Quota 4

The document provides details on the required quantities and sizes of reinforcing bars for different elements of a construction project. It calculates the number of pieces, lengths, and mass of rebar needed for footings, columns, wall footings, slabs, and other structural components. The quantities are determined based on the dimensions and spacing requirements of each element. Various bar diameters and commercial bar lengths are considered to efficiently supply the calculated rebar requirements.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
204 views13 pages

Quota 4

The document provides details on the required quantities and sizes of reinforcing bars for different elements of a construction project. It calculates the number of pieces, lengths, and mass of rebar needed for footings, columns, wall footings, slabs, and other structural components. The quantities are determined based on the dimensions and spacing requirements of each element. Various bar diameters and commercial bar lengths are considered to efficiently supply the calculated rebar requirements.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 13

CE 522- MO1

IV. REINFORCING BARS

A. FOOTING BARS:
F-1 (8 units)= 1.250 m x 1.250 m ; cutting= 1.250 m
Req’d no. of pcs = (No. of bars / footing) (No. of units)
= (5 x 2) (8 units)
= 80 pcs - 12mm Ø bars x 1.25m
*using 12 mmØ x 7.5m:
No. of cuts/length = length of 1 bar/cutting
= 7.5m / 1.25m/cut
= 6 cuts / length
Req’d. no. of lengths = req’d no. of pcs. / (no. of cuts/length)
= 80 / 6
= 12 lengths - 12mm Ø bars x 7.5m &
= 1 lengths - 12mm Ø bars x 10.5m
F-2 (8 units)= 1.50 m x 1.50 m ; cutting= 1.50 m
Req’d no. of pcs = (No. of bars / footing) (No. of units)
= (8 x 2) (8 units)
= 128 pcs - 12mm Ø bars x 1.5m
*using 12 mmØ x 6m:
No. of cuts/length = length of 1 bar/cutting
= 6m / 1.5m/cut
= 4 cuts / length
Req’d. no. of lengths = req’d no. of pcs. / (no. of cuts/length)
= 128 / 4
= 32 lengths - 12mm Ø bars x 6m
F-3 (7 units)= 1.750 m x 1.750 m ; cutting= 1.750 m
Req’d no. of pcs = (No. of bars / footing) (No. of units)
= (12 x 2) (7 units)
= 168 pcs - 12mm Ø bars x 1.75m
*using 12 mmØ x 10.5m:
No. of cuts/length = length of 1 bar/cutting
= 10.5m / 1.75m/cut
= 6 cuts / length
Req’d. no. of lengths = req’d no. of pcs. / (no. of cuts/length)
= 128 / 6
= 28 lengths - 12mm Ø bars x 10.5m
Mass= 520.812 kg

B. COLUMN BARS:
Req’d no. of pcs = (No. of bars / column) (No. of units)
= (4)(21)
= 84 pcs - 16mm dia. bars x 8.29 m
*using 16 mmØ x 9m:
No. of cuts/length = commercial length / length of bar
= 9m / 8.29 m
= 1.09 cut/ length ≈ say 1 cut/ length
Req’d no. of lengths = Req’d no. of pcs. / (no. of cuts/length)
= 84 pcs / 1
= 84 lengths - 16mm Ø bars x 9m
Mass= 1193.47 kg

C. COLUMN TIES:
Cutting = (220x4) + (35x2) = 950 mm = 0.95m
No. of ties per column: (ground floor)
Spaced @ 50 mm = 2 pcs x 2 = 4 pcs @ 50mm= 200 mm
Spaced @ 100 mm = 5pcs. x 2 = 10pcs. @ 100mm = 1000mm
Spaced @ 250mm = 3300 - 1200 = 2100 mm = 9 pcs @ 250 mm
250 mm

Total no. of ties per column = 10 + 4 + 9 = 23 pcs. - 10mm dia. bars x 0.95m
Total no of column ties for ground floor = 23 x 21 = 483 pcs. - 10mm dia. Bars x 0.95m
*using 10 mmØ x 10.5 m:
No. of cuts/length = commercial length / length of bar
= 10.5 m/ 0.95
= 11 cuts / length
Req’d no. of lengths = Req’d no. of pcs. / (no. of cuts/length)
= 483 pcs / 11
= 44 lengths - 10mm Ø bars x 10.5m
Mass= 284.9 kg

