Breif Note On Proposed Lift / Gravity Scheme To Feed Annamayya Project Reservoir / Ayacut From GNSS Canal
The document proposes a lift scheme and gravity scheme to feed water from the GNSS Canal to the Annamayya Project Reservoir and ayacut. The lift scheme would require 5.94 MW of power to pump 2 TMC of water over 30 days through a 2.5m diameter, 2km long pipe at a total head of 22m, at an estimated cost of 50 crores. Alternatively, a 2km long gravity channel carrying 160 cusecs could deliver 0.5 TMC to the ayacut over 30 days and improve groundwater recharge.
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
60 views
Breif Note On Proposed Lift / Gravity Scheme To Feed Annamayya Project Reservoir / Ayacut From GNSS Canal
The document proposes a lift scheme and gravity scheme to feed water from the GNSS Canal to the Annamayya Project Reservoir and ayacut. The lift scheme would require 5.94 MW of power to pump 2 TMC of water over 30 days through a 2.5m diameter, 2km long pipe at a total head of 22m, at an estimated cost of 50 crores. Alternatively, a 2km long gravity channel carrying 160 cusecs could deliver 0.5 TMC to the ayacut over 30 days and improve groundwater recharge.
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2
Breif Note on Proposed Lift / Gravity scheme to feed
Annamayya Project Reservoir / ayacut from GNSS Canal
The Annamayya Project Reservoir is located at Badanagadda Village of Rajampeta Mandal in Y.S.R.Kadapa District.The Annamayya Project Main Canal is crossing the GNSS Main Canal at Km 167.866 of Package-6 under Phase-II of GNSS. A lift scheme was proposed to feed the Annamayya Project Reservoir earlier. The details of the Lift scheme is as follows Gross Storage Capacity of Annamayya Project Reservoir : 2.234 TMC Proposed Capacity of Water to lift from the GNSS main canl to the Reservoir : 2.00 TMC Assumed number of days for pumping : 30 days Assumed pumping per day : 2 X 11574/30 = 772Cusecs or say 800 cusecs Discharge required to pump 2 TMC in to the Reservoir in 800 Cusecs/day or 30 days : 23 Cumecs/day Available water level in the canal : +187.329 Bottom level of the pump : +185.329 Platform level of the pump : +189.700 Delivery Level at cistern at Annmayya Project Reservoir Forshore : +204.600 Static Head : 17.27m Losses : 4.67m Total Head required : 21.941m or say 22m Total Power required : 5.94 Mw Diameter of the pipe : 2.50m No of rows : 2Rows Length of Pipe : 2.00Km Tentative Cost as per SSR 2012-13 : 50 Crores
Ayacut proposed under Gravity
The Annamayya Project ayacut can be directly irrigated by excavating a Leeding channel from GNSS Main Canal at Chainage Km167.860 for length of approxmatley 2.00Km with carrying capacity of 160Cusecs similar to the existing Annamayya Project Main Canal. Accordingly nearly 0.5 TMC of water can be drawn by way of Gravity through out the leeding channel from the GNSS Main Canal over period of 30 days to feed the Annamayya Project ayacut to improve the Ground water and to recharge six Minor Irrigation Tanks available with in the ayacut of Annamayya Project.