DB Lecture 6
DB Lecture 6
PART 1 : CONTRACTS
#2
• As 'contract administrator' with bestowed powers, the Architect assumes a
position of 'leadership'
... setting the tone/culture of the project,
... establishing ethical standards,
... applying professional competence and technical know-how in the design &
supervision of the Works (c.f. Articles 3, 4 & 5 wrt Architect, QS & Consultants ...
'design' and 'supervision' roles).
• Which also gives the Architect status in the wider construction industry.
#3
• Professional competency in contract administration is a significant part of
'architectural services'
... business opportunity.
... (c.f. SIA Scope Matrix: Design, QP, CA, PA/DM)
2. Contracts
a. In a contract between two parties, there is an agreement in
consideration of mutual exchange of things of value (e.g. a
transaction)...
b. • ... both parties mutually executing or refraining from doing
something, where that conduct results in something of
detrimental value to the executor or beneficial value to the
other party.
c. • For example: one party makes a promise to the other for
‘performance’ (e.g. payment in “$”) ... in return for:
‘performance’ or promise of ‘performance’ (e.g. to construct
the building).
d. Both parties have ‘rights’ and ‘obligations’ (e.g. duties) under
the terms of a contract ...
i. ... expressed or implied,
ii. ... stipulated or as reasonably determined.
iii. • For example:
_expressed (mentioned) terms specifying materials
_implied (non-mentioned) terms for SOPA applicability
_Implied (non-mentioned) terms by custom
_implied (non-mentioned) terms by the court (eg prevention)
_stipulated timeframes for payment
_reasonable timeframes for responding to RFIs
e. “Unilateral” Contract:
i. A contract in which only one party makes an express promise, or undertakes
a performance without first securing a reciprocal agreement from the other
party.
ii. In a unilateral, or one-sided, contract, one party, known as the offeror, makes
a promise in exchange for an act (or abstention/refrenation from acting) by
another party, known as the offeree. If the offeree acts on the offeror's
promise, the offeror is legally obligated to fulfil the contract, but an offeree
cannot be forced to act (or not act), because no return promise has been
made to the offeror. After an offeree has performed, only one enforceable
promise exists, that of the offeror.
iii. E.g. Lost dog poster w reward.
f. “Bilateral” Contract ...
i. An agreement formed by an exchange of a promise in which the promise of
one party is consideration supporting the promise of the other party.
ii. eg the Buyer promises to pay the Vendor if the Vendor promises to give an ice
cream, OR vice versa!
iii. ‘Building / Construction Contracts’ are a mode of bilateral contract: ... the
promise of construction of a building in consideration of a promise for
payment.
4. • Formed / made / exists –vs– void* / nullity (if not done properly,
depends on these situations and agreements when it was made.)
a. • Capacity to Contract (eg age, state of mind)
b. • Certainty or Completeness of Terms
c. • Illegality or contra to Public Policy
d. • some Mistakes (fundamental, by both parties)
*eg “void ab initio” = deemed: the contract never existed from the start!
In practical terms, "void" ("null" – never existed) is usually used in contra-distinction to "voidable"
(existed, but rolled back 'as if' it did not exist, and thus unenforceable), the principal difference being
that an action which is 'voidable' remains valid until it is avoided ... it is not ' void ab initio'.
Often a defence when being sued for breach of contract ... asserting that there has never really been a contract !
Often a defence when being sued for breach of contract ... asserting that there is no valid contract !
But the aggrieved party must activate the rescission by opting to rescind and promise or execute return of all benefits obtained under the
contract to the other party, then can sue for restoration to the condition that the parties were in prior to the contract formation.
1. [
C O
N T
R A
C T
===========================================================
4. ['WORKS' COMPLETE] (ie upon date certified in 'substantial' "Completion Certificate" or "Certificate of
Re-Entry")
------------------------------------------------------------------
For example:
• ‘Build-only’ mode #
• D&B (Design & Build / Construct)
• DBO (Design-Build-Operate)
• PPP / PFI (Public-Private Partnership)(DBFO)
• Partnering / Alliances
# Note: Architect is engaged by the Employer (Developer), either: (i) directly [preferred] (ii) under a
Lead Consultant (as a sub-consultant, despite »Arch Act obligations to do/direct on Archi design/drawings
»Architect acting as Contract Administrator)
// Architects typically only "administer" the building contract between the developer and builder, as an independent certifier, under the
'traditional' mode of procurement.
NOTES:
(A) Do not 'change' terms (from tender documents) or the LOA will become a counter-offer! (So, no need for
Contractor to 'agree' to the terms of the LOA, simply to 'acknowledge receipt' of the LOA--i.e. the 'acceptance' must
be communicated).
(B) It is assumed that the blanks in the 'Articles' and 'Appendix' to the Conditions in the standard for SIA building
contract are filled in for the tender documents, so only the above-mentioned 'Confirmation of Terms' are needed for
the LOA to complete the necessary & essential contract terms.
PART 2: THE SIA FORM OF BUILDING CONTRACT
Building Contracts by SIA:
The Singapore Institute of Architects has currently published the following forms
of building contract:
• Articles and Conditions of Building Contract– With Quantities (fka Measurement)contract
• Articles and Conditions of Building Contract– Without Quantities(fka Lump Sum)contract
• Conditions of Sub-Contract to use in conjunction with the Main Contract
• Articles and Conditions of Building Contract for Minor Works
• Specimen Forms and Certificates for use in conjunction with the Main Contract Conditions
• Guidance Notes on Articles and Conditions of Building Contract
3. Sub-Contract:
Whereas a Main Contract (the Lump Sum and Measurement contracts in this case)
is a contract between the Employer and the Contractor, the Sub-Contract is a
contract between the Contractor and a Sub-Contractor.
