Genenral Abstract of Cost PC-I Cost (Million)

This document contains cost estimates for various infrastructure projects including: 1) Widening and rehabilitation of roads and streets in villages totaling $34.62 million. 2) Upgradation of a canal patrol road including excavation, concrete work, drainage, signage and road markings for $23.48 million. 3) Estimates are also provided for items like dismantling concrete, laying sewer pipes, road construction and painting totaling several additional millions.

Uploaded by

Khan Engr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
96 views22 pages

Genenral Abstract of Cost PC-I Cost (Million)

This document contains cost estimates for various infrastructure projects including: 1) Widening and rehabilitation of roads and streets in villages totaling $34.62 million. 2) Upgradation of a canal patrol road including excavation, concrete work, drainage, signage and road markings for $23.48 million. 3) Estimates are also provided for items like dismantling concrete, laying sewer pipes, road construction and painting totaling several additional millions.

Uploaded by

Khan Engr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 22

-

GENENRAL ABSTRACT OF COST

PC-I Cost
S. No. Description
(Million)

Widening & Rehabilitation of Char Pul Road Village


1 16.75
pirpiai

3 Construction of Zahoor Korona Street Moh: Janabad 4.74309872878

4 Construction of Drain from pirpiai stop to nano pull. 5.68555458781


5 Construction of Drain at pirpiai main khwar 0.72104352
Construction of Hayat Gul Korona Street Mohallah
6 0.52738978038
Janabad
Construction of Shahid Khan Korona Street Mohallah
0.52488071175
Janabad
7 Construction of Rafiq Korona Street Mohallah Janabad 0.74526056989
Construction of irfan gafar house to karnal betak Street
8 1.53344678599
Mohallah Misken Khel
Construction of Bas Ali Jan korona Street Mohallah
9 0.74526056989
Kamar Khel
Construction of Nadr Kor to Shrikh Derai Mohallah Baba
10 2.63685177369
khel
Sub Total (A) 34.62
Peshawar Uplift Programme ADP No. 1111 / 130647 (2014-15)

Up-Gradation/Improvement and widening of Canal Patrol Road Along Warsak Gravity Canal From RD 55+000 To 58+000 (Package- I)

ITEM WISE COMPARATIVE STATEMENT

BOQ Revised Diffirence


S. No. Item No Description Unit Rate Total Amount
Qty Amount Rs. Quantity Qty Amount Rs.
(Rs)

1 #REF! #REF! m2 20 5577.69 111553.8 #REF! #REF! #REF! #REF!

2 #REF! #REF! m3 260 1610.31 418680.6 #REF! #REF! #REF! #REF!

3 #REF! #REF! m3 30.195 0 0 #REF! #REF! #REF! #REF!

4 #REF! #REF! m3 1800 1917.62 3451716 #REF! #REF! #REF! #REF!

5 #REF! #REF! m3 2200 2674.91 5884802 #REF! #REF! #REF! #REF!

6 #REF! #REF! m3 16514 976.74 16129884.36 #REF! #REF! #REF! #REF!

7 #REF! #REF! m3 18600 697.67 12976662 #REF! #REF! #REF! #REF!

8 #REF! #REF! m2 50 3806.4 190320 #REF! #REF! #REF! #REF!

9 #REF! #REF! m2 135 14288.56 1928955.6 #REF! #REF! #REF! #REF!

10 #REF! #REF! m3 615 358.26 220329.9 #REF! #REF! #REF! #REF!

11 #REF! #REF! m3 4860 200 972000 #REF! #REF! #REF! #REF!

12 #REF! #REF! m3 6470 102 659940 #REF! #REF! #REF! #REF!

13 #REF! #REF! m3 517 28.14 14548.38 #REF! #REF! #REF! #REF!

Excavation in open cut for sewers & manhole except


14 03-44-a m2 138.02 535.02 73843.4604 #REF! #REF! #REF! #REF!
shingle, gravel & rock : Upto 2m
Pacca brick work other than building upto 10 ft.
15 07-07-a-03 height : m3 5519.547 0 0 #REF! #REF! #REF! #REF!
Cement, sand mortar 1:4

16 11-08-c Cement plaster 1:3 upto 20' height 3/4" thick m3 228.24 0 0 #REF! #REF! #REF! #REF!

