Regarding The Maintenance and Calibration For The Guages: PLM Enterprise Asset Management (EAM) /plant Maintenance (PM)

1. The document discusses maintaining calibration for gauges like vernier calipers used in production. 2. The key steps include procuring gauges, stocking them, issuing them to production lines, and calibrating them at regular intervals with inspection result recording. 3. Suggested steps are to create a calibration process with a sampling procedure, master inspection characteristic, and maintenance task list to schedule calibration maintenance plans and generate orders for result recording.

Uploaded by

ramakrishna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views

Regarding The Maintenance and Calibration For The Guages: PLM Enterprise Asset Management (EAM) /plant Maintenance (PM)

1. The document discusses maintaining calibration for gauges like vernier calipers used in production. 2. The key steps include procuring gauges, stocking them, issuing them to production lines, and calibrating them at regular intervals with inspection result recording. 3. Suggested steps are to create a calibration process with a sampling procedure, master inspection characteristic, and maintenance task list to schedule calibration maintenance plans and generate orders for result recording.

Uploaded by

ramakrishna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

An equipment PRT has its own equipment master record and has the full equipment functionality.

This category is particularly useful for those production resources or tools which you must
maintain yourself or which must be serviced at regular intervals. With the equipment category,
you can furnish proof of service or usage values for the production resource/tool.

Regarding the Maintenance and


Calibration for the Guages
Hello Experts,
In our Scenario, we need a Process for Guage Maintenance.
actually my requirement is as follows.
I need to Procure Guages like Vernier Calliper.
I need to stock them,
Then I need to Issue them to the Production Line.
and in the regular Intervals I need to do the Calibration for them, and this requires the Inspection
results Recording.
I have some understanding for the same process but can someone please give me the clear idea
for the steps involved.
Please help.
Yawar Khan
 
PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM)

 Follow
  RSS Feed

Sort by: 

  Best Answer

Former Member

Posted onJun 13, 2013 at 10:36 AM

Hi
For above process you required “Calibration Process”.
Following are the steps:
1) Create Sampling Procedure (T-code: QDV1)
2) Create Master Inspection Characteristic (T-code: QS21)
3) Create Maintenance Task list, here provide Inspection Pt. 300 for equipment
or 310 for functional location. Then assign MIC & sampling procedure to
operation in Task list.
4) Create Maintenance Plan, here provide Maint. Plan description, Equipment,
Order type- PM05, Task list
5) Then schedule the maintenance plan.
6) When Order is generated with the reference of this task list, after releasing
the maintenance order Inspection lot get generated for this order.
7) Then go for Result Recording (T-code: QA32)
For detail explanation please refer the following Link:
http://scn.sap.com/docs/DOC-29392
http://scn.sap.com/thread/3174451
http://scn.sap.com/thread/1316901
http://www.slideshare.net/subhrajyotibhattacharjee7/sap-pm-test-equipment-
managementcalibration-process
Try at your end, may be helpful to you!
Regards
Ritesh

o Share

Gyanaranjan Rout

Posted onJun 13, 2013 at 10:42 AM

Hi,
i) Create equipment as vernier caliper and create same equipment as a spare
part
ii)create purchase requisition
iii)Create purchase order
iv)Receive the material In MIGO T.code
v)Check in MMBE stock overview
then
Config: Assign Calibration inspection type-14 to respective PM Order type.
Master Data:
1. You first create Maintenance Plan (IP41). Considering you've already an
Equipments (IE01), General Taks List for equipment (IA05) created/available in
system in PM module.
2. Then you schedule Maintenance Plan using IP10.
3. After Scheduling, system generates a Maintenance Order automatically in
background.
4. Then you release Maintenace Order (IW32). Once PM order releaseed, an
inspection lot is generated (Based on Configuration done).
5. Then process the Insp Lot (UD)n depending on which a status will be
updated for an equipment.
6. Subsequently, process the Maintenace Order & close it.
Config: Assign Calibration inspection type-14 to respective PM Order type.
Master Data:
1. You first create Maintenance Plan (IP41). Considering you've already an
Equipments (IE01), General Tasks List for equipment (IA05) created/available
in system in PM module.
2. Then you schedule Maintenance Plan using IP10.
3. After Scheduling, system generates a Maintenance Order automatically in
background.
4. Then you release Maintenace Order (IW32). Once PM order releaseed, an
inspection lot is generated (Based on Configuration done).
5. Then process the Insp Lot (UD)n depending on which a status will be
updated for an equipment.
6. Subsequently, process the Maintenace Order & close it.
If any query, revert back.
Regards,

o Share

Former Member

Posted onJun 13, 2013 at 10:52 AM

o Create Vernier Caliper as Material with Serial Number Profile


o GR will create the Equipment in background
o Use IE4N method to install the vernier caliper for specific location
o Create Maintenance Plan for the equipment
o Do the scheduling
o According to date of order execution, either In Line inspection or Work
shop inspection can be done
o In Line Inspection doesn't require the vernier caliper to dismantle from
the location
o Workshop Inspection will require dismantling (IE4N) to do the
inspection
As mentioned above, you can get many links for IE4N, Serial Number with
Equipment, Maintenance Planning process.

o Share
o
Former Member
Posted onJun 27, 2013 at 08:40 AM
0
Thanks a lot, Ritesh, Gyan and Maheshwaran.
I was able to have the Inspection lot generated with the help of your replies.
now I have to restrict the PM order generation of the Vernier calippers which
are actually in the stock and not being used on the field.
Regards,
Yawar Khan

o Share

2 Comments
o Former Member
Jun 27, 2013 at 11:45 AM
HI
Just providing the same process which maheswaran mentioned in detail
First create each Vernier Calliper as a separate equipment.
Then move to the config path Plant Maintenance -> Master data in PM-> Basic Settings->
Define User Status
In this create a User Status Profile having User statuses eg. In StocK & In production
During entry of User Status In Stock Select In Stock and in the Menu Bar click Goto->
Transaction control
In transaction Control click on new entries and enter the transaction for Order Assignment
Click on the radio button Forbidden for order assignment
Hence after this whichever vernier caliper has an in stock status it will be forbidden to be
used in an Order or a Not.

hi Karim,
I haven't had much exposure to PRT's but I recall a discussion with some colleagues a while
back that there's isn't any tracking functionality so bear this in mind. Perhaps, one of our experts
here with hands on experience can provide you with more information on the end to end process.
Below is a link to SAP help you may find useful (explore the topics on the left).
Creating Equipment PRTs - Production Resources/Tools (PRT) - SAP Library
Handy transaction codes:
 IE25
 CF25
 CF26
 CF27