The SIA form of Sub-Contract is intended for use in conjunction with the Main
Contract under which the Sub-Contractor is nominated or designated by the
Architect (on behalf of the Employer).
When would you use Lump Sum, and when would you use Measurement?
Some considerations:
• Lump Sum doesn’t require BQ so may be faster*(but diff schs of thought from CLoke) to prepare
tender documents.
• Lump Sum does not require actual measurement of as built quantities by the QS, so may have
advantages in regard to time and resources to administer claims for payment.
• As distinct to BQ, in Lump Sum the Contractor assumes the risk of estimating quantities, but may
factor in ‘risk pricing.’
• Lump Sum (if without ‘fluctuation’ of prices) gives a ‘fixed’ price which may be required by
Developer’s financial institutions
1. Authority for architects to command over the contractors (but not unlimited power – only in
relation to the Contractor’s primary contractual obligations…”
2. Power to Certify things
3. Powers to give orders (that the contractor must comply to)
A "Direction" will be used to secure compliance with the Contract and to regularise
unauthorised changes.
But consider that the PSSCOC & SIA MWC do not have 'directions' (only
'instructions' that can cover the purposes of SIA-A&CBC 'directions'):
(hence, if using these contracts, should add on if there should be scope for
additional payment or not)
PSSCOC Sn 19.1 provides that: "The term "variation" … shall exclude any instruction (which would otherwise be a
variation) which has arisen due to or is necessitated by or is intended to cure any default of or breach of contract by
the Contractor." SIA MWC has no "directions" per se, only types of instructions.
Wrongful order
Note: Clause 1 provides that the Contractor may be entitled to
‘compensation’ if the Architect gives an Instruction or Direction without
power or justification to do so.
• Additional Payment / Compensation
• Maybe EOT (where appropriate)
Note: Clause 1 also provides that the Contractor need not comply with:
• Verbal (oral) directions and instructions (not confirmed in writing) by
either Architect or Clerk of Works,
• Other orders or requests not expressed to be instructions or directions
• Be clear/unambiguous (eg use plain simple language) and to the point/succinct although thorough (ie
give the full picture and avoid doubt/misunderstandings).
• Be factual and objective (not emotive) – portray your fairness and impartiality.
• It is good to record the Employer's 'approval' for a variation to be ordered with extra cost (if there is
no formal corresponding RAOV process).
• Some Architects indicate whether EOT is applicable or not.
• Remember that PSSCOC and SIA-MWC only have 'instructions' (and no 'directions') so it may be good
to indicate in the order whether there is any cost implication intended.
• An instruction for variation will be reflected in the financial accounts/payments, thus: Orders for
Variations should be clear on what is 'omitted' from, and what is 'added' to, the Contract (eg "to
provide 'A' in lieu of 'B'"), including clarity of extent & location, specification, etc
– through description &/or by reference to (revised) plans / other Contract Documents.
... and don’t forget to account for ‘aborted’ works already done, including dealing with materials
already ordered, (if applicable).
• Variations often comprise 'design changes' – eg; … you [Contractor] are instructed to provide 600 x 600
x 20mm thk granite slab flooring (to Architect's selection) in the master bedroom, in lieu of the timber strip
flooring specified in the original Contract Documents, in the layout shown in revised drawing No.123 (Rev-01)
…
• Orders should 'echo' the provisions of Contract, eg copy or paraphrase the wording of the Conditions
…
• This is necessary especially for the PSSCOC where there are no standard 'specimen' formats of
orders and certificates, but
• SIA forms of contract do have corresponding standard 'specimen' formats for orders and certificates
which can be used as a basis.
• REMEMBER ... the Conditions do not state that the Order (Instruction/Direction) must be in any
particular ‘Format’ ... • ... ie, the SIA Specimens are for reference only, and are not mandatory!
• Orders must be in writing, either:
• Given in writing (in the first instance)
• Confirmed in writing, if given Orally in the first instance
• ‘In writing’ can be in Format (eg per SIA specimens), by email message, by letter (irrespective of
mode of sending—email or fileshare attachment, by post, by hand, by dispatch, etc).
• Also see SIA MWC: “Architect’s Instruction” for matters with cost and time implication, c.f.
“Architect’s written instruction” to eg secure compliance with contract (maybe just as emails).
What is a “variation?”
Clause 12(2) defines variation as: “…any change in the original contract
intention [or descriptions] …”
Note: PSSCOC similarly provides that:
Sn 19.1: "The term "variation" shall mean any change in the original Contract intention as deduced
from the Contract as a whole describing or defining the Works to be carried out and shall include ...
any changes ... which may be designed to alter the use to which the Works will be put …"
Note:
In PSSCOC, there is only S.O. “Instructions”.
In SIA MWC, there is “Architect’s written instructions” and “Architect’s Instructions”.
Neither have “Directions” per se, but orders with such content are given in
writings/instructions.
“Direction” is unique to the SIA A&CBC forms.
One must read the terms of the Form of Contract in question to determine the means by
which variations can be ordered!