RCC in roof slab, beam, column & other structural


17 06-06-a-03 m2 7351.866 0 0 #REF! #REF! #REF! #REF!
members, insitu or precast. Type C (1:2:4)

Supply & fabricate M.S. reinforcement for cement


18 06-07-b Ton 118000 1.99 234820 #REF! #REF! #REF! #REF!
concrete (Hot rolled deformed bars Grade 60)

Plain Cement Concrete including placing,


19 06-05-h m3 5190 364.014 1889232.66 #REF! #REF! #REF! #REF!
compacting, finishing & curing (Ratio 1:3:6)

20 04-19-c Dismantling : Plain Cement Concrete 1:2:4 m3 1686 30.03 50630.58 #REF! #REF! #REF! #REF!

21 04-19-b Dismantling : Plain Cement Concrete 1:3:6 m3 1380 89.65 123717 #REF! #REF! #REF! #REF!

Road signs (not exceeding 1 m2) without reflection


22 16-16-a sheet & lettering : Supply and Fixing at site with PCC m2 6921 9 62289 #REF! #REF! #REF! #REF!
1:3:6 upto max 3' depth
Supply and Fixing reflective sheet on MS/aluminium
23 16-18-b road signs etc including lettering : High intensity m2 5396 9 48564 #REF! #REF! #REF! #REF!
grade
Pavement marking in reflective thermoplast paint with
24 16-65-a m 120 4874.66 584959.2 #REF! #REF! #REF! #REF!
glass beads for line 15 cm width.

25 16-19-c-03 Supply & Fixing Cat Eye single as specified Each 285.62 0 0 #REF! #REF! #REF! #REF!

Supply and Fixing aluminium alloy road studs as per


26 16-19-b-01 specs Medium, strip 114x18mm, 74 beads: Uni- Each 460 1328 610880 #REF! #REF! #REF! #REF!
direction
P/F Precast Concrete 7000 psi TUFF Tiles over bed
27 10.-45 m2 725 0 0 #REF! #REF! #REF! #REF!
of 2" thick sand & 4" thick brick ballast comp
Providing and fixing kerb stone (12"x18"x6") in
28 16-63-a cement sand mortar 1:3 in center media or round m 650 3656 2376400 #REF! #REF! #REF! #REF!
about as specified.
Prepare & Paint new corrugated surface, Kerb
29 13-06-a-01 m2 104 1096.8 114067.2 #REF! #REF! #REF! #REF!
Stone : Priming coat

Prepare & Paint new corrugated surface, Kerb


30 13-06-c-02 m2 74 1096.8 81163.2 #REF! #REF! #REF! #REF!
Stone : subsequent coat of paint

Providing and Laying RCC pipe sewers complete As


31 23-03-a-03 m 2508 45 112860 #REF! #REF! #REF! #REF!
per ASTM C-76-79, Class II : 18" i/d, Wall B
Providing and Laying RCC pipe sewers complete As
32 23-03-a-01 m 1608 43.76 70366.08 #REF! #REF! #REF! #REF!
per ASTM C-76-79, Class II : 12" i/d, Wall B

Providing and Laying cut, joint, test, disinfect PVC


33 24-18-a-02 m 563 50.76 28577.88 - - (50.76) (28,577.88)
pipe line BSS Class 'B'working pressure : 4" i/d

#REF! #REF! m3 68.96 0 0 #REF! #REF! #REF! #REF!

34 03-56 Clearing & Grubbing m2 10 1828 18280 #REF! #REF! #REF! #REF!

35 03-58 Compaction of Natural Ground m2 10 861.68 8616.8 #REF! #REF! #REF! #REF!

36 03-62-c Subgrade Preparation on Existing Road m2 45 5384.32 242294.4 #REF! #REF! #REF! #REF!

Dressing of earthwork (done by machinery or otherwise &


37 03-22 m2 6.50 1568.93 10198.045 #REF! #REF! #REF! #REF!
left undressed) to designed section

Leveling dressing and compaction with power roller of


38 16-62 m2 110 9597 1055670 #REF! #REF! #REF! #REF!
existing base coarse layer after asphalt scarification.

Formation of Embankment from Roadway Excavation in


39 03-61-a m3 310 989.89 306865.9 #REF! #REF! #REF! #REF!
Common Material including compaction by power roller.

