Planning Norms-11 KV
Planning Norms-11 KV
1. 11kV Network:
The 11kV Network shall be considered from Secondary of the Power Transformer in the Grid Substation up to and
including Distribution Transformer.
3. Time Horizon:
The 11kV network shall be studied for a period of 2 years.
4. Loading Conditions:
Distribution Transformer--The Peak Load experienced by the individual DT during last one year irrespective of the
time of incident. (i.e. not simultaneous peak). The data source is Energy audit Group.
11 KV feeders---Trend peak of the last one year under Normal Operating Conditions. The data source is SCADA.
5. Technical Losses
The Peak Technical Loss Limit for 11kV Network shall be 4% max without taking into account LLF.
6. HT Consumers:
The actual peak load (MDI) as per Meter data in last one year or sanctioned load whichever is higher.
7. HVDS:
HVDS connected load shall be assumed with 40% Load Factor for Residential Loads and 60% Load Factors for
Commercial and other loads on the sanctioned load. On this load allocation to be done. In case of industrial HVDS
sum of MDI of individual connections connected on a DT is to be taken as connected load and then load allocation
to be performed. Till such a time DT wise connection detail is not available; allocation to be done on the basis of
installed KVA capacity.
8. Voltage Regulation:
+6% to -9% over declared System voltage of 11kV
Nominal Voltage: 11kV (10.8)
Highest Voltage: 11.66kV (11.44)
Lowest Voltage: 10.01kV (9.83)
Start
Yes
Is there
SLD of 11 KV Validation of SLD Update the Send to GIS
any
Network from GIS by Zone discrepan
SLD for Updation
cy ?
No
Step ‘C’
NO
Modify the N/W as per results of analysis and
Repeat the step ‘A ’ till inadequacy is
addressed
``
Repeat Step’A’ to ‘C’ considering
load growth for 2 and 5 years
respectively.
I
End