Name: Rishnay Akash Lal ID: S2018000228 (School of Building and Civil)

This document contains a CPM (Critical Path Method) network analysis for a project with activities A through K. It lists the activities, expected durations, earliest and latest start and finish times, and identifies the critical path through the network as activities A, C, F, I, and K with a total project duration of 23 days. It also includes calculations to determine the probability of completing the project within certain timeframes and identifies latest start times to achieve a 96% probability.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views

Name: Rishnay Akash Lal ID: S2018000228 (School of Building and Civil)

This document contains a CPM (Critical Path Method) network analysis for a project with activities A through K. It lists the activities, expected durations, earliest and latest start and finish times, and identifies the critical path through the network as activities A, C, F, I, and K with a total project duration of 23 days. It also includes calculations to determine the probability of completing the project within certain timeframes and identifies latest start times to achieve a 96% probability.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Name: Rishnay Akash Lal ID: S2018000228 (School of Building and Civil)

CPM Tutorial Exercise


Activit Predecessor Optimisti Most Pessimistic Expected Variance S. Dev
y c (a) Likely (b) time (V) (σ)
(m) (ET)
A None 4 6 8 6 0.44 0.66
B None 1 4.5 5 4 0.44 0.66
C A 3 3 3 3 0 0
D A 4 5 6 5 0.11 0.33
E A 0.5 1 1.5 1 0.03 0.17
F B, C 3 4 5 4 0.11 0.33
G B, C 1 1.5 5 2 0.44 0.66
H E, F 5 6 7 6 0.11 0.33
I E, F 2 5 8 5 1 1
J D, H 2.5 2.75 4.5 3 0.11 0.33
K G, I 3 5 7 5 0.44 0.66

Activity Durations Earliest Earliest Late Late Floats/Slacks Critical


(Days) Start (ES) Finish Start Finish Path
(EF) (LS) (LF)
A 6 0 6 0 6 0 Yes
B 4 0 4 5 9 5
C 3 6 9 6 9 0 Yes
D 5 6 11 15 20 9
E 1 6 12 12 13 6
F 4 9 13 9 13 0 Yes
G 2 9 11 16 18 7
H 6 13 19 14 20 1
I 5 13 18 13 18 0 Yes
J 3 19 22 20 23 1
K 5 18 23 18 23 0 Yes
Name: Rishnay Akash Lal ID: S2018000228 (School of Building and Civil)

Network Diagram

d (5,0.11)

2 5

j (3,0.11)
a (6,0.44)
e (1,0.03)
h (6,0.11)
CRITICAL
7
TIME = 23
1 c (3,0)
4

i (5,1)
b (4,0.44) a (5,0.44)
f (4,0.11)

3 6
g (2,0.44)
Name: Rishnay Akash Lal ID: S2018000228 (School of Building and Civil)

1. Calculate the probability z if x= 24 days, if x=22 days, x=25days


V = 0.44 +0 + 0.11 + 1 + 0.44 = 2 SD = √ 2
x−CP
z=
√V
a. X = 24 days
24−23
z=
1.41
The probability value of Z = 1/ √ 2 is 0.76
b. X = 22 days
22−23
z=
1.41
The probability value of Z = -1/ √ 2, is 0.24
c. X = 25 days
25−23
z=
1.41
The probability value of Z = √ 2, is 0.92
2. If probability is given 96% state the latest time each activity should have started and completed?

Z = 0.96, is 1.75 L T= D−Cp


D = CP + 1.41(1.75) = 25.47 - 23
= 23 + 2.47 = 2.47 DAYS
= 25.48 days
6 5 11
Name: Rishnay Akash Lal ID: S2018000228 (School of Building and Civil)
D
15 9 20
19 3 22
0 6 6 6 3 9 J
A C 20 1 23
0 0 6 6 0 9

6 1 7
E
7 6 13
12 6 13
H
START 14 1 20
END

9 4 13
F 18 5 23
9 0 13 K
18 0 23
0 4 4 13 5 18
B I
5 5 9 13 0 18

9 2 11
G
16 7 18