Dumb Barge - Split Hopper Barge - Accommodation Barge - Offshore Barge Designs
Dumb Barge - Split Hopper Barge - Accommodation Barge - Offshore Barge Designs
We have many barge designs which are proven, fit for purpose and economical.
Over the years we have gained experience from operation side and clients, which
helps to refine these barge designs.
DECK BARGE DESIGNS
These
dumb barges
are built
based on the
experiences
and feedback
received from
clients ,
equipped with
more
equipment on
deck such as
Ramp Door,
stanchions
and handrail
installed while
maintaining
its capabilities
of cargo
deadweight;
from 1000 to
10000 tonne
s and
deckloading ;
15 to 20
t/m2 . Her
design and Dumb Barge Design
capabilities is
most suitable
for heavy
equipment
transport,
RORO
operations as
well as acting
as a crane
barge . We
have many
designs of
dumb barge
to carry rock
and other
materials to
cater clients
requirement.
CRANE BARGE DESIGNS
This barge is designed for 200 mt crane for 360 degree operation. Barge is
equipped with anti heeling tanks for full operation.
The barge is raked stem with forecastle, transom stern with tug, pusher and
derrick equipments. The main hull below main deck is divided by transverse
and longitudinal bulkheads into ballast water tanks, fresh water tanks, void
tanks and engine room.The barge is designed for carriage of containers as
non-propelled Barge.
A split hopper barge is a vessel with a large open hold, used to load and
transport dredged material. The barge is loaded by a Cutter Suction Dredger
or by a Backhoe Dredger. The barge is self-propelled, and sails to the
deposit area, where it unloads the soil. The vessel consists of two halves,
and unloading is done by opening, or ‘splitting’, the two halves, and
depositing the soil on the seabed.
These designs are suitable for hopper capacity of 600 m3 to 5000 m3 and
deadweight capacity of 1200 mt to 8000 mt. These designs are equipped
with main engine, electric or conventional propulsion, bow thruster, and
suitable accommodation space.
We provides customize structural engineering consultancy services including ship hull design and
offshore engineering starting from feed to economical solution and completion with engineering
supervision in the fabrication, production and regulatory certification stage.
Our experienced naval architects and structure engineers having wide skills in the fields of hull design,
analysis, production support and deep knowledge of the shipbuilding, marine industry and offshore
industry (DNV, ABS, RINA, ASME, API) provide best solutions.
We emphasize on continuous feedback and supervision with shipyards and
manufacturers, where continuous feedback, monitoring and testing reduces
production issues and increases significantly reliability within the entire lifetime of our
design.
Application of modern CAD software (AUTOCAD) allows for efficient passage from
conceptual to detailed design phase (fabrication drawings and 3D models for
structural analysis) ensuring the necessary flexibility to adapt to changing customer
needs.
Softwares like ANSYS, STAAD, etc. allows for analysis and optimization of structures
for yielding,buckling,and fatigue failure modes.
SOLVING MARINE AND OFFSHORE STRUCTURAL PROBLEMS
Our structural engineers and naval architects provide best solutions in finite element
analysis codes assisted by, pre- and post-processing analysis softwares programs to
assess structural adequacy for:
Working stress, LRFD or reliability-based results are provided for detail and
production drawings which will further utilized in bidding and fabrication.
Our professional background includes everything from analysis, research to provide
practical and cost effective production solutions.
MARINE AND OFFSHORE STRUCTURE VIBRATION
Vibration due to diesel engines, whirling vibration of engine shaft lines and plummer
blocks axial vibration are potential problems for any ship's propulsion system.
We are using special assessment tools to provide shaft line alignment analysis and
other supervision techniques to solve operation problems.
We provide FEM solutions for propeller induced vibration,engine foundation vibration
with surrounding hull and accommodation.
We are able to provide measurements of modal characteristics and response
shapes, as well as strain measurements.
FINITE ELEMENT TECHNIQUES
We have the expertise for FE analysis of whole ship and offshore structures,
particularly in the field of dynamic load simulation.We provide best solutions for Hull
Girder Strength & Scantlings , General & Production Structural Drawings, Finite
Element analysis of the Global Hull structure as well as detailed Local analysis of
foundations.
FEM STATIC ANALYSIS
Static analysis is used to determine the displacements, stresses, strains, and forces
in structures or components caused by loads that do not induce significant inertia and
damping effects. Steady loading and response conditions are assumed; that is, the
loads and the structure's response are assumed to vary slowly with respect to time.