No. of ties per column: (second floor)


Spaced @ 50 mm = 2 pcs x 2 = 4 pcs @ 50mm= 200 mm
Spaced @ 100 mm = 5pcs. x 2 = 10pcs. @ 100mm = 1000mm
Spaced @ 250mm = 2600 - 1200 = 1400 mm = 6 pcs @ 250 mm
250 mm

Total no. of ties per column = 10 + 4 + 6 = 20 pcs. - 10mm dia. bars x 0.95m
Total no of ties per column = 20 x 21 = 420 pcs. - 10mm dia. bars x 0.95m
Req’d no. of cuts/length = commercial length / length of bar
= 10.5 / 0.95
= 11 cuts / length
Req’d no. of lengths = Req’d no. of pcs. / (no. of cuts/length)
= 420 pcs/ 11
= 39 lengths - 10mm Ø bars x 10.5m
Mass= 252.525 kg

D. WALL FOOTING REINFORCING BARS:


WF-1 LONGITUDINAL BARS
Total length of WF-1 = 58.5 m
*using 12mm Ø x 6m
Effective Length of Bar = length of bar - (40D)
= 6000 - (40x12)
= 5520 mm = 5.52m
Req’d no. of lengths = (length of wf-1 / effective length) x no. of pcs.
= (58.5 m / 5.52 m) x 3 pcs
= 11 x 3
= 33 lengths - 12mm Ø bars x 6m
Mass= 175.824 kg
LATERAL TIES
Cutting of WF-1 Lateral Ties = 0.4m
Req’d no. of bars = length of wf-1 / spacing
= 58.5 m / 0.25 m
= 234 pcs - 10mm Ø bars x 0.4m
No. of cuts/length = commercial length / length of bar
= 6 m / 0.4 m
= 15 cuts / length
Req’d no. of lengths = Req’d no. of pcs. / (no. of cuts/length)
= 234 pcs/ 15
= 16 lengths - 10mm Ø bars x 6m
Mass= 59.2 kg

WF-2 LONGITUDINAL BARS


Total length of WF-2 = 33.5 m
*using 12mm Ø x 6m
Effective Length of Bar = length of bar - (40D)
= 6000 - (40x12)
= 5520 mm = 5.52m
Req’d no. of lengths = (length of wf-2 / effective length) x no. of pcs.
= (33.5 m/ 5.52 m) x 2 pcs
=7x2
= 14 lengths - 12mm Ø bars x 6m
Mass= 74.592 kg
LATERAL TIES
Cutting of WF-2 Lateral Ties = 0.832m
Req’d no. of bars = length of wf-2 / spacing
= 33.5 m / 0.25 m
= 134 pcs - 10mm Ø bars x 0.832m
No. of cuts/length = commercial length / length of bar
= 7.5 / 0.832
= 9 cuts / length
Req’d no. of lengths = Req’d no. of pcs. / (no. of cuts/length)
= 134 pcs / 9
= 15 lengths - 10mm Ø bars x 6m
Mass= 55.5 kg

E. CHB REBARS
Using AREA METHOD: 477
Mass of CHB Rebars = (net area) (mass / m^2)
= (435.12 m2) (2.47 kg per m2)
= 1074.75 kg
*using 10 mm Ø bars x 6m:
Mass of 1 length = 3.7kg

Req’d no. of lengths = mass of CHB rebars / mass of 1 length


= 1074.75 kg / 3.7 kg
= 291 lengths - 10mm Ø bars x 6m

F. LINTEL BEAM
LONGITUDINAL BARS
Effective Length of Bar = length of bar - (40D)
= 6000 - (40x12)
= 5520 mm = 5.52m
Req’d no. of lengths = (length of wf-1 / effective length) x no. of pcs.
= (58.5 m / 5.52) x 2
= 11 x 2
= 22 lengths - 12mm Ø bars x 6m
Mass= 117.216 kg
LATERAL TIES
Cutting of Lateral Ties = 0.24m