Scarifying/Dismantling old road surface, including


40 16-10 m2 24 2513.5 60324 #REF! #REF! #REF! #REF!
removal of debris within one chain (NHA specified)

41 16-58-a Cold Milling of asphalt concrete 0-70 mm m2 139 4195.26 583,141.14 #REF! #REF! #REF! #REF!

42 16-58-b Cold Milling of asphalt concrete 0-50 mm m2 97 1398.42 135,646.74 #REF! #REF! #REF! #REF!

43 NHA103 Sripping m3 150 124.65 18,697.50 #REF! #REF! #REF! #REF!

Providing and Laying grouted stone pitching, in 1:8 c/s


44 19-30-a m3 4065 974.02 3959391.3 #REF! #REF! #REF! #REF!
mortar Top layer on slope

Providing and Fixing gantry of structural steel sections as


45 16-20 Kg 118.08 1 118.08 #REF! #REF! #REF! #REF!
per design / drawings including foundation complete

Suppy and Fixing concrete paver approved manufacture as


46 10-45' m2 725 287.49 208430.25 #REF! #REF! #REF! #REF!
per specs as directed by engineer.

47 NHA501a RCC pipe dia 310 mm AASHTO M170 m 1600 34.92 55872 #REF! #REF! #REF! #REF!
48 SP-5 RCC Pipe dia 450mm m 2000 28.6 57200 #REF! #REF! #REF! #REF!

Structural Backfill using Granular Material brought from


49 03-60-d m3 914 279.69 255636.66 #REF! #REF! #REF! #REF!
outside

Structural backfill using Common Material available at


50 03-60-c m3 327 12 3924 #REF! #REF! #REF! #REF!
site.

PCC 1:3:6 in mass concrete less formwork using 50%


51 06-36-a m3 3546 891.7 3,161,968.20 #REF! #REF! #REF! #REF!
boulders

Erection and removal of steel Form work for RCC or Plain


52 06-39-b m3 790 3993.83 3,155,125.70 #REF! #REF! #REF! #REF!
Concrete vertical
Excavation in foundation of building, bridges etc
53 03-23-c complete m3 180 492.95 88,731.00 #REF! #REF! #REF! #REF!
: in hard soil or soft murum
Erecting & removing formwork to concrete in any shape /
54 06-38-b m2 428 2310.88 989,056.64 #REF! #REF! #REF! #REF!
position (Vertical)

55 NSI Guard rail /fencing as per drawing and specification m 100 885 88,500.00 #REF! #REF! #REF! #REF!

56 03-60-a Structural Excavation in Common Material m3 219 283.4 62,064.60 - - (283.40) (62,064.60)

RCC including Precast/Prestressed slab, column, beam,


57 06-06-c-03 m3 9164 104.47 957,363.08 - - (104.47) (957,363.08)
lintel, girder etc. Type C (1:2:4).

58 04-46. Dismantling and removing road metalling m3 306 342.45 104,789.70 - - (342.45) (104,789.70)

TOTAL AMOUNT RS. 65,009,669 #REF! #REF!


ift Programme ADP No. 1111 / 130647 (2014-15)

al Patrol Road Along Warsak Gravity Canal From RD 55+000 To 58+000 (Package- I)

EM WISE COMPARATIVE STATEMENT

Remarks

The Qty Decreases as


per site Requirment
/Design
The Qty Increases as
per site Requirment
/Design

The Item Added as


Site Requirment
/Design

The Qty Decreases as


per site Requirment
/Design

The Qty Decreases as


per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Increases as
per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Increases as
per site Requirment
/Design

The Qty Increases as


per site Requirment
/Design

The Qty Increases as


per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Increases as
per site Requirment
/Design
The Item Added as
Site Requirment
/Design
The Item Added as
Site Requirment
/Design

The Item Added as


Site Requirment
/Design

The Qty Increases as


per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design

The Qty Decreases as


per site Requirment
/Design

The Qty Decreases as


per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Item Added as
Site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Increases as
per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design
The Qty Decreases as
per site Requirment
/Design

The Qty Increases as


per site Requirment
/Design

The Item Added as


Site Requirment
/Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design
The Item Not Required
as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Qty Increases as


per site Requirment
/Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design

The Item Not Required


as site /Design
Peshawar Uplift Programme ADP No. 1111 / 130647 (2014-15)
Up-Gradation/Improvement and widening of Canal Patrol Road Along Warsak Gravity Canal From RD 55+000
To 58+000 (Package- I)

BILL OF QUANTITY (BOQ) ROAD WORK L/S

Total Amount
S. No. Item No Description Unit Quantity Rate
(Rs)
1 #REF! #REF! m2 #REF! 20 #REF!

