Quota 4
Quota 4
A. FOOTING BARS:
F-1 (8 units)= 1.250 m x 1.250 m ; cutting= 1.250 m
Req’d no. of pcs = (No. of bars / footing) (No. of units)
= (5 x 2) (8 units)
= 80 pcs - 12mm Ø bars x 1.25m
*using 12 mmØ x 7.5m:
No. of cuts/length = length of 1 bar/cutting
= 7.5m / 1.25m/cut
= 6 cuts / length
Req’d. no. of lengths = req’d no. of pcs. / (no. of cuts/length)
= 80 / 6
= 12 lengths - 12mm Ø bars x 7.5m &
= 1 lengths - 12mm Ø bars x 10.5m
F-2 (8 units)= 1.50 m x 1.50 m ; cutting= 1.50 m
Req’d no. of pcs = (No. of bars / footing) (No. of units)
= (8 x 2) (8 units)
= 128 pcs - 12mm Ø bars x 1.5m
*using 12 mmØ x 6m:
No. of cuts/length = length of 1 bar/cutting
= 6m / 1.5m/cut
= 4 cuts / length
Req’d. no. of lengths = req’d no. of pcs. / (no. of cuts/length)
= 128 / 4
= 32 lengths - 12mm Ø bars x 6m
F-3 (7 units)= 1.750 m x 1.750 m ; cutting= 1.750 m
Req’d no. of pcs = (No. of bars / footing) (No. of units)
= (12 x 2) (7 units)
= 168 pcs - 12mm Ø bars x 1.75m
*using 12 mmØ x 10.5m:
No. of cuts/length = length of 1 bar/cutting
= 10.5m / 1.75m/cut
= 6 cuts / length
Req’d. no. of lengths = req’d no. of pcs. / (no. of cuts/length)
= 128 / 6
= 28 lengths - 12mm Ø bars x 10.5m
Mass= 520.812 kg
B. COLUMN BARS:
Req’d no. of pcs = (No. of bars / column) (No. of units)
= (4)(21)
= 84 pcs - 16mm dia. bars x 8.29 m
*using 16 mmØ x 9m:
No. of cuts/length = commercial length / length of bar
= 9m / 8.29 m
= 1.09 cut/ length ≈ say 1 cut/ length
Req’d no. of lengths = Req’d no. of pcs. / (no. of cuts/length)
= 84 pcs / 1
= 84 lengths - 16mm Ø bars x 9m
Mass= 1193.47 kg
C. COLUMN TIES:
Cutting = (220x4) + (35x2) = 950 mm = 0.95m
No. of ties per column: (ground floor)
Spaced @ 50 mm = 2 pcs x 2 = 4 pcs @ 50mm= 200 mm
Spaced @ 100 mm = 5pcs. x 2 = 10pcs. @ 100mm = 1000mm
Spaced @ 250mm = 3300 - 1200 = 2100 mm = 9 pcs @ 250 mm
250 mm
Total no. of ties per column = 10 + 4 + 9 = 23 pcs. - 10mm dia. bars x 0.95m
Total no of column ties for ground floor = 23 x 21 = 483 pcs. - 10mm dia. Bars x 0.95m
*using 10 mmØ x 10.5 m:
No. of cuts/length = commercial length / length of bar
= 10.5 m/ 0.95
= 11 cuts / length
Req’d no. of lengths = Req’d no. of pcs. / (no. of cuts/length)
= 483 pcs / 11
= 44 lengths - 10mm Ø bars x 10.5m
Mass= 284.9 kg
Total no. of ties per column = 10 + 4 + 6 = 20 pcs. - 10mm dia. bars x 0.95m
Total no of ties per column = 20 x 21 = 420 pcs. - 10mm dia. bars x 0.95m
Req’d no. of cuts/length = commercial length / length of bar
= 10.5 / 0.95
= 11 cuts / length
Req’d no. of lengths = Req’d no. of pcs. / (no. of cuts/length)
= 420 pcs/ 11
= 39 lengths - 10mm Ø bars x 10.5m
Mass= 252.525 kg
E. CHB REBARS
Using AREA METHOD: 477
Mass of CHB Rebars = (net area) (mass / m^2)
= (435.12 m2) (2.47 kg per m2)
= 1074.75 kg
*using 10 mm Ø bars x 6m:
Mass of 1 length = 3.7kg
F. LINTEL BEAM
LONGITUDINAL BARS
Effective Length of Bar = length of bar - (40D)
= 6000 - (40x12)
= 5520 mm = 5.52m
Req’d no. of lengths = (length of wf-1 / effective length) x no. of pcs.