Req’d no. of pcs = length of wf-1 / spacing


= 58.5 m / 0.20 m
= 293 pcs - 10mm Ø bars x 0.24m
No. of cuts/length = commercial length / length of bar
= 6 m / 0.24 m
= 25 cuts / length
Req’d no. of lengths = Req’d no. of pcs. / (no. of cuts/length)
= 293 pcs / 25
= 12 lengths - 10mm Ø bars x 6m
Mass= 44.4 kg
G. SLAB ON GRADE

A1= 9m x 3m
Along S (Length of bar= 3m)
L
Req’d no. of pcs= +1
spacing
9m
= + 1 = 31 pcs – 10 mm Ø x 3m
0.30 m
*using 10 mm Ø x 6 m
6m
No. of cuts/length= = 2 cuts/length
3m
31 pcs
Req’d no. of lengths= ≈ say 16 lengths- 10 mm Ø x 6 m
2 cuts per length

Along L (Length of bar= 9m)


S
Req’d no. of pcs= +1
spacing
3m
= + 1 = 11 pcs – 10 mm Ø x 9 m
0.30 m
*using 10 mm Ø x 9 m
9m
No. of cuts/length= = 1 cut/length
9m
11 pcs
Req’d no. of lengths= ≈ say 11 lengths- 10 mm Ø x 9 m
1cuts per length

A2= 9m x 8m
Along S (Length of bar= 8m)
L
Req’d no. of pcs= +1
spacing
9m
= + 1 = 31 pcs – 10 mm Ø x 8m
0.30 m
*using 10 mm Ø x 9 m
9m
No. of cuts/length= = 1 cut/length
8m
31 pcs
Req’d no. of lengths= ≈ say 31 lengths- 10 mm Ø x 9 m
1cut per length

Along L (Length of bar= 9m)


S
Req’d no. of pcs= +1
spacing
8m
= + 1 = 28 pcs – 10 mm Ø x 9 m
0.30 m
*using 10 mm Ø x 9 m
9m
No. of cuts/length= = 1 cut/length
9m
28 pcs
Req’d no. of lengths= ≈ say 28 lengths- 10 mm Ø x 9 m
1cut per length

A3= 6m x 4m
Along S (Length of bar= 4m)
L
Req’d no. of pcs= +1
spacing
6m
= + 1 = 21 pcs – 10 mm Ø x 4m
0.30 m
*using 10 mm Ø x 9 m
9m
No. of cuts/length= = 2 cuts/length
4m
21 pcs
Req’d no. of lengths= ≈ say 11 lengths- 10 mm Ø x 9 m
2 cuts per length

Along L (Length of bar= 6m)


S
Req’d no. of pcs= +1
spacing
4m
= + 1 = 15 pcs – 10 mm Ø x 6 m
0.30 m
*using 10 mm Ø x 6 m
6m
No. of cuts/length= = 1 cut/length
6m
15 pcs
Req’d no. of lengths= ≈ say 15 lengths- 10 mm Ø x 6 m
1cut per length

H. CATCH BASIN
Size= 0.60 m x 0.60 m (9 units)
U-bars:
Cutting = ((0.55 + (0.05 / 2)) x 2) +0.5
= 1.65m
Req’d no. of pcs. = 2 pcs - 10mm dia. bars x 1.65m (per unit)
=2x9
= 18 pcs - 10mm dia. bars x 1.65m
Req’d no. of cuts per length = commercial length / cutting length
= 10.5 / 1.65
= 6 cuts per length
Req’d no. of lengths = Req’d no. of pcs. / Req’d no. of cuts per length
= 18 / 6
= 3 lengths - 10mm dia. bar x 10.5m

O-bars:
Cutting = 0.5(4) + 0.035(2)
= 2.07m
Req’d no. of pcs. = 2 pcs - 10mm dia. bars x 2.07m (per unit)
=2x9
= 18 pcs - 10mm dia. bars x 2.07m
Req’d no. of cuts per length = commercial length / cutting length
= 10.5 / 2.07
= 5 cuts per length
Req’d no. of lengths = req’d no. of pcs. / req’d no. of cuts per length
= 18 / 5
= 4 lengths - 10mm dia. bar x 10.5m