2 #REF! #REF! m3 #REF! 260.00 #REF!

3 #REF! #REF! m3 #REF! 30.20 314,227

4 #REF! #REF! m3 #REF! 1800.00 #REF!

5 #REF! #REF! m3 #REF! 2200.00 #REF!


6 #REF! #REF! m3 #REF! 16514.00 #REF!
7 #REF! #REF! m3 #REF! 18600.00 #REF!
8 #REF! #REF! m 2
#REF! 50.00 #REF!

9 #REF! #REF! m2 #REF! 135.00 #REF!


10 #REF! #REF! m 3
#REF! 615.00 #REF!

11 #REF! #REF! m3 #REF! 633.15 #REF!

12 #REF! #REF! m3 #REF! 517.00 #REF!

TOTAL AMOUNT #REF!


Widening & Rehabilitation of Char Pul Road Village pirpiai
DETAIL ESTIMATE OF ROAD WORK
Item
S. No. MRS 2013 Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
(Avg) (Avg)
Grooving in existing BT road of size 4x4 cm @
1 16-61
2 meter c/c.

M2 1 1000 3.657 - 3657.42


Total Qty in M2 3657.42 41.69 152,478

2 03.-56 Clearing & Grabbing

Shoulder M2 2 1000 1.8 - 3657.42


Total Qty in M3 3657.42 27.04 98,897
Formation of Embankment from Borrow
3 03-61-c Excavation in Common Material including
compaction by power roller.
Widening Portion M3 2 600 1.8 0.3 658.34
Total Qty in M3 658.34 828.72 545,576

4 16-03-a Granular Sub Base Using pit run gravels

Main Road M3 1 1000 7.3 0.15 1097.23


Total Qty in M3 1097.23 1522.39 1,670,407

5 16-04-b Water Bound Macadam Base Course

Main Road M3 1 1000 5.5 0.15 822.92


Total Qty in M3 822.92 2479.59 2,040,504
Formation of shoulder with permeable
6 16-57 material Passing less than 7 % from 200 seive
and P.I less than 4 as specified.
Shoulder M3 2 1000 0.9 0.2 365.74
Total Qty in M3 365.74 1401.68 512,653
7 16-06 Bitumenous Prime Coat
M2 1 1000 5.5 5500
Total Qty in m2 5500.00 157.61 866,855
Asphaltic Wearing Course (Asphalt Batch
8 16-12-b
Plant Hot Mixed)
M2 1 1000 5.5 0.050 274.31
Total Qty in M3 274.31 19514.68 5,353,006
Plain Cement Concrete including placing,
9 06-05-i
compacting,finishing & curing (Ratio 1:4:8)
M3 1 200.00 5.5 0.15 165
Total Qty in M3 165.00 5316.24 877,180

Plain Cement Concrete including placing,


10 06-05-f
compacting, finishing & curing (Ratio 1:2:4)

M3 1 200.00 5.5 0.15 165


Total Qty in M3 165.00 6997.38 1,154,568

Pavement marking in reflective thermoplast


11 16-65-a
paint with glass beads for line 15 cm width.

M 2.5 1200.00 - - 3000


Total Qty in M3 3000.00 151.37 454,110
12 16-19-c-03 Supply & Fixing Cat Eye single as specified
Each 2800 - - - 2800
Total Qty in M3 2800.00 336.85 943,180
Road signs (not exceeding 1 m2) without
reflection sheet & lettering : Supply and Fixing
13 16-16-a
at site with PCC 1:3:6 upto
max 3' depth
M2 6 - - - 6 8125.05 48,750
Supply and Fixing reflective sheet on
14 16-18-a MS/aluminium road signs etc including
lettering : Diamond grade
M2 6 - - - 6 6763.53 40,581

