Ims Operation Manual Purchase Department: Ivrcl Limited, Hyderabad
Ims Operation Manual Purchase Department: Ivrcl Limited, Hyderabad
CONTENTS
Status Identification
Sl No Name of Document Page No
Rev No Date
AMENDMENT RECORD
PURCHASE PROCEDURE
Obtain a clear Purchase Indent from the Site duly signed by the Site In-charge as per the delegation
of Authority indicated under ‘Delegation of Authority.
Capital Equipment Indents to be forwarded to Executive Director for approval.
ACE price to be mentioned in the Indent wherever possible.
Locate the materials, if already available in surplus from the existing stock at Sites or godown.
Obtain three to four quotations from the approved suppliers in case the material is to be procured.
Make comparative analysis on the Offers received (Technical/Commercial).
Decide strategy of procurement, payments, etc.
Negotiate with the Manufacturers/Suppliers.
Prepare clear Purchase Order, in two copies to be distributed to
a) Suppliers
b) Purchase Department
The Purchase Orders should be signed by the Authorised Signatory as per “Delegation of Authority”.
Expedite receipt of the material to the concerned Site.
Obtain confirmation of receipt in the form of Material Receipt Note as per format from sites along with
t he rejection report, if any.
Copy of Rejection Report intimation to the supplier to be attached to MRN.
Coordinate with Finance/Accounts Department to liquidate the Purchase Orders for balance payment
to the supplier.
Purchase Orders which are liquidated i.e. on which payment has been made are to be noted as being
paid with the details of amount, date, etc.
Maintain a register of all Purchase Orders being issued.
Bills from suppliers are to be taken in triplicate for Accounts Dept./Site copy/Purchase Department
Suppliers of critical materials used for construction purpose, purchased at regional office level shall be
evaluated for their capability to meet the requirements of IVRCL. The existing suppliers, who have
already supplied materials to IVRCL in the past, shall be considered to be registered. The cut-off date for
the same shall by end of year. Information regarding new supplier shall be collected in Details for Supplier
Registration form (IVRCL/OM/PUR/F-01). The supplier registration shall be approved by Vice President –
Commercial / Head – Purchase in the Regional Office. On registration of new supplier, the Approved
Supplier List shall be updated.
The requirement for supplier registration will not be applicable for once-off purchases of off the shelf
items.
Site In-charge shall inform the Site Accounts Officer/Accountant/Purchase Officer to carry out purchase as
per the following procedures:
Obtain a clear Purchase Indent as per format IVR/POL/OSP/PUR 01, duly signed by the Site In-charge.
Obtain two to three quotations from the approved suppliers, for comparison. Site may ask for material
rates from HO, if the material cannot be arranged locally. Head Office shall be contacted by forwarding
the Purchase Indent to Head Office Purchase Department at least two weeks in advance.
Negotiate with the suppliers regarding rates and delivery.
Make comparative analysis on the Offers received.
The offers received. if not fitting within Accepted Cost Estimation (ACE) prices, prior approval should be
obtained from Executive Director submitting due justification/reasons for exceeding the limits.
Prepare clear PURCHASE ORDER and obtain the signature of the Site In-charge to be sent to the
supplier. File a copy of PURCHASE ORDER with supporting offers and comparative statements for
record.
Send copies of PO to HO on weekly/fortnightly basis, indicating clearly the Finance requirement, if any.
Expedite receipt of material.
Receive Delivery Challan (DC)/LR, check whether the material received is as per PURCHASE ORDER,
take into stocks and maintain the stock register. Prepare Material Receipt Note as per format
IVR/POL/OSP/PUR 03 for use of Site Accounts Department.
While accepting the material and acknowledging the receipt to suppliers, it should be clearly mentioned
“The material is accepted subject to re-verification of quantity and quality”. The revivification of quantity &
quality is to be done at the earliest and before the payment due date to the supplier.
Coordinate with Finance/ Accounts Department to liquidate the PO for balance payment to the
supplier.
Note: In case of emergency purchase (which is impossible to plan in advance), Site may purchase the
material to meet the project requirement and regularize the documents within a week. However,
intimation in this regard should be communicated to concerned RO/Division Office/ Executive Director by
Telephone/Fax/Email, etc., and confirmation to be obtained before ordering & procurement.
3.1 Delegation of Financial Powers to procure the materials/equipments at Site/RO /Corporate office per
Purchase Order shall be as follows:
INDENT
The Indent should be given clearly in terms of technical specifications, the minimum order lot quantity,
prevailing units of measurements, Accepted Cost Estimation (ACE) prices, payback period, last procured
price, delivery date, alternative material if acceptable and relevant Indian Standard Code number. The
indentor should mention clearly the name of the Site, place of delivery and put their name below their
signature on every indent.
MATERIAL RECEIPT
Insist for PO copy while accepting the material along with delivery challan (DC). The MRN to be forwarded
immediately to the concerned for necessary action. The rejection advice, if any, to be forwarded to the
supplier immediately and acknowledgement obtained preferably. The MRN to be prepared correctly by
mentioning all the details as detailed in the format.
While placing the PO necessary test certificates to be insisted. Suppliers should be selected carefully as
per their past experience, market survey, getting supporting documentary evidence of their credentials,
etc. to ensure that the material delivered is of good quality only. Try to procure the material directly from
the manufacturer wherever possible. Insist on the quality verification immediately on receipt of material.
Prior samples to be obtained along with the quotations to avoid discrepancies, in future.
START
INDENT
SOURCING OF MATERIAL
TRANSFER INDENT
USE EXISTING DATABASE
3 TO 4 QUOTATIONS
FINAL
END APPROVAL NEGOTIATIONS
PLACEMENT OF ORDER
FOLLOW UP
ORDER COMPLETION
END PAYMENTS
Measurement Records/
Sl No Key Result Area (KRA) Objectives Defined Target
Frequency Reference
1.
2.
(B)Telephone No(S):
(C)Fax No(S):
A) Details of supplier:
Name of the Supplier:
Status of supplier
Purchases made
(in financial year)
Category:
Items dealt:
C) Marks obtained in each criterion to calculate the overall efficiency of the supplier:
Marks obtained
Criteria (Please refer the Contribution Total Points
Full Marks (Max) in each criteria
Rating Procedure) percentage ( M x F)
(M)
Brand Image & service
10
offered: (B)
Quality: (Q) 10
Delivery: (D) 10
Price: (P) 10
Total Points for overall efficiency (out of 100 points) %
Below 35 Rejected
PURCHASE ORDER
Project:
Dear Sir,
We are pleased to inform you that your offer has been accepted to the extent indicated below and as per terms
and conditions specified herein and overleaf. Kindly arrange to supply accordingly.
Del.
Sl No Item Description Unit Quantity Rate Amount in Rs.
Date
Total in Rs.
Remarks
Note:
Please supply the following against this order in accordance with terms & conditions printed overleaf.
PURCHASE INDENT
Date:
P.I. NO. IVRCL
To,
Indentor Details: HO/Site
Payment by: HO/Site
Material to reach site by (Date)
Sir,
Kindly arrange to purchase the following material.
MATERIAL DESCRIPTION
Sl No RATE AMOUNT
(Indentor to indicate clearly the details of materials to be UNIT Qty.
(If known) Rs. Ps.
purchased with relevant specifications L.S. No’s)