EAE Head Quarters Building: Certificate of Payment No.
EAE Head Quarters Building: Certificate of Payment No.
Project: EAE Head Quarters Building Main Contract with VAT 53,303,373.90
AMOUNT (BIRR)
As per the attached Statement the value of work executed and/or material supplied to date is
24,101,470.74
Date AMOUNT (BIRR)
No. AMOUNT (BIRR)
1 Advance 9,270,151.98 Previous payments 17,590,404.24
2 pyt no.1 3,005,664.15 Rebate 15% -
3 pyt no.2 4,075,135.28 Retention 5% 1,150,785.20
4 pyt no.3 4,466,559.43 Penalty -
5 pyt no.4 2,832,543.49 Advance repayment 20% 4,820,294.15
6 pyt no.5 1,501,757.78 Others
We certify the Contractor is now entitled to the sum of Seven Hundred Thirty Six Thousand Nine Hundred Ninety One &
70/100 birr only
I/We_____________ _ here by certify that the above figures are correct and the total value of work executed
and/or material supplied to date is Birr Twenty Four Million One Hundred One Thousand Four Hundred
Seventy &74/100
I/We____________ _ here by certify that the above figures are correct and the total value of work executed
and/or material supplied to date is Birr Eighteen Million Five Hundred Ninety One Thousand Thirty & 81/100 only
I/We____________ _ here by certify that the above figures are correct and the total value of work executed
and/or material supplied to date is Birr Two Hundred Sixty Seven Thousand Ninety Four & 80/100 only
I/We______________ here by certify that the above figures are correct and the total value of work executed
and/or material supplied to date is Birr Six Million Nine Hundred Forty One Thousand One Hundred Seventy
Nine & 21/100 only
I/We____________ _ here by certify that the above figures are correct and the total value of work executed
and/or material supplied to date is Birr Forty Four Thousand Five Hundred Thirty Nine & 65/100 only
I/We____________ _ here by certify that the above figures are correct and the total value of work executed
and/or material supplied to date is Birr Seven Thousand Two Hundred Fifty Nine & 28/100 only
Quantity
Previously Todate
Item Description Unit Contract Excuted Executed Rate Amount
SITE WORK
5. ASPHALT ROAD
CONSTRUCTION
5.1 EXCAVATION & EARTH
5.1.2 WORK
Cart away excavated material m3 6404.8 5694.36 5935.44 45.00 267,094.80
Quantity
Previously To date
Item Description Unit Contract Executed Executed Rate Amount
A. SUB STRUCTURE
1.0 EXCAVATION & EARTH WORK
Back fill around footings, under hardcore
1.4 and arround the building to maintain the m3 34.6 - 269.70 120.00 32,364.00
desired level with selected excavated
Cartaway surplus excavated material to a
1.5 material and compact in layers not
distance not exceeding 5kms.
exceeding 200mm. m3 39.3 - 270.57 45.00 12,175.65
Total to Summary 44,539.65
Item
no Description Unit Qty Rate Amount
1 Cement (OPC) qtl 250 320 80,000.00
2 Cement (PPC) qtl 255 167.75 42,776.25
3 Sand m3 80 170 13,600.00
4 Aggregate m3 64 140 8,960.00
5 Selected Material m3 240 100 24,000.00
6 Reinforcement bars
Dia. 8 kg 6,454.0 11.55 74,543.70
Dia. 10 kg 14,156.6 11.55 163,508.73
Dia. 12 kg 4,930.4 10.85 53,494.84
Dia. 14 kg 1,653.5 10.85 17,940.04
Dia. 16 kg 6,887.6 11.20 77,141.12
Dia. 20 kg 1,894.0 11.20 21,212.80
Dia. 24 kg 9,632.0 11.20 107,878.40
7 RHS 100*100*3.5 Pcs 75.0 745.31 55,898.25
8 RHS 80*80*3.0 Pcs 14.0 425.14 5,951.96
9 RHS 25*25*2.5 Pcs 250.0 93.57 23,392.50
10 RHS 40*40*1.5 Pcs 150.0 127.40 19,110.00
11 RHS 30*30*1.5 Pcs 67.0 93.57 6,269.19
12 HCB 20cm Thick pcs 29,234 8.00 233,872.00
13 HCB15cm Thick pcs 7,623 7.00 53,361.00
14 HCB 10cm Thick pcs 476 6.00 2,856.00
Total 1,085,766.78