Total Amount Rs. = 14,758,744

Total Amount Rs. (in Million) = 14.759


RETAINING WALL 1.5 m Height
1 03-60-a Structural Excavation in Common Material
M3 1 250.00 0.8 0.6 120
Total Qty in M3 120.00 358.75 43,050
Plain Cement Concrete including placing,
2 06-05-i
compacting,finishing & curing (Ratio 1:4:8)
M3 1 100.00 0.8 0.15 12
Total Qty in M3 12.00 5316.24 63,795
PCC 1:3:6 in mass concrete less formwork
3 06-36-c
using 30% boulders
1st Step M3 1 100.00 0.8 0.6 48
2nd Step M3 1 100.00 0.7 0.75 52.5
3rd Step M3 1 100.00 0.6 0.75 45
Total Qty in M3 145.50 4739.05 689,532
Erecting & removing formwork to concrete in
4 06-38-b
any shape / position (Vertical)
M2 2 100.00 - 2.1 420
Total Qty in M2 420.00 567.92 238,526

Total Amount Rs. = 1,034,903

Total Amount Rs. (in Million) = 1.035


Drain Work
1 03-60-a Structural Excavation in Common Material
M3 1 200.00 0.9 0.6 108
Total Qty in M3 108.00 358.75 38,745
Plain Cement Concrete including placing,
2 06-05-i
compacting,finishing & curing (Ratio 1:4:8)
1st Step M3 1 200.00 0.9 0.15 27
Total Qty in M3 27.00 5316.24 143,538
Plain Cement Concrete including placing,
3 06-05-h
compacting,finishing & curing (Ratio 1:3:6)
Drain Bed M3 1 200.00 0.45 0.075 6.75
Drain Walls M3 2 200.00 0.08 0.45 13.5
Total Qty in M3 20.25 6093.48 123,393
Erecting & removing formwork to concrete in
4 06-38-b
any shape / position (Vertical)
M2 4 200.00 - 0.45 360
Total Qty in M2 360.00 567.92 204,451

Total Amount Rs. = 510,128

Total Amount Rs. (in Million) = 0.510


Pipe Culvert
1 03-60-a Structural Excavation in Common Material
M3 10 9.14 0.45 0.45 18.52
Total Qty in M3 18.52 358.75 6,643
Plain Cement Concrete including placing,
3 06-05-i
compacting,finishing & curing (Ratio 1:4:8)
1st Step M3 10 9.14 0.45 0.15 6.17
Total Qty in M3 6.17 5316.24 32,811
Plain Cement Concrete including placing,
2 06-05-h
compacting,finishing & curing (Ratio 1:3:6)
M3 10 9.14 0.45 0.45 18.51569643
D/d of Pipe Dia M3 10 9.14 0.07 6.459920756
Total Qty in M3 24.98 6093.48 152,188
Erecting & removing formwork to concrete in
4 06-38-b
any shape / position (Vertical)
M2 20 9.14 - 0.9 164.5839683
Total Qty in M2 164.58 567.92 93,471
Providing and Laying RCC pipe sewers
4 23-03-a-01 complete As per ASTM C-76-79, Class II : 12"
i/d, Wall B
M 10 9.14 - - 91.436
Total Qty in M 91.44 1813.36 165,806

Total Amount Rs. = 450,918

Total Amount Rs. (in Million) = 0.451

G. Total Rs = 16,754,693
16.75
Construction of Zahoor Korona Street Moh: Janabad
DETAIL ESTIMATE
Item
S.
MRS Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
No.
2013

Plain Cement Concrete including


9 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

M3 1 700.00 3.66 0.11 281.6215


Total Qty in M3 281.62 5316.24 1,497,167
Plain Cement Concrete including
10 06-05-f placing, compacting, finishing &
curing (Ratio 1:2:4)
M3 1 700.00 3.66 0.11 281.6215
Total Qty in M3 281.62 6997.38 1,970,612
Drain Work
Structural Excavation in
1 03-60-a
Common Material
M3 1 500.00 0.9 0.6 270
Total Qty in M3 270.00 358.75 96,863

Plain Cement Concrete including


2 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

1st Step M3 1 500.00 0.9 0.15 67.5


Total Qty in M3 67.50 5316.24 358,846

Plain Cement Concrete including


3 06-05-h placing, compacting,finishing &
curing (Ratio 1:3:6)

