Method of Statement Excavation and Backfilling
Method of Statement Excavation and Backfilling
PREPARATION/PROTECTION
Protect existing features - temporary barriers and enclosures and applicable local regulations.
Keep excavations clean, free of standing water, and loose soil.
Where soil is subject to significant volume change due to change in moisture content, cover and
protect to owner’s representative’s approval.
Protect natural and man-made features required to remain undisturbed. unless otherwise
indicated or located in an area to be occupied by new construction, protect existing trees from
damage. protect buried services that are required to remain undisturbed.
STRIPPING OF TOPSOIL
Commence topsoil stripping of areas after area has been cleared of brush, weeds and grasses and
removed from site.
Dispose of unused topsoil.
STOCKPILING
Stockpile fill materials in areas designated by Main Contractor. stockpile granular materials in
manner to prevent segregation.
Protect fill materials from contamination.
EXCAVATION
Excavate to lines, grades, elevations and dimensions as indicated by Main Contractor.
Remove concrete, masonry, paving, walks, demolished foundations and rubble and other
obstructions encountered during excavation - selective site demolition.
Excavation must not interfere with bearing capacity of adjacent foundations.
Do not disturb soil within branch spread of trees or shrubs that are to remain. if excavating
through roots, excavate by hand and cut roots with sharp axe or saw.
Keep excavated and stockpiled materials a safe distance away from edge of trench as directed by
Main Contractor.
Restrict vehicle operations directly adjacent to open trenches.
Dispose of surplus and unsuitable excavated material off site.
Do not obstruct flow of surface drainage or natural watercourses.
Earth bottoms of excavations to be undisturbed soil, level, free from loose, soft or organic
matter.
Obtain Main Contractor approval of completed excavation.
Remove unsuitable material from trench bottom to extent and depth as directed by Main
Contractor.
BACKFILLING
Vibratory compaction equipment: approved by Main Contractor.
Do not proceed with backfilling operations until Main Contractor has inspected and approved
installations.
Areas to be backfilled to be free from debris, snow, ice, water and frozen ground.
Place backfill material in uniform layers not exceeding 150 mm compacted thickness up to
grades indicated. compact each layer before placing succeeding layer.
Backfill around installations.
2
Place bedding and surround material.
Place layers simultaneously on both sides of installed work to equalize loading.
difference not to exceed 600 mm.
RESTORATION
Upon completion of work, remove waste materials and debris, trim slopes, and correct
defects as directed by owner’s representative.
Replace topsoil as indicated by Main Contractor.
Reinstate lawns to elevation which existed before excavation.
Clean and reinstate areas affected by work as directed by Main Contractor.
Use temporary plating to support traffic loads over unshrinkable fill for initial 24 h.