100% found this document useful (1 vote)
2K views2 pages

Gantry Piling - Method

The document describes the process of constructing cast-in-situ bored piles using a piling gantry. Key steps include: 1) Fabricating a piling platform with rigs, mixers, and a crane to facilitate piling work. 2) Driving a steel liner into the ground in sections and boring soil out with a bailer to reach the founding level. 3) Lowering prefabricated reinforcement cages into the borehole in sections and securing them together. 4) Concreting the piles using the tremie method by pouring concrete from the bottom up to prevent soil from entering the borehole. 5) Repeating the process by moving the gantry

Uploaded by

naseeb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views2 pages

Gantry Piling - Method

The document describes the process of constructing cast-in-situ bored piles using a piling gantry. Key steps include: 1) Fabricating a piling platform with rigs, mixers, and a crane to facilitate piling work. 2) Driving a steel liner into the ground in sections and boring soil out with a bailer to reach the founding level. 3) Lowering prefabricated reinforcement cages into the borehole in sections and securing them together. 4) Concreting the piles using the tremie method by pouring concrete from the bottom up to prevent soil from entering the borehole. 5) Repeating the process by moving the gantry

Uploaded by

naseeb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

1.

CONSTRUCTION OF CAST-IN-SITU BORED PILES USING PILING GANTRY: -

We propose to carry out bored piles by end-on method using travelling piling platform
/ gantry. The piling platforms are equipped with piling rigs, concrete mixer, genset,
etc. required for carrying out boring and concreting works. A derrick crane of about 1
T capacity is also mounted on piling platform to facilitate handling of construction
materials required for the piling work.

Initially, the piling platform is fabricated / assembled on the existing berth or land
such that the front portion is supported at the end, and cantilevered upto the first row
of piles.

Initially MS liner/Casing of adequate  length is accurately pitched, held in position


with suitable guides and  driven into the ground. Thereafter additional lengths of MS
liners (1.0 to 1.50 m length) are added  and  driven till  refusal. Thereafter, the soil
within  the  liner  is bored out by flap valve bailer, till the boring is slightly deeper than
the casing. At this stage additional length  of casing is welded, and driven down.
This sequence of lengthening  the  liner, boring within, and driving is  continued till
the bottom of the casing reaches the scour  level,  or refusal whichever  occurs
earlier. Thereafter,   further boring is carried out by bailer upto the founding level. If
rock is encountered, the same is loosened by chiselling  and removed  by  Bailer
boring. After reaching  the  founding level, the bottom of the bore is cleared by short
strokes of the bailer  to remove the finer  fragments  and sediments. While carrying
out the boring, the pile bore is always  kept filled  with Bentonite slurry of adequate
specific  gravity to avoid blowing/piping of soil/sand into the  pile  bore. Before  the
pile is concreted, windows of suitable size  are cut in the MS liner at the desired cut-
off level of pile  to facilitate overflow of concrete till good concrete is available at the
cut off level.

The specified reinforcement for the piles will be  prefabricated  into cages of
convenient lengths, and the  rings  are tack welded to the main reinforcement to
provide rigidity to the  cage. Concrete/cement mortar roller cover blocks  will be
provided  to the cage at intervals of about  two  metres suitably  staggered. The
prefabricated reinforcement cages are  properly tack welded besides securing them
by  binding wire. The Reinforcement cages are then lowered into the pile bore.  After
the first cage is lowered into the pile  bore, the same is temporarily held in position by
a cross bar, and the  next length of cage is lifted into  position,  aligned with  the
bottom cage, the laps are suitably matched  and  secured  together by binding wire,
and suitably  tack  welded. Thereafter the  cage is lowered into the bore and  held  in
position to facilitate joining the next length of the  cage. The  sequence  is repeated
till the  reinforcement  cage  is provided to the depth as shown in the drawings.
The piles are concreted by Tremie method as indicated  hereunder:-

A  tremie  pipe of 200 mm dia in  suitable  lengths  with screwed  joints is lowered in
the bore hole  upto  the founding level of the pile.

a) The top end of the tremie pipe is screwed on a Steel Funnel shaped hopper. The
bottom of the funnel will be closed with a steel plate.
b) The funnel is filled with fresh concrete having a slump of 150mm to 200mm with
maximum size of aggregate 20/25mm.

The steel plate/plug provided at the bottom of the funnel is removed, and the
concrete is allowed to flow down the tremie  in  a continuous column. As the
concrete  flows down,  the tremie pipe is slightly raised  to  facilitate deposition  of the
concrete at the bottom of  the  bore hole;  and batches of fresh concrete are poured
into  the funnel.  Thereafter concreting is done in a continuous manner  upto  the
required level. While  doing  so,  it will always be ensured that the bottom of the
tremie pipe is within the concrete already laid by about 2 Mtrs.to avoid mixing of
fresh concrete with the bentonite slurry. The concreting is allowed to overflow
through the windows provided in the MS liner till fresh concrete is available at the
cut-off level.

The top of the piles are provided with a steel plate and wheel blocks are mounted on
it. The Gantry is rolled forward on these wheel blocks to the required location and
piles are constructed. The newly constructed piles are suitably braced together to
eliminate any disturbance. A set of wheel blocks are placed on the completed piles,
the piling platform is rolled forward on to the location of next row of piles. This
sequence of construction of piles, providing bracings, placement of wheel blocks,
and forward movement of the gantry supported thereon for construction of next row
of piles.

The pile muffs are constructed using the derrick mounted at the rear end of the piling
platform. The RCC beams are precast in the casting yard and are transported to the
berth location. These precast elements are placed in position and insitu concrete for the
deck is done

You might also like