Drain Bed M3 1 500.00 0.45 0.075 16.875


Drain Walls M3 2 500.00 0.08 0.45 33.75
Total Qty in M3 50.63 6093.48 308,482
Erecting & removing formwork to
4 06-38-b concrete in any shape / position
(Vertical)
M2 4 500.00 - 0.45 900
Total Qty in M2 900.00 567.92 511,128

Total Amount Rs. = 4,743,099

Total Amount Rs. (in Million) = 4.743


Peshawar Uplift Programme ADP No. 1111 / 130647 (2014-15)
Up-Gradation/Improvement and widening of Canal Patrol Road Along Warsak Gravity Canal From RD 55+000
To 58+000

BILL OF QUANTITY (BOQ) GUARD RAIL/FENCING L/S

Total Amount
S. No. Item No Description Unit Quantity Rate
(Rs)

1 #REF! #REF! m2 #REF! 100 #REF!

2 #REF! #REF! m3 #REF! 5190.00 #REF!


TOTAL AMOUNT #REF!
Construction of Drain from pirpiai stop to nano pull.
DETAIL ESTIMATE
Item
S.
MRS Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
No.
2013
Structural Excavation in
1 03-60-a
Common Material
M3 1 1000.00 1.2 1.2 1462.969
Total Qty in M3 1462.97 358.75 524,840
Formation of Embankment from
Borrow Excavation in Common
2 03-61-c
Material including compaction by
power roller.
M3 1 500 1.5 0.6 450.00
Total Qty in M3 450.00 828.72 372,924

Plain Cement Concrete including


3 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

M3 1 1000.00 1.2 0.15 180


Total Qty in M3 180.00 5316.24 956,923

Plain Cement Concrete including


4 06-05-h placing, compacting,finishing &
curing (Ratio 1:3:6)

Drain Bed M3 1 1000.00 0.60 0.075 45


Drain Walls M3 2 1000.00 0.30 0.6 360
Total Qty in M3 405.00 6093.48 2,467,859
Erecting & removing formwork to
5 06-38-b concrete in any shape / position
(Vertical)
M2 4 1000.00 - 0.6 2400
Total Qty in M2 2400.00 567.92 1,363,008

Total Amount Rs. = 5,685,555

Total Amount Rs. (in Million) = 5.686


Construction of Drain at pirpiai main khwar
DETAIL ESTIMATE
Item
S.
MRS Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
No.
2013
Structural Excavation in
1 03-60-a
Common Material
M3 1 200.00 0.9 0.9 162
Total Qty in M3 162.00 358.75 58,118

Plain Cement Concrete including


2 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

M3 1 200.00 0.9 0.15 27


Total Qty in M3 27.00 5316.24 143,538

Plain Cement Concrete including


3 06-05-h placing, compacting,finishing &
curing (Ratio 1:3:6)

Drain Bed M3 1 200.00 0.30 0.075 4.5


Drain Walls M3 2 200.00 0.30 0.3 36
Total Qty in M3 40.50 6093.48 246,786
Erecting & removing formwork to
5 06-38-b concrete in any shape / position
(Vertical)
M2 4 200.00 - 0.6 480
Total Qty in M2 480.00 567.92 272,602

Total Amount Rs. = 721,044

Total Amount Rs. (in Million) = 0.721


Construction of Hayat Gul Korona Street Mohallah Janabad
DETAIL ESTIMATE
Item
S.
MRS Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
No.
2013
Structural Excavation in
1 03-60-a
Common Material
M3 1 60.00 4.3 0.3 76.86
Total Qty in M3 76.86 358.75 27,574

Plain Cement Concrete including


9 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

M3 1 60.00 4.27 0.11 28.16215


Total Qty in M3 28.16 5316.24 149,717
Plain Cement Concrete including
10 06-05-f placing, compacting, finishing &
curing (Ratio 1:2:4)
M3 1 60.00 4.27 0.11 28.16215
Total Qty in M3 28.16 6997.38 197,061
Drain Work
Structural Excavation in
1 03-60-a
Common Material
M3 1 60.00 0.9 0.6 32.4
Total Qty in M3 32.40 358.75 11,624

Plain Cement Concrete including


2 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

1st Step M3 1 60.00 0.9 0.15 8.1


Total Qty in M3 8.10 5316.24 43,062

Plain Cement Concrete including


3 06-05-h placing, compacting,finishing &
curing (Ratio 1:3:6)

