute but shall be at least 0.5 litre
per minute.
f. There must be a Company approved line communication facility between the
plant operator and wet blast operative.
g.
The area to be blast cleaned must be solvent washed by an approved technique before
blast cleaning commences.
All areas likely to be affected by the impingement of water and abrasive must be
securely masked and water and abrasive must be contained to stop contamination at
other areas.
The surface appearance must be equivalent to the required visual standards from BS
7079, as detailed in the relevant appendix.
30
i. Two surfaces must be available so that one surface can be blast cleaned while the
other is painted. Each area must be completely screened from the platform and
each other.
J.
k. Immediately on completion of blast cleaning and in any case within 1 hour the
surface must be pressure washed with fresh potable water, paying particular
attention to crevices.
The surfaces must then be dried with a clean squeegee and then blown
dry with clean compressed air at a delivery not less than 100 p.s.i.,
again paying particular attention to crevices. (This may not be necessary
when using moisture tolerant-coatings).
Itnmediately on completion of the drying process the surface must be
inspected by a Company representative. If approved, an approved
primer must be applied.
n.
Water lances must be a minimum 1 m in length.
NB. Because this specification does not approve the use of inhibitors,
slight surface discoloration is allowable. The primers used must only
replace those specified in the relevant appendices where wet blast
cleaning has been approved by the Company.
SURFACE DEFECTS
Same as for onshore work
BLAST CLEANING RESTRICTIONS
Finish blast cleaning restrictions may not be carried out when surfaces are less than
3°C above the dew point or when the RH is above 85%.
Brush application can be carried out with the prior permission of British Gas to areas
which cannot be sprayed.
* In the brushing of solvent based coatings care must be taken so that no lifting or
degradation of former coats occurs.
Surfaces not accessible to brush painting shall be painted by other suitable
means ensuring a uniform film of adequate thickness.
* The finished surface must be free from runs, sags etc, and the coating must be
thoroughly brushed into crevices, corners etc.
INSPECTION
CONTRACTOR INSPECTION AND TESTING RESPONS IBILITIES
The contractor is responsible for undertaking all inspection and testing required, and
to record these fully. 1
1
The contractor must maintain a daily log throughout the work programme and must
contain details of
Weather Conditions
The log should be signed off by the appropriate quality control or British Gas
personnel to indicate satisfactory completion of the work.
Personnel involved in the supervision of coating processes and the inspection of
coatings shall be qualified in accordance with the INSTITUTE OF CORROSION
standards (Not Operated).
British Gas has the right to inspect the contractors tools, materials, staging and
scaffolding, preparation/application and testing equipment, and the right to remove,
replace or rectify any items which do not meet the required standards. In addition they
have the right to inspect each preparation, painting and coating application. Where
this right is exercised subsequent work shall not proceed without permission.
British Gas have the right to condemn any surface preparation or coating which fails
to meet set standards.
Each coating must be inspected and subsequent coats must not be applied until
permission is given by the British Gas inspector.
SURFACE CLEANLINESS may be assessed against BS 7079 (OS-59-00).
Small steel reference panels should be prepared daily to the cleaning standard and
amplitude for the specification. These should be used as a visual comparator, for
cleanliness and as' a. means of calibrating . instruments for amplitude measurement.,
The surface amplitude is measured by direct assessment of replicas taken from the
surface (Testex tape with dial micrometer). .
RELATIVE HUMIDITY - DEWPOINT MEASUREMENT
A psychrometer shall be used to measure the relative humidity before and during blast
cleaning and painting.
FILM THICKNESS MEASUREMENT
Wet film thickness shall be determined in random tests as an indication of the D.F.T ,
except in the case of MIO systems where it is part of the control procedure.
D.F.T. of individual coats and the total coating system shall be checked against the
specification requirements.
`Destructive thickness testing may be required particularly where maintenance
I,painting is carried out over existing systems.
HOLIDAY DETECTION
Carried out as required by British Gas to an approved procedure. The voltage applied
will be that specified by the manufacturer. 100% holiday detection must be carried out
on the high build coatings applied to the submerged zone, splash zone, atmospheric
zone and conductors, and any defects found must be marked, repaired and retested.