= (58.5 m / 5.52) x 2
= 11 x 2
= 22 lengths - 12mm Ø bars x 6m
Mass= 117.216 kg
LATERAL TIES
Cutting of Lateral Ties = 0.24m
A1= 9m x 3m
Along S (Length of bar= 3m)
L
Req’d no. of pcs= +1
spacing
9m
= + 1 = 31 pcs – 10 mm Ø x 3m
0.30 m
*using 10 mm Ø x 6 m
6m
No. of cuts/length= = 2 cuts/length
3m
31 pcs
Req’d no. of lengths= ≈ say 16 lengths- 10 mm Ø x 6 m
2 cuts per length
A2= 9m x 8m
Along S (Length of bar= 8m)
L
Req’d no. of pcs= +1
spacing
9m
= + 1 = 31 pcs – 10 mm Ø x 8m
0.30 m
*using 10 mm Ø x 9 m
9m
No. of cuts/length= = 1 cut/length
8m
31 pcs
Req’d no. of lengths= ≈ say 31 lengths- 10 mm Ø x 9 m
1cut per length
A3= 6m x 4m
Along S (Length of bar= 4m)
L
Req’d no. of pcs= +1
spacing
6m
= + 1 = 21 pcs – 10 mm Ø x 4m
0.30 m
*using 10 mm Ø x 9 m
9m
No. of cuts/length= = 2 cuts/length
4m
21 pcs
Req’d no. of lengths= ≈ say 11 lengths- 10 mm Ø x 9 m
2 cuts per length
H. CATCH BASIN
Size= 0.60 m x 0.60 m (9 units)
U-bars:
Cutting = ((0.55 + (0.05 / 2)) x 2) +0.5
= 1.65m
Req’d no. of pcs. = 2 pcs - 10mm dia. bars x 1.65m (per unit)
=2x9
= 18 pcs - 10mm dia. bars x 1.65m
Req’d no. of cuts per length = commercial length / cutting length
= 10.5 / 1.65
= 6 cuts per length
Req’d no. of lengths = Req’d no. of pcs. / Req’d no. of cuts per length
= 18 / 6
= 3 lengths - 10mm dia. bar x 10.5m
O-bars:
Cutting = 0.5(4) + 0.035(2)
= 2.07m
Req’d no. of pcs. = 2 pcs - 10mm dia. bars x 2.07m (per unit)
=2x9
= 18 pcs - 10mm dia. bars x 2.07m
Req’d no. of cuts per length = commercial length / cutting length
= 10.5 / 2.07
= 5 cuts per length
Req’d no. of lengths = req’d no. of pcs. / req’d no. of cuts per length
= 18 / 5
= 4 lengths - 10mm dia. bar x 10.5m
I. SUSPENDED SLAB
A1
Bottom Bars
Along y
Req’d no. of pcs. = (L / spacing) +1
= (4 m / 0.2 m) + 1
= 21 pcs. - 12mm dia. bar x 3m
= use 11 lengths - 12mm dia. bar x 6 m
Along x (Length of bar = 4 m)
Req’d no. of pcs. = (3 m / 0.2 m) + 1
= 16 pcs. - 12mm dia bars x 4m
= use 8 lengths - 12mm dia. bars x 9m
Top Bars
Cutting = 3 / 4
=3/4
= 0.75 m
Req’d no. of pcs. = (L / spacing) + 1
= (4 m / 0.2 m) + 1
= 21 pcs - 12 mm dia. bars x 0.75 m
= use 3 lengths - 12mm dia. bars x 6 m
Cutting = L / 4
=5/4
= 1.25m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 1.25 m
= use 1 length - 12mm dia. bars x 7.5m
= use 1 length - 12mm dia. bars x 10.5m
Cutting = L / 4
=7/4
= 1.75m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 1.75 m
=use 1 length - 12mm dia. bars x 6m
= use 2 length - 12mm dia. bars x 10.5m
Cutting = L / 4
=8/4
= 2m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 2 m
= use 4 lengths - 12mm dia. bars x 7.5m
Cutting = L / 4
=4/4
= 1m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 1 m
= use 2 lengths - 12mm dia. bars x 7.5m
Cutting = L / 4
= 2.5 / 4
= 0.625m
Req’d no. of pcs. = (L / spacing) + 1
