Safe Work Method Statement For Erection of All Works:: Client Consultant

This document provides a safe work method statement for erecting works at a height of 13 meters. It outlines the scope of work, tools and equipment used, personal protective equipment required, job procedures, and safety procedures. The key steps are positioning scaffolding and scissor lifts, obtaining daily work and height permits, inspecting power tools, and removing sharp materials when work is complete. Safety measures include screening workers, using harnesses above 2 meters, cleaning areas for welding, inspecting scaffolds, and providing adequate lighting.

Uploaded by

soubhagya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
481 views

Safe Work Method Statement For Erection of All Works:: Client Consultant

This document provides a safe work method statement for erecting works at a height of 13 meters. It outlines the scope of work, tools and equipment used, personal protective equipment required, job procedures, and safety procedures. The key steps are positioning scaffolding and scissor lifts, obtaining daily work and height permits, inspecting power tools, and removing sharp materials when work is complete. Safety measures include screening workers, using harnesses above 2 meters, cleaning areas for welding, inspecting scaffolds, and providing adequate lighting.

Uploaded by

soubhagya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PROJECT : M/

CLIENT CONSULTANT : M/S


CONTRACTOR : M/S

SAFE WORK METHOD STATEMENT FOR


ERECTION OF ALL WORKS

SCOPE OF WORK : ERECTION OF ALL WORK

LOCATION :

WORKING AT HEIGHT : GROUND LEVEL (AND) 13 MTR HEIGHT

USAGE OF MATERIAL : Cable Tray, Gripple ,Light fitting, Wires& Cables

TOOLS& EQUPMENTS : HAMMER, SCAFFOLDING, SPANNER.SCISSOR LIFT

POWER TOOLS : CUTTING M/C, TESTER, CUTTING PLIER.


USAGE OF PPE : HELMET, SHOE, REFLECTIVE JACKET HAND
GLOVESE, GOGGLES.

WORK INVOLVEMENT : SITE ENGINEER

: SAFETY OFFICER

: SITE SUPERVISOR

: WORKERS

SAFE WORK METHOD STATEMENT FOR


ERECTION OF ALL WORKS

1. JOB PROCEDURE

 Based on the daily work program schedule usage of quality of material


is been taken place.
 The required material had shifting from the storage yard to work
place.(Permissible of 20 kgs. per person)
 Based on the drawing physically location are identified and light fitting
are erected on site
 The light fitting are being hanged with the help of support (clamp,
Gripple rod-stud)
 Proper Scaffolding& Scissor lift will be positioned on the work location
 Height work Permit& Night work permit will be obtained on Daily
basis
 The power hand tools will be checked for healthiness of Electrical
System
 Before leaving work place sharp materials and cut pieces are removed
and stored in scrap yard.

2. SAFETY PROCEDURE
 All workmen Involved in the operation Should be screened /inducted
 Before start of the work proper PPEs given to the workers
 Inspect work/walk area for potential slip and trip fall obstructions prior
to start of work and remove ,if not possible mark with visible tape/
signage
 Before start of the work Tool box talk to be given
 Permit (height &hot work) to be done before start of the work.
 All persons should wear full body safety harness while working at
height (2 MTR to 13 MTR level).
 Cleaning for the flammable Material before start welding work
 Scaffolds and working platforms shall be erected, altered and
dismantled under the supervision of the competent person
 All bracing shall be in position and lock properly
 Scaffold must be inspected and tag to be used (GREEN-Safe for use,
RED-not in use)
 Don’t move the scaffolding while persons working at height
 Fire Extinguisher shall be in working Area
 Engaged to fire watcher
 Never allow the scaffold to run over the electrical cable
 Do not used damaged and defective sockets
 Switch on after plug in , switch off before plug out
 Call the electrician if any work needs to the done in DB
 Check the power supply is off before change in blade and drill bit
 Cleaning of all debris and waste material after complete to the work.
 Adequate Lighting provided for all areas

3. BASIC MANDATORY PPE’S:


Helmet, shoes, hand gloves, goggles, nose mask, jacket

4. HEIGHT WORK PPE’S:


Full body Safety Harness, life line rope, fall arrester
5. HOT WORK PPE’S:
Face shield, goggles, cotton gloves & nose mask.

PREPARED BY CHECKED BY CONFIREMED BY