Drain Bed M3 1 60.00 0.45 0.075 2.025


Drain Walls M3 2 60.00 0.08 0.45 4.05
Total Qty in M3 6.08 6093.48 37,018
Erecting & removing formwork to
4 06-38-b concrete in any shape / position
(Vertical)
M2 4 60.00 - 0.45 108
Total Qty in M2 108.00 567.92 61,335

Total Amount Rs. = 527,390

Total Amount Rs. (in Million) = 0.527


Construction of Shahid Khan Korona Street Mohallah Janabad
DETAIL ESTIMATE
Item
S.
MRS Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
No.
2013
Structural Excavation in
1 03-60-a
Common Material
M3 1 80.00 2.7 0.3 65.76
Total Qty in M3 65.76 358.75 23,591

Plain Cement Concrete including


9 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

M3 1 80.00 2.74 0.11 24.13898


Total Qty in M3 24.14 5316.24 128,329
Plain Cement Concrete including
10 06-05-f placing, compacting, finishing &
curing (Ratio 1:2:4)
M3 1 80.00 2.74 0.11 24.13898
Total Qty in M3 24.14 6997.38 168,910
Drain Work
Structural Excavation in
1 03-60-a
Common Material
M3 1 80.00 0.9 0.6 43.2
Total Qty in M3 43.20 358.75 15,498

Plain Cement Concrete including


2 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

1st Step M3 1 80.00 0.9 0.15 10.8


Total Qty in M3 10.80 5316.24 57,415

Plain Cement Concrete including


3 06-05-h placing, compacting,finishing &
curing (Ratio 1:3:6)

Drain Bed M3 1 80.00 0.45 0.075 2.7


Drain Walls M3 2 80.00 0.08 0.45 5.4
Total Qty in M3 8.10 6093.48 49,357
Erecting & removing formwork to
4 06-38-b concrete in any shape / position
(Vertical)
M2 4 80.00 - 0.45 144
Total Qty in M2 144.00 567.92 81,780

Total Amount Rs. = 524,881

Total Amount Rs. (in Million) = 0.525


Construction of Rafiq Korona Street Mohallah Janabad
DETAIL ESTIMATE
Item
S.
MRS Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
No.
2013
Structural Excavation in
1 03-60-a
Common Material
M3 1 100.00 3.35 0.3 100.5791
Total Qty in M3 100.58 358.75 36,083

Plain Cement Concrete including


9 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

M3 1 100.00 3.35 0.11 36.879


Total Qty in M3 36.88 5316.24 196,058
Plain Cement Concrete including
10 06-05-f placing, compacting, finishing &
curing (Ratio 1:2:4)
M3 1 100.00 3.35 0.11 36.879
Total Qty in M3 36.88 6997.38 258,056
Drain Work
Structural Excavation in
1 03-60-a
Common Material
M3 1 100.00 0.9 0.6 54
Total Qty in M3 54.00 358.75 19,373

Plain Cement Concrete including


2 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

1st Step M3 1 100.00 0.9 0.15 13.5


Total Qty in M3 13.50 5316.24 71,769

Plain Cement Concrete including


3 06-05-h placing, compacting,finishing &
curing (Ratio 1:3:6)

Drain Bed M3 1 100.00 0.45 0.075 3.375


Drain Walls M3 2 100.00 0.08 0.45 6.75
Total Qty in M3 10.13 6093.48 61,696
Erecting & removing formwork to
4 06-38-b concrete in any shape / position
(Vertical)
M2 4 100.00 - 0.45 180
Total Qty in M2 180.00 567.92 102,226

Total Amount Rs. = 745,261

Total Amount Rs. (in Million) = 0.745


Construction of irfan gafar house to karnal betak Street Mohallah Misken Khel
DETAIL ESTIMATE
Item
S.
MRS Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
No.
2013
Dismantling brick work in lime or
1 04.-13
cement mortar
M3 1 200.00 4.27 0.22 187.88
Total Qty in M3 187.88 651.78 122,456

Plain Cement Concrete including


9 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

M3 1 200.00 4.27 0.11 93.87382


Total Qty in M3 93.87 5316.24 499,056
Plain Cement Concrete including
10 06-05-f placing, compacting, finishing &
curing (Ratio 1:2:4)
M3 1 200.00 4.27 0.11 93.87382
Total Qty in M3 93.87 6997.38 656,871
Drain Work
Structural Excavation in
1 03-60-a
Common Material
M3 1 100.00 0.9 0.6 54
Total Qty in M3 54.00 358.75 19,373