= (5 / 0.2) + 1
= 26 pcs - 12 mm dia. bars x 0.625 m
= use 1 lengths - 12mm dia. bars x 6m
= use 1 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
= 3.5 / 4
= 0.875m
Req’d no. of pcs. = (L / spacing) + 1
= (8 / 0.2) + 1
= 41 pcs - 12 mm dia. bars x 0.875 m
= use 3 lengths - 12mm dia. bars x 10.5m
A2
Bottom Bars 1:
Along x:
Length of bar = 13m
Req’d no. of pcs. = (L / spacing) +1
= (3.5 / 0.2) + 1
= 19 pcs. - 12mm dia. bar x 13m
= use 38 lengths - 12mm dia. bar x 7.5m
Along y :
Length of bar = 3.5m
Req’d no. of pcs. = (13 / 0.2) + 1
= 66 pcs. - 12mm dia bars x 3.5m
= use 22 lengths - 12mm dia. bars x 7.5m
Top Bars 1:
Cutting = L / 4
=2/4
= 0.5m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 0.5 m
= use 1 length - 12mm dia. bars x 10.5m
Cutting = L / 4
=5/4
= 1.25m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1.25 m
= use 3 lengths - 12mm dia. bars x 7.5m
= use 1 length - 12mm dia. bars x 6m
Cutting = L / 4
=7/4
= 1.75m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1.75 m
= use excess length from cutting = 5/4
=use 1 length - 12mm dia. bars x 9m
= use 2 length - 12mm dia. bars x 10.5m
Cutting = L / 4
=8/4
= 2m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 2 m
= use 4 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
=4/4
= 1m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1 m
= use 2 lengths - 12mm dia. bars x 6m
= use 1 length - 12mm dia. bars x 7.5m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (5 / 0.2) + 1
= 26 pcs - 12 mm dia. bars x 1.375 m
= use 4 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (8 / 0.2) + 1
= 41 pcs - 12 mm dia. bars x 1.375 m
= use 6 lengths - 12mm dia. bars x 10.5m
A3
Bottom Bars 1:
Along x:
Length of bar = 3.5m
Req’d no. of pcs. = (L / spacing) +1
= (2.5 / 0.2) + 1
= 14 pcs. - 12mm dia. bar x 3.5m
= use 7 lengths - 12mm dia. bar x 7.5m
Length of bar = 4.5m
Req’d no. of pcs. = (L / spacing) +1
= (3.5 / 0.2) + 1
= 19 pcs. - 12mm dia. bar x 4.5m
= use 10 lengths - 12mm dia. bar x 9m
Length of bar = 2.5m
Req’d no. of pcs. = (L / spacing) +1
= (3.5 / 0.2) + 1
= 19 pcs. - 12mm dia. bar x 2.5m
= use excess from length of bar = 4.5m
= use 6 lengths - 12mm dia. bar x 7.5m
Length of bar = 1.5m
Req’d no. of pcs. = (L / spacing) +1
= (1 / 0.2) + 1
= 6 pcs. - 12mm dia. bar x 1.5m
= use 1 length - 12mm dia. bar x 9m
Length of bar = 2.5m
Req’d no. of pcs. = (L / spacing) +1
= (1.5 / 0.2) + 1
= 9 pcs. - 12mm dia. bar x 2.5m
= use 3 lengths - 12mm dia. bar x 7.5m
Along y :
Length of bar = 2.5m
Req’d no. of pcs. = (3.5 / 0.2) + 1
= 19 pcs. - 12mm dia bars x 2.5m
= use 10 lengths - 12mm dia. bars x 6m
Length of bar = 3.5m
Req’d no. of pcs. = (L / spacing) +1
= (4.5 / 0.2) + 1
= 24 pcs. - 12mm dia. bar x 3.5m
= use 12 lengths - 12mm dia. bar x 7.5m
Length of bar = 3.5m
Req’d no. of pcs. = (L / spacing) +1