Global Analysis
Three hold analysis for Bulk Carriers and Tankers
Hull Openings or moonpool structural analysis
Heavy Crane foundation structure analysis
Helideck Structural Analysis
Accommodation structural Analysis
Mooring winch and towing winch structure Analysis
External Turret Structural Analysis
Jack Up Leg strength Analysis
Stem-to-stern structural analysis of many ships and offshore structures,
beginning with hydrodynamic loads from CFD codes
FATIGUE ANALYSIS
We have provided many high end marine and offshore structure fatigue solutions to
the industry
6 m Boat 40 MT BP Tug
10 m Boat 60 MT BP Tug
20 m Crew Boat 70 MT BP Tug
High Speed Boat Fire fighting Tug
High speed craft Tractor Tug
Police Boat Z pull Tug boat
Resistance and propulsion analysis has been performed for range of vessels for
engineering and consultancy companies to ship owners and from governmental
bodies through classification societies to ship design offices. We focus always on
improving the product of its clientele, or solving their problems.
We have hand on experience in ship resistance & prediction and have used multiple
tools for analysis. We provide following services
We provide stability assessment for all kind of vessels using industry standard
software and classification societies.
Intact stability is the basic and utmost check for ship's sea worthiness and very
important when ship is not damaged.We have done intact stability using various
codes and regulation. Intact stability criteria mainly includes area ratio
checks,minimum area requirement up to down flooding angle or angle of vanishing
stability,Angle for max GZ position and minimum GM etc.
Different classification societies have different set of intact stability rules however
most of these rules have been extracted from IMO code.
Many special conditions Intact stability checks are performed with different codes like
for Towing, lifting,fire fighting,anchor chain handling.
Sufficient GM is very important for Intact stability check and always regarded as one
of the most significant indicator for sufficient stability.
We have years of experience in working with the ABS, Lloyds, DNV, BV, USCG and
IMCI, and can quickly prepare a stability analysis that is fully compliant and rapidly
reviewed and approved by these organizations.
DETERMINISTIC & PROBABILISTIC DAMAGE STABILITY ANALYSIS
Inclining experiment is first step in way of determining ship's stability. It provides vital
data for stability calculation.
Inclining experiment is done in calm weather. Normally weight transfer method or
ballast transfer method is used for inclining experiment. Weights or ballast are shifted
in various stages and heeling angles are measured at every stage.After 6 or 8
stages, we create a relationship between moment generated and heel angle produce
which helps to determine GM of the vessel. Considering Inclining loading condition
VCG, LCG and TCG can be determined. Theses figures obtained from Inclining
experiment will be used to access the stability of the vessel.
))))
SEA KEEPING & SEA WORTHINESS STUDIES
We provide services to provide detailed prediction of sea trials test and and vessel's
motion during navigation,Our in House software can predict vessel's dynamic
stability, turning ability, stopping ability and reverse speed capability. Our expertise is
helping many clients to improve their basic design.
NAVAL ARCHITECTURE & SHIP'S BIDDING PACKAGE
We provide complete engineering solutions for structural analysis and design of lifting
vessel's deck strength and equipment foundations, lifting points, padeyes design,
cross beam design,spreader beam design,lifting gear, cargo seafastening / tie downs
arrangement, reinforcements ,skid shoes / tracks / link bridges and Barge
transportation analysis.
DYNAMIC LIFTING CHECKS
We provide dynamic lifting analysis supported by our high end software packages,
anchoring / mooring patterns, lift rigging , detail drawings, procedure and heavy lifting
safety manuals.Rigging Design to be performed to ensure that the rigging capacity is
within the allowable limit.
MOORING DESIGN & MOORING ANALYSIS IN INDIA
Our naval architects and consultants utilize best industry practices to provide
solutions for mooring analysis such as spread mooring and single point mooring
systems, which includes turrets, CALMs, SALMs, towers, submerged buoys, and
more. We have vast experience in mooring consultation of harbor and jetty moorings,
ships, Barges,accommodation vessels small ships, and for various other offshore
structure
MOORING DESIGN CAPABILITY
We are able to analyze frequency and fully coupled, time domain mooring analysis
for floating vessels, FPSOs and FSOs
Spread mooring
Single point mooring
Semi-Submersible Platforms
Tendon Leg Platforms
Drill ships
Accommodation vessels
Mooring during offshore operation
SPARs
The line hook-up procedure would be repeated for next set of middle lines .These
Mooring lines also shall be re-adjusted to get the final pretensions. In this way, The
line hook-up procedure would be repeated for next set of lines. So basic is that
starting from inner most lines tugs shall work on next set of lines. At the end of this
stage, all mooring lines are connected. Once all the mooring lines are connected and
tensioned, adjustment of the mooring line tension shall be performed to get the
correct positioning of the FPSO (midship location, riser porch location and FPSO
heading). The following sequence is to be used to hook-up each mooring lines to the
FPSO.
