Please note that time temperature and concentration are interdependent on each other, thus
set the parameters accordingly.
EQUIPMENT :
Plastic or FRP lined M.S. tanks/containers should be used. Where heating of the bath is required
then Teflon coated electric immersion heater should be used or external heating can be employed,
but care should be taken that temperature does not exceed 45C.
II. SWABBING/BRUSHING
Concentration:- For heavy contamination : 1:1 or 1:2 with water
For medium contamination : 1:3 or 1:4 with water
For light contamination : 1:5 or 1:6 with water
Prepare above solution of SCALGUN-B in a Plastic Container or FRP lined MS tank, then dip
brush or cloth in this solution and apply on the contaminated surface and leave solution for 2 to 5
minutes till surface is completely clean then wipe clean with cloth soaked in water. For removal of
heavy soils, scrubbing or wire brushing is advisable. This will speed up soil removal. This process
can also be adopted before dipping process in cases of heavily soiled surfaces to extend life and
strength of bath solution of dipping tank.
( P.T.O.)
ISO 9001: 2008 Ref.No.FM/CR/01
The above process should be repeated if necessary, in cases where rust or oil still remains after first
application. Parts can then be processed further for phosphating or they should be dried
immediately and RUST PREVENTIVE such as ASFOSIL DW-95 should be applied by brush or
cloth if parts are to be preserved or stored.
PRECAUTIONS:
1) Use Rubber/PVC gloves while handling with this solution.
2) If SCALGUN-B is splashed on skin or eyes wash off with plenty of water.
NON-WARRANTY: The information in this bulletin is based on our experience and tests which we believe
to be reliable, but offer no guarantee and accept no responsibility for operations not under our direct control.