I. SUSPENDED SLAB
A1
Bottom Bars
Along y
Req’d no. of pcs. = (L / spacing) +1
= (4 m / 0.2 m) + 1
= 21 pcs. - 12mm dia. bar x 3m
= use 11 lengths - 12mm dia. bar x 6 m
Along x (Length of bar = 4 m)
Req’d no. of pcs. = (3 m / 0.2 m) + 1
= 16 pcs. - 12mm dia bars x 4m
= use 8 lengths - 12mm dia. bars x 9m
Top Bars
Cutting = 3 / 4
=3/4
= 0.75 m
Req’d no. of pcs. = (L / spacing) + 1
= (4 m / 0.2 m) + 1
= 21 pcs - 12 mm dia. bars x 0.75 m
= use 3 lengths - 12mm dia. bars x 6 m
Cutting = L / 4
=5/4
= 1.25m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 1.25 m
= use 1 length - 12mm dia. bars x 7.5m
= use 1 length - 12mm dia. bars x 10.5m
Cutting = L / 4
=7/4
= 1.75m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 1.75 m
=use 1 length - 12mm dia. bars x 6m
= use 2 length - 12mm dia. bars x 10.5m
Cutting = L / 4
=8/4
= 2m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 2 m
= use 4 lengths - 12mm dia. bars x 7.5m
Cutting = L / 4
=4/4
= 1m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 1 m
= use 2 lengths - 12mm dia. bars x 7.5m
Cutting = L / 4
= 2.5 / 4
= 0.625m
Req’d no. of pcs. = (L / spacing) + 1
= (5 / 0.2) + 1
= 26 pcs - 12 mm dia. bars x 0.625 m
= use 1 lengths - 12mm dia. bars x 6m
= use 1 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
= 3.5 / 4
= 0.875m
Req’d no. of pcs. = (L / spacing) + 1
= (8 / 0.2) + 1
= 41 pcs - 12 mm dia. bars x 0.875 m
= use 3 lengths - 12mm dia. bars x 10.5m

A2
Bottom Bars 1:
Along x:
Length of bar = 13m
Req’d no. of pcs. = (L / spacing) +1
= (3.5 / 0.2) + 1
= 19 pcs. - 12mm dia. bar x 13m
= use 38 lengths - 12mm dia. bar x 7.5m
Along y :
Length of bar = 3.5m
Req’d no. of pcs. = (13 / 0.2) + 1
= 66 pcs. - 12mm dia bars x 3.5m
= use 22 lengths - 12mm dia. bars x 7.5m
Top Bars 1:
Cutting = L / 4
=2/4
= 0.5m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 0.5 m
= use 1 length - 12mm dia. bars x 10.5m
Cutting = L / 4
=5/4
= 1.25m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1.25 m
= use 3 lengths - 12mm dia. bars x 7.5m
= use 1 length - 12mm dia. bars x 6m
Cutting = L / 4
=7/4
= 1.75m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1.75 m
= use excess length from cutting = 5/4
=use 1 length - 12mm dia. bars x 9m
= use 2 length - 12mm dia. bars x 10.5m