= (2.5 / 0.2) + 1
= 14 pcs. - 12mm dia. bar x 3.5m
= use 7 lengths - 12mm dia. bar x 7.5m
Length of bar = 1m
Req’d no. of pcs. = (L / spacing) +1
= (1.5 / 0.2) + 1
= 9 pcs. - 12mm dia. bar x 1m
= use 1 length - 12mm dia. bar x 9m
Length of bar = 1.5m
Req’d no. of pcs. = (L / spacing) +1
= (2.5 / 0.2) + 1
= 14 pcs. - 12mm dia. bar x 1.5m
= use 3 lengths - 12mm dia. bar x 7.5m
Top Bars 1:
Cutting = L / 4
= 3.5 / 4
= 0.875m
Req’d no. of pcs. = (L / spacing) + 1
= (2.5 / 0.2) + 1
= 14 pcs - 12 mm dia. bars x 0.875 m
= use 1 length - 12mm dia. bars x 6m
= use 1 length - 12mm dia. bars x 7.5m
Cutting = L / 4
=8/4
= 2m
Req’d no. of pcs. = (L / spacing) + 1
= (4.5 / 0.2) + 1
= 21 pcs - 12 mm dia. bars x 2 m
= use 4 lengths - 12mm dia. bars x 6m
Cutting = L / 4
=7/4
= 1.75m
Req’d no. of pcs. = (L / spacing) + 1
= (1.5 / 0.2) + 1
= 9 pcs - 12 mm dia. bars x 1.75 m
=use 1 length - 12mm dia. bars x 6m
= use 1 length - 12mm dia. bars x 10.5m
Cutting = L / 4
=7/4
= 1m
Req’d no. of pcs. = (L / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs - 12 mm dia. bars x 1 m
= use 1 length - 12mm dia. bars x 6m
Cutting = L / 4
= 2.5 / 4
= 0.625m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 0.625 m
= use 2 lengths - 12mm dia. bars x 6m
= use 1 length - 12mm dia. bars x 7.5m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1.375 m
= use 3 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (4.5 / 0.2) + 1
= 24 pcs - 12 mm dia. bars x 1.375 m
= use 6 lengths - 12mm dia. bars x 10.5m
Cutting = L / 4
= 1.5 / 4
= 0.375m
Req’d no. of pcs. = (L / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs - 12 mm dia. bars x 0.375 m
= use 1 length - 12mm dia. bars x 6m
Cutting = L / 4
= 2.5 / 4
= 0.625m
Req’d no. of pcs. = (L / spacing) + 1
= (1.5 / 0.2) + 1
= 9 pcs - 12 mm dia. bars x 0.625 m
= use 1 length - 12mm dia. bars x 6m
Cutting = L / 4
= 5.5 / 4
= 1.375m
Req’d no. of pcs. = (L / spacing) + 1
= (3.5 / 0.2) + 1
= 19 pcs - 12 mm dia. bars x 1.375 m
= use 3 lengths - 12mm dia. bars x 10.5m
J. STAIRS
Bar 1 - 12 mm dia. bar spaced @ 200mm O.C.
Cutting = 0.15 + y1 + L + x1 + y2
= 0.15 + 0.5 + 2.12 + 1 + 0.28
= 4.05 m
Req’d no. of pcs. = (stair width / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs. - 12 mm dia. bar x 4.05m
= use 3 pcs. - 12mm dia. bars x 9m
Bar 2 - 12mm dia. bar spaced @ 390mm O.C. (temp. bar)
Cutting = stair width
= 1m
Req’d no. of pcs. = (stair width / spacing) + 1
= (1 / 0.39) + 1
= 4 pcs. - 12 mm dia. bars x 1m
= use 1 pc. - 12mm dia. bar x 6m
Bar 3 - 12mm dia. bar spaced @ 200mm O.C.
Cutting = 0.15 + y1 + (L/4)
= 0.15 + 0.5 + (2.12 / 4)
= 1.18 m
Req’d no. of pcs. = (stair width / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs. - 12mm dia. bars x 1.18m
= use 1 pc. - 12mm dia. bar x 7.5m
Bar 4 - 12mm dia. bar spaced @ 200mm O.C.
