The document reports on three trials conducted to test different rolling patterns for compacting dense bituminous macadam on a roadway section. Trial I found that one high vibration pass followed by one plane pass achieved 98.37% compaction and was the best pattern. Trial II determined two passes of high vibration followed by one plane pass achieved 97.37% compaction. Trial III concluded that four passes of low vibration achieved 97.73% compaction but two passes of pneumatic tired roller followed by one plane pass achieved the highest compaction of 99.13%. The best overall pattern from Trial I is recommended.

Uploaded by

naseeb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
605 views1 page

DBM Trail Stretch

The document reports on three trials conducted to test different rolling patterns for compacting dense bituminous macadam on a roadway section. Trial I found that one high vibration pass followed by one plane pass achieved 98.37% compaction and was the best pattern. Trial II determined two passes of high vibration followed by one plane pass achieved 97.37% compaction. Trial III concluded that four passes of low vibration achieved 97.73% compaction but two passes of pneumatic tired roller followed by one plane pass achieved the highest compaction of 99.13%. The best overall pattern from Trial I is recommended.

Uploaded by

naseeb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

Continental Engineering Corporation

1st Floor, Y.S.Reddy Complex, Ram Nagar Extension, Anantapur-515 001. A.P.
Phone: 08554-276547, Fax: 08554-276548.

ABSTRACT OF TRIAL REPORTS

Trail I: At Km. 357.910 to Km. 357.810 LHS, DBM 1st Layer

% of Compaction Average core


Rolling Pattern adopted Remarks
Achieved by NDG compaction
1 Plane Pass 93.80 < 98%
3 Low Vibration 95.96 99.7 < 98%
1 High Vibration 98.37 > 98%
2 PTR + 1 Plane Pass 99.97 > 98%

Trail II: At Km. 357.810 to Km. 357.700 LHS, DBM 1st Layer

% of Compaction Average core


Rolling Pattern adopted Remarks
Achieved By NDG compaction
1 Plane Pass + 2 Low
96.30 < 98%
Vibration
2 High Vibration 97.37 99.08 < 98%
2 PTR + 1 Plane Pass 99.67 > 98%

Trail III: At Km. 357.700 to Km. 357.600 LHS, DBM 1st Layer

% of Compaction Average core


Rolling Pattern adopted Remarks
Achieved by NDG compaction
1 Plane Pass 93.59 < 98%
4 Low Vibration 97.73 99.3 < 98%
2 PTR + 1 Plane Pass 99.13 > 98%

CONCLUSION:

Rolling Pattern of Trail I is comparatively better and satisfies the requirements.