Typical voltages - 5 volts per micron, 5 KV per mm.
ADHESION
Adhesion testing where required shall be undertaken by an approved method.
REPAIR OF REJECTED WORK
Damage to paintwork incurred at any stage of transit or installation, including site
welding operations, shall be prepared to the original quality and recoating carried out
in line with the appropriate specification.
Preparation shall extend SO mm on to the sound paintwork with 25 mm of sound
paintwork being lightly abraded to feather the region. Repainting shall then cover the
area, extending 50 mm on to the adjoining prepared paint surface.
Prior to the application of each coat, all damaged or rejected previous coats shall be
repaired.
British Gas may direct that blast cleaning is not carried out and that the surface is
prepared by hand or power tool cleaning, chipping or wet blasting.
INADEQUATE COATING THICKNESS
Areas shall be thoroughly cleaned and _abraded if necessary. Additional coats then
applied until they meet the required specification. These coats must blend in with the
final coating on adjoining areas.
CONTAMINATED SURFACES
Surfaces to be overcoated should be cleaned with an approved solvent where
contaminated, followed by washing of the whole surface with a liquid detergent in
fresh water (Tepol, Jizer, Citroclene) and then rinsed with fresh water.
COATING DAMAGE NOT EXPOSING STEEL SUBSTRATE
The coating around the damaged area suitably cleaned and chamfered to ensure patch
coating is continuous. The coating system then applied as required to build up to the
required specification thickness.
COATING DAMAGE EXPOSING STEEL SUBSTRATE
The damaged area re-cleaned to the original specified standard for that surface,
followed by priming with the specified coating. The re-cleaning shall extend 50 mm
on to the sound paintwork. The remaining coats applied to build up to the specified
thickness shall extend. 50 mm on to the sound paintwork. (The edges of the damaged
area to be feathered)
SELECTION OF COATINGS
Coating systems for offshore work are selected on the basis of the location of the work
to be carried out, the nature of the substrate, the temperature at which the component
operates and in the case of tanks etc., what they contain.
Coatings with (volatile organic compound) reduction are being developed by the paint
industry. This means in general terms that the new coatings are water based. They will
play an ever increasing role in paint usage in the coming years, as they have the
advantage of health and safety considerations and are kinder to the environment.
The contractor shall ensure that the paint manufacturer provides a technical and safety
specification which addresses the following.
* Paint system type of classification.
* Composition of the products.
* Test methods and results which prove the suitability of the coating
in terms of the service environment and design life of the
substrate to be treated.
* Previous relevant experience.
* Substrate preparation, coating application, and drying, curing and
overcoating procedures.
* Health and safety information to be operated during application of the coating
system.
This information shall be agreed with quality assurance and made available to the
painting contractor.
/
PERFORMANCE
I
P
TESTING
aint systems offered for the protection of the topside, atmospheric, splash and
submerged zones shall be evaluated using the following tests.
TOPSIDE ZONE SYSTEMS
INITIAL ADHESION TEST
(BS 3900 Part 10, pull of test for
adhesion). Intercoat adhesion shall be in
excess of 250 psi. Cohesive adhesion
shall be in excess of 200 psi. Cross cut
testing shall also be carried out.
RESISTANCE TO SALT SPRAY
(BS 3900 part F4 resistance to continuous salt spray).
Results shall be reported after 1000, 2000 and 3000 hours exposure with
particular reference being made to blistering and undercutting.
PROHESION TESTING
Panels of the paint system shall be submerged to exposure in a prohesion
test cabinet cycling between 1 hour salt spray and 1 hour drying at 35°.
Prohesion test results shall be reported after 1000, 2000 and 3000 hours
with particular reference being made to blistering and undercutting.
ACCELERATED WEATHERING
Resistance to weathering shall be assessed by using the three tests listed below:
a. BS 3900 Part F3 "Resistance to Artificial
Weathering" (Enclosed carbon arc). ~ --`"
b. A.S.T.M.G. 53 - 84 using a continuous UV cycle
produced by LTVA tubes wave length range 315 -
400 nm operating at a cabinet temperature of 50°C.
c. A.S.T.1vLG. 53 - 84 as for the previous test but
using LTVB tubes with a wave length of 270 - 315
nm.