Cutting = (L/4) + x1 + y2
=(2.12 / 4) + 1 + 0.28
= 1.81m
Req’d no. of pcs. = (stair width / spacing) + 1
= (1 / 0.2) + 1
= 6 pcs. - 12mm dia. bar x 1.81m
= use 1 pc - 12mm dia bar x 7.5m
= use excess length from bars 1 and 2
Bar 5 - 12mm dia. bar spaced @ 200mm O.C. (nosing bar)
Cutting = stair width
= 1m
Req’d no. of pcs. = no. of steps
= 8pcs. - 12mm dia. bars x 1m
= use 1 pc. - 12mm dia. bar x 9m
Bar 6 - 12mm dia. bar spaced @ 200mm O.C.
Cutting = x + y
= 0.25 + 0.18
= 0.43m
Req’d no. of pcs. = ((stair width / spacing) + 1)(total no. of steps)
= ((1 / 0.2) + 1) x 8
= 48 pcs. - 12mm dia. bars x 0.43m
= use 2 pcs. - 12mm dia. bars x 10.5m
K. BEAM REBARS
I. Top Bars
Total Length of Top Bars= 10.46 m
ETB 1
Length= 1.58 m
Req’d= 1 pc- 25mm Ø x 1.58 m
ETB 2
Length= 2.55 m
Req’d= 1 pc- 25mm Ø x 2.55 m
ETB 3
Length= 1.83 m
Req’d= 1 pc- 25mm Ø x 1.83 m
L. STIRRUPS
Cutting of stirrups= 170(2) + 320(2) + 35(2)= 1050 mm = 1.05 m
L1
Spaced @ 50 mm= 2 x 2 = 4 pcs @ 50 mm= 200 mm
Spaced @ 100 mm= 5 x 2 = 10 pcs @ 100 mm= 1000 mm
Spaced @ 150 mm= 4000-1200= 2800 mm/ 150mm = 19 pcs
No. of stirrups for L1= 33 pcs- 10mm Ø x 1.05 m
L2
Spaced @ 50 mm= 2 x 2 = 4 pcs @ 50 mm= 200 mm
Spaced @ 100 mm= 5 x 2 = 10 pcs @ 100 mm= 1000 mm
Spaced @ 150 mm= 5000-1200= 3800 mm/ 150mm = 26 pcs
No. of stirrups for L1= 40 pcs- 10mm Ø x 1.05 m
Total number of B1 stirrups= 73 pcs- 10mm Ø x 1.05 m
*using 10 mm Ø x 10.5 m
10.5 m
No. of cuts/ length= = 10 cuts/length
1.05
73 pcs
Req’d no. of lengths= = 7.3 lengths
10 cuts per length
≈ say 8 lengths- 10 mm Ø x 10.5 m
Req’d No. 16 GI Tie Wire = 2% (Total mass of rebars) = 2% (9076.1 kg) = 181.522 kg
A. MATERIAL COST
365 lengths - 10mm Ø bars x 6m @ php162.62 = PHP 59,356.00
81 lengths - 10mm Ø bars x 9m @ php243.94 = PHP 19,759.14
170 lengths - 10mm Ø bars x 10.5m @ php284.59 = PHP 48,380.30
110 lengths - 12mm Ø bars x 6m @ php234.43 = PHP 25,757.30
113 lengths - 12mm Ø bars x 7.5m @ php293.04 = PHP 33,113.52
25 lengths - 12mm Ø bars x 9m @ php351.65 = PHP 8,791.25
39 lengths - 12mm Ø bars x 10.5m @ php410.26 = PHP 16,000.14
105 lengths - 16mm Ø bars x 6m @ php412.80 = PHP 43,334.00
68 lengths - 16mm Ø bars x 9m @ php619.21 = PHP 42,106.28
50 lengths - 25mm Ø bars x 6m @ php1007.94 = PHP 50,397.00
40 lengths - 25mm Ø bars x 7.5m @ php1259.93 = PHP 50,397.20
181.522 kg No. 16 GI Tie Wire – php85.00/kg = PHP 15,429.37
Total Material Cost = PHP 412,821.50
MANPOWER CAPABILITY
*Fabrication & installation of rebars
1 steel crew can accomplish 100 kg/day
B. MANPOWER COST
2 Steelman @ PHP 380.00/day for 49 days= PHP 37,240.00
2 Laborers @ PHP 366.00/day for 49 days= PHP 35,868.00
Total Manpower Cost = PHP 73,108.00
C. EQUIPMENT RENTAL
1 bar cutter @ PHP 200.00/day for 49 days = PHP 9,800.00