Plain Cement Concrete including


2 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

1st Step M3 1 100.00 0.9 0.15 13.5


Total Qty in M3 13.50 5316.24 71,769

Plain Cement Concrete including


3 06-05-h placing, compacting,finishing &
curing (Ratio 1:3:6)

Drain Bed M3 1 100.00 0.45 0.075 3.375


Drain Walls M3 2 100.00 0.08 0.45 6.75
Total Qty in M3 10.13 6093.48 61,696
Erecting & removing formwork to
4 06-38-b concrete in any shape / position
(Vertical)
M2 4 100.00 - 0.45 180
Total Qty in M2 180.00 567.92 102,226

Total Amount Rs. = 1,533,447

Total Amount Rs. (in Million) = 1.533


Construction of Bas Ali Jan Korona Street Mohallah Kamar Khel
DETAIL ESTIMATE
Item
S.
MRS Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
No.
2013
Structural Excavation in
1 03-60-a
Common Material
M3 1 100.00 3.35 0.3 100.5791
Total Qty in M3 100.58 358.75 36,083

Plain Cement Concrete including


9 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

M3 1 100.00 3.35 0.11 36.879


Total Qty in M3 36.88 5316.24 196,058
Plain Cement Concrete including
10 06-05-f placing, compacting, finishing &
curing (Ratio 1:2:4)
M3 1 100.00 3.35 0.11 36.879
Total Qty in M3 36.88 6997.38 258,056
Drain Work
Structural Excavation in
1 03-60-a
Common Material
M3 1 100.00 0.9 0.6 54
Total Qty in M3 54.00 358.75 19,373

Plain Cement Concrete including


2 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

1st Step M3 1 100.00 0.9 0.15 13.5


Total Qty in M3 13.50 5316.24 71,769

Plain Cement Concrete including


3 06-05-h placing, compacting,finishing &
curing (Ratio 1:3:6)

Drain Bed M3 1 100.00 0.45 0.075 3.375


Drain Walls M3 2 100.00 0.08 0.45 6.75
Total Qty in M3 10.13 6093.48 61,696
Erecting & removing formwork to
4 06-38-b concrete in any shape / position
(Vertical)
M2 4 100.00 - 0.45 180
Total Qty in M2 180.00 567.92 102,226

Total Amount Rs. = 745,261

Total Amount Rs. (in Million) = 0.745


Construction of Nadr Kor to Shrikh Derai Mohallah Baba khel
DETAIL ESTIMATE
Item
S.
MRS Description Unit Nos. Length Width H/Thickness Quantity Rate Amount Rs.
No.
2013
Structural Excavation in
1 03-60-a
Common Material
M3 1 300.00 4.27 0.3 384.0293
Total Qty in M3 384.03 358.75 137,770

Plain Cement Concrete including


9 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

M3 1 300.00 4.27 0.11 140.8107


Total Qty in M3 140.81 5316.24 748,584
Plain Cement Concrete including
10 06-05-f placing, compacting, finishing &
curing (Ratio 1:2:4)
M3 1 300.00 4.27 0.11 140.8107
Total Qty in M3 140.81 6997.38 985,306
Drain Work
Structural Excavation in
1 03-60-a
Common Material
M3 1 300.00 0.9 0.6 162
Total Qty in M3 162.00 358.75 58,118

Plain Cement Concrete including


2 06-05-i placing, compacting,finishing &
curing (Ratio 1:4:8)

1st Step M3 1 300.00 0.9 0.15 40.5


Total Qty in M3 40.50 5316.24 215,308

Plain Cement Concrete including


3 06-05-h placing, compacting,finishing &
curing (Ratio 1:3:6)

Drain Bed M3 1 300.00 0.45 0.075 10.125


Drain Walls M3 2 300.00 0.08 0.45 20.25
Total Qty in M3 30.38 6093.48 185,089
Erecting & removing formwork to
4 06-38-b concrete in any shape / position
(Vertical)
M2 4 300.00 - 0.45 540
Total Qty in M2 540.00 567.92 306,677

Total Amount Rs. = 2,636,852

Total Amount Rs. (in Million) = 2.637