Results shall be reported after 500, 1000, 2000 and 3000 hours, with
particular emphasis on colour change, loss of gloss, challdna or c_rang of
the paint film.
46
RESISTANCE TO MOI STURE PERMEABILITY
Initial adhesion test Resistance to salt sp 'ray Prohesion testing Resistance to cold check
cycling Resistance to environmental cycling
In addition Resistance to Impact Damne Which shall be assessed according to
ASTM 14-77 using a punch hammer type indentor,
, which will accomodate a 14.3 mm diameter ball bearing and be equipped
with a minimum impact weight of 1 Kg. Minimum impact values shall
be specified by the paint manufacturer. Acceptance coatings shall not
exhibit any excessive disbonding around the impact area. Impact areas
shall be tested for failure using a holiday detector set a &voltage of 125
v per 25 um of coating thickness (this thickness relates to coating before
impact damage) and is measured using an approved thickness gauge.
SPLASH AND SUBMERGED ZONE SYSTEMS
The following tests are as for the topside and atmospheric zone systems.
v
Initial adhesion test
Using a tidal simulator the test panels me positioned to where 1/4 of the panel is
immersed. After 6 hours the crank immerses 3/4 of the test panel and then returns to 1/4
of the panel being immersed after 12 hours. Two complete cycles (24 hours) are carried
out. At the end of the test remove the panels and examine visually. .
Note the time from the start of the test when the film becomes resistant to
delamination and ridge splitting.
The drying paint film shall resist delamination, show less than 20% thinning due to
ridge formation and exhibit no porosity within the cured paint system.
Resistance to Cathodic Disbondiat
There are two types of test namely static and cyclic which are used to asses the
comparative resistance of coatings in a damaged condition to loss of adhesion and
blistering when exposed to . cathodic protection. The testing procedure relates closely
to that described in BS 3900 Part F10 1985 (Cathodic Disbonding
51
PREPARATION OF STEEL TEST PANEL SUBSTRATES
After blast cleaning panels shall be naturally weathered according to BS U 148, 14 for
a period of 2 to 3 months to produce a surface which is evenly rusted but not si '
cantly pitted an equivalent to BS 7079 rust grade C. Prior. to coating, panels shall be
hand or power wire brushed to achieve a CSt3 finish.
PREPARATION OF WET SALT CONTAMINATED SUBSTRATES
Steel panels shall be prepared by the Swedish SO finish as described '
Before coating, panels shall -be immersed in a 3°f° solution of sodium chloride,
immediately removed and allowed to drain for 2 to 3 minutes. The surface produced
small be damp but not running with water any may show slight flash rusting, before
application of the first coat of paint.
These salt contaminated test panels are for use in evaluating coating systems for the
atrnospherlc. sula sh and subm zones and are used as a comparator
- - ,
for levels of acce ptabl e pe rmance against the test panels described at the top of this
page.
COATING SYSTEMS FOR SUBMERGED ZONE
COATING SYSTEM FOR SUBMERGED ZONE PRIMARY AND SECONDARY
STRUCTURAL STEEL WITH ANTI-FOULING SYSTEM APPLIED DURING
CONSTRUCTION WORK AND MAINTAINING AND REPAIR WORK
ONSHORE
SCOPE
Anti corrosion system from -Z.5 m L.A.T. (allowing 150 mm overlap) to seabed.
Anti-fouling system applied between +8 m L.A.T. and the seabed including part of
the splash zone.
EXCLUSIONS
Anti corrosion systems - Non submerged areas, risers, conductors and J
tubes. Anti fouling systems - J tubes above - 2.5 m of L.A.T., risers,
temporary attachments.and areas where alternative anti fouling systems or
cladding have been specified.
Minimum SA 2%z at the time of
Surface Preparation -
coating
Primer - Epoxy 30 pm min DFT
SCOPE As stated in the title except where area is fireproofed. The coating shall
extend 150 mm on to the splash zone protection.
For maintenance and repair onshore and offshore using blast cleaning procedures the
system is the same as above.
For maintenance and repair onshore and offshore using mechanical procedures a
different primer is used and therefore a tie coat is not required. This system is set out
below.