Cutting = L / 4
=8/4
= 2m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 2 m
= use 4 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
=4/4
= 1m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1 m
= use 2 lengths - 12mm dia. bars x 6m
= use 1 length - 12mm dia. bars x 7.5m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (5 / 0.2) + 1
= 26 pcs - 12 mm dia. bars x 1.375 m
= use 4 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (8 / 0.2) + 1
= 41 pcs - 12 mm dia. bars x 1.375 m
= use 6 lengths - 12mm dia. bars x 10.5m
A3
Bottom Bars 1:
Along x:
Length of bar = 3.5m
Req’d no. of pcs. = (L / spacing) +1
= (2.5 / 0.2) + 1
= 14 pcs. - 12mm dia. bar x 3.5m
= use 7 lengths - 12mm dia. bar x 7.5m
Length of bar = 4.5m
Req’d no. of pcs. = (L / spacing) +1
= (3.5 / 0.2) + 1
= 19 pcs. - 12mm dia. bar x 4.5m
= use 10 lengths - 12mm dia. bar x 9m
Length of bar = 2.5m
Req’d no. of pcs. = (L / spacing) +1
= (3.5 / 0.2) + 1
= 19 pcs. - 12mm dia. bar x 2.5m
= use excess from length of bar = 4.5m
= use 6 lengths - 12mm dia. bar x 7.5m
Length of bar = 1.5m
Req’d no. of pcs. = (L / spacing) +1
= (1 / 0.2) + 1
= 6 pcs. - 12mm dia. bar x 1.5m
= use 1 length - 12mm dia. bar x 9m
Length of bar = 2.5m
Req’d no. of pcs. = (L / spacing) +1
= (1.5 / 0.2) + 1
= 9 pcs. - 12mm dia. bar x 2.5m
= use 3 lengths - 12mm dia. bar x 7.5m
Along y :
Length of bar = 2.5m
Req’d no. of pcs. = (3.5 / 0.2) + 1
= 19 pcs. - 12mm dia bars x 2.5m
= use 10 lengths - 12mm dia. bars x 6m
Length of bar = 3.5m
Req’d no. of pcs. = (L / spacing) +1
= (4.5 / 0.2) + 1
= 24 pcs. - 12mm dia. bar x 3.5m
= use 12 lengths - 12mm dia. bar x 7.5m
Length of bar = 3.5m
Req’d no. of pcs. = (L / spacing) +1
= (2.5 / 0.2) + 1
= 14 pcs. - 12mm dia. bar x 3.5m
= use 7 lengths - 12mm dia. bar x 7.5m
Length of bar = 1m
Req’d no. of pcs. = (L / spacing) +1
= (1.5 / 0.2) + 1
= 9 pcs. - 12mm dia. bar x 1m
= use 1 length - 12mm dia. bar x 9m
Length of bar = 1.5m
Req’d no. of pcs. = (L / spacing) +1
= (2.5 / 0.2) + 1
= 14 pcs. - 12mm dia. bar x 1.5m
= use 3 lengths - 12mm dia. bar x 7.5m

Top Bars 1:
Cutting = L / 4
= 3.5 / 4
= 0.875m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 0.875 m
= use 1 length - 12mm dia. bars x 6m
= use 1 length - 12mm dia. bars x 7.5m
Cutting = L / 4
=8/4
= 2m
Req’d no. of pcs. = (L / spacing) + 1
= (4.5 / 0.2) + 1
= 21 pcs - 12 mm dia. bars x 2 m
= use 4 lengths - 12mm dia. bars x 6m
Cutting = L / 4
=7/4
= 1.75m
Req’d no. of pcs. = (L / spacing) + 1
= (1.5 / 0.2) + 1
= 9 pcs - 12 mm dia. bars x 1.75 m
=use 1 length - 12mm dia. bars x 6m
= use 1 length - 12mm dia. bars x 10.5m
Cutting = L / 4
=7/4
= 1m
Req’d no. of pcs. = (L / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs - 12 mm dia. bars x 1 m
= use 1 length - 12mm dia. bars x 6m

Cutting = L / 4
= 2.5 / 4
= 0.625m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 0.625 m
= use 2 lengths - 12mm dia. bars x 6m
= use 1 length - 12mm dia. bars x 7.5m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1.375 m
= use 3 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (4.5 / 0.2) + 1
= 24 pcs - 12 mm dia. bars x 1.375 m
= use 6 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
= 1.5 / 4
= 0.375m
Req’d no. of pcs. = (L / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs - 12 mm dia. bars x 0.375 m
= use 1 length - 12mm dia. bars x 6m
Cutting = L / 4
= 2.5 / 4
= 0.625m
Req’d no. of pcs. = (L / spacing) + 1
= (1.5 / 0.2) + 1
= 9 pcs - 12 mm dia. bars x 0.625 m
= use 1 length - 12mm dia. bars x 6m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1.375 m
= use 3 lengths - 12mm dia. bars x 10.5m