Retrieve mooring line end using the subsea or pennant buoy (at the line end
location). Chain end is recovered and locked onto the installation vessel. Buoys and
pennant wires are stored on AHT deck Moves towards FPSO stern corner, relocating
the line up to fairlead of mooring line. Installation vessel shall (with the end of the
chain) move as close as possible towards FPSO, so that it will have minimum
distance from the appropriate fairlead. Meanwhile on the FPSO, mooring wire and
winch sockets are prepared and connected to fairlead. The mooring wire shall be
placed through the chain stopper (open) and stored into the chain chute. At the end
of the mooring wire, A messenger line is attached to the socket. Once the installation
vessel close to the FPSO, the synthetic rope (messenger line) free end is sent to the
installation vessel (while the other end remains attached to the socket). Once the
messenger line is connected to a winch on the installation vessel, the mooring wire is
paid-out from the mooring winch through the chain stopper and fairleads; and the
synthetic rope in paid-in from the AHT to guide the open spelter socket from the
FPSO to the installation vessel. Once the socket at end of the mooring wire is on-
board the AHT deck, the open spelter socket is connected to the last chain link. Once
the chain has passed 15 links inside the chain stopper, chain stopper shall be closed
and messenger line shall be retrieved which is ready to be used onto the next line.
Then the chain stopper shall be opened and the mooring winch is used to set the
chain at 50% of final pretension.
Tugs Requirements
Lead and Stern Tugs
The tugs used for the hook-up operations are usually the same the one used for the
towing operation. Towing is usually designing but in any case, following requirements
are needed for the Lead and Stern Tugs.Bollard pulls of tugs are calculated based on
the force required to keep the FPSO in position with only two lines connected in
specified wave heights, wind and current load in beam and quartering directions.
Installation Vessel
An Installation vessel(INSTALLATION VESSEL) is required to support the hook-up
operation.
The installation vessel shall be fitted with Anchor Handling systems. The installation
vessel shall be able to fit a studless link hydraulic stopper. Installation vessel shall be
fitted with auxiliary winch to heave the messenger line with drum capacity of about
50m.
MEASURES AND TOLERANCES
Positioning System
Recommended systems for the operation are:
DGPS1 with an accuracy of this system lower than +/- 1m. Gyrocompass with an
accuracy lower than +/- 0.2 degree. A DGPS1 surface positioning system shall be
used on the FPSO to position the vessel in the target box. A survey Gyrocompass
shall be sued to install the FPSO with the proper heading. An additional DGPS1/2
system shall be placed at the riser porch tie-in location to monitor the good location
of the riser connection. Positioning systems shall be set with Projection UTM Zone
48, local datum.
Positioning Tolerances
The positioning of the FPSO using above equipment shall be as follow:
FPSO horizontal position tolerance is a box with +/-5m sides from reference point
FPSO heading tolerance is +/-2 deg from reference heading, with a maximum
accuracy of +/- 0.5 deg
Mooring Lines Pretensions
The chain tension will be confirmed by a chain angle measurement gauge that will be
fitted to each mooring chain outboard of the chain chutes.ROV survey between the
distance between the fairleads and the mooring lines touch-down point on the
seabed can be used as confirmation results of the proper tensioning.
Tensions Tolerance
The chain angle accuracy shall be measure with accuracy of 0.5 deg. If ROV
assistance is used, the distance from fairleads to TDP shall be measured with an
accuracy of 5m.Tension calculation using above measurements shall be +/- 5MT
from recommended pretension.
Mooring Chain Twist
The installation shall minimize the twist of the mooring lines. The twist tolerances
shall be as follow:
There shall not be more than 1 twist every 100m. Not more than 3 twists all along the
mooring lines shall be occurring along the whole line. A ROV survey of the mooring
lines shall be conducted to ensure that allowable twist and no kinked chain link
occurs along the mooring lines. Marking of the chain can be used to help control of
the twist during ROV survey.