SCOPE
Structural steel, decks (not covered by screed system), pipework, vessels, tanks,
ductwork and fittings which operate up to 100°C (continuous dry service
temperature).
EXCLUSIONS
Walkways, decks (screed covered), underside of cellar decks, internal surfaces of
tanks and vessels, corrosion resistant materials.
Surface Preparation Minimum SA 2 %z at the time of
Primer coating
Zinc Rich Epoxy
Tie Coat Epoxy
1 st Coat Epoxy M10. Pigmented
2nd Coat E o Hi Build
Finish Coat Urethane Acrylic
Typical D.F.T. of system before finish "
coat 325 m
Note Finish coat to be applied to manufacturers recommended D.F.T.
* First. and second coat shall be of contrasting and neutral colours.
* Second coat shall be compatible for fuush coat to achieve good opacity.
SCOPE
Structural steel, decks (not covered by screed system), gipework, vessels, tanks,
ductwork and fittings which operate up to 100°C (continuous dry service
temperature).
EXCLUSIONS
Walkways, decks (screed covered), underside of cellar decks, internal surfaces of
tanks and vessels, corrosion resistantmate~ri4ls.
Surface Preparation Muoiw um ST3 at the time of
Primer coating
Hi "
1st Coat Epoxy, M.I.O. Pigmented
2nd Coat Epoxy Hi Build
Finish Coat Urethane Acrylic
Typical D.F.T. of system before
300
finish coat
* Second coat shall be compatible for finish coat to achieve good opacity.
* Coating applied in accordance with the appropriate colour schedules.
7
DFT Total 3mm +
100~n
ALTERNATIVE, Power tool cleaning to ST3 and non skid tiles (3 mm)
-
LIGHT DUTY
63
COPPER-NICKEL,_ ALUNHNIUVI AND OTHER NON FERROUS
CORROSION RESISTANT MATERIALS
SCOPE Where coating is required for cosmetic and colour coding purposes only.
Eg. Fire Water Pipework.
Surface Preparation Degrease, Lightly Abrade, Wash with Min
fresh water and dry. DFT
Primer Etch Primer
1st Coat Urethane or Epoxy
Top Coat Urethane or Epoxy 70 p.m
Total DFT 70
INSTRUMENTS/ELECTRICAL EOUIPIYIENT
COATING SYSTEM FOR INSTRUMENTS. ELECTRICAL EQUIPMENT
AND ASSOCIATED EQUIPMENT APPLIED DURING CONSTRUCTION.
MAINTENANCE AND REPAIR WORK.
SCOPE
Instruments and associated equipment, and applied to manufactured items such
as transmitters, control panels, and to site fabricated stands. switchgear and panels.
Electrical
EXCLUSIONS
Self coloured plastic or plastic compound components.
Aluminium. surfaces. For aluminium surfaces refer to copper, nickel, aluminium, etc.,
Data Sheet.
Note Items which are to be located in fully enclosed environmentally controlled areas
may, with the agreement of the Company, be painted to the Vendor's standard system.
Surface Preparation Minimum of ST3 at the time of coating
High Solids Epoxy, Aluminium
Primer
Pigmented
1 st Coat Epoxy Hi Build
Finish Urethane Acrylic or
Typical D.F.T. Before Application of
250 m
Finish Coat
CORROSION-RESISTANT MATERIAL SURFACES AND
GALVANISED SURFACES
All gratings, ladders, cages, handrails and supports, fences, stairway gratings,
stairboards, walkways, kick plates, ductwork and~ er specified, items will be hot dip
galvanised in compliance with BS-729. ,/.
Solid galvanised surfaces (not rungs, gratings, dc) shall be overpainted to extend
their life.
Small areas of galvanised coating damaged by cutting, welding, drilling or any
preparation during fabrication, erection, transportation or installation, shall be
thoroughly cleaned by an approved technique, and the area of damaged
galvanising shall be mechanically cleaned. The areas so prepared shall then be
renovated in accordance with this document.
Stainless steel will not normally be painted. However, if for any reason such
as chloride contamination, colour coding, or high temperature service this has
to be effected, then the systems specified shall be followed.
If for similar reasons stated above, copper-nickel or other nickel alloys have
to be painted, then the systems specified shall be followed.