J. STAIRS
Bar 1 - 12 mm dia. bar spaced @ 200mm O.C.
Cutting = 0.15 + y1 + L + x1 + y2
= 0.15 + 0.5 + 2.12 + 1 + 0.28
= 4.05 m
Req’d no. of pcs. = (stair width / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs. - 12 mm dia. bar x 4.05m
= use 3 pcs. - 12mm dia. bars x 9m
Bar 2 - 12mm dia. bar spaced @ 390mm O.C. (temp. bar)
Cutting = stair width
= 1m
Req’d no. of pcs. = (stair width / spacing) + 1
= (1 / 0.39) + 1
= 4 pcs. - 12 mm dia. bars x 1m
= use 1 pc. - 12mm dia. bar x 6m
Bar 3 - 12mm dia. bar spaced @ 200mm O.C.
Cutting = 0.15 + y1 + (L/4)
= 0.15 + 0.5 + (2.12 / 4)
= 1.18 m
Req’d no. of pcs. = (stair width / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs. - 12mm dia. bars x 1.18m
= use 1 pc. - 12mm dia. bar x 7.5m
Bar 4 - 12mm dia. bar spaced @ 200mm O.C.
Cutting = (L/4) + x1 + y2
=(2.12 / 4) + 1 + 0.28
= 1.81m
Req’d no. of pcs. = (stair width / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs. - 12mm dia. bar x 1.81m
= use 1 pc - 12mm dia bar x 7.5m
= use excess length from bars 1 and 2
Bar 5 - 12mm dia. bar spaced @ 200mm O.C. (nosing bar)
Cutting = stair width
= 1m
Req’d no. of pcs. = no. of steps
= 8pcs. - 12mm dia. bars x 1m
= use 1 pc. - 12mm dia. bar x 9m
Bar 6 - 12mm dia. bar spaced @ 200mm O.C.
Cutting = x + y
= 0.25 + 0.18
= 0.43m
Req’d no. of pcs. = ((stair width / spacing) + 1)(total no. of steps)
= ((1 / 0.2) + 1) x 8
= 48 pcs. - 12mm dia. bars x 0.43m
= use 2 pcs. - 12mm dia. bars x 10.5m

K. BEAM REBARS
I. Top Bars
Total Length of Top Bars= 10.46 m

A. Continuous Top Bars


CTB 1
Length= 7.5 m
Req’d = 4 pcs- 25mm Ø x 7.5 m
CTB 2
Length= 10.46 m – 7.5 + 40(0.02) = 3.76 m
Req’d= 4 pcs- 25mm Ø x 3.76 m

B. Extra Top Bars

ETB 1
Length= 1.58 m
Req’d= 1 pc- 25mm Ø x 1.58 m
ETB 2
Length= 2.55 m
Req’d= 1 pc- 25mm Ø x 2.55 m
ETB 3
Length= 1.83 m
Req’d= 1 pc- 25mm Ø x 1.83 m

II. Bottom Bars


A. Continuous Bottom Bars
Total Length of CBB= 10.38 m
CBB 1
Length= 6 m
Req’d= 2 pcs- 25mm Ø x 6m
CBB 2
Length= 5.18 m
Req’d= 2 pcs – 25mm Ø x 5.18 m

B. Extra Bottom Bars


EBB 1
Length= 2.4 m
Req’d= 1 pc- 25mm Ø x 2.4 m
EBB2
Length= 3 m
Req’d= 1 pc- 25mm Ø x 3 m

Summary of 1 unit- B1 Rebars


CTB 1: 4 pcs- 25mm Ø x 7.5 m
CTB 2: 4 pcs- 25mm Ø x 3.76 m Use 2 lengths @ 9m
ETB 1: 1 pc- 25mm Ø x 1.58 m Use 1 length @ 6m (Fab. [email protected], [email protected], [email protected])
ETB 2: 1 pc- 25mm Ø x 2.55 m Use excess from ETB 1
ETB 3: 1 pc- 25mm Ø x 1.83 m Use excess from ETB 1
CBB 1: 2 pcs- 25mm Ø x 6m
CBB 2: 2 pcs – 25mm Ø x 5.18 m Use 2 lengths @ 6m
EBB 1: 1 pc- 25mm Ø x 2.4 m Use 1 length @ 6m (Fab. 1 @ 2.4m, 1 @ 3m)
EBB 2: 1 pc- 25mm Ø x 3 m Use excess from EBB 1

L. STIRRUPS
Cutting of stirrups= 170(2) + 320(2) + 35(2)= 1050 mm = 1.05 m

L1
Spaced @ 50 mm= 2 x 2 = 4 pcs @ 50 mm= 200 mm
Spaced @ 100 mm= 5 x 2 = 10 pcs @ 100 mm= 1000 mm
Spaced @ 150 mm= 4000-1200= 2800 mm/ 150mm = 19 pcs
No. of stirrups for L1= 33 pcs- 10mm Ø x 1.05 m