Emergency Response Plan
The FPSO approach will be timed for the slack water prior to the start of the weaker
ebbing tidal stream. As an overall statement, weather condition shall not exceed for
mooring lines hook-up operation:
Significant Wave Height less than specified Wind speed less than specified Current
velocity less than specified Otherwise, Mooring Line Hook-up is aborted and the line
is retrieved and laid on seabed by the Support Tug. Mooring lines hooked-up remains
attached to the FPSO. The Lead and Stern Tug sets back into a towing configuration
in order to face the up-coming weather.
FPSO Preparation
Prior to FPSO entering the field, a dedicated rigging team will board the vessel to
make final preparations for the hook-up works.
The Tow Master will be in overall charge in Positioning of the FPSO, he will liaise
closely with the Clients Offshore Installation Manager to instruct the different
tugboats for the approach and to hold the FPSO in position during the hookup.
Mooring winches shall be used for the tensioning of the mooring chain legs. Chain
angle measurement gauge shall be prepared.For the hookup operation, synthetic
ropes and appropriate equipment will be prepared on deck at the fore and aft bundles
of the FPSO. All safety equipment shall be as per SOLAS specification, National
Regulation and International applicable standards mooring hookup.
FPSO SPREAD MOORING METHODLOGY
Viscous / drag loads on the hull provides major contribution to the low
frequency damping for all the motions. Estimation is derived from a standard
linear formulation (ITTC).
Damping from mooring lines dynamic: shallow water combined with semi-taut
mooring and limited FPSO motions leads to small contributions to the total
damping
Wave drift damping is also rather small because wave height and low
frequency motions are reduced. Then influence of current on wave drift
damping is also neglected.
Seabed effects : motions on the mooring lines close to the seabed are too
limited to induce friction effects leading to low frequency damping
Then a resulting global linear component has been introduced in the low frequency
simulations with different values for surge, sway and yaw.
The associated levels of damping correspond to 3% of the critical damping in surge
and sway, and 5% in yaw.
Intact load cases matrix
Extreme weather data shall be provided for every regular azimuth angle. Wind, wave
and current are considered collinear and environments are then applied at every
step.
Damaged conditions
In order to predict the maximum offset, cases having the most loaded line for each
bundle of mooring lines shall be considered broken. In order to predict the maximum
tension, another case where the second most loaded line considered broken is
added.
Transient conditions
For the intact cases where the maximum tensions occur (one case per FPSO
loading), transient analyses are performed in order to quantify the transient effect of
one-line failure.
The simulation to be selected should satisfy the following criteria:
The maximum tension is the closest to its design tension in intact conditions,
and
The maximum occurs while the low frequency component of the tension is
increasing.
If the second criterion is not met, the selection procedure should be resumed with the
highest second maximum in the same simulation.
Using the same sets of Airy waves and wind simulations can be repeated. During
these simulations, the line should be broken at different times equally distributed
between the two instants identified.
Extreme Lines Dynamic Analyses
The time series of six D.O.F FPSO motions will be imposed concurrently with the
wave and current effect onto the mooring line. The analysis will be carried out in the
range of the times that cover the maximum line tension and FPSO motions.
The two FPSO loading conditions in the intact and damage cases will be considered.
Sensitivity Analyses
Additional cases will be performed to check the sensitivity of the mooring system in
response to the slight variation conditions as shown below.
Anchor installation tolerances Sensitivity
Sensitivity analyses are carried out in intact condition only. The following anchor
installation tolerance is carried out:
Full QTF Sensitivity
Sensitivity analysis on the two worst cases for each of the 100% and 10% Loaded
Conditions will be performed using Full QTF matrix. This is to compare against the
same cases where Newman approximation is considered.
Hs / Tp Sensitivity
+/- 1s of Tp will be the sensitivity case to investigate the effects of the mooring
system due to changes in Tp and Hs. It will be tested only for the cases that lead to
maximum line tension for both 100% and 10% Loaded Conditions.
Non-Collinear Sensitivity
For the cases that lead to maximum line tension for both 100% and 10% Loaded
Conditions, variation of the wind and current direction from the wave direction shall
be considered.To investigate the effect of the mooring system due to non collinear
environment. These conditions shall be considered
1. With wind @ -30° from waves and current @ +45° from waves.
2. With wind @ +30° from waves and current @ -45° from waves.
3. With wind @ -45° from waves and current @ +30° from wave.
4. With wind @ +45° from waves and current @ -30° from waves.
Offset Sensitivity
+/- 1s of Tp will be the sensitivity case to investigate the effect to the mooring system
due to changes in Tp. It will be tested only for the cases that lead to maximum offset
for both 100% and 10% Loaded Conditions.