Care shall be taken to ensure that copper-nickel is not blast cleaned. Thorough
degreasing shall be undertaken. _
GALVANISED STEEL SURFACES
COATING SYSTEM FOR GALVANISED STEEL SURFACES
APPLIED DURING CONSTRUCTION WORK
Z 911 1
CONDUCTORS AND RISING MAIN CAISSONS
COATING SYSTEM FOR CONDUCTORS AND RISING MAIN CAISSONS
(WITH ANTI-FOULING SYSTEM) AND JOINTS BETWEEN CONDUCTORS
APPLIED DURING CONSTRUCTION AND MAINTENANCE WORK.
Surface Preparation 1
Minimum SA 2 /z at the time of coating
Coating 1, 2 or 3 Coats Hi Build Epoxy Urethane
Tie Coat According to Paint Manufacturer 2 mnd
-
Anti Fouling 3 or 4 coats compatible stem
Typical
2 mm -
D.F.T.
Note: 12-06/A States 2 mm DFT. CP-C-155 states 3 mm DFT.
ALTERNATIVE COATING
:; Te ,
INTERNAL COATINGS
MAINTAINANCE ONSHORE AND OFFSHORE
The same system, is applied as for new construction work except
surface preparation is blast cleaning to SA 2%2 or mechaifical cleaning
to ST 3.
NOTE Mechanical cleaning must be kept to an absolute minimum.
NOTE The system must comply with d meet water byelaws advisory
council requirements. The tank cleaning procedure shall meet the
requirements of the H.S.E.
69
COATING SYSTEM FOR THE INTERNAL SURFACES OF PRODUCTION
CAISSONS APPLIED DURING CONSTRUCTION WORK
SCOPE As stated in title.-- -
EXCLUSIONS All other areas. _
C.S. CRUDE STORAGE TANK FLOOR & 1.5 M OF TANK SHELL AND ROOF
SPACE FOR FIXED ROOF TANKS
Surface Preparation Min SA 3 at the time of
Primer coating
Red'Oxide 2 PK Epoxy 1 Coat 50 pm
Finish 2 PK Epoxy Coal Tar 3 Coat X 125 w
Typical D.F.T. 4 2 5 a +
Note - Includes roof and all fittings down to 1.5 m below top of upper shell strake.
BS 4800
SERVICE COLOUR CODE
NON-STRUCTURAL STEEL
BS 4800
SERVICE COLOUR
CODE
Tanks and vessels Off White 10-B-15
VBS 1710
Specification for Identification of Pipelines & Services.
/BS 3416 Specification for bitumen-based coatings for cold :
application, suitable for use in contact with potable water.
V/ BS 381C Specification for Colours for Identification, Coding & Special
Purposes.
,/BS 3900 Me~ thods,of tests ,for.paints_: Part D5: Measurement of
specular gloss of non-metallic paint films at 20°, 60° and 85°.
,r BS 4800 Specification for paint colours for building purposes.
,iBS 5378 Safety signs and colours. .
BS 5493 Code of practice for protective coating of iron and steel structures
against corrosion.
BS 5750 Quality Systems.
BS 5252 Framework for colour co-ordination for building purposes.
75
BS 6920 Suitability for non-metallic products for use in contact . with water
intended for human consumption with regard to their effect on the
quality of the water.
BS 7079 Preparation of steel substrates before application of paints and
related products.
Other Publications
Paintmakers Association of Great Britain Ltd publication
Personnel Protection; advice for the use of marine paints and compositions.
OCMA (Oil Company's Materials Association) publication.
MEC of BP200 Recommendations for the protection of diesel engines in
hazardous areas.
Health & Safety Executive
HSE Publication Occupational exposure Limits. EH40
HSE Publication Offshore Installations - Guidance on Design, Construction and
Certification.
Steel Structures Painting Council
(SSPC) Pittsburgh Good Painting Practice and Surface Preparation. BGE &
P Documents
140 Units
Urethane Acrylic
ST3
High Solids Aluminium Epoxy x 125 pm
300 lrm
r Not reqd for small areas if overcoated quickly
Midcoats - l st Epoxy with M. L O. 2nd Epoxy High Build Finish coat omitted if under
insulation.