L2
Spaced @ 50 mm= 2 x 2 = 4 pcs @ 50 mm= 200 mm
Spaced @ 100 mm= 5 x 2 = 10 pcs @ 100 mm= 1000 mm
Spaced @ 150 mm= 5000-1200= 3800 mm/ 150mm = 26 pcs
No. of stirrups for L1= 40 pcs- 10mm Ø x 1.05 m
Total number of B1 stirrups= 73 pcs- 10mm Ø x 1.05 m

*using 10 mm Ø x 10.5 m
10.5 m
No. of cuts/ length= = 10 cuts/length
1.05
73 pcs
Req’d no. of lengths= = 7.3 lengths
10 cuts per length
≈ say 8 lengths- 10 mm Ø x 10.5 m

GENERAL SUMMARY OF REINFORCING BARS


365 lengths - 10mm Ø bars x 6m
81 lengths - 10mm Ø bars x 9m
170 lengths - 10mm Ø bars x 10.5m
110 lengths - 12mm Ø bars x 6m
113 lengths - 12mm Ø bars x 7.5m
25 lengths - 12mm Ø bars x 9m
39 lengths - 12mm Ø bars x 10.5m
105 lengths - 16mm Ø bars x 6m
68 lengths - 16mm Ø bars x 9m
50 lengths - 25mm Ø bars x 6m
40 lengths - 25mm Ø bars x 7.5m
Total Mass= 1350.5 + 449.55 + 1100.75 + 586.08 + 752.58 + 199.8 + 363.636 + 994.56 + 966.144
+ 1156.25 + 1156.25
Total Mass= 9076.1 kg

Req’d No. 16 GI Tie Wire = 2% (Total mass of rebars) = 2% (9076.1 kg) = 181.522 kg
A. MATERIAL COST
365 lengths - 10mm Ø bars x 6m @ php162.62 = PHP 59,356.00
81 lengths - 10mm Ø bars x 9m @ php243.94 = PHP 19,759.14
170 lengths - 10mm Ø bars x 10.5m @ php284.59 = PHP 48,380.30
110 lengths - 12mm Ø bars x 6m @ php234.43 = PHP 25,757.30
113 lengths - 12mm Ø bars x 7.5m @ php293.04 = PHP 33,113.52
25 lengths - 12mm Ø bars x 9m @ php351.65 = PHP 8,791.25
39 lengths - 12mm Ø bars x 10.5m @ php410.26 = PHP 16,000.14
105 lengths - 16mm Ø bars x 6m @ php412.80 = PHP 43,334.00
68 lengths - 16mm Ø bars x 9m @ php619.21 = PHP 42,106.28
50 lengths - 25mm Ø bars x 6m @ php1007.94 = PHP 50,397.00
40 lengths - 25mm Ø bars x 7.5m @ php1259.93 = PHP 50,397.20
181.522 kg No. 16 GI Tie Wire – php85.00/kg = PHP 15,429.37
Total Material Cost = PHP 412,821.50

MANPOWER CAPABILITY
*Fabrication & installation of rebars
1 steel crew can accomplish 100 kg/day

Using 2 steel crews:


Accomplishment/day= 100 kg/day x 2 steel crews
= 200 kg/day
9076.1 kg
No. of days= ≈ 49 days
200 kg per day

B. MANPOWER COST
2 Steelman @ PHP 380.00/day for 49 days= PHP 37,240.00
2 Laborers @ PHP 366.00/day for 49 days= PHP 35,868.00
Total Manpower Cost = PHP 73,108.00

C. EQUIPMENT RENTAL
1 bar cutter @ PHP 200.00/day for 49 days = PHP 9,800.00

Total Direct Cost = Material Cost + Manpower Cost + Equipment Rental


Total Direct Cost = PHP 495,729.50
PHP 495,729.50
Direct Unit Cost= = PHP 54.62/ kg
9076.1 kg
Adjusted Unit Cost (40% Mark-up)= PHP 54.62/kg x 1.40 = PHP 76.47/ kg
Total Adjusted Cost = PHP 76.47/ kg x 9076.1 kg
Total Adjusted Cost = PHP 694,049.37