Lusail Katara Hotel, Lusail District, Doha INSPECTION REQUEST LOG Date 7/8/2016

The document is an inspection request log from Lusail Katara Hotel in Doha, Qatar dated July 8, 2016. It lists 13 inspections of concrete counterweight blocks in areas T5-1 and T5-3, including inspections of reinforcements before closing formwork, formwork before pouring concrete, and witnessing the concrete pouring. The inspections covered the first and second layers of construction at ground levels 42-43.

Uploaded by

edla3710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
89 views

Lusail Katara Hotel, Lusail District, Doha INSPECTION REQUEST LOG Date 7/8/2016

The document is an inspection request log from Lusail Katara Hotel in Doha, Qatar dated July 8, 2016. It lists 13 inspections of concrete counterweight blocks in areas T5-1 and T5-3, including inspections of reinforcements before closing formwork, formwork before pouring concrete, and witnessing the concrete pouring. The inspections covered the first and second layers of construction at ground levels 42-43.

Uploaded by

edla3710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

LUSAIL KATARA HOTEL , LUSAIL DISTRICT, DOHA

INSPECTION REQUEST LOG date 7/8/2016

SURVE
DATE OF DATE OF
REV. TIME OF Y
S.No INR NO. SUBMISSIO INSPECTIO DISCIPLINE AREA LOCATION ACTIVITY DESCRIPTION REF. DRAWING NO. CONSULTANT REMARK SIGNATURE QC REMARKS QC NAME & DATE
NO. INSPECTION REPOR
N N
T NO.

KH-TP2-HBK-INR-CV- T5-AREA 3 (GL: 42-43/ A- COUNTERWEIGHT BLOCK - INSPECTION FOR REINFORCEMENTS FOR CONCRETE
8 0 6-Aug-16 7-Aug-16 5:00 AM CIVIL T5
3123 C) - 2ND LAYER REINFORCEMENT BLOCK PRIOR TO CLOSE FORMWORK

KH-TP2-HBK-INR-CV- T5-AREA 3 (GL: 42-43/ A- COUNTERWEIGHT BLOCK - TO INSPECT FORMWORK FOR CONCRETE BLOCK PRIOR
9 0 6-Aug-16 7-Aug-16 7:00 PM CIVIL T5
3124 C) - 2ND LAYER FORMWORK TO CONCRETE POURING

KH-TP2-HBK-INR-CV- T5-AREA 3 (GL: 42-43/ A- COUNTERWEIGHT BLOCK -


10 0 6-Aug-16 7-Aug-16 8:00 PM CIVIL T5 TO WITNESS POURING OF CONCRETE BLOCK
3125 C) - 2ND LAYER CONCRETE

KH-TP2-HBK-INR-CV- T5-AREA 1 (GL: 42-43/K- COUNTERWEIGHT BLOCK - INSPECTION FOR REINFORCEMENTS FOR CONCRETE
11 0 6-Aug-16 7-Aug-16 5:00 AM CIVIL T5
3126 M) - 1ST LAYER REINFORCEMENT BLOCK PRIOR TO CLOSE FORMWORK

KH-TP2-HBK-INR-CV- T5-AREA 1 (GL: 42-43/K- COUNTERWEIGHT BLOCK - TO INSPECT FORMWORK FOR CONCRETE BLOCK PRIOR
12 0 6-Aug-16 7-Aug-16 7:00 PM CIVIL T5
3127 M) - 1ST LAYER FORMWORK TO CONCRETE POURING

KH-TP2-HBK-INR-CV- T5-AREA 1 (GL: 42-43/K- COUNTERWEIGHT BLOCK -


13 0 6-Aug-16 7-Aug-16 8:00 PM CIVIL T5 TO WITNESS POURING OF CONCRETE BLOCK
3128 M) - 1ST LAYER CONCRETE

1 OF 1