Sensitivity analysis on the worst case for each of the 100% and 10% Loaded
Conditions will be performed using different wind spectrum. This is to compare
against the same cases where another wind spectrum is considered.
fpso_spread_mooring_analysis_guide_for_benign_condition.pdf
Download File
JACKET TOPSIDE TRANSPORTATION SEA FASTENING AND INSTALLATION
We provide stability analysis and planning for heel and trim balance by ballasting and
deballasting sequence and loading / off loading, and the up-ending of heavy
structures by heavy lifting crane / ballasting.
A transportation structural analysis shall be performed on the deck subjected
to barge motions associated with towing. Seafastening and grillages shall be
modeled explicitly as structural elements.
Load cases based on conservative combinations of motions are developed using
barge motion data determined by a hydrodynamic analysis for the transportation
barge.
transportation analysis of the topside or heavy modules during wet tow from the
sheltered area to the final installation site requires following checks
The jackets are designed to be placed on the seabed without undue risk of being
overturned, or moved, by the action of wave and current prior to establishment of the
piled foundation.
FLOTATION/UPENDING ANALYSIS
Jacket flotation and upending stability, and jacket member stresses are determined
by using a three dimensional computer simulation.
The stability of the jacket during upending are assessed for roll and pitch movement.
During upend by controlled ballasting, the minimum bottom clearance for the
substructure will follow Noble Denton rules.
Mudmats are designed for the on-bottom weight of the jacket and the additional loads
generated by wind, waves and current prior to installing the piled foundation. The
weight of any piles hanging from the jacket prior to pile driving operations are
included.
The mudmats and their supports shall be designed in accordance with the provisions
of API RP 2A.
MODULAR SPUD BARGE
Modular barges are high quality-built, welded-high tensile steel pontoons specifically
designed for shallow-water, inland-marine environments.
These pontoons are reinforced to withstand repeated and cyclic use under extreme
load conditions. These pontoons are designed in the size of ISO containers, so that
modules can be transferred easily on trucks. These modular units will have recessed
lift shackels at four corners for ease of lifting. This provides an easily accessible
multi-point lift connection for handling the modular units. Special designed locking
system allows these modules to be easily connected side-to-side, end-to-end or end-
to-side. These modular pontoons can be connected in various shape and sized which
allows diversified transport and marine construction activities.
These modular barges are designed to cover ranges of application requirements
involved in various marine activities. These ranges of selectivity provide the user with
the necessary options in portability, strength, and flexibility to obtain the maximum
economic advantage in designing assemblies best suited for their application.
100 MT CAPACITY MODULAR SPUD BARGE
These modular units are designed for upto 100 mt load capacity and easy transport.
Various units of these units are designed for standard shape and size for easy
transportation on loading trucks. These units can be utilized for supporting cranes
with up to 40-ton capacity, pipeline construction, core drilling, dive platforms and
lighter duty material transports. These units also can be used for smaller platforms or
support units for larger platforms.
400 MT CAPACITY MODULAR SPUD BARGE
These modular pontoons are designed to carry 400 mt deck load capacity. Designed
for easy transportation on trucks and trailers.
This pontoons are used as floating and bridging unit in the material and equipment
transportation, dam and bridge construction, mid-range bucket dredging and oil well
servicing. These modular units are designed for operation of 150 mt crane operation.
2500 MT MODULAR SPUD BARGE
These modular pontoons are designed to provide maximum buoyancy and strength.
These are optimum design which can be easily transported on trucks.
This pontoons can take cranes of up to 300-ton capacity and capable of transporting
static loads exceeding 2500 tons. These units are often used in severe applications
involving the heaviest track-mounted and mobile cranes, large hydraulic excavators
and bucket dredges, and deep-well drilling rigs.
MODULAR SELF ELEVATING PLATFORM
We provide complete engineering solutions for structural analysis and design of lifting
vessel's deck strength and equipment foundations, lifting points, padeyes design,
cross beam design,spreader beam design,lifting gear, cargo seafastening / tie downs
arrangement, reinforcements ,skid shoes / tracks / link bridges and Barge
transportation analysis.
DYNAMIC LIFTING CHECKS
We provide dynamic lifting analysis supported by our high end software packages,
anchoring / mooring patterns, lift rigging , detail drawings, procedure and heavy lifting
safety manuals.Rigging Design to be performed to ensure that the rigging capacity is
within the allowable limit.