1) Scaffolding and shuttering will be constructed at four grid locations to support the pouring and formation of concrete staircases.
2) Reinforcement steel will be cut, bent, and placed according to specifications before concrete is poured from a batching plant and compacted into the shuttering.
3) Continuous supervision will be provided during staging, concreting, and de-shuttering to ensure proper bracing and support.
1) Scaffolding and shuttering will be constructed at four grid locations to support the pouring and formation of concrete staircases.
2) Reinforcement steel will be cut, bent, and placed according to specifications before concrete is poured from a batching plant and compacted into the shuttering.
3) Continuous supervision will be provided during staging, concreting, and de-shuttering to ensure proper bracing and support.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 4
METHOD STATEMENT
Staircase (Process Plant)
Location 1) At Grid (1-2)(B-C) 2) At Grid (7-8) ( A- B) 3) At Grid (4-5) (F-G) 4) At Grid (1-2) (H-J)
Shuttering,Concreting & De-Shuttering
Scaffolding will be done for beam & step supports, (a) Area will be levelled; sole support is kept under all vertical supports230 * 300mm wide. (b) All scaffolding/staging/platform has base plate under neath. (c) Compaction report for the soil is available. At the top U jack is kept for grip of channel, 100mmISMB or ledger pipe. Above channel/ledger 4”*3” wooden batten will be kept & fixed with channel/ledger Pipe. For bottom shuttering ply wood making will be done in making yard. All bottom shuttering is fixed & rested on wooden battens. Sides shuttering made of ply wood & wooden planks and fixed with bottoms. Jali will be kept for men movement along with beam sides. Shuttering Plywood& plates for covering Staircase will be lifted by ropes. Reinforcement steel will cut, bent and made as per specification at steel yard Steel is to be shifted to site work using tractor, tough rider & lifted to slab using ropes or manually. All supports, staging and reinforcement inserts and props place & get checked. Concreting has to be started after approval site engineer incharge (Consultant). Concrete is going to come from batching plant using transit mixtures. Poured in to vessel lifted by tower, cranes and poured at slab level. Concrete will be levelled, compacted & finished using Fouti, Trovel, Vibrators, and manually. Two people will be there for holding the bucket of tower crane. Additional bracing is to be done for stiffening & tightening of staging using ledger pipes and couplers.
Continuous supervision will be provided at the time of
staging, concreting and de-shuttering. Ledger pipes will be fixed using couplers. Cross bracing will also be provided wherever required. For slab supports acrow span & propsets will be used for supports, for adjustment of vertical supports shoulders or wooden batten will be used. Vertical Cup locks & Horizontals i.e. Cup